About this file
This document is a Contract Price Schedule Template for a National Park Service (NPS) project to rehabilitate the Hurricane Ridge Water System at Olympic National Park. The solicitation (Number 140P8325R0005) outlines a pricing structure with five contract line items (CLINs), including three base line items and two optional items. The base line items cover Water Distribution System Replacement, Water System Controls, and Water Storage Tank Rehabilitation, each priced as a lump sum. The optional items include Demolition (Option A) and Remote Monitoring (Option B), also priced as lump sum items. Offerors are required to submit pricing for all base line items, with a warning that failure to do so may render the proposal unacceptable. The template provides specific instructions for pricing, such as providing total prices for lump-sum items and unit prices for unit-priced items, with provisions for handling calculation errors.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Price Schedule Template National Park Service (NPS) -
Solicitation Number:
PARK - PMIS: OLYM - 306966 & 307067
(Project Management Information System)
Developed Area: Olympic National Park
Project Title: Rehabilitate Hurricane Ridge Water System
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars.
Contract Line
Item Number
(CLIN)
Contract Line Item (CLI) Title Quantity Unit of Measure Unit Price Total Price
1 Water Distribution System Replacement 1 Lump Sum
2 Water System Controls 1 Lump Sum
3 Water Storage Tank Rehabilitation 1 Lump Sum
TOTAL BASE PRICE (Contract Line Item Number 1 through 3) ---------------------------------------------------------------------------------
4 OPTION A, (Demolition) 1 Lump Sum
5 OPTION B, (Remote Monitoring) 1 Lump Sum
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 4 through 5) -----------------------------------------------------------
TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 5) --------------------------
All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items.