B08_Attachment_4_Example_Task_Order_Deliverable_Timeline_and_Payment_Schedule.xlsx
XLSX spreadsheet 28 KB Posted
- Attached to
- Prospectus Develpment IDIQ Firm Fixed Price
- Solicitation number
- 140P2125Q0008
About this file
This file is a detailed deliverable timeline and payment schedule spreadsheet for a National Park Service (NPS) concessions contract development project running from April 2025 to December 2026. The timeline breaks down 10 major tasks: Project Planning, Market Analysis, Rate Comparability Study, Personal Property Valuation, Financial Investment Analysis, Initial Prospectus Development, Roundtable Meeting, Final Prospectus Documents, Panel Support, and Additional Scenario Analysis (optional).
The schedule includes specific payment percentages tied to deliverables within each task, with major milestones including a site visit (Task 1, 75% payment), market analysis report (Task 2, 75% for draft), personal property valuation report (Task 4, 70% for draft), and financial investment analysis (Task 5, multiple payments). The timeline incorporates review periods by NPS, typically 2-4 weeks per deliverable, and includes both virtual and in-person meetings. Optional travel components are noted for scenario meetings and panel evaluations. Each task has specific deliverable requirements including reports, Excel workbooks, presentations, and memos, with clearly defined turnaround times ranging from 5 to 20 business days.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Example Deliverable Timeline
| Task Name | Deliverable Type | Payment Schedule (% based per task) | Start Date | End Date | Duration (weeks) | Deliverable Timing |
| Project Planning | ||||||
| Task 1: Planning and Due Diligence | ||||||
| Introductory Meeting | Virtual Meeting | Monday, April 21, 2025 | Friday, April 25, 2025 | 1 | 1-2 hour call occurs within 2 weeks (10 business days) of task order award. | |
| Draft Advanced Information Request (AIR), Daily Fieldwork Schedule, Site Visit Presentation/Agenda | Memo and Presentation | 20% | Monday, April 28, 2025 | Friday, May 02, 2025 | 1 | The consultant will submit the AIR, cover letter, and Daily Fieldwork Schedule within 1 week (5 business days) after the Introductory Meeting. |
| NPS Review of AIR, Fieldwork Schedule, and Site Visit Presentation/Agenda | Monday, May 05, 2025 | Friday, May 09, 2025 | 1 | 1 week (5 business days) to review the draft AIR, fieldwork schedule and site visit presentation/agenda. | ||
| Final AIR and Fieldwork Schedule | Memo and Presentation | 5% | Monday, May 12, 2025 | Friday, May 16, 2025 | 1 | The consultant will have 1 week (5 business days) to incorporate NPS comments, issue a final Daily Fieldwork Schedule and Presentation/Agenda, and send the AIR and cover letter to existing concessioner. |
| Site Visit w/ Fieldwork Kick-off Presentation | Meeting/Presentation | 5% | Monday, May 19, 2025 | Friday, May 23, 2025 | 1 | The consultant will incorporate NPS comments and be prepared to present the finale at the kick-off meeting. |
| Site Visit Exit Briefing | Meeting/Presentation | 75% + travel | Monday, May 19, 2025 | Friday, May 23, 2025 | 1 | This can be done onsite or remotely on a later date if needed. The consultant will provide a copy to the COR. |
| NPS/Concessioner AIR Response | Monday, May 26, 2025 | Friday, June 13, 2025 | 3 | The consultant will submit information collected from the AIR, 3 weeks (15 business days) following the Fieldwork Exit Briefing. | ||
| Task 2: Market Analysis | ||||||
| Draft Market Analysis | Report | 75% | Monday, May 26, 2025 | Friday, June 20, 2025 | 4 | The consultant will submit the Draft Market Analysis 4 weeks (20 business days) following the Fieldwork Exit Briefing (Task 1). |
| NPS Review of Draft Market Analysis | Monday, June 23, 2025 | Friday, July 18, 2025 | 4 | 4 weeks (20 business days) to review the Draft Market Analysis. | ||
| Final Draft Market Analysis | Report | 25% | Monday, July 21, 2025 | Friday, August 01, 2025 | 2 | The consultant will have 2 weeks (10 business days) to incorporate NPS comments on the Draft Market Analysis and provide the final. |
| Task 3: Rate Comparability Study (optional) | ||||||
| Draft List of Potential Comparables | Memo | 5% | Monday, April 28, 2025 | Friday, May 09, 2025 | 2 | The consultant will have 2 weeks (10 business days) after the Introductory Meeting (Task 1) to deliver a Draft List of Potential Comparables. |
| NPS Review of Potential Comparables | Monday, May 12, 2025 | Friday, May 23, 2025 | 2 | 2 weeks (10 business days) to review the Potential Comparables | ||
| Draft Rate Study | Report | 75% | Monday, May 26, 2025 | Friday, June 20, 2025 | 4 | The consultant will submit the Draft Rate Study 4 weeks (20 business days) following the Fieldwork Exit Briefing (Task 1). |
| NPS Review of Draft Rate Study | Monday, June 23, 2025 | Friday, July 18, 2025 | 4 | 4 weeks (20 business days) to review the Draft Rate Study. | ||
| Final Rate Study | Report | 20% | Monday, July 21, 2025 | Friday, August 01, 2025 | 2 | The consultant will have 2 weeks (10 business days) to incorporate NPS comments and provide the Final Rate Study. |
| Task 4: Personal Property Valuation, Replacement Schedule, and Estimates | ||||||
| Draft Personal Property Valuation (PPV) Report and Draft Cost Estimates for Personal Property Improvements | Report and Excel Workbook | 70% | Monday, May 26, 2025 | Friday, June 20, 2025 | 4 | The consultant will submit the Draft PPV report within 4 weeks (20 business days) following the Fieldwork Exit Briefing (Task 1, including a text narrative that describes all methodologies, data sources, and assumptions used. |
| NPS Review of Draft PPV Report and Draft Cost Estimates for Personal Property Improvements | Monday, June 23, 2025 | Friday, July 18, 2025 | 4 | 4 weeks (20 business days) to review Draft PPV Repor and Cost Estimates. | ||
| Final PPV Report and Cost Estimates for Personal Property Improvements | Report and Excel Workbook | 30% | Monday, July 21, 2025 | Friday, August 01, 2025 | 2 | The consultant will have 2 weeks (10 business days) to incorporate NPS comments and return the final PPV. |
| Task 5: Financial Investment Analysis and Scernio Meeting | ||||||
| Pre Baseline Call | Virtual Meeting | 5% | Monday, August 04, 2025 | Friday, August 08, 2025 | 1 | The consultant must schedule and facilitate this call within 1 week (5 business days) of submitting the draft PP improvement cost estimates. NOTE: NPS should have CA and LSI data by this point. |
| Draft Baseline Buildup (Report and Financial Model) | Report and Excel Workbook | 30% | Monday, August 04, 2025 | Friday, August 15, 2025 | 2 | The consultant will provide the Baseline Buildup and the financial model at least 2 weeks (10 business days) after the delivery of the final Market Analysis. |
| NPS Review of Draft Baseline Buildup | Monday, August 18, 2025 | Friday, September 05, 2025 | 3 | 3 (15 business days) weeks to review Baseline Buildup and model. | ||
| Post Draft Baseline and Model Review | Virtual Meeting | 5% | Monday, August 18, 2025 | Friday, August 22, 2025 | 1 | The consultant will schedule this call within 1 week (5 business days) of the delivery of the Draft Baseline Buildup. |
| Final Baseline Buildup (Report and Financial Model) | Report and Excel Workbook | 10% | Monday, September 08, 2025 | Friday, September 12, 2025 | 1 | The consultant will have 1 week (5 business days) to incorporate NPS comments and deliver the final. |
| Draft Scenario Meeting Presentation (final being presented at the SM) | Presentation | 5% | Monday, September 15, 2025 | Friday, September 19, 2025 | 1 | The consultant will submit a PowerPoint presentation at least 1 week (5 business days) before the Scenario Meeting. |
| NPS Review of Draft Presentation | Monday, September 22, 2025 | Friday, September 26, 2025 | 1 | At least 3 days to review the draft presentation. | ||
| Scenario Meeting (SM) Attendance | Meeting/Presentation | 5% | Monday, September 29, 2025 | Friday, October 03, 2025 | 1 | The consultant will facilitate the meeting and present final PowerPoint. |
| Scenario Meeting Travel (optional) | Travel | travel cost | Monday, September 29, 2025 | Friday, October 03, 2025 | 1 | |
| Draft SM Analysis Executive Summary and Insurance Requirements Request Form | Memo | 10% | Monday, October 06, 2025 | Friday, October 17, 2025 | 2 | The consultant will submit an Executive Summary and the completed Insurance Requirements Request form 2 weeks (10 business days) after the Scenario Meeting. |
| NPS Review of Draft SM Analysis Executive Summary and Insurance Requirements Request Form | Monday, October 20, 2025 | Friday, October 31, 2025 | 2 | 2 weeks (10 business days) to review SM Executive Summary and Insurance Requirements Request Form | ||
| Final SM Analysis Executive Summary | Memo | 5% | Monday, November 03, 2025 | Friday, November 14, 2025 | 2 | The consultant will have 2 weeks (10 business days) to incorporate NPS comments on the draft executive summary report and deliver the final. |
| Draft Franchise Fee Analysis (FFA) | Report and Excel Workbook | 15% | Monday, November 03, 2025 | Friday, November 28, 2025 | 4 | The consultant will provide the draft FFA reportand all supporting documents (including spreadsheets, models, and analysis) 4 weeks (20 business days) after receiving NPS comments on the SM Executive Summary. |
| NPS Review of Draft FFA | Monday, December 01, 2025 | Friday, December 26, 2025 | 4 | 4 weeks (20 business days) to review the draft FFA and supporting docs. | ||
| Final FFA | Report and Excel Workbook | 5% | Monday, December 29, 2025 | Friday, January 09, 2026 | 2 | The consultant will have 2 weeks (10 business days) to incorporate NPS comments and provide the final FFA and all supporting documents. |
| PSF4 Panel Evaluation Forms | Excel Workbook | 5% | Monday, February 16, 2026 | Friday, February 27, 2026 | 2 | The consultant must deliver the PSF4 Panel Forms two weeks after receiving comments on the Draft 2 prospectus documents (task 7) |
| Task 6: Initial Prospectus Development Documents | ||||||
| Draft 1 Prospectus Documents | Documents | 100% | Monday, December 01, 2025 | Friday, December 12, 2025 | 2 | The consultant will submit draft 1 prospectus documents 2 weeks (10 business days) after submitting the draft FFA. |
tc={26606888-55AC-47D7-AA1F-13890B4A26DB}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
You may adjust the timing of this deliverable based on project team preference. You could have the documents delivered at the same time as the draft FFA or stagger the deliverable so they do not overlap at all.
| NPS Review of Draft 1 Prospectus Docs (Project Team) | Monday, December 15, 2025 | Friday, January 09, 2026 | 4 | 4 weeks (20 business days) for NPS/Project Team Review of Draft 1. | ||
| Task 7 Roundtable Meeting | ||||||
| Draft 2 Prospectus Documents | Documents | 40% | Monday, January 12, 2026 | Friday, January 23, 2026 | 2 | The consultant will have 2 weeks (10 business days) to incorporate NPS Draft 1 comments and provide a revised draft (Draft 2). |
| NPS Review of Draft 2 (RT Participants, Project Team, BCs) | Monday, January 26, 2026 | Friday, February 13, 2026 | 3 | 3 weeks (15 business days) to review Draft 2 prospectus docs. | ||
| Pre-roundtable Issues Memo and Meeting Agenda | Memo | 10% | Monday, February 16, 2026 | Friday, February 20, 2026 | 1 | 1 week for the consultant to clean up Draft 2 comments in preparation for RT meeting discussion and provide issues memo and agenda. |
| Roundtable Meeting Attendance | Meeting with Presentation | 40% | Monday, February 23, 2026 | Friday, February 27, 2026 | 1 | 1-2 days during this week. |
| Rountable Meeting Travel (optional) | travel cost | Monday, February 23, 2026 | Friday, February 27, 2026 | |||
| Post Roundtable Memo | Memo | 10% | Monday, March 02, 2026 | Friday, March 06, 2026 | 1 | The consultant will deliver the Post Roundtable Memo 1 week (5 business days) after the conclusion of the Roundtable. |
| Task 8: Final Prospectus Documents | ||||||
| Draft 3 Roundtable Prospectus documents (Post- Roundtable Documents) | Documents | 50% | Monday, March 09, 2026 | Friday, March 27, 2026 | 3 | After the Post-RT Memo is delivered, the consultant will make changes to the prospectus documents as needed within 3 weeks (15 business days). |
| NPS Review of Draft 3 Prospectus Documents (all NPS review BC,RC,SOL,Project Team) | Monday, March 30, 2026 | Friday, April 17, 2026 | 3 | 3 weeks (15 business days) for review of Draft 3. | ||
| Final (Draft 4) Prospectus Documents | Documents | 50% | Monday, April 20, 2026 | Friday, May 01, 2026 | 2 | The consultant will deliver "camera-ready" final (draft 4) documents incorporating NPS comments within 2 weeks (10 business days) of receiving draft 3 comments. |
| Task 9: Panel Support | ||||||
| Panel Evaluation (optional) | Meeting | 100% | Monday, December 07, 2026 | Friday, December 11, 2026 | 1 | 2-3 weeks to convene evaluation panel after receiving offers |
| Panel Travel (optional) | travel cost | Monday, December 07, 2026 | Friday, December 11, 2026 | |||
| Task 10: ADDITIONAL SCENARIO ANAYSIS (OPTIONAL) | ||||||
| ADDITIONAL SCENARIO ANAYSIS (OPTIONAL) | Meeting | 100% | TBD | TBD | ||
| TRAVEL TO THE SECOND SCENARIO MEETING (OPTIONAL) | travel cost | TBD | TBD |