B11_Site_Visit_Q_A_0002.docx

DOCX document 1 MB Posted

Attached to
Olympic NP - REHAB HURRICANE RIDGE WATER
Solicitation number
140P8325R0005
Issued by

About this file

This document is a Site Visit Questions and Answers (Q&A) file for Solicitation 140P8325R0005, a project to rehabilitate the Hurricane Ridge Water System at Olympic National Park. The solicitation involves water system infrastructure work, with key details including demolition of a lower intake dam, temporary water service installation, and site-specific operational considerations. The project has critical timeline constraints, with demolition work required between August 1 and Labor Day during the "dry" season, and anticipated contract award by the end of July 2025.

The Q&A addresses technical specifications, site access protocols, and project logistics, including specific guidance on navigating park entrance procedures during construction, water demand expectations, and scheduling limitations. Contractors are advised to schedule deliveries before 10 am, can request line bypasses at the entrance station during heavy traffic, and must adhere to road closure restrictions. The park will provide a park radio and contact information for entrance station coordination. The project involves working with existing water infrastructure, including capping water mains, managing temporary water services for trailers, and removing non-native materials from the site, with recognition of challenging work conditions from November through April due to weather constraints.

View the file

Other files

File Type Posted
Sol_140P8325R0005_Amd_0004.pdf PDF
Final_Questions_NPS_Responses_0004.xlsx XLSX spreadsheet
B09_questions_1_7-_6_5_25_0003.docx DOCX document
Sol_140P8325R0005_Amd_0003.pdf PDF
Sol_140P8325R0005_Amd_0002.pdf PDF
A06_Specifications_OLYM_PMIS_306966-307067_Signed_100__Final_0002.pdf PDF
B11_Site_Visit_Sign-in_0002.docx DOCX document
B08_2024_Construction_RFP_Clauses_5_13_2025_0001.pdf PDF
Sol_140P8325R0005_Amd_0001.pdf PDF
A06_Attachment_C_-_Fire_Hydrant_Assembly.pdf PDF
A07_Plans_OLYM_PMIS_306966-307067_22x34_Signed_100__Final_attachment_2.pdf PDF
B08_Project_Experience_Questionnaire_Attachement__7.docx DOCX document
B08_Contract_Price_Schedule_OLYM_Final_attachment_3.pdf PDF
A06_Specifications_OLYM_PMIS_306966-307067_Signed_100__Final_attachment_1.pdf PDF
B08_Offeror_s_representations_and_certificates_to_be_provided_with_proposal_Attachment__9.pdf PDF
B08_PAST_PERFORMANCE_QUESTIONNAIRE_Attachememt___6.docx DOCX document
B08_Limitations_on_Subcontracting_Worksheet_Attachment_8.xlsx XLSX spreadsheet
B08_Hurricane_Ridge_Water_Rehab_Photos_attachment.pdf PDF
Sol_140P8325R0005.pdf PDF
A03_-_Construction_Contract_Administration_attachment___5.docx DOCX document
B03_WA20250044_01_03_2025_SAM_Attachment_4.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P8325R0005 Rehabilitate Hurricane Ridge Water System 5/29/2025 Site Visit Q&A

1. Are there any technical specifications for this solicitation?

YES! The original solicitation posting only included the Division 1 specifications. A new file including all technical specifications is being posted under Amendment 0002.

2. Are COVID-19 vaccines required for workers on this project?

Contractors working on federal construction contracts are no longer required to ensure their employees are vaccinated against COVID-19 as a condition of federal contracts. The federal government has ceased enforcement of the mandate, and agencies should not be including vaccination clauses in new contracts or solicitations.

3. When the Hurricane Ridge parking lot is full, the entrance station begins to enforce a one-car-out, one-car-in policy, which can result in a long line and wait at the entrance station. Can this line be bypassed during construction?

Contractors are encouraged to schedule deliveries and arrange for employees to be onsite prior to 10 am to avoid delays associated with waiting in line. However, Contractors will be issued a park radio and provided contact information for the entrance station such that if the line of traffic is unavoidable (typically considered 25 or more cars in the queue), Contractors may contact the entrance station identifying themselves as entering on official business at the back of the line requesting a bypass. Once the ranger on the phone or radio indicates that traffic is being held and it is safe to bypass, proceed cautiously up the outbound lane until past the entrance station. Use flashers and be on the lookout for any cars that may be turning around from the line into your lane of travel. Don’t exceed 10 miles per hour.

4. For demolition of the lower intake dam, can you confirm that concrete may be left onsite?

In accordance with Key Notes 10 on drawing sheet C05, concrete material from the lower dam may remain onsite to weather in place. However, all non-native material (e.g., rebar) associated with the partial dam deconstruction shall be removed from the site.

5. For the proposed temporary water service plan (drawing sheet G01, General Notes 19), can you provide more detail on how and where to cap the 6-inch AC distribution main?

See photo below for information on where the 1.5” HDPE water service line for the temporary trailers connects to existing pipe. The C900 PVC pipe received a saddle tap for new 1.5” HDPE water line service to the temporary trailers during modifications completed in 2023. This water line drops down the hill from the saddle tap and runs east between the sidewalk and the fire hydrant. NPS installed a new 6” valve in the C900 PVC main west of the saddle tap. Contractor may cut and cap 6-inch C900 PVC pipe (instead of AC pipe) east of the new 1.5” HDPE service line saddle tap to establish temporary water service in accordance with the proposed plan description referenced above.

Pipe segment that received a 1.5” service line saddle tap for temporary trailers and 6” shut-off valve during modifications in November 2023

6. What should we expect for typical water demand at the temporary trailers, and how much does this fluctuate month-to-month?

Potable water service was restored to Hurricane Ridge in May 2024, so the park only has a single year of data operating with the temporary trailers (in lieu of the Hurricane Ridge Day Lodge); see graphs above. Note that from June through September, water production serves both the temporary trailers as well as the two comfort stations located out Hurricane Hill Road. Wastewater flow is only generated by the temporary trailers and does not include wastewater from the comfort stations, which each have a dedicated septic system. Thus wastewater flow may be more representative of actual water demand at the temporary trailers. Note that data in the graphs above are averaged by month and peak days within a month (especially holiday weekends) may be significantly higher than the average daily demand by month.

7. There are various references throughout the Division 1 specifications and in the solicitation to key milestone dates that have passed, as well as conflicting information on the period of performance. What dates/milestones are still relevant, and how much flexibility can we request with the period of performance if key items have long lead times that make it impossible to complete the project in 2025?

Given the current project timeline, we now anticipate making a contract award before the end of July 2025. Demolition work associated with Option A still needs to occur between August 1 and Labor Day, i.e. the “dry” season. Partial closures of roads or parking between July and Labor Day will be limited to emergency or unusual circumstance only. Partial closures of roads (including Monday through Thursday weekday closures of Hurricane Hill Road) and parking will be allowed with approval of the Contracting Officer after Labor Day. Contractor’s proposed schedule shall reflect these milestones and closure limitations. Documentation of long lead items that impact project schedule should be included with the project schedule if a significant portion of the work is delayed until 2026. Note that weather generally creates challenging onsite work conditions from November through April each year.

Hurricane Ridge Water System ID# NP3904 - Water Production

2016 January February March April May June July August September October November December 2024 January February March April May June July August September October November December 3914.5962500000001 5663.7039999999997 8246.0235483870965 6286.7145161290318 4919.6263333333327 2767.2945161290322 2288.4536666666668 1887.3432258064515 2025 January February March April May June July August September October November December 1753.2393548387097 3143.5646428571426 3291.9687096774192 2919.0623333333333 2584.6129032258063 2017 January February March April May June July August September October November December 1775.8709677419354 1377.9642857142858 282.7967741935484 0 3702.0967741935483 6008.6 11162.741935483871 9102.7419354838712 7068.7 2332.7096774193546 332.16666666666669 1288.5483870967741 2018 January February March April May June July August September October November December 993.87096774193549 821.53571428571433 1344.0967741935483 967.5333333333333 4699.4193548387093 7736.1333333333332 11242.677419354839 9188.1290322580644 6099.7 2684.516129032258 869.36666666666667 30.35483870967742 2019 January February March April May June July August September October November December 355.93548387096774 867.17857142857144 1315.5483870967741 1320.2 4542.4838709677415 6966.0333333333338 10053.290322580646 9232.2258064516136 6071.3 1686.4516129032259 1428.4 1136.6129032258063 2020 January February March April May June July August September October November December 1035.2903225806451 1682.7931034482758 425.25806451612902 0 0 3485.7666666666669 14253.870967741936 20536.516129032258 17605.2 5208.6451612903229 718.3 504.93548387096774 2021 January February March April May June July August September October November December 1403.3548387096773 1164.2142857142858 103.19354838709677 1705.6666666666667 3827.7741935483873 8680 18959.16129032258 14218.241935483871 8963.8611111111131 4562.0537634408602 0 2792.4193548387098 2022 January February March April May June July August September October November December 2186.7096774193546 3440.6071428571427 2143.6451612903224 4807.666666666667 11774.838709677419 9350.0666666666675 11756.258064516129 11538.612903225807 5367.1733333333332 2359.4309677419355 41.195999999999998 3181.4164516129035 2023 January February March April May June July August September October November December 1156.8867741935483 1074.152142857143 599.14032258064515 272.23366666666664 Average Daily Water Production (GPD)

Hurricane Ridge LOSS CLM045 - Wastewater Flow (Temporary Trailers Only)