B08_Section_J_Specifications_Volume_1_of_3.pdf

PDF 2 MB Posted

Attached to
PT BONITA LIFT STATION & WATERLINE FOR GOLDEN GATE
Solicitation number
140P8621R0029
Issued by

About this file

This document provides specifications for the rehabilitation of the Point Bonita Lift Station and installation of a new water pipeline at Golden Gate National Recreation Area in California. The scope of work includes removing the existing lift station and septic tank, installing a new lift station, cleaning and testing the existing force main, installing a new water pipeline, and rehabilitating the gravel road between the end of the paved road and the lift station. The work will be conducted in phases to minimize service outages. The specifications establish requirements for construction scheduling, coordination, submittals, RFIs, meetings, environmental protection, and safety. They provide definitions for contract line items and identify the National Park Service as the contracting agency.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VOLUME 1 OF 3

GOLDEN GATE NATIONAL

RECREATION AREA

PMIS No. 233751

REHABILITATE POINT BONITA LIFT STATION

PMIS No. 253304

POINT BONITA WATER LINE

Division 01

CONSTRUCTION SPECIFICATIONS

NATIONAL PARK SERVICE

PACIFIC WEST REGION

August 3, 2021

RFP No. 140P8621R0017 Section J - Attachment No. 002

GOGA - 233751 TOC - 1

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS NO. OF PAGES

01 11 00 Summary of Work 01 11 40 Work Restrictions 01 27 00 Definition of Contract Price Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 32 33 Photo Documentation 01 33 23 Submittal Procedures 01 34 00 Natural Habitat Requirements 01 35 13 Archeological Protection (Low Sensitivity) 01 35 23 Safety Requirements 01 35 30 Hazardous Materials 01 40 00 Quality Requirements 01 50 00 Temporary Facilities & Controls 01 52 00 Field Offices & Sheds 01 56 00 Barriers 01 57 19.12 Noise & Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention (1 Acre Minus) 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management & Disposal 01 77 00 Closeout Procedures 01 78 23 Operation & Maintenance Data 01 81 13 Sustainability Design Requirements 01 81 13.13 Sustainable Design Requirements for Non-Leed Projects 01 89 31 Soils Management Appendix A Submittal List Appendix B Closeout List

DIVISION 01

GENERAL REQUIREMENTS

GOGA - 233751 01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00

SUMMARY OF WORK

PART 1 – GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Contractor use of premises.

5. Not Used.

6. Work Restrictions.

7. Special Construction Requirements.

8. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Golden Gate National Recreation Area, California, Point Bonita, Marin County.

B. The Work consists of the following:

1. Installation of new lift station and electrical components:

a. Installation of a new sewer lift station to replace an existing lift station.

b. Removal of existing 3,000-gallon septic/holding tank effluent and clean tank.

c. Removal of existing 3,000-gallon septic/holding tank structure and appurtenances.

d. Install temporary sewer bypass from six-inch sewer main serving residences to existing lift station during demolition of existing 3,000-gallon septic/holding tank and the construction of new sewer lift station.

e. Keep the existing lift station fully operational under its current operating conditions until cutover is made to the new fully operational lift station system.

f. Removal of the existing lift station including effluent, temporary bypass and appurtenances.

g. Clean existing force main with pigging equipment and pressure test the line.

h. Install force main connection between new lift station and existing force main.

i. Test new wet well pump operations along with pressure testing the complete force main between new wet well and manhole outlet.

j. Install gravel roadway from end of pavement to the lift station as shown on the construction drawings. Existing roadway was damaged during previous wet weather events.

k. The new concrete wet well tank is to be pressure tested, If the tank fails, it will have penetrations sealed and tank retested.

2. Rehabilitate gravel roadway between end of road and lift station.

3. Installation of new water pipeline:

GOGA - 233751 01 11 00 - 2

a. The Work consists of the following: install approximately 300 linear feet of 2-inch HDPE NSF rated water line and five 2-inch service gate valves. All fittings will be fusion welded. Line will be buried 36 inches with locating conductor wire.

Demolition of a portion of existing asphalt drive will be required to install the pipeline. The backfill over the pipe shall be typical sand base with the surface being base rock compaction, asphalt drive, or grass to match existing surface conditions.

New water line will tie into previously installed two-inch galvanized lateral off the newer 6-inch ductile hydrant line. The lateral is saddle tapped off the 6-inch ductile and currently has a control valve installed with a 2-inch nipple capped off for future use (this project). The new line will connect the Fire hydrant main to the individual house water meters. Work includes replacing the demolished asphalt drive.

4. This Project will be constructed under a single prime contract.

5. The Contractor will be responsible for their work which will include:

a. Clean septic tank and pump vault prior to removal. Contractor shall use best management practices for all tank excavations and piping installation.

b. Provide and install submersible pumps compatible to the pump vaults to include all wiring, controls, floats, alarms, and appurtenances as specified. Pump vaults shall be plumbed into the riser of the pump vault and the pump controls wired to the control and electrical panels. Contractor shall employ best management practices for all underground tank, piping and wiring installation to prevent site environmental impacts.

c. Supply and install final lift station to pump effluent to the Marin Headlands sewer system as shown on the plans and specifications. Work shall include all piping and controls wiring necessary to manage and control the system from the NPS Supervisory Control and Data Acquisition (SCADA).

1) SCADA integration.

2) The NPS SCADA system to be integrated into its “Mission Control”

3) Local audio/visual alarms.

d. Contractor shall ensure all materials, equipment, equipment installation, and construction will produce fully a functional lift station, that are capable of being controlled (by the SCADA system).

e. Install electrical conduit and wire as depicted, including utility service and all main conduit group between control panel and electrical components.

f. Install communications conduit, cable, and ancillaries as depicted and specified.

g. Install piping and valves as shown on plans to convey sewer effluent to the Marin

Headlands sewer system.

h. Fill with imported material to rough grade elevation, including special foundation excavation and special engineered sub-grade for reinforced earth.

i. Fine grade and restore site surfaces as depicted on plans.

j. Cleanup, repair, and restore areas temporarily used during construction, including road repair.

1.3 WORK PHASES

A. The Work to install the pipeline shall be conducted to complement and not interfere with the work at the lift station.

B. The Work at the lift station shall be conducted in phases in the below order, with each phase substantially complete before beginning the next phase. Purpose of phasing is to minimize service outages/temporary services and impacts to adjacent property owners during construction. Note that local weather conditions will have greater impact to some of the phases with respect to the State of California SWPPP permitting and monitoring and should be

GOGA - 233751 01 11 00 - 3

considered in the approach and scheduling of work. Modification to phasing may be considered if benefits can be demonstrated that achieve fundamental purpose of phasing.

Phase I: Existing Septic Tank – Installation of sewer bypass around existing septic tank, septic tank removal that will allow for new system to be constructed and put into service without additional construction. Includes soil stabilization requirements based on Golden Gate National Recreation Area (GGNRA) standard BMP’s as per Appendix D, and approved SWPPP/permit. Includes site cleanup; does not include any required paving/patching as that can be done concurrently with other paving/patching for the project.

Phase II: New Lift Station Construction – Installation of new lift station, testing, startup and providing a fully operational system capable of conveying effluent to the Marin Headlands gravity sewer system. Work also includes cleaning existing sewer force main using pigging equipment and pressure testing the line prior to connecting the new lift station to the force main.

Phase III: Remove Existing Lift Station, Temporary Bypass – Removal of existing lift station and restoration of construction area surroundings.

Phase IV: Rehabilitate Gravel Road Between End of Pavement and Lift Station

Installation of new gravel roadway from existing asphalt roadway to lift station area as shown on the drawings.

1.4 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to within the areas specifically delineated on the construction drawings

2. Access: U.S. Highway 1 to Alexander Avenue will be used for all access to Point Bonita for construction personnel, construction equipment, deliveries, etc.

3. Contractor is responsible upon start-up and cut over of facilities to the new lift station to maintain the operation of the existing lift station system until substantial completion and owner training has been completed. Contractor will provide certified manufactures representative to conduct field startup of the Lift Station system and upon substantial completion a second site visit to conduct final programming of the system, ensure system is performing as per design/manufactured and finally conduct owner training.

4. Park Archeologist may be required to be on site during excavation, contractor’s weekly meeting two week look ahead must specifically address ground disturbance coordination.

During excavation if any items encountered are of potential archeological importance, contractor will stop work in that location and relocate work effort to other parts of the project until the site is cleared by the NPS.

5. Utilities to support construction activities by contractor:

a. Water: Contractor to install NPS approved backflow preventer and meter at NPS specified location. Contractor will be billed monthly at rate of $65 per 1,000 gallons not to exceed 10,000 gallons per day. Prior to using water, agreement between NPS and contractor must be signed. Billings are sent electronically via

GOGA - 233751 01 11 00 - 4

email, thus additional information from contractor is point of contact information to send billings and finally company tax ID number.

b. Power: Contractor may use power from existing facilities while working directly on the facilities. Acceptable uses are for equipment associated with direct construction of the project. Objective to allowing contractor utilize power at facilities is to limit use of portable generators when possible to reduce noise and greenhouse gases (carbon footprint of project).

B. Storage of Materials: Confine storage of materials to within the areas as described and delineated on the construction drawings for Point Bonita lift station system replacement.

C. Preservation of Natural Features:

1. All equipment shall be power washed and inspected before being off-loaded at Point Bonita to ensure it is free of non-native weeds and/or seeds. In addition, sources of imported rock, sand, gravel, and soil shall be inspected for invasive non-native plants, weeds and/or seeds. The Contractor shall submit a list of proposed sources, end use and temporary storage requirements for imported material, 30 calendar days prior to delivery.

Imported material shall be free of non-native weeds and/or seeds. Imported material shall be shipped directly from the source to the Park without intermediary storage or staging.

Shipping vessels shall be covered to prevent spillage or blowing of their contents while in transit. Refer to specification 01 89 31 – “Soils Management” for a list of pre-approved sources and requirements for contractor testing of non-pre-approved materials.

2. Top 6” of soil in any area will not be re-utilized as suitable fill within 18 inches from finish grade to prevent spread of invasive vegetation.

3. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

4. Provide temporary barriers to protect existing trees and plants and root zones.

5. Do not remove, injure, or destroy trees or other plants without prior approval.

6. Do not fasten ropes, cables, or guys to existing trees.

7. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

8. Erosion control measures will be in accordance with GGNRA’s BMP’s per Appendix D, weed free, rice straw, and burlap outer filter/cover, NO plastic netting products.

9. The NPS will conduct re-vegetation and restoration of the project area post project completion. Contractor is responsible for erosion control and stabilization of each area as specified in construction drawings and in accordance with GGNRA’s BMP’s in appendix of the specifications; lastly in accordance with Specification 01 57 23 in lieu of State of California General Construction SWPPP Permit.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, emergency vehicles and tenants at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Construction Camp: Establishment of a camp within the park will not be permitted.

GOGA - 233751 01 11 00 - 5

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment. Tunnel clearance through Bunker Road tunnel is 13’ – 6”.

Conzelman Road is the only other route to the site.

1.5 PUBLIC USE OF SITE

A. Contractor shall always conduct his operations to ensure the least inconvenience to the public.

1.6 OCCUPANCY REQUIRMENTS FOR BUILDINGS

A. Existing Buildings

1. Not Used.

1.7 WORK RESTRICTIONS

A. On-Site Work Hours: Tenants are located nearby the site and will remain throughout the duration of the project. Work shall be generally performed during normal business working hours of 8:00 a.m. to 4:30 p.m., Monday through Friday, no Federal Holidays. Extension of work hours may be authorized to allow for ten (10) hour work days with noise restrictions upon request and approval by Contracting Officer.

B. Vegetation Removal Restriction

1. No vegetation removal shall be performed during “Bird Nesting Season” from March 1st to July 31st.

C. Existing Utilities

1. Existing Utilities: USA Notification & Utility Field Meeting

a. The Contractor shall contact Underground Service Alert (USA) (1-800-642-2444) seven (7) calendar days prior to start of each ground disturbing phase and shall be responsible for maintaining a valid USA location tag through renewal during the construction. The Contractor shall schedule a utility field meeting prior to any excavation. This shall be so stated in the USA notification. The Contractor shall be responsible to coordinate the utility field meeting at which time he shall explain the limits and impacts to USA member utilities.

b. Most of the utilities within Point Bonita are owned by NPS. As such, very few utilities will be marked out by USA. It is the Contractor's responsibility to field locate & mark all utilities within the project work area. Field location and marking shall be performed a minimum of three (3) days prior to ground disturbance; notify CO upon completion of field location and marking for CO review and approval.

No trenching shall be performed prior to CO approval.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

GOGA - 233751 01 11 00 - 6

D. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than five (5) days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours for Utility Shutdowns: Point Bonita lift station may be non-operational, when required, upon specific approval of Contracting Officer for a maximum of twenty four

(24) hours.

1.8 SPECIAL CONSTRUCTION REQUIREMENTS

A. Contractor is responsible for erosion control and stabilization of each area as specified in construction drawings and in accordance with GGNRA’s BMP’s in appendix of the specifications; lastly in accordance with Specification 01 57 23 in lieu of State of California General Construction SWPPP Permit.

1.9 ADDITIONAL REPORTS

A. NPS Standard BMPs; Appendix A.

B. NPS Standard Signage; Appendix B.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION

GOGA - 233751 01 11 40 - 1

WORK RESTRICTIONS

SECTION 01 11 40

WORK RESTRICTIONS

PART 1 – GENERAL

1.1 PARK REGULATIONS

A. General: The Contractor must comply with the following rules and conditions:

1. Ensure personnel (contractors or subcontractors) working in the park become familiar with and obey all park regulations, wear hard hats in designated areas, and do not enter any restricted areas unless required to do so and until cleared for such entry.

2. Ensure equipment is conspicuously marked for identification.

3. The Contractor shall restrict employees / representatives to the work site and control travel directly to and from the work site.

4. Restore all traffic / parking / security signs and markings, including space numbers, designations, and lines, to their original form if such signs / markings are defaced or deleted during construction / repair.

5. Control and provide security of Contractor-owned equipment and materials at the work site. Report immediately missing / lost / stolen property to the park dispatch / law enforcement rangers at (415-561-5656).

6. Vehicles / Heavy Equipment:

a. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings.

Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.

b. Vehicle Parking: Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts. Vehicles and heavy equipment will be permitted at designated parking areas only.

c. Vehicle Exhaust: All vehicles will be properly maintained to insure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.

d. Spills: Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the Contracting Officer of spills.

e. Commercial Vehicle Safety Inspections: The Contractor, employees, contractors, and subcontractors shall fully cooperate regarding safety inspections of commercial vehicles within the Park. Commercial vehicle safety inspections are conducted unannounced for employee and visitor safety. Vehicles are checked for safety and mechanical deficiencies and for compliance with current state and federal laws and regulations. Driver licenses and medical certificates are also checked.

f. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.

GOGA - 233751 01 11 40 - 2

g. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.

h. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road).

Oversized vehicles must not exceed the clearances along the Park road corridor.

Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates and estimated arrival times at the park entrance, and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.

i. Road Work: Contractor shall provide adequate traffic control, including flaggers on either side of any work performed on the road. Any workers on or near the road must wear highly visible, bright clothing. (See Section 01 50 00 for additional details).

j. Law Enforcement: Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity. Contractor must immediately comply with any instructions issued by a park law enforcement ranger.

7. Emergency Medical and Accident Reporting:

a. The Contractor or subcontractor shall contact Park Dispatch for any medical emergency or traffic accident occurring within the Park.

b. Emergency number: Dial 911 as needed.

c. Park Dispatch: (415-561-5656)

d. Park Dispatch is called so that the entrance station will be prepared should any emergency vehicles (e.g. ambulance) need to enter the Park and so that any available Emergency Medical Services personnel in the Park might respond until such time as the ambulance arrives.

e. The Contractor or subcontractor is required to report ANY personal injury and / or property damage incident occurring within the park. This report must be made to a Law Enforcement Ranger at the first available opportunity before leaving the park:

f. Park Dispatch: (415-561-5656)

1.2 RESOURCE PROTECTION

A. General: The park is committed protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:

1. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles, equipment, tools, supplies, and materials prior to packing / loading. The park requires, and will perform, inspections to ensure non-transport of non-native species PRIOR to arriving at the park entrance. Contact the COR directly at least (3) three days in advance of park entry to arrange for inspection(s) at the loading dock or point of origin.

2. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and keep an eye out for animals on or alongside road. Contact COR immediately if animal is hit or injured or will not move off the road.

GOGA - 233751 01 11 40 - 3

3. Archaeological Resources: Archaeological resources are physical evidences of past human activity, including evidences of the effects of that activity on the environment.

Archaeological resources are found above and below ground and underwater. The contractor shall refer to Specification 01 35 13, Archaeological Protection (Low Sensitivity) during all ground-disturbing activities. If any potential artifact is discovered during excavation the contractor shall stop work or relocate work to a non-sensitive area and contact the contracting officer immediately. Archaeological resources typically found in the park or at the project site will be discussed further at the preconstruction meeting.

4. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the contracting officer.

END OF SECTION

GOGA - 233751 01 27 00 - 1

DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00

PART 1 – GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 – EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No. 1 – Installation of New Lift Station and Electrical Components.

1. This item consists of work and cost associate with the removal of existing lift station and septic tank, sewer bypass associated with demolition of septic tank, keeping the existing lift station fully operational during the installation and startup of the new lift station; site restoration and clean up. Also includes cleaning, pigging and pressure testing existing two-inch HDPE force main.

2. No separate measurement will be made.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item No. 2 – Gravel Road Improvements

1. This item consists of work and cost associated with placement of road base and surface materials over an existing finished grade to produce an all-weather access road to the lift station facility. This work will also repair and stabilize surfaces under the new gravel road damaged in previous wet weather events by filling in ruts with either pit run, aggregate base or both.

2. No separate measurement will be made.

3. Payment will be made at the contract lump sum price.

C. Contract Line Item No. 3 – Install Water Pipeline

1. This item consists of work and cost associated with furnishing and installing a water pipeline and accoutrements as described in the specifications at the location shown on the map and marked in the field.

2. Work also includes replacing asphalt pavement removed to install the pipeline.

3. No separate measurement will be made.

4. Payment will be made at the contract lump sum price.

3.2 LIST OF CONTRACT BID OPTIONS

GOGA - 233751 01 27 00 - 2

A. Contract Bid Option No. A – NOT USED

GOGA - 233751 01 31 00 - 1

PROJECT MANAGEMENT & COORDINATION

SECTION 01 31 00

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Construction Coordination.

2. Coordination Drawings.

3. Requests for Information (RFIs).

4. Project meetings.

5. Environmental Coordination.

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

1.2 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

GOGA - 233751 01 31 00 - 2

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Pre-installation conferences.

7. Project closeout activities.

1.3 SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of one (1) week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Contractor’s Project Superintendent and Project Manager.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Site Specific Safety and Health Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

8. Demolition Plan.

9. Waste Management Plan.

10. Quality Control Plan.

11. State of California SWPPP (Stormwater Pollution Prevention Plan).

12. Lift Station and Controls Start Up Plan.

13. Traffic Control Plan.

B. All items listed must be provided to the Contracting Officer before the Pre-Construction

Conference is held. If all these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

C. Division 02-49 Submittal Documents: The following documents shall be submitted to the Contracting

Officer prior to construction start. If these documents have not been received and approved by the NPS prior to construction, the construction start date may be delayed.

1. Product Data – Submit product cut sheets / material data on all products to be used for approval.

Indicate the size, model, or type of each recommended product.

2. Samples – When requested, submit a physical sample of a product or an array of color choices for approval.

3. Shop Drawings - Submit shop drawings that embody all major elements of the work.

a. Drawings shall be developed in AutoCAD or similar drafting software.

b. Drawings shall include details, dimensions, notational information and other data to ensure the contractor has a complete understanding of the work.

GOGA - 233751 01 31 00 - 3

c. Drawings shall be submitted to the Contracting Officer in PDF format. Allow 2 weeks for the drawings to be reviewed by NPS staff. The Contractor shall incorporate review comments into the shop drawings and resubmit for final approval.

1.4 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. CO will return RFIs submitted by other entities controlled by Contractor with no response.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Unique RFI number, numbered sequentially

2. Project name.

3. Contract number.

4. Date.

5. Name of Contractor.

6. RFI single subject/ topic.

7. Specification Section number and title and related paragraphs, as appropriate.

8. Drawing number and detail references, as appropriate.

9. Field dimensions and conditions, as appropriate.

10. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

11. Contractor's signature.

12. Requested date for response.

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms: Utilize the RFI form that can be downloaded from the Workflows website at http://www.nps.gov/dscw/con_rfi217.htm or Software-generated form with substantially the same content as indicated above, approved by the Contracting Officer.

1. Attachments shall be electronic files in Adobe Acrobat PDF format.

D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following Contractor-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

RFP No. 140P8621R0017 http://www.nps.gov/dscw/con_rfi217.htm

GOGA - 233751 01 31 00 - 4

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.5 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Resolution of comments on required Division 01 documents.

4. Coordination of Subcontractors.

5. Labor law application.

6. Modifications.

7. Payments to Contractor.

8. Payroll reports.

9. Contract time.

10. Liquidated damages.

11. Display of Hotline posters.

12. Notice to proceed.

13. Correspondence procedures.

14. Acceptance/rejection of work.

15. Progress meetings.

16. Submittal procedures.

17. NPS Final Accessibility Inspection.

18. Environmental requirements.

19. As-constructed drawings/operation and maintenance (O&M) manuals.

20. Saturday, Sunday, holiday and night work.

21. Reference materials.

22. Value engineering.

B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the

Contractor. Contractor will be required to manage weekly meetings including but not limited to the following: establish an agenda, take notes, produce minutes for NPS approval, and maintain a file of all documentation related to the weekly meeting.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.

All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

GOGA - 233751 01 31 00 - 5

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections, etc.)

h. Construction Schedule update (provide updated CPM).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

C. Pre-installation Conferences: Conduct a pre-installation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Possible conflicts.

i. Compatibility requirements.

j. Time schedules.

k. Weather limitations.

l. Manufacturer's written instructions.

m. Warranty requirements.

n. Compatibility of materials.

o. Acceptability of substrates.

p. Temporary facilities and controls.

q. Space and access limitations.

r. Regulations of authorities having jurisdiction.

s. Testing and inspecting requirements.

t. Installation procedures.

u. Required performance results.

v. Protection of adjacent work.

w. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

GOGA - 233751 01 31 00 - 6

1.6 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

1. Qualifications: Minimum three (3) years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of the Waste Management Plan (WMP).

c. Implementation of the Storm Water Pollution Prevention Plan (SWPPP).

d. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.

e. Training for Contractor personnel in accordance with their position requirements.

f. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Noise & Acoustics Management.

4. Temporary Storm Water Pollution Prevention Environmental Management.

5. Construction Waste Management.

C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:

1. Overview of environmental issues related to the building industry.

2. Overview of environmental issues related to the Project.

3. Review of site specific procedures and management plans:

a. Construction Waste Management.

b. Noise & Acoustics Management.

c. Temporary Storm Water Pollution Prevention.

4. Compliance with environmental regulations: As specified in Regulatory Requirements.

Submit Contractor 40 CFR employee training records upon request of Contracting Officer.

D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, and Storm Water Pollution Prevention Plan.

PART 2 – PRODUCTS (Not Used)

PART 3 – EXECUTION (Not Used)

GOGA - 233751 01 31 00 - 7

Project:

Contract No.: Date:

To:

cc:

From:

Subject:

Please provide the following information or clarification:

Response required by ___\____\____

Date:

To:

From:

Subject:

REQUEST FOR INFORMATION # __

GOGA - 233751 01 32 16 - 1

CONSTRUCTION SCHEDULE

SECTION 01 32 16

PART 1 - GENERAL

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

1.2 SUBMITTALS

A. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

B. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit a baseline schedule, large enough to show entire schedule for entire construction period.

C. Construction Schedule Updates: Prior to the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data.

1.3 COORDINATION

A. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, payment requests, and other required schedules and reports.

PART 2 - PRODUCTS

2.1 SCHEDULE OF VALUES

A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-

GOGA - 233751 01 32 16 - 2

sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.

B. Do not break down unit price items. Use only the contract price for unit price items.

C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.

D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting

Officer before the first progress payment is processed.

2.2 CONSTRUCTION SCHEDULE REQUIREMENTS

A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using computerized scheduling software.

1. Construction Baseline Schedule shall show submittal review, construction start date, work activities / staff resources, activity durations, major milestones, inspection dates, closeout activities, and project end date.

2. Establish procedures for updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.

3. Contracting Officer may request an updated Construction Schedule at any time to confirm progress of the work.

GOGA - 233751 01 32 33 - 1

PHOTO DOCUMENTATION

SECTION 01 32 33

PHOTOGRAPHIC DOCUMENTATION

A. This Section includes administrative and procedural requirements for the following:

1. Existing Condition images prior to demolition.

2. Periodic construction images.

B. See Division 01 Section 01 77 00 "Closeout Procedures" for a complete listing of closeout documents.

A. Construction Images: Submit images electronically within seven (7) days of taking the image.

Include the following for each:

1. Include Date, time and number (sequentially number all images) in filename.

2. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.

3. Submit digital images exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.

B. Closeout: Submit a complete set of digital image electronic files as a Project Record Document.

Submit on either a Compact Disc (CD) or Digital Video Disc (DVD).

1. Provide an index as a separate file on the Disc. List each image as a file name with number, date, and time. Include description and or vantage point image was taken.

2. Submit images that have the same aspect ratio as the sensor, un-cropped.

PART 2 – PRODUCTS

2.1 FORMAT REQUIREMENTS

A. Media: CD-R Archival Gold or DVD-R Archival Gold

B. Media Labels: Archival CD/DVD labeling markers, archival labels, or direct print CD

C. Images: Provide color images in JPEG format. Minimum sensor size of eight (8) mega pixels, and at an image resolution of not less than 3200 by 2400 pixels.

GOGA - 233751 01 32 33 - 2

PHOTO DOCUMENTATION

3.1 CONSTRUCTION IMAGES

A. General: Take digital images using the maximum range of depth of field, and that are in focus, to clearly show the Work. Images with blurry or out-of-focus areas will not be accepted.

1. Maintain index with each set of Construction images that identifies the number, date, time, and description for each.

2. Maintain one (1) set of images accessible in the field office at the Project site, available at all times for reference.

B. Existing Condition Images: Before commencement of demolition or starting construction, take color digital images of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by Contracting Officer.

1. Flag construction limits before recording construction images.

2. Take eight (8) separate images to show existing conditions adjacent to property before starting the Work.

3. Take eight (8) separate images of existing buildings either on or adjoining property to accurately record physical conditions at start of construction.

C. Periodic Construction Images: Take twelve (12) color, digital images weekly, with timing each month adjusted to coincide with the cutoff date associated with each Application for Payment.

Select vantage points to show status of construction and progress since last images were taken.

D. Additional Images: Contracting Officer may issue requests for additional images, in addition to periodic Construction images specified.

1. Three (3) days’ notice will be given, where feasible.

2. In emergency situations, take additional images within twenty-four (24) hours of request.

3. Circumstances that could require additional images include, but are not limited to, the following:

a. All below grade construction that will not be visible after project completion: Items include but not limited to; connections, unions, foundations, etc.

b. Immediate follow-up when on-site events result in construction damage or losses.

c. Images to be taken at fabrication locations away from Project site.

d. Substantial Completion of a major phase or component of the Work.

e. Extra record images at time of final acceptance.

GOGA - 233751 01 33 23 - 1

SUBMITTAL PROCEDURES

SECTION 01 33 23

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

1.2 DEFINITIONS

A. Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.

B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.

C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.

D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.

1.3 GENERAL SUBMITTAL PROCEDURES

A. General: Prepare and submit submittals required by the project submittal log. Types of submittals are indicated in the project submittal log. Refer to indicated specification for additional information.

1. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with Contract Documents.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related…