B08_Attachment_4_-_Construction_Contract_Administration_Provision.pdf
PDF 104 KB Posted
- Attached to
- Lowell National Historical Park - REPLACE COOLING Federal contract opportunity
- Solicitation number
- 140P4326R0020
About this file
This document is a reference guide to Construction Contract Administration policies and procedures. The document cites Federal Acquisition Regulation (FAR) 36.211(b), which requires federal agencies to provide descriptions of their policies and procedures governing the definitization of equitable adjustments for change orders under construction contracts. The document also references requirements for agencies to provide data on the time required to complete the definitization process for equitable adjustments on construction contract change orders. The specific policies, procedures, and timeline data referenced in this requirement can be accessed through the Department of Interior's acquisition policy webpage at https://www.doi.gov/pam/acquisition/policy/constructioncontract. This document does not contain substantive contract requirements, solicitation details, or procurement specifications; it serves solely as a pointer to external resources where the detailed construction contract administration information is maintained.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P4326R0020_Amd_0002.pdf | ||
| B09-Amd0002-RFIs_1-9_0002.pdf | ||
| Attachment_6_-_Sign_in_sheet_-2_0001.pdf | ||
| Attachment_5_-_Sign_in_sheet-1_0001.pdf | ||
| Sol_140P4326R0020_Amd_0001.pdf | ||
| B03_Attachment_3_-_Davis_Bacon_Wage_Determination_MA20260001_(1).pdf | ||
| Sol_140P4326R0020.pdf | ||
| B08_Attachment_1_-_Scope_of_Work.pdf | ||
| B08_Attachment_2_-_Specifications_-_PMIS_337427.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Contract Administration
Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at:
https://www.doi.gov/pam/acquisition/policy/constructioncontract.
https://www.doi.gov/pam/acquisition/policy/constructioncontract