B08_Attachment_8_TORFQ_Task_Order_00001.docx

DOCX document 43 KB Posted

Attached to
OTWSC Construction and Maintenance IDIQ
Solicitation number
140G0126Q0018
Issued by

About this file

This is a Task Order Request for Quote (RFQ) for construction and maintenance services at a stream gage site. Task Order 0001 is for the Whitsett Stream Gage Site (USGS site number 08208000) and represents a firm fixed-price project with an estimated value under $25,000. The contractor must submit pricing for the complete job as a single line item (CLIN 0001), along with a detailed cost breakdown covering labor, supervision, engineering, design, materials, equipment, tools, parts, supplies, and transportation. Work must commence within 10 calendar days of receiving the notice to proceed and be completed within 120 calendar days of task order award, including final site cleanup.

The task order is issued under a Department of Interior, U.S. Geological Survey (USGS) Oklahoma-Texas Water Science Center IDIQ contract (Solicitation Number 140G0126Q0018) that is set-aside for 100% small business concerns under NAICS code 237990 with a $45 million size standard. Contractors must maintain liability insurance of at least $100,000 per person for Workers' Compensation and Employers' Liability and $500,000 per occurrence for General and Bodily Injury Liability, with $500,000 for property damage. An acceptable insurance certificate must be provided prior to beginning work. The detailed Statement of Work and DOL Wage Determination are provided as attachments.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

THIS INFORMATION GOES IN BLOCK 10 OF THE SF 1442:

This information is provided for the following project: Task Order 0001 – Whitsett Stream Gage Site (08208000)

SECTION B – PRICE SCHEDULE

B.1. Propose your best prices for each of the work items in accordance with the Statement of Work (SOW) and attachments. Price must be submitted following the price schedule/format herein. Incomplete price submissions will not be considered for award.

CLIN
DESCRIPTION
UNIT
UNIT PRICE
TOTAL FFP PRICE
0001
Task Order 0001 – Whitsett Stream Gage Site (08208000)
1 Job
$
$_____________

SECTION B – PRICE BREAKDOWN

Contractor shall provide a breakdown of labor, supervision, engineering, design, materials, equipment, tools, parts, supplies, and transportation to perform the services described in the drawings and specifications for each individual task order. Format is to be determined by the Contractor.

SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1. Disclosure of the magnitude of construction projects. In accordance with FAR 36.204, the estimated price range of this project is:

(a) Less than $25,000.

* Please refer to Section J of this solicitation for additional scoping documents.

SECTION D – PACKAGING AND MARKING

* Please refer to the IDIQ for requirements related to this section.

SECTION E – INSPECTION AND ACCEPTANCE

* Please refer to the IDIQ for requirements related to this section.

SECTION F – DELIVERIES OR PERFORMANCE

F.1. FAR 52.211-10 Commencement, Prosecution, and Completion of Work (April 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days after award of the task order. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

* Please refer to the IDIQ for all additional requirements related to this section.

SECTION H – SPECIAL CONTRACT REQUIREMENTS

* Please refer to the IDIQ for all additional requirements related to this section.

SECTION I – CONTRACT CLAUSES

I.3. DIAR 1452.228-70 LIABILITY INSURANCE – DEPARTMENT OF THE INTERIOR (JULY 1996)

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

$_100,000.00__each person, Workers Compensation and Employers’ Liability Insurance

$_500,000.00__each occurrence, General Liability Insurance, Bodily Injury Liability Insurance

$_500,000.00__property damage

(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.

SECTION J – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

NO.
TITLE OF DOCUMENT OR FORM
NO. OF PAGES
TASK ORDER 0001 STATEMENT OF WORK
9
DOL WAGE DETERMINATION
5

SECTION K – REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

All representations, certifications, and other statements made at the IDIQ level.

* Please refer to the IDIQ for all additional requirements related to this section.

SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS

* Please refer to the IDIQ for all additional requirements related to this section.

SECTION M – EVALUATION FACTORS FOR AWARD

END OF TASK ORDER REQUEST FOR QUOTE