This is a comprehensive Project Manual for the Yellowstone National Park Mammoth Wastewater Collection System Replacement project (Solicitation Number 140P2025B0001). The project involves replacing approximately 8,600 linear feet of existing sanitary sewer mains within the Mammoth Hot Springs area through multiple rehabilitation techniques, including open cut excavation, pipe bursting, CIPP lining, and manhole repairs/replacements.

The project is divided into eight Contract Line Item Numbers (CLINs), with specific work scopes including: CLIN 1 for mobilization, CLIN 2 for open cut excavation and point repairs (3,646 linear feet), CLIN 3 for pipe bursting (3,888 linear feet), CLIN 4 for manhole repairs/lining, and optional bid items for additional open cut excavation, manhole replacements, and CIPP lining. The work will require careful coordination with the National Park Service, adherence to strict environmental protection guidelines, and implementation of temporary bypass pumping systems to maintain continuous wastewater flow during construction. The project specifications detail comprehensive requirements for materials, installation methods, testing, and restoration of disturbed areas.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

National Park Service Yellowstone National Park Mammoth Hot Springs, WY

Replace Mammoth Wastewater Collection System

YELL 311631

Construction Documents

Project Manual

April 2025

This page intentionally left blank.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM

YELL - 311631

TABLE OF CONTENTS

TABLE OF CONTENTS

DIVISION 01 — GENERAL REQUIREMENTS

01 11 00 - SUMMARY OF WORK

01 12 00 - NATURAL FEATURES PROTECTION

01 22 00 - MEASUREMENT AND PAYMENT

01 26 01 - CONTRACT MODIFICATION PROCEDURES

01 27 00 - DEFINITION OF CONTRACT LINE ITEMS

01 31 00 - PROJECT MANAGEMENT AND COORDINATION

01 32 16 - CONSTRUCTION SCHEDULE

01 33 23 - SUBMITTAL PROCEDURES

01 35 13.22 - ARCHEOLOGICAL PROTECTION

01 35 23 - SAFETY REQUIREMENTS

01 40 00 - QUALITY REQUIREMENTS

01 42 00 - REFERENCE STANDARDS

01 50 00 - TEMPORARY FACILITIES AND CONTROLS

01 50 00A - TEMP FACILITY CONTROLS HOT WORK PERMIT

01 57 19.12 - NOISE AND ACOUSTICS MANAGEMENT

01 57 23 - TEMPORARY STORM WATER POLLUTION PREVENTION

01 67 00 - PRODUCT REQUIREMENTS

01 73 29 - CUTTING AND PATCHING

01 73 40 - EXECUTION

01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 77 00 - CLOSEOUT PROCEDURES

DIVISION 02 — EXISTING CONDITIONS

02 41 00 - DEMOLITION

DIVISION 09 — FINISHES

09 96 00 - HIGH PERFORMANCE INDUSTRIAL COATINGS

DIVISION 31 — EARTHWORK

31 10 00 - SITE CLEARING

31 23 17 - ROCK EXCAVATION

31 23 19 - DEWATERING

31 23 33 - TRENCHING, BACKFILLING, AND COMPACTING FOR UTILITIES

DIVISION 32 — EXTERIOR IMPROVEMENTS

32 11 23 - AGGREGATE BASE COURSES

32 12 16 - ASPHALTIC CONCRETE VEHICULAR PAVING

32 13 13 - CONCRETE PAVEMENT

32 15 40 - CRUSHED STONE SURFACING

32 16 13 - CONCRETE CURB AND GUTTER

32 16 23 - CONCRETE SIDEWALK AND STEPS

32 91 19.13 - TOPSOIL PLACEMENT AND GRADING

32 92 00 - TURF AND GRASSES

DIVISION 33 — UTILITIES

33 05 08 - GLASS REINFORCED PLASTIC CURED-IN PLACE-PIPE (GRP-CIPP) LINING OF

EXISTING SEWERS

33 05 09 - PIPE BURSTING

33 05 16 - PRECAST CONCRETE MANHOLE STRUCTURES

33 05 23 - PIPELINE UNDERCROSSINGS

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM

YELL - 311631

TABLE OF CONTENTS

33 05 31.11 - POLYVINYL CHLORIDE GRAVITY SEWER PIPE

33 05 33.23 - POLYETHYLENE PRESSURE PIPE AND TUBING (AWWA C901 AND AWWA

C906)

33 31 11 - GRAVITY SEWER PIPELINE AND MANHOLE CONSTRUCTION

33 32 00 - TEMPORARY WASTEWATER BYPASS PUMPING SYSTEMS

D I V I S I O N 0 0

PROCUREMENT AND CONTRACTING

REQUIREMENTS

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 00 01 07 - 1

YELL - 311631 SEALS AND SIGNATURES

00 01 07 - SEALS AND SIGNATURES

I hereby certify that the portion of the Specifications described below was prepared by me or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the State of Wyoming.

INSERT NAME MM/DD/2025

Pages or Specifications divisions or sections covered by this seal:

END OF SEALS AND SIGNATURES

Christopher Bailey, PE 01/23/2025

D I V I S I O N 0 1

GENERAL REQUIREMENTS

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 11 00 - 1

YELL - 311631 SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Work Phases

3. Work Under Other Contracts

4. Government-Furnished Materials

5. Construction Contractor Use of Site

6. Public Use of Site

7. Occupancy Requirements for Buildings

8. Conduct of Operations

9. Work Restrictions

10. Special Construction Requirements

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Sewer rehabilitation throughout the Mammoth Hot Springs, WY area as shown and detailed in the construction plans.

B. This project is separated into eight (8) Contract Line Item Numbers (CLIN) and includes gravity sewer replacement, rehabilitation, and repair throughout the Mammoth Hot Springs wastewater collection system service area. Open cut excavation replacement and point repairs, CIPP and sectional lining, pipe bursting, and manhole replacement/rehabilitation are all a part of the project scope as detailed in the plans and specifications.

1. CLIN 1 – Mobilization.

a. This item consists of moving personnel, equipment, material and incidentals to the project and performing work necessary before staring work at the project site.

This work also includes obtaining permits, insurance and bonds.

2. CLIN 2 – Open Cut Excavation and Point Repairs.

a. This item consists of open cut excavation pipe replacement and point repairs of approximately 3,646 linear feet of 6-12” sanitary sewer pipe throughout the

Mammoth Hot Springs collection system as shown on plan sheets C1-C64. This item also includes:

1) Replacement of seven (7) manholes (MA 3237, MA 3263, MA 3235, MA

3359, MA 3234, MA 3233, and MA 3232), as shown on sheets C19-C20.

2) Replacement of two (2) manholes (MA 3192 and MA 3191), as shown on sheet C5.

3) Replacement of one (1) manhole (MA 3170), as shown on sheet C18.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 11 00 - 2

3. CLIN 3 – Pipe Bursting.

a. This item consists of pipe bursting of approximately 3,888 linear feet of 6-8” sanitary sewer pipe throughout the Mammoth Hot Springs collection system as shown on plan sheets C1-C64, and the replacement of twenty-eight (28) manholes that are associated with pipe bursting access pits.

4. CLIN 4 – Manhole Repair/Lining.

a. This item consists of repairing/lining five (5) sanitary sewer manholes throughout the Mammoth Hot Springs collection system as shown on plan sheets C1-C64.

5. CLIN 5 – Bid Option A: Open Cut Excavation

a. This item consists of open cut excavation pipe replacement of approximately 527 linear feet of 8” sanitary sewer pipe for the segment listed below, and the replacement of five (5) manholes that are associated with Bid Option A and noted on the plan sheets. If this option is selected it will remove/deduct the 10’ sectional liner (included in CLIN 8) and the 10’ point repair (included in CLIN 2) between manholes MA 3224 and MA 3225.

1) MA 3224 and MA 3226 (Plan Sheet C21)

2) MA 3227 and MA 3230 (Plan Sheet C21)

6. CLIN 6 – Bid Option B: Open Cut Excavation.

a. This item consists of open cut excavation pipe replacement of approximately

1,734 linear feet of 8” and 12” sanitary sewer pipe between the segments listed below, and the replacement of seven (7) manholes that are associated with Bid

Option B and noted on the plan sheets.

1) MA 3199 and MA 3370A (Plan Sheets C1, C2, C4)

2) MA 3470 and MA 3358 (Plan Sheets C11, C14, C15)

3) MA 3479 and MA 3432 (Plan Sheets C22, C23)

7. CLIN 7 – Bid Option C: Manhole Replacement.

a. This item consists of replacing twenty-four (24) sanitary sewer manholes throughout the Mammoth Hot Springs collection system as shown on plan sheets

C1-C64.

8. CLIN 8 – Bid Option D: Cured-In-Place Pipe (CIPP) Lining and Sectional Lining.

a. This item consists of CIPP lining (full pipe length and sectional lining) of approxi-mately 4,052 linear feet of 6-18” sanitary sewer pipe throughout the Mammoth

Hot Springs collection system as shown on plan sheets C1-C64.

C. Project will be constructed under a single prime contract.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 11 00 - 3

1.3 WORK PHASES

A. The Work shall be conducted in one (1) phase with subphases to be proposed by the Contractor to complete all the work with the time restrictions listed in this Specification Section.

1.4 WORK UNDER OTHER CONTRACTS

A. General: Cooperate with separate Construction Contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate

Work of this Contract with work performed under separate contracts.

B. Preceding Work: Government has awarded separate contract(s) for the following construction operations at Project site. Those operations are scheduled to be substantially complete before work under this Contract begins.

1. Mammoth Temporary WWTP: A separate contract has been awarded to Tepa, LLC. For the installation of a temporary WWTP located in Mammoth Hot Springs, WY. The temporary WWTP is substantially complete and in operation/treating wastewater. The

Contractor shall coordinate with the NPS and Tepa, LLC for any items that may affect their work.

C. Concurrent Work: Government anticipates awarding a separate Contract for the following operations at Project site. Those operations are scheduled to last from June 2025 through

November 2026.

1. Fort Yellowstone Buildings Exterior Rehabilitation: The project will rehabilitate the exte-rior of six (6) buildings along Officer's Row in Fort Yellowstone. The work is not ex-pected to overlap with the work awarded in this Contract, except that the replacement of

Manhole MA 3156 (CLIN 7 / Plan Sheet C8) and adjacent point repair (CLIN 2 / Plan

Sheet C8) will take place in the staging area set aside for the Fort Yellowstone Contactor.

Coordinate activities with the Fort Yellowstone Contractor.

1.5 CONSTRUCTION CONTRACTOR USE OF SITE

A. General: Construction Contractor shall have full use of the site for construction operations during the construction period. Construction Contractor's use of the site is limited only by the

Government's right to perform work or to retain other Construction Contractors on portions of

Project.

B. General: Construction Contractor shall have limited use of site for construction operations.

Limit use of premises to areas within the Construction limits indicated on Drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.

C. Storage of Materials: Confine storage of materials to staging areas shown on the plans and confirmed with the NPS.

D. Parking: Confine parking to designated locations within the construction limits and coordinated with the NPS.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 11 00 - 4

E. Stockpiling: Confine stockpiling to staging areas shown on the plans and approved by the NPS.

F. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

G. Areas noted on the plans as “Sensitive Areas” will require monitoring by a contractor provided monitor (Archaeological or botanist). Qualifications of the monitor shall be submitted to the

Contracting Officer for review and approval.

H. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

I. Construction Camp:

1. Establishment of a camp within park will not be permitted.

2. Contractor shall be responsible for obtaining housing outside of the park. The use of campgrounds or other in-park commercial lodging is prohibited.

J. The following conditions shall be followed during the Contractor’s stay at the park:

1. The Contractor and all Contractor employees and families at the Park will be required to attend bear orientation sessions presented by the National Park Service.

2. Notify the CO immediately if:

a. A grizzly bear or wolf remains within 200 meters of the work site; or

b. Any carrion or roadkill is within 200 meters of the work site.

3. To prevent unnatural attractants to bears, no food, garbage, drinks, trash, or food and drink containers shall be placed outside trailers or buildings, except during actual use.

Store lunch pails and all food inside vehicles or job trailers.

4. All trash cans that are not of the bear-resistant design shall be located inside trailers or buildings.

5. Waste produced by the Contractor is the responsibility of the Contractor and may not be put in the National Park Service containers.

6. All work site food and drink trash or garbage shall be placed in trash cans.

7. All barbecue units shall be stored in trailers and buildings and not outside when not in use.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 11 00 - 5

8. Bird feeders are prohibited.

9. Pets are prohibited.

10. Feeding of any wildlife is prohibited.

11. Any mishandling of garbage, trash, foods, and other potential bear attractants described above will result in the responsible person or Contractor receiving a citation subject to a fine and/or court appearance before the U.S. Magistrate.

12. All costs for bear management actions directly related to the mishandling of garbage, trash, foods, and other potential bear attractants described above shall be at no additional expense to the Government.

K. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Construction Contractor of liability for damage which may result from moving of equipment.

1. Contractor will be required to submit a travel control plan and haul route plan to the

Contracting Officer for review and approval prior to hauling in the park.

L. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.

M. Steam-clean all construction vehicles and equipment, including the undercarriage, prior to entering the Park. Vehicles and equipment are required to pass an inspection to verify that they are free of mud, dirt, and plant material prior to being allowed into the park. Coordinate with

Entry Gate officials a minimum of 4 calendar days in advance to schedule vehicle inspections by Park officials before entering the Park. Inspections are generally available Monday through

Thursday. Contractor is requested to group as many inspections together as possible.

N. Temporary Controls on Site:

1. Keep project neat, orderly, and in a safe condition at all times.

2. Provide erosion control around the project site as necessary and in accordance with

Section 01 57 23.

3. Wet down dry materials and rubbish to prevent blowing dust.

4. Keep volatile wastes in covered containers. Do not dispose of volatile wastes or oils in storm or sanitary drains.

5. Immediately remove hazardous rubbish from the project site.

1.6 PUBLIC USE OF SITE

A. The project area will be open to the public during construction. The Contractor shall have an approved traffic control plan in place prior to beginning work in each location.

B. Construction Contractor shall conduct operations to ensure the least inconvenience to public.

Road closures may be permitted, when required, upon specific approval of Contracting Officer for a maximum of 2 days. Partial closures with flagger control during work hours will be permitted as needed.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 11 00 - 6

C. Contractor shall provide notification to residents of planned construction affecting their access a minimum of 7 days prior to work starting.

1.7 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings:

1. Full Government Occupancy: Government will occupy buildings adjacent to construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.

b. Maintain existing building in weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and occupants during construction period.

1.8 ADMINISTRATIVE ACCESS DURING CONSTRUCTION

A. Vehicle access to the Mammoth Hot Springs area from Gardiner, Montana, is allowed year-round. Many other Park roads are open to regular vehicle traffic from approximately mid-April to early November but are only open to oversnow traffic during the winter. Adverse weather may cause short-term closures of Park roads.

B. The Contractor is responsible for clearing snow from the job site. The Contractor shall not conduct snow removal activities on Park main roads.

C. Prior to any winter shutdown, all equipment, materials, and stockpiles must be located and adequately marked so that they can be easily identified during snow plowing operations the following spring. All excavations must be backfilled prior to a winter shutdown.

D. Access into the Park will only be allowed upon presentation of proper identification with this

Project, prior notification of Park officials, or by securing gate passes or stickers.

E. Contractor shall at all times conduct their operations to ensure the least inconvenience to the public. All traffic on Park roads must be permitted to pass. If excavation, backfill, or paving operations require a temporary closure of a street, the Contractor shall route traffic on a clearly signed and marked detour. The Contractor will be required to place and maintain signs for all detours.

1.9 CONDUCT OF OPERATIONS

A. Construction Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 11 00 - 7

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 2 business days in advance of the Work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.10 WORK RESTRICTIONS

A. On-Site Work Hours and Dates: Work shall be generally performed during normal business working hours of 8 a.m. to 6 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: 8 a.m. to 6 p.m. Contractor must submit a request in writing a minimum of 48 hours in advance of weekend work and request must be approved by the

Contracting Officer prior to working.

2. Early Morning Hours: Confirm any restrictions with the Contracting Officer prior to construction.

3. Hours for loud construction activities: Confirm any restrictions with the Contracting

Officer prior to construction.

4. All Work in the Cabin Area north of the main entry road shall be completed when the cabins are closed in the fall after October 14th. Work within the Cabin Area includes, but is not limited to, the open cut excavation between SSMH MA 3332 and SSMH MA 3201.

5. Work affecting traffic on the main entry road shall be completed after October 14th and pavement patching completed by May 1st. Patching shall be completed as soon as possible following installation of the sewer. Temporary gravel surfacing will be allowed but the contractor is responsible for maintenance of temporary surfacing until final surfacing is placed.

6. Work in the wetlands areas identified in the plans shall be completed after October 1st.

Construction equipment shall be cleaned per section 1.5.M prior to working in wetlands and after completion of wetland work to eliminate weed spread.

B. Existing Utilities

1. Existing Utilities: The contractor shall first contact One-call of Wyoming, then the

Yellowstone Branch of Information Systems Management. The contractor shall have the

One-call of Wyoming ticket number ready to provide to the Yellowstone Branch of

Information Systems.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government. Provide repair materials and fittings onsite during construction for immediate repair of damaged water mains.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

4. Utility Contact List:

5. One-call of Wyoming, 800.849.2476 for locates.

6. Yellowstone Branch of Information Systems Management, Mammoth, 307.344.2470

(telephone) and 307.344.2067 (fax) for locates.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 11 00 - 8

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by

Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify the Contracting Officer not less than two weeks in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without the Contracting Officer’s written permission.

3. Hours and length of Utility Shutdowns: Full shutdowns of the sanitary sewers in the project area will not be allowed. The contractor shall have an approved bypass pumping plan in place prior to beginning work in each area.

D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within

25 feet of entrances, operable windows, or outdoor air intakes.

1.11 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Management and Communication Software: Software administered by the NPS shall be used to manage communication and document sharing during construction.

1. See Section 01 31 00 "Project Management and Coordination" for requirements on using the NPS project management and communication software.

1.12 UNEXPECTED DISCOVERY OF ARCHAEOLOGICAL RESOURCES

A. The Contractor is not expected to encounter archeological resources in any non-sensitive project areas. However, if any concealed archaeological resources are encountered, the Contractor must cease work within 50 feet of the discovery immediately and notify the Contracting Officer immediately. The site and the artifacts need to be assessed to determine if an archeological site has been unexpectedly uncovered. Work in the discovery area cannot resume until the

Contractor obtains approval from the Contracting Officer. Work may proceed outside of the discovery area.

B. Any and all historic objects discovered during this project (i.e., under foundations, in wall, attic, or crawl spaces, on the ground surface, etc.) shall be turned over immediately with provenience information to the Contracting Officer.

C. In the event that human remains are discovered during construction activities, all activities in the vicinity of the discovery must stop and the Contracting Officer shall be contacted immediately. If the remains are determined to have no forensic value and are of Native

American descent or an historical person, all provisions outlined in the Native American Graves

Protection and Repatriation Act (1990), as amended, will be followed.

1.13 GEOLOGY

A. Immediately stop work in the area and notify the Contracting Officer if any of the following conditions are encountered:

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 11 00 - 9

1. A hole in the ground the size of a basketball, or larger.

2. Standing or flowing water, either hot or cold.

3. A “rotten egg” smell.

B. Mammoth is an active hydrothermal area. These three conditions are strong indications of hy-drothermal activity. If any of these conditions are encountered, the Contractor shall immediately notify the Contracting Officer, the Contracting Officer will immediately notify the park geolo-gist so that trained personnel can assess the level of hydrothermal activity.

1.14 CONSTRUCTION MATERIALS

A. All materials, including borrow and aggregates, shall be obtained from a pit that has been certified weed-free by the park. These materials are Contractor-provided from outside the Park.

A list of certified pits will be provided to the Contractor upon request. Contact the Contracting

Officer for the most up-to-date list of certified facilities in the Greater Yellowstone Ecosystem.

B. Dispose of excess excavated materials (including rocks and boulders) that cannot be used in construction outside of the Park or as directed.

1.15 PROJECT CLEANUP

A. All work and storage areas shall be kept clean and free from paper, garbage, and trash. Such materials shall be removed by the Contractor and disposed of in properly designated areas.

B. Fuels, lubricants, petroleum products, chemicals, or other waste materials shall be disposed of in properly designated areas off Government premises.

C. No burning of rubbish on Government premises will be allowed.

D. Tools, equipment, and temporary facilities shall be removed when no longer required for execution of the work.

E. After all work is completed according to the specifications of this contract, the Contractor shall clean the worksite areas, and perform all other work incidental to leaving a neat professional finish to the job.

F. Cost of hauling materials to a legal disposal site shall be the responsibility of the Contractor.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01 11 00

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 12 00 - 1

YELL - 311631 NATURAL FEATURES PROTECTION

SECTION 01 12 00 – NATURAL FEATURES PROTECTION

PART 1 - GENERAL

1.1 DESCRIPTION

A. The work of this Section consists of protection of vegetation and native soils, inside and outside or wetlands, to be retained within and adjacent to the perimeter work limits of this project. This

Section also consists of evaluation processes and mitigation measures in the event of unauthorized passage outside authorized work limits.

PART 2 - PRODUCTS

2.1 WORK LIMITS - CONSTRUCTION FENCING

A. 4 FT high orange plastic mesh construction fencing.

B. 6 FT steel posts.

2.2 TEMPORARY GROUND PROTECTION MATS

A. Provided by Contractor and approved by CO prior to use.

PART 3 - EXECUTION

3.1 PROTECTION INSTALLATION

A. Provide temporary work limit fencing and tree barricades to protect existing trees, plants and critical root zones as directed by the Contracting Officer. Protections shall be in place before any excavation work or heavy equipment is allowed on site.

3.2 CONSTRUCTION FENCING

A. Within the perimeter work limits, protect groups of shrubs and small trees and undisturbed soils as directed by the Contracting Officer with construction fencing. Firmly anchor fences to the ground a minimum of 2 FT from the nearest plant. Completely and continuously enclose areas of trees and shrubs to be protected with fencing.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 12 00 - 2

3.3 PROTECTIVE MATS

A. If required by the Contracting Officer, install ground protecting mats. Mats will be required for all work in wetland areas and to protect vegetation where no roads exist for access. Use and

Place mats according to the manufacturer’s recommendations.

B. Prior to use, inventory and inspect mats for damage with the CO or CMR.

C. Contractor shall replace mats damaged during construction at no cost to the Government.

3.4 PROTECTION MAINTENANCE

A. In establishing construction boundaries, minimize impacts on vegetation by avoiding shrubs and trees (including their root systems) where possible. Prohibit the damage or removal of vegetation without prior approval in the Project Documents or from Contracting Officer.

B. Only after all tree and plant protection has been installed, and the Contracting Officer has inspected and given written approval of the tree and plant protection, will the Contractor be allowed to begin excavation. All tree and plant protection shall be maintained throughout the duration of this project.

C. If any fencing, barriers, staking or marking, which designates protected areas, limits of demolition or work limits, is knocked down, moved or destroyed by the Contractor, the

Contractor will immediately move the work operation to another area, wholly or in part, or suspend work operations, until the fence or other protection is repaired to the Contracting

Officer's satisfaction at the Contractor's expense. Time lost due to such stoppage will not be considered basis for adjustment of completion date nor additional payment.

D. Parking vehicles and storing materials or supplies shall be confined to areas designated as staging areas on the plans or as specifically approved by Contracting Officer. Vehicle and material storage activities are strictly prohibited from protected and fenced sensitive soil and vegetation areas.

E. Fastening ropes, cables, or guys to existing trees and disposing of materials including, but not limited to paint, paint thinner, fiberglass materials, fiberglass thinners, concrete or cement residue, washings from cement or concrete mixers or any other material considered harmful by the Contracting Officer is prohibited anywhere in the project area.

F. Do not remove, injure, or destroy trees or other plants without prior approval of the Contracting

Officer. Consult with the Contracting Officer and remove agreed upon roots and branches that interfere with excavation or pipe placement. All pruning of canopy or cutting of roots will be done under the supervision of the Contracting Officer, and shall be done as set forth by the

National Arborist Association or the International Society of Arboriculture.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 12 00 - 3

G. If within the critical root zone, excavate with hand tools.

H. At project completion, the Contractor shall remove all protections and be properly disposed of or recycled.

3.5 WETLAND PROTECTION

A. Implement best management practices to avoid or minimize potential adverse impacts on wetlands, stream channel, and water quality.

B. Stripping and Storing Wetland Topsoil

1. Place stockpiled wetland topsoil to ensure survivability as determined by the CO if wetland topsoil is stockpiled longer than 24 HRS.

2. Keep wetland topsoil and plant material moist while stockpiled. If the hydric soils are to be stockpiled for longer than 14 calendar days, they shall be covered with impermeable material or otherwise protected from desiccation in a manner approved by the

Contracting Officer.

3. Excavate down to a depth of 12 inches to collect wetland topsoil and sod, with willows and other plants intact, from the areas designated as wetlands on the plans.

4. Excavate topsoil pieces with a minimum of 1/3 square yard to a maximum of 1 square yard to collect, transport, and stockpile in one operation without breaking the topsoil piece.

5. Exercise care to prevent damage to bark, branches, foliage, and root systems.

C. Conduct the action so it has only negligible to minor, new adverse effects on normal movement, migration, reproduction, or health of aquatic or terrestrial fauna, including at low flow conditions.

D. Conduct the action to avoid degrading water quality to the maximum extent practicable.

Employ measures to prevent or control spills of fuels, lubricants, or other contaminants from entering the waterway or wetland in accordance with the Hazardous Spill Plan described in

Section 01 50 00, “Temporary Facilities and Controls.”

E. Ensure all actions are consistent with state water quality standards and Clean Water Act Section

401 Certification Requirements.

F. Maintain appropriate erosion and siltation controls during construction, and permanently stabilize all exposed soil or fill material at the earliest practicable date. Properly maintain structures or fill material to avoid adverse impacts on aquatic environments or public safety.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 12 00 - 4

G. Avoid heavy equipment use in wetlands if at all possible. Place heavy equipment used in wetlands on protective mats, or take other measures to minimize soil and plant root disturbance and to preserve preconstruction ground and water surface elevations.

H. Whenever possible, place excavated material on an upland site. However, when this is not feasible, place temporary stockpiling of excavated material in wetlands on filter cloth, mats, or some other semi-permeable surface, or take comparable measures to ensure that underlying wetland habitat is protected. Stabilize the material with filter cloth, or other appropriate means to prevent reentry of excavated material into the waterway or wetland. All measures and precautions shall be taken to prevent entry of said material into a surface water of the state as a result of high water or precipitation events.

I. Remove temporary stockpiles or other temporary disturbances in wetlands in their entirety as soon as practicable. Return wetland areas temporarily disturbed by stockpiling or other activities during construction to their pre-existing elevations, and restore soil, hydrology, and native vegetation communities as soon as practicable.

END OF SECTION

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 22 00 - 1

YELL - 311631 MEASUREMENT AND PAYMENT

SECTION 01 22 00 - MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. General provisions on unit prices and quantities.

2. Listing of the various bid/pay items in the Project, together with criteria for measuring

Unit Price Work for payment.

1.2 GENERAL PROVISIONS ON UNIT PRICES AND QUANTITIES

A. Quantities:

1. Quantities of Unit Price Work indicated in the Bid Form and in the Contract (at the time the Agreement was signed by the parties) are estimates for purposes of pricing and comparison of Bids.

2. The Contracting Officer (CO) does not represent, either expressly or by implication, or agree that the nature of materials encountered below ground surface or in concealed areas, or actual quantities of Unit Price Work required, will correspond with the quantities in the Contract at the time the Agreement was signed by the parties. The CO reserves the right to increase or decrease quantities, and to eliminate quantities, as the CO may deem necessary or as may be necessary due to Site conditions encountered.

3. Quantities eligible for payment will be actual quantities furnished and installed (as applicable) in accordance with the Contract Documents, within the pay limits shown or indicated, as measured by the COR (or other entity so empowered in the Contract

Documents) and recommended for payment by the COR.

4. At Contractor’s expense, Contractor may independently verify quantities measured by the

COR for payment. Should Contractor disagree with quantities measured and recommended for payment by the COR, submit appropriate Change Proposal (appealing the COR’s measurements) indicating the specific reasons for Contractor’s appeal, with detailed reasons therefor and associated calculations and estimates, in accordance with the Contract Documents.

5. Quality Overruns:

a. When the quantity of a pay item of Unit Price Work eligible for payment exceeds the pay item’s quantity included in the Contract, the CO will pay for quantities that exceed those in the Contract only while the estimated total payments to

Contractor under the Contract will not exceed the Contract Price. Otherwise, a

Change Order is required to modify the associated quantity in the Contract, thus changing the Contract Price.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 22 00 - 2

6. Except as may be established elsewhere in the Contract Documents, make no claim for anticipated profit, loss of profit, damages, or additional compensation arising from difference between quantities of Unit Price Work eligible for payment and the estimated quantities in the Contract.

B. Measuring for Payment:

1. At the COR’s option, the COR may delegate to Construction Management Representative

(CMR) (if any), some or all of the COR’s responsibilities for measuring Unit Price Work eligible for payment.

2. Unless expressly indicated otherwise in the Contract Documents, measurements will be in United States standard measurements.

3. Unless indicated otherwise elsewhere in the Contract Documents, quantities of Unit Price

Work eligible for payment will be rounded to the nearest whole number.

4. In the event of conflict between this Section and the measurement criteria in the

Specifications of Divisions 02-49, the measurement criteria in this Section will govern.

5. Assistance with Measurements:

a. Assist the COR and Construction Management Representative (CMR) (if any), by providing measuring equipment, labor, and survey personnel necessary to measure quantities eligible for payment.

6. Quantities eligible for payment can be adjusted by the COR to correct quantities included in Contractor’s prior payment requests, and for incomplete or defective Unit Price Work.

Such corrections are at the COR’s sole discretion.

C. Payment for tasks not specifically listed in Subsection 01 22 00 1.3:

1. All project costs are to be included in one of the 8 CLINs listed below. No extra payment will be made on the basis of a specific task not being listed in the CLIN descriptions in

Subsection 01 22 00 1.3.

1.3 BID ITEMS:

A. CLIN 1 – Mobilization.

1. Measurement of payment for Mobilization will be as described in Subsection 01 27 00

3.1.A.

2. The price of this CLIN may not exceed 10 percent of the original contract amount.

3. The Lump Sum price shall include:

a. Moving personnel, equipment, material and incidentals to the project and performing work necessary before starting work at the project site.

b. Obtaining permits.

c. Obtaining insurance.

d. Obtaining bonds.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 22 00 - 3

B. CLIN 2 – Open Cut Excavation and Point Repairs; CLIN 5 – Bid Option A: Open Cut

Excavation; CLIN 6 – Bid Option B: Open Cut Excavation.

1. Measurement of payment for open cut excavation and point repairs will be per linear foot of pipe furnished and installed, complete in place, measured along centerline of pipe, including fittings, excluding manholes and equipment.

2. The price for open cut excavation and point repairs shall include:

a. Allaying dust and mud, daily cleanup, erosion and sediment control, site restoration and cleanup, and stakeout and surveying.

b. Minor relocation of buried cables, gas lines, water lines, sewer lines, or similar utility lines 2 inches and smaller in diameter, pavement marking, and final surface restoration.

c. Sawcutting, removing, and disposing of pavement, sidewalks, curbs, and gutters.

d. Restoration of pavements, sidewalks, curbs, paved gutters, and landscaped areas.

e. Locating and protecting existing underground utilities.

f. Linear trench dewatering; including all labor, equipment, and materials necessary for dewatering.

g. Excavation to the limits shown on the Drawings, including all subsurface material not covered under other bid/pay items; stockpiling and handling of materials;

proper disposal of excess excavated materials; handling and proper disposal of groundwater; and support of excavations.

h. Preparation of excavation for piping installation.

i. Providing pipe of the size, material, wall thickness or class, and joint type indicated; gaskets; jointing; connections to existing piping and facilities shown;

and specified source quality control. Install piping on continuous downward slope as shown on the Drawings.

j. Performing specified field quality control. When not expressly indicated otherwise in the Contract Documents, at minimum, required field quality control shall include successfully completing the following:

1) Verifying alignment and elevation.

2) Visual observation prior to backfilling.

3) Vacuum testing.

4) Mandrel testing.

5) Lamping.

k. Providing specified bedding material, to not less than the limits shown on the

Drawings or indicated in the Contract Documents.

l. Providing and backfilling with imported backfill in excavations in paved areas, other areas subject to vehicular traffic, or areas over which building or structure will be located; in such excavations, provide materials for and backfill with indicated material up to bottom of pavement base or bottom of building footing and slab, as applicable.

m. Backfilling with imported backfill in excavations not in pavement or other travelled areas unless shown otherwise.

n. Compaction and testing of subgrade and backfill.

o. Providing specified pipeline identification materials and devices.

p. Pre and/or post television inspection for sewer pipe replacement, sewer pipe rehabilitation, or point repairs.

q. Bypass pumping, in accordance with Specification Section 33 32 00.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 22 00 - 4

r. Traffic control, if required.

s. Testing.

t. Tracer wire and marking tape, complete in place.

u. Replacement of manholes, as noted in the Summary of Work, in accordance with the measurement and payment for CLIN 5.

v. Other Work necessary, shown, and indicated for providing the required sewer in place, and complete, not included under other bid/pay items.

3. Payment: Unit price per linear foot for this item will be full compensation for all buried gravity sewer pipe of the indicated size, material, wall thickness or class, and joint type, with all related Work performed under this item, complete in accordance with the

Contract Documents, and not specifically included under other bid/pay items or contracts.

C. CLIN 3 – Pipe Bursting.

1. Measurement for payment of pipe bursting shall be from center of manhole to center of manhole.

2. The price per linear foot of pipe bursting shall include:

a. Debris collection and disposal.

b. Dewatering.

c. All labor, materials, and equipment.

d. Elimination of sags, if encountered.

e. Erosion and sediment control.

f. Replacement of manholes on each end of the pipe being burst (for access pits).

g. Fittings.

h. Ingress and egress procedures, (in accordance with all notes and provisions on the

Drawings).

i. Bypass pumping, in accordance with Specification Section 33 32 00.

j. Pipeline cleaning.

k. Pre- and post-television inspection.

l. Re-instatement of service connections.

m. Removal of protruding service connections.

n. Required compliance tests.

o. Replacement of pavement and restoration of areas damaged by pipe bursting activities, such as heaves, sags, etc.

p. Replacement pipe (HDPE).

q. Root removal.

r. Site cleanup and restoration.

s. Testing.

t. Traffic control, if required.

D. CLIN 4 – Manhole Repair/Lining.

1. Measurement for payment of manhole repairs will be made for each repair as noted on the Drawings.

2. The price per manhole repair shall include:

a. All labor, materials, tools, and equipment required for the specific repair as noted on the Drawings.

b. Safety equipment.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 22 00 - 5

c. Bypass pumping, in accordance with Specification Section 33 32 00.

d. Traffic control, if required.

3. Measurement for payment for manhole lining will be made for each successful manhole liner installed.

4. The price per manhole lining shall include:

a. All labor, materials, tools, and equipment required for coating/liner installation.

b. Surface preparation.

c. Equipment necessary for the mixing and application of all coating/liner materials.

d. Sealing of all surfaces including walls, chimney, inverts, and benches.

e. Root removal, repair of existing surfaces as required for coating/liner.

f. Coating/liner application.

g. Final cleaning of concrete surfaces.

h. Safety equipment.

i. Bypass pumping, in accordance with Specification Section 33 32 00.

j. Testing recommended by the coating/lining manufacturer.

k. Traffic control, if required.

E. CLIN 7 – Bid Option C: Manhole Replacement.

1. Measurement for payment of manholes will be made for each manhole installed and satisfactorily tested.

2. The price per manhole replacement shall include:

a. All appurtenances required for satisfactory operation.

b. Backfill.

c. Bedding.

d. Compaction.

e. Dewatering, including all labor, equipment, and materials necessary for dewatering.

f. Bypass pumping, in accordance with Specification Section 33 32 00.

g. Disposal of surplus material.

h. Excavation to the limits shown on the Drawings, including all subsurface material not covered under other bid/pay items; stockpiling and handling of materials;

proper disposal of excess excavated materials; handling and proper disposal of groundwater; and support of excavations.

i. Removal and disposal of existing manhole.

j. Inside or outside drop connection including drop pipe, fittings, attachments, and concrete.

k. Manhole, complete including benches, inverts and troughs, frame and cover, and riser (as required).

l. Steps.

m. Invert shaping.

n. Sheeting and shoring.

o. Testing.

p. Traffic control, if required.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 22 00 - 6

F. CLIN 8 – Bid Option D: Cured-In-Place Pipe (CIPP) Lining and Sectional Lining.

1. Measurement of payment for CIPP lining and sectional lining will be the actual distance measured along the centerline of the pipe. The CIPP lining distance will be measured from centerline to centerline for manhole-to-manhole installations, of each size pipe, excluding manhole diameter. For sectional lining, the liner will be measured along the centerline of the pipe from the beginning of the liner to the termination point of the liner.

2. The price per linear foot of CIPP and sectional liner shall include:

a. Debris collection and disposal.

b. Infiltration control.

c. Ingress and egress procedures (in accordance with all notes and provisions on the

Drawings).

d. Removal of intruding services, if required.

e. Manhole invert reshaping, if required.

f. All labor, materials, and equipment.

g. Bypass pumping, in accordance with Specification Section 33 32 00.

h. Pipeline cleaning.

i. Pre-, post-, and warranty television inspection.

j. Re-instatement of service connections.

k. Removal and replacement of manhole frames and covers as necessary.

l. Sealing at manholes.

m. Sediment and root removal.

n. Site cleanup and restoration.

o. Temporary service to affected properties.

p. Testing.

q. Traffic control, if required.

PART 2 - PRODUCTS - (NOT USED)

PART 3 - EXECUTION - (NOT USED)

END OF SECTION

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 26 01 - 1

YELL - 311631 CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager (PM), Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 26 01 - 2

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General

Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker.

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare

3) Workers Compensation – Policy and company calculation to be made available.

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.

REPLACE MAMMOTH WASTEWATER COLLECTION SYSTEM 01 26 01 - 3

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally…