B08__Attachment_6_Cost_Proposal_Form_(257195_EISE).xlsx

XLSX spreadsheet 62 KB Posted

Attached to
HPTC ROOF REPLACEMENT ON EISENHOWER HOME Federal contract opportunity
Solicitation number
140P2123R0023
Issued by
Department of the Interior National Park Service

About this file

This document contains a cost proposal form and line item cost summary for a roof replacement project at Eisenhower National Historic Site. The cost proposal form provides material, installation, and total costs for various line items involved in the project, including exterior enclosure, roofing, special construction, selective demolition, and special use elements. However, all cost values are currently listed as errors, indicating the form requires additional information to be populated. The related federal contract opportunity is solicitation number 140P2123R0023 from the Department of the Interior National Park Service for an HPTC roof replacement on the Eisenhower Home. No further details are provided on response dates, award dates, pricing terms, or set asides.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Cost Summary

Project:Eisenhower N.H.S Roof ReplacementEstimate By:
Park:Eisenhower National Historic SiteDate:
Reviewed By:
Date:
Asset / Project ElementSize/CountUnits
Asset / Project Element Name37Unit
Item No.WBSDescriptionMaterial Cost/UnitTotal Material CostInstallation Cost/UnitTotal Install CostDirect Cost/UnitTotal Direct CostsNET Cost/UnitTotal NET Costs
4B20Exterior Enclosure$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0ERROR:#REF!ERROR:#REF!
5B30Roofing$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0ERROR:#REF!ERROR:#REF!
16F10Special Construction$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0ERROR:#REF!ERROR:#REF!
17F20Selective Building Demolition$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0ERROR:#REF!ERROR:#REF!
23XXSpecial Use - 1$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0ERROR:#REF!ERROR:#REF!

Subtotal Direct Construction Costs $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $0 ERROR:#REF! ERROR:#REF!

Direct Cost Subtotal without GFP .$ - 0$ - 0$0
Remoteness Factor$0
State & Local Taxes$0
Total Direct Construction Costs$0
General & Adminstration Costs$0
Historic Preservation Factor$0
Subtotal NET Construction Cost$0
Overhead$0
Profit$0
Estimated NET Construction Cost$0
Bonds & Permits$0
Contracting Method Adjustment$0
Inflation EscalationMonthsAnnual Rate =0.00%Inc. Bonds & CMAERROR:#REF!
Total Estimated NET Cost of ConstructionERROR:#REF!

&"Arial,Bold"United States Department of the Interior National Park Service Class B Construction Cost Estimate&4 &"Arial,Regular" &"Arial,Bold"&13PROJECT COST SUMMARY

&6&F &A Page &P of &N &6Print Date: &D, &T

B20 - Exterior Enclosure

Summary Item B20 Exterior Enclosure Total Cost: $0

Uniformat II WBS CodeDescriptionQuantityUnitMATERIALINSTALLATIONTOTALS
Material Cost/UnitTotal Material CostInstall Cost/UnitTotal Install CostTotal Cost/UnitTotal Cost
B2010EXTERIOR WALLS
Basic RequirementWood connectors20e
Basic RequirementSteel nails for air nailers, 2500, 16D1e
Basic RequirementSteel nails for air nailers, 2500, 10D2e
Basic RequirementSteel nails for air nailers, 2500, 8D1e
Basic RequirementInstall new blocking, flashing and transition30sq ft
Basic Requirementsurface prep, exterior, painting30sq ft
Basic RequirementPre formed joint seals6CLF
SUBTOTALEXTERIOR WALLS37Unit$ - 0$0$ - 0$0$ - 0$0
Summary ItemB20Exterior Enclosure
Uniformat II WBS CodeDescriptionQuantityUnitMATERIALINSTALLATIONTOTALS
Material Cost/UnitTotal Material CostInstall Cost/UnitTotal Install CostTotal Cost/UnitTotal Cost

B20 Exterior Enclosure 37 Unit $ - 0 $0 $ - 0 $0 $ - 0 $0

Class B Construction Cost Estimate&8 (expanded)&6

&12LINE ITEM COST SUMMARY

&6&F, &A &9&P of &N &6&D &T

B30 - Roofing

Summary Item B30 Roofing Total Cost: ERROR:#REF!

Uniformat II WBS CodeDescriptionQuantityUnitMATERIALINSTALLATIONTOTALS
Material Cost/UnitTotal Material CostInstall Cost/UnitTotal Install CostTotal Cost/UnitTotal Cost
B3010ROOF COVERINGS
Basic RequirementSlate Roof Shingles64sq
Basic RequirementInstallation of wood shingles64sq
Basic RequirementFlashing copper 16 oz sheets305SF
Basic RequirementCut flashing88sf
Basic RequirementRoofing Felt64sq
Basic RequirementSheathing plywood CDX 5/8"3200sq ft
Basic Requirementpreformed joint seals6Unit
Basic Requirementnails, material only, vinyl coated sinkers100lb
SUBTOTALROOF COVERINGS37Unit$ - 0$0$ - 0$0$ - 0$0

Class B Construction Cost Estimate&8 (expanded)&6

&12LINE ITEM COST SUMMARY

&6&F, &A &9&P of &N &6&D &T

F10 - Special Construction

Summary Item F10 Special Construction Total Cost: $0

Uniformat II WBS CodeDescriptionQuantityUnitMATERIALINSTALLATIONTOTALS
Material Cost/UnitTotal Material CostInstall Cost/UnitTotal Install CostTotal Cost/UnitTotal Cost
F1010SPECIAL STRUCTURES
Basic RequirementScaffolding, rental, assemble, disassemble1Unit
Basic Requirementaerial lift truck, 60ft boom - rental30day
Basic RequirementTemp fencing, safety fence, heavy duty/Protection barrier2000LF
Basic RequirementPortable toilet4wk
SUBTOTALSPECIAL STRUCTURES37Unit$ - 0$0$ - 0$0$ - 0$0
Summary ItemF10Special Construction
Uniformat II WBS CodeDescriptionQuantityUnitMATERIALINSTALLATIONTOTALS
Material Cost/UnitTotal Material CostInstall Cost/UnitTotal Install CostTotal Cost/UnitTotal Cost

F10 Special Construction 37 Unit $ - 0 $0 $ - 0 $0 $ - 0 $0

Class B Construction Cost Estimate&8 (expanded)&6

&12LINE ITEM COST SUMMARY

&6&F, &A &9&P of &N &6&D &T

F20 - Selective Demolition

Summary Item F20 Selective Building Demolition Total Cost: $0

Uniformat II WBS CodeDescriptionQuantityUnitMATERIALINSTALLATIONTOTALS
Material Cost/UnitTotal Material CostInstall Cost/UnitTotal Install CostTotal Cost/UnitTotal Cost
F2010BUILDING ELEMENTS DEMOLITION
Basic RequirementSelective demo, rubbish handling, dumpster, 5 ton capacity4wk
Basic Requirementthermal/moisture protection, flashing, sheet metal removal350SF
Basic Requirementroofing, removal of shingles64sq
Basic RequirementSheathing removal3200sq ft
SUBTOTALBUILDING ELEMENTS DEMOLITION37Unit$ - 0$0$ - 0$0$ - 0$0
Summary ItemF20Selective Building Demolition
Uniformat II WBS CodeDescriptionQuantityUnitMATERIALINSTALLATIONTOTALS
Material Cost/UnitTotal Material CostInstall Cost/UnitTotal Install CostTotal Cost/UnitTotal Cost

F20 Selective Building Demolition 37 Unit $ - 0 $0 $ - 0 $0 $ - 0 $0

Class B Construction Cost Estimate&8 (expanded)&6

&12LINE ITEM COST SUMMARY

&6&F, &A &9&P of &N &6&D &T

Special Use- 1

Summary Item XX Special Use - 1 Total Cost: $0

Uniformat II WBS CodeDescriptionQuantityUnitMATERIALINSTALLATIONTOTALS
Material Cost/UnitTotal Material CostInstall Cost/UnitTotal Install CostTotal Cost/UnitTotal Cost
BASE CODEBASE ELEMENT
Basic RequirementField Personal, Safety2wk
Basic RequirementField Personal, Superintendent8wk
Basic RequirementDaily Cost Crew Per diem (Federal rate)60days
Basic RequirementDaily Cost Crew Food diem (federal rate)60days
Basic RequirementField Personal, Quality Control/Enginner8wk
SUBTOTALBASE ELEMENT37Unit$ - 0$0$ - 0$0$ - 0$0
Summary ItemXXSpecial Use - 1
Uniformat II WBS CodeDescriptionQuantityUnitMATERIALINSTALLATIONTOTALS
Material Cost/UnitTotal Material CostInstall Cost/UnitTotal Install CostTotal Cost/UnitTotal Cost

XX Special Use - 1 37 Unit $ - 0 $0 $ - 0 $0 $ - 0 $0

Class B Construction Cost Estimate&8 (expanded)&6

&12LINE ITEM COST SUMMARY

&6&F, &A &9&P of &N &6&D &T

File details come from the government source that posted it. Updated .