B08_Attachment_2_-_Specifications_-_PMIS_337427.pdf

PDF 16 MB Posted

Attached to
Lowell National Historical Park - REPLACE COOLING Federal contract opportunity
Solicitation number
140P4326R0020
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This is a project specification document for the replacement of cooling tower equipment and associated mechanical and electrical systems at Lowell National Historical Park's Boott Cotton Mill #6 facility. The work consists of three contract line items: (1) replacing the existing rooftop cooling tower #1 and associated valves at the Boott Cotton Mill; (2) installing one condenser pump and two circulator pumps with piping and valves; and (3) as an option, installing one additional circulator pump in an adjacent building's mechanical room. The cooling tower is a low-profile centrifugal type with a maximum operating weight of 6,820 pounds, meeting Baltimore Aircoil Model VTL-171-L specifications or approved equal. The project includes replacement of degraded two-way control valves (approximately 6), ball valves (approximately 24), butterfly valves (4), flexible joints, one automatic control valve, piping connections, and vibration isolation springs. All equipment must be integrated into the existing Trane Building Management System, with new variable frequency drives for motor control and field painting of the cooling tower in Benjamin-Moore charcoal slate color E-86.

Work must be performed during normal business hours (7:30 a.m. to 4:00 p.m., Monday through Friday) at the Boott Cotton Mill, a government-occupied building. The contractor is limited to two parking spaces within the courtyard, must provide its own porta-potty, and has restricted storage to the mechanical room. Primary access for personnel and removal of demolition materials is through the building interior stairs and roof hatch. The project requires coordination with the National Park Service, including security background checks for site supervisors before unescorted access, submission of comprehensive submittals within 30 days of contract award, and monthly progress schedule updates using NPS project management software. All work is subject to Davis-Bacon labor standards, compliance with OSHA requirements, and formal quality control and safety plans, with liquidated damages applicable for schedule delays. The contractor must also complete all necessary piping and electrical rough-in work, coordinate with electrical contractors for motor power connections, and comply with the park's environmental and waste management requirements, including recycling and source reduction goals.

View the file

Other files for this federal contract opportunity

Other files attached to Lowell National Historical Park - REPLACE COOLING, newest first.
File Type Posted
Sol_140P4326R0020_Amd_0002.pdf PDF
B09-Amd0002-RFIs_1-9_0002.pdf PDF
Attachment_6_-_Sign_in_sheet_-2_0001.pdf PDF
Attachment_5_-_Sign_in_sheet-1_0001.pdf PDF
Sol_140P4326R0020_Amd_0001.pdf PDF
B03_Attachment_3_-_Davis_Bacon_Wage_Determination_MA20260001_(1).pdf PDF
Sol_140P4326R0020.pdf PDF
B08_Attachment_1_-_Scope_of_Work.pdf PDF
B08_Attachment_4_-_Construction_Contract_Administration_Provision.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lowell National Historical Park

Replace Cooling Tower #1, Condenser and Circulator Pumps, and

Valves at Boott Cotton Mill #6

PMIS NO. 337427 A & C

Solicitation # __

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

LOWE – 337427 000110 - 1

TABLE OF CONTENTS

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work

01 26 01 Contract Modification Procedures

01 27 00 Definition of Contract Line Items

01 31 00 Project Management and Coordination

01 32 16 Construction Schedule

01 33 23 Submittal Procedures

01 35 23 Safety Requirements

01 40 00 Quality Requirements

01 42 00 References

01 50 00 Temporary Facilities and Controls

01 67 00 Product Requirements

01 73 29 Cutting and Patching

01 73 40 Execution

01 74 19 Construction Waste Management and Disposal

01 77 00 Closeout Procedures

01 78 23 Operation and Maintenance Data

DIVISION 02 - EXISTING CONDITIONS

02 41 19 Selective Demolition

DIVISION 15 – HVAC

15 6000 HVAC

DIVISION 16 – ELECTRICAL

16 0000 Electrical

PLANS Performance Engineering Plans

LOWE - 337427 01 11 00 - 1

SUMMARY OF WORK

DIVISION 1 SPECIFICATIONS

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Work Phases

3. Work Under Other Contracts

4. Government-Furnished Materials

5. Contractor Use of Site

6. Public Use of Site

7. Occupancy Requirements for Buildings

8. Conduct of Operations

9. Work Restrictions

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Boott Mill #6, 115 John Street, Lowell National Historical Park, Lowell, MA.

B. The Work consists of:

1. The work is for a cooling tower replacement on the roof of the fifth floor of the Boott

Cotton Mill #6. The project involves removing the existing rooftop cooling tower by crane

(placed at adjacent Bridge Street, requiring police detail for traffic control) and installing a new low-rise cooling tower on new vibration rails on a steel structure without disturbing the newly installed EPDM roof. Piping connections are to be made at the roof level and replace degraded connecting valves. This is one of two cooling towers for the building.

The roof does not have a parapet, so emphasis will be placed on the safety plan for the work. Work will include replacing variable frequency drives to the cooling tower system.

2. Work also includes replacing one 384 gpm 90’ head condenser pump and two 500 gpm 70’ head circulatory pumps that connect Chiller #1 (the chiller is not in this scope of work, but a separate contract will be implemented to rebuild it, and work could overlap) to the

Cooling Tower #1. Work also includes replacing degraded 6 two-way control valves, approx. 24 ball valves and flexible joints, 1 automatic control valve, 4 butterfly valves, approximately 16 lf of pipe and connections necessary to complete the connections, 3 sets of vibration springs and mounting to existing concrete pads. Electrical work shall include new conduit and wiring as necessary to tie in the new motors.

3. Option #1 is to replace one circulatory pump in the adjacent building basement mechanical room. Work will include adding variable frequency drive to the pump. Work includes replacing degraded 2 two-way control valves, 8 ball valves, 1 automatic control valve, 2

LOWE - 337427 01 11 00 - 2

butterfly valves, approximately 8 lf of pipe and connections necessary to complete the system, 1 set of vibration springs and mounting to existing concrete pad; and program the cooling tower and the pump to the Trane Building Management System. Electrical work shall include any new conduit and wiring.

4. Refer to the balance of Contract Specifications and Plans for complete Scope.

5. The cooling tower and the pumps shall be integrated into Trane Integrated Building

Systems controls and tested.

6. While not required, it is recommended to be present for the site visit during solicitation.

C. Project will be constructed under a single prime contract.

1.3 WORK PHASES

A. The Work shall be conducted in one phase in the following order, with each phase substantially complete before beginning next phase:

1. Phase One: Demolition and Work of this phase shall be substantially complete and ready for phase two, which will be any repairs necessary, then the installation of the new work as indicated on the drawings and the scope of work. These two phases shall run without interruption.

2. The remaining Work shall be substantially complete and ready for occupancy at time of

Substantial Completion.

1.4 WORK UNDER OTHER CONTRACTS

A. General: Cooperate with separate Construction Contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate

Work of this Contract with work performed under separate contracts.

B. Preceding Work: N/A.

C. Concurrent Work: The Chiller #1 rebuild could be concurrent or ahead of this project.

D. Future Work: N/A

1.5 GOVERNMENT-FURNISHED MATERIALS

A. In case of Government -furnished materials:

1. Government will arrange and pay for delivery of Government-furnished items according to Construction Contractor's Construction Schedule.

2. Construction Contractor is responsible for initial inspection, receiving, unloading, and handling Government-furnished items at Project site.

LOWE - 337427 01 11 00 - 3

3. Government will inspect delivered items for damage after delivery. Construction

Contractor shall be present for and assist in Government's inspection.

4. Government will arrange for replacement if Government-furnished items are damaged, defective, or missing.

5. Construction Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.

6. If Government-furnished items are damaged as a result of Construction Contractor's operations, Construction Contractor shall repair or replace them.

7. Construction Contractor shall install and otherwise incorporate Government-furnished items into Work.

B. Government-Furnished Materials:

1. Government is not providing any furnished materials.

1.6 CONSTRUCTION CONTRACTOR USE OF SITE

A. General: Construction Contractor shall have full use of the site for construction operations during the construction period. Construction Contractor's use of the site is limited only by the

Government's right to perform work or to retain other Construction Contractors on portions of

Project.

B. General: Construction Contractor shall have limited use of site for construction operations. Limit use of premises to the mechanical room, and a set aside office work will be provided by the Park.

1. Limits: Confine constructions operations to areas indicated on the drawings or as directed by the CO.

C. Storage of Materials: Confine storage of materials to areas as indicated on the drawings.

D. Parking: Confine parking to two spaces to be directed by the CO within the Boott Mill courtyard.

E. Porta-potty shall be provided by contractor, placement to be determined and approved by the CO.

F. Stockpiling: Confine stockpiling to the mechanical room, or as directed by the CO.

G. The primary access for construction personnel and for loading and removal of construction materials shall be from building interior stairs and roof hatch. Additional information could be included at the Preconstruction Meeting.

H. Preservation of Natural Features: N/A

I. Driveways and Entrances: Keep driveways and entrances of the Boott Courtyard serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

J. Construction Camp: Establishment of a camp within park will not be permitted.

LOWE - 337427 01 11 00 - 4

K. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Construction Contractor of liability for damage which may result from moving of equipment.

L. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.

1.7 PUBLIC USE OF SITE

A. Full Government Occupancy: Government will occupy the Boott Cotton Mill during the time the project is under construction for entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

B. Building security regulations require the Site Superintendent and PM to obtain security back-ground checks through the government prior to Notice to Proceed. All subcontractors must have someone with the clearance present or always have a government employee present.

C. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.

Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.

D. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

E. Construction Contractor shall conduct his operations to ensure the least inconvenience to public.

Street closures may be permitted, when required, upon specific approval of Contracting Officer for a maximum time as needed and allowable by the City. Crane placement on Bridge Street will require a police detail.

F. Existing Security System: All existing interior motion sensing security devices are to remain operational throughout the construction period.

1.8 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Full Government Occupancy: Government will occupy buildings under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

LOWE - 337427 01 11 00 - 5

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.

b. Maintain existing building in weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and occupants during construction period.

1.9 CONDUCT OF OPERATIONS

A. Construction Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.10 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:30 a.m. to 4:00 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: Permitted only with specific approval of the Contracting Officer.

2. Early Morning Hours: Permitted only with specific approval of the Contracting Officer, and as allowed under local noise restriction ordinances.

3. Restricted Work Days: No work will be permitted during the annual Folk Festival (last weekend in July) or other federal holidays. During this period, there shall be no on-site activity by the Contractor, and all of the Contractor’s equipment and vehicles shall be stored within the designated, fenced staging area. No construction related deliveries to the site will be allowed, except as approved by the Contracting Officer and with minimum two-day prior notice.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for any excavation.

2. Construction Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

LOWE - 337427 01 11 00 - 6

1. Notify Contracting Officer not less than ten (10) business days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

D. Damage to Existing Utilities: Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, the Contractor shall make repairs at no additional cost to the Government.

E. Nonsmoking Building and Site: Smoking is not permitted on Government Property or in the courtyard.

1.11 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Management and Communication Software: Software administered by NPS shall be used to manage communication and document sharing during construction.

1. See Section 01 31 00 "Project Management and Coordination" for requirements on using

NPS project management and communication software.

1.12 SOILS INVESTIGATION REPORT

A. N/A

1.13 ADDITIONAL REPORTS

A. N/A

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

LOWE - 337427 10 26 01 - 1

CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 - CONTRACT MODIFICATION PROCEDURES

PART 1 -- GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for handling and processing Contract modifications.

B. Related Sections include the following:

1. Division 1 Section "Allowances" for procedural requirements for handling and processing allowances.

2. Division 1 Section "Unit Prices" for administrative requirements for using unit prices.

3. Division 1 Section “Payment Procedures” for processing payments of change orders.

4. Division 1 Section "Substitutions" for administrative procedures for handling requests for substitutions made after Contract award.

1.3 MINOR CHANGES IN THE WORK

A. The Park will issue through COR supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time

1.4 PROPOSAL REQUESTS

A. Park-Initiated Proposal Requests: The Park through Contracting Officer will issue a detailed description of proposed changes in the Work that may require adjustment to the

Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Proposal Requests issued by the Park through Contracting Officer are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.

2. Within 10 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

LOWE - 337427 10 26 01 - 2

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

B. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change to the

Contracting Officer.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

5. Comply with requirements in Division 1 Section "Substitutions" if the proposed change requires substitution of one product or system for product or system specified.

C. Proposal Request Form: No form is required but as a minimum, information stated above must be provided in order to take action on proposal.

DEFINITIONS AND ALLOWANCES

Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

Rent

Utilities

Furnishings

Office equipment

Executive and management staff not exclusively assigned to the project

Support, accounting, and administrative staff

Preparation of cost proposals, estimating, and schedule analyses connected with Modifications

Estimating and preconstruction services

Mortgage costs

LOWE - 337427 10 26 01 - 3

Real estate and corporate taxes

Automobile maintenance and travel costs for home office personnel

Home office insurances i.e. structure, automotive, umbrella, flood, etc.

Depreciation of equipment and other assets

Home office supplies (paper, staples, etc.)

Legal services

Accounting and data processing

Professional fees/registration

General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed.

The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating

General Conditions:

Project Manager, Assistant Project Manager

Superintendent, Assistant Superintendent

Quality Control, Safety Officer, Environmental Manager, etc.

Engineers

Travel, lodging, and per diem (as established by Federal Travel Regulations)

Scheduling

Field Office Trailers and associated temporary utilities

Field office supplies

Mailing and couriers

Reproduction costs

Storage

Phones

Computers

Copiers

Personal vehicles i.e. Superintendent Pickup trucks

General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General

Requirements:

Hoisting

Material handling

Temporary fencing

Port-a-lets

Trash removal, dumpsters

Barricades

Small tools

Safety supplies

Scaffolding

Daily cleaning

Traffic control

Temporary signage

LOWE - 337427 10 26 01 - 4

Temporary heating and power

Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

Base Rate: This is the hourly rate paid directly to the worker

Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums, such as:

Social Security

Medicare

Workers Compensation– Policy and company calculation to be made available.

FUTA– Cap Rate and percentage to be proportionally allocated over one year.

SUTA– Cap Rate and percentage to be proportionally allocated over one year.

Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

Fringe Benefits: Various non-wage compensations provided to employees such as:

Health Care Insurance Premiums

Cell Phone

Clothing

401K and Pensions

Vehicle allowances

Gas allowance

Life insurance premiums

Disability insurance

Other Fringe Benefits required under an enforceable collective bargaining agreement

Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General

Requirements, Hourly Worker Rates, or the direct costs of work.

General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank

LOWE - 337427 10 26 01 - 5

Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.

Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction

Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the

Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

Materials:

http://www.nps.gov/dscw/publicforms.htm#ct

LOWE - 337427 10 26 01 - 6

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.

Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the

US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors

LOWE - 337427 10 26 01 - 7

found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead…………10%

Profit………………8%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

1.5 ALLOWANCES

A. Allowance Adjustment: To adjust allowance amounts, base each Change Order proposal on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins.

1. Include installation costs in purchase amount only where indicated as part of the allowance.

2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other margins claimed.

3. Submit substantiation of a change in scope of work, if any, claimed in Change

Orders related to unit-cost allowances.

4. Park reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.

B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the Purchase Order amount or

Contractor's handling, labor, installation, overhead, and profit. Submit claims within 14 days of receipt of the Change Order or Construction Change Directive authorizing work to proceed. Park will reject claims submitted later than 14 days after such authorization.

1.6 CHANGE ORDER PROCEDURES

On Park's approval of a Proposal Request, Contracting Officer will issue a Change Order for signatures of Park and Contractor. Upon signature of both parties, change order will be in effect and binding.

PART 2 -- PRODUCTS (Not Used)

LOWE - 337427 10 26 01 - 8

PART 3 -- EXECUTION (Not Used)

END OF SECTION 01 26 01

LOWE - 337427 10 26 01 - 9

[THIS PAGE INTENTIONALLY LEFT BLANK]

LOWE - 337427 01 27 00 - 1

DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

This item consists of all work indicated in the contract documents and the Scope of Work (Specifications, this SOW, and shown on drawings).

A. Contract Line Item No. 0001

1. Replace the cooling tower #1 and associated valves at Boott Cotton Mill #6, as per the

Contract Documents.

2. Payment will be made monthly from the contract lump sum price, based on percentages of the schedule of values.

B. Contract Line Item No. 0002

1. Install one circulator pump and one condenser pump, piping, and associated valves at Boott

Cotton Mill #6, as per the Contract Documents.

C. Contract Line Item No. 0003

1. Install one additional circulator pump, piping, and associated valves at the adjacent building (pump is on the same system) as per the Contract Documents.

LOWE - 337427 01 27 00 - 2

DEFINITION OF CONTRACT LINE ITEMS

END OF SECTION 01 27 00

LOWE – 337427 01 31 00 - 1

PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination

3. Submittals

4. Coordination Drawings

5. Requests for Information (RFIs)

6. NPS Project Management and Communication Software

7. Project Meetings

8. Environmental Coordination

9. Permits

B. Related Requirements:

1. Section 01 32 16 "Construction Schedule" for preparing and submitting Construction

Contractor’s construction schedule.

2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.

1.2 DEFINITIONS

A. Agency with Jurisdiction

B. Construction Permits – Contractor Provided

C. Government Furnished Permits

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Construction Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make provisions to accommodate items scheduled for later installation.

http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm

LOWE – 337427 01 31 00 - 2

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other Construction Contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:

1. Preparation of Construction Contractor Construction Schedule

2. Preparation of the Schedule of Values

3. Installation and removal of temporary facilities and controls

4. Delivery and processing of submittals

5. Progress meetings

6. Permit requirements

7. Pre-installation conferences

8. Project closeout activities

1.4 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination

Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.

c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.

d. Indicate required installation sequences.

2. Refer to individual Sections for Coordination Drawing requirements for Work in those

Sections.

3. Follow NPS DSC Electronic Drawing Standards. See CAD/BIM (Computer Aided

Design/Building Information Modeling) & Drafting Standards page > DSC Requirements section.

https://www.nps.gov/dscw/ds-cad-bim-drafting.htm https://www.nps.gov/dscw/ds-cad-bim-drafting.htm

LOWE – 337427 01 31 00 - 3

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Roof Plan: Provide plan and section drawings where required to describe the extent of work at the roof, and in the mechanical room.

2. Mechanical Room plan: Show extend of work associated with two replacement pumps.

3. Mechanical and Plumbing Work:

a. Existing utilities are to remain.

4. Electrical Work:

a. Existing electrical systems are to remain.

5. Retain "Coordination Digital Data Files" paragraph below and delete "Coordination

Drawing Organization" paragraph above if requiring electronic files for coordination drawings submittal for review and for record.

C. Coordination Digital Data Files: Prepare coordination digital data files according to:

1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.

2. Contracting Officer will furnish Construction Contractor one set of digital data files

(AutoCad.dwg) of Drawings for use in preparing coordination digital data files.

a. Contracting Officer makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in AutoCad.dwg.

D. Division 1 documents:

1. Letter designating Project Superintendent

2. Construction Schedule

3. A Comprehensive Schedule of Values

4. Accident Prevention Plan

5. A List of Subcontractors for this project

6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.

7. Certificates of Insurance and Standard Form SF1413 for Contactor and all Subcontractors

8. Waste Management Plan

9. Quality Control Plan

10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP)

11. Indoor Air Quality (IAQ) Management Plan

12. Construction Contractor Commissioning Plan

13. Historic Preservation Treatment Plan (HPTP)

14. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit

b. Agency(ies) with Jurisdiction issuing the permit

c. Information required from Government to complete permit application

LOWE – 337427 01 31 00 - 4

E. Provide items listed to Contracting Officer at least one week prior to Pre-Construction

Conference, or as directed by Contracting Officer.

1. Failure to submit items may result in:

a. Construction conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies.

b. Work shall not commence until written Notice to Proceed has been issued and

Certificates of Insurance and SF1413 documents are received for Construction

Contractor and all Subcontractors.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of

Contract Documents, Construction Contractor shall prepare and submit an RFI utilizing form created on NPS project management and communication software.

1. Contracting Officer will not respond to RFIs submitted by other entities controlled by

Construction Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially

2. Date

3. RFI subject

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Construction Contractor's suggested resolution: If suggested resolution impacts Contract

Time or Contract Sum, Construction Contractor shall state impact in RFI.

8. Construction Contractor's signature

9. Requested date for response

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete and submit on NPS project management and communication software.

D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Construction Contractor's means and methods.

LOWE – 337427 01 31 00 - 5

d. Requests for coordination information already indicated in Contract Documents.

e. Requests for adjustments in Contract Time or Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.

3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or

Contract Sum. All contract changes will be processed following terms and conditions of contract.

1.6 PROJECT MANAGEMENT AND COMMUNICATION SOFTWARE

A. Use to manage project communication and document sharing during contract period on:

1. Project directory

2. Project correspondence

3. Meeting agendas and minutes

4. Contract modifications forms and logs

5. RFI form and processing

6. Task and issue management

7. Photo documentation

8. Baseline schedule, schedule updates and calendar management

9. Submittal form and processing

10. Payment coordination documentation

11. Reminder and tracking functions

12. Archiving functions

13. Notification of submittal and RFI statuses and current responsible party

14. Permits and addendums

B. Some documents are not suitable to be shared using NPS project management and communication software. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared and shall be coordinated with project team as appropriate.

1.7 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Construction Contractor. Meeting agenda will include the following as a minimum:

1. Roles & Responsibilities / Lines of Authority

2. Park rules and regulations

3. Jobsite Safety

4. Resolution of comments on required Division 1 documents

5. Coordination of Subcontractors

6. Labor law application

7. Modifications

8. Payments to Construction Contractor

9. Payroll reports

LOWE – 337427 01 31 00 - 6

10. Contract time

11. Liquidated damages

12. Construction Contractor Performance Evaluation

13. Display of Hotline posters

14. Notice to proceed

15. Correspondence procedures

16. NPS project management and communication software

17. Acceptance/rejection of work

18. Progress meetings

19. Submittal procedures

20. NPS Final Accessibility Inspection

21. Environmental requirements

22. Permit requirements

23. As-constructed drawings/operation and maintenance (O&M) manuals.

24. Saturday, Sunday, holiday and night work.

25. Reference materials

26. Value engineering

27. Schedule of Values

B. Progress Meetings: Contracting Officer will schedule weekly meetings with Construction

Contractor.

1. Attendees: In addition to Government Representatives, each Construction Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented.

Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:

a. Approval of minutes of previous meetings

b. Submittal status

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)

h. Construction Schedule update (provide updated Critical Path Method (CPM)).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

k. Permit requirements

C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting

Officer of scheduled meeting dates.

LOWE – 337427 01 31 00 - 7

2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:

a. Contract Documents

b. Options

c. Related RFIs

d. Related Change Orders

e. Purchases

f. Deliveries

g. Submittals

h. Review of mockups

i. Possible conflicts

j. Compatibility requirements

k. Time schedules

l. Weather limitations

m. Manufacturer's written instructions

n. Warranty requirements

o. Compatibility of materials

p. Acceptability of substrates

q. Temporary facilities and controls

r. Space and access limitations

s. Regulations of agency(ies) with jurisdiction

t. Testing and inspecting requirements

u. Installation procedures

v. Coordination with other work

w. Required performance results

x. Protection of adjacent work

y. Protection of construction and personnel

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.

1.8 ENVIRONMENTAL COORDINATION

A. Construction Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Construction Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

LOWE – 337427 01 31 00 - 8

b. Implementation of Waste Management Plan (WMP).

c. Implementation of Indoor Air Quality (IAQ) Management Plan.

d. Implementation of Storm Water Pollution Prevention Plan (SWPPP).

e. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.

f. Training for Construction Contractor personnel in accordance with position requirements.

g. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements

2. Regulatory Requirements

3. Indoor Air Quality (IAQ) Management

4. Noise and Acoustics Management

5. Temporary Storm Water Pollution Prevention Environmental Management

6. Construction Waste Management

C. Construction Contractor’s Environmental Training Program: Construction Contractor shall provide environmental training for workers performing work on project site. Training shall include:

1. Overview of environmental issues related to building industry.

2. Overview of environmental issues related to Project.

3. Review of site-specific procedures and management plans:

a. Construction Waste Management

b. Indoor Air Quality (IAQ) Management

c. Noise…

This is the start of the file's text. The full file is on GovTribe.