B08_Attachment_10_Past_Performance_Questionnaire.pdf

PDF 412 KB Posted

Attached to
DEPO-REPLACE COMFORT STATION Federal contract opportunity
Solicitation number
140P8524R0002
Issued by
Department of the Interior National Park Service

About this file

This document is a Past Performance Questionnaire for a federal contract opportunity. It provides a template for evaluating the past performance of a contractor on a previous federal contract. The questionnaire covers criteria such as quality of work, timeliness, and business relations, with ratings ranging from Excellent to Unacceptable. The related federal contract opportunity is for the demolition of an existing comfort station and construction of a new comfort station at Devils Postpile National Monument, with an estimated construction value between $1,000,000 and $5,000,000. The procurement is set-aside for Small Business concerns, with a NAICS code of 236220 and a small business size standard of $45.0 million. All questions must be submitted by April 10, 2024.

View the file

Other files for this federal contract opportunity

Other files attached to DEPO-REPLACE COMFORT STATION, newest first.
File Type Posted
Sol_140P8524R0002_Amd_0010.pdf PDF
B08_Attachment_3_DEPO230327_CD100Dwg_R1_06_25_2024_0010.pdf PDF
B08_Updated_Solicitation_6-25-24_0010.pdf PDF
B08_Attachment_2_DEPO230327_CD100Specs_R3_06_25_2024_0010.pdf PDF
B08_Attachment_4_Wage_Determination_CA20240018_5-24-2024_0010.pdf PDF
Sol_140P8524R0002_Amd_0009.pdf PDF
Sol_140P8524R0002_Amd_0008.pdf PDF
Sol_140P8524R0002_Amd_0007.pdf PDF
Sol_140P8524R0002_Amd_0006.pdf PDF
Sol_140P8524R0002_Amd_0005.pdf PDF
Sol_140P8524R0002_Amd_0004.pdf PDF
B08_Attachment_11_Electrical_Asbuilts_0003.pdf PDF
Questions_and_Answers_0003.docx DOCX document
B08_Attachment_12_Geotech_Report_0003.pdf PDF
Sol_140P8524R0002_Amd_0003.pdf PDF
Sol_140P8524R0002_Amd_0002.pdf PDF
DEPO_Virtual_Site_Visit_Attendance_and_Notes_0002.docx DOCX document
Sol_140P8524R0002_Amd_0001.pdf PDF
B08_Attachment_5_DEPO_Comfort_Station_Site_Video.mov MOV file
B08_Attachment_9_General_References.pdf PDF
B08_Attachment_8_Limitations_On_Subcontracting_Report.xlsx XLSX spreadsheet
B08_Attachment_2_Specs.pdf PDF
Sol_140P8524R0002.pdf PDF
B08_Attachment_6_DEPO_New_Site_Pictures.pdf PDF
B08_Attachment_7_Existing_Comfort_Station_Pictures.pdf PDF
B08_Attachment_1_ContractPriceSchedule.xls XLS spreadsheet
B08_Attachment_3_Drawings.pdf PDF
B08_Attachment_4_Wage_Determination_CA20240018.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP No. 140P8524R0002 Section J – Attachment No. 8

PAST PERFORMANCE QUESTIONNAIRE

(OFFEROR: COMPLETE SECTIONS I AND II AND SUBMIT WITH THE TECHNICAL PROPOSAL)

I. CONTRACT IDENTIFICATION

CONTRACTOR NAME: CONTRACT NO.:

CONTRACTOR ADDRESS: CONTRACT TYPE:

FIRM-FIXED-PRICE

COST REIMBURSEMENT

OTHER

ACTIVE COMPLETED

ROUTINE COMPLEX

DATES OF PERFORMANCE: AWARD AMOUNT $

TOTAL WITH MODS $

PROJECT DESCRIPTION:

RFP No. 140P8524R0002 Section J – Attachment No. 8

II. AGENCY (CUSTOMER) IDENTIFICATION

AGENCY (CUSTOMER) NAME:

POC NAME/TITLE/PHONE:

***Government Use Only – The following to be completed by Technical Evaluation Panel***

III. PAST PERFORMANCE RATING

Rating Scale: E = Excellent references are excellent in all respects G = Good references indicate good performance on past projects A = Acceptable references indicate acceptable performance on past projects M = Marginal references indicate marginal performance on past projects U = Unacceptable references indicate unacceptable performance on past projects N = Neutral no performance information was provided or available

1. QUALITY: (circle applicable rating)

a. Conformance with contract requirements E G A M U N

b. Quality of workmanship (including subcontractors) E G A M U N

c. General oversight by project manager and superintendent E G A M U N

d. Coordination with and control of subcontractors E G A M U N

e. Compliance with Davis-Bacon wage rate and labor usage requirements E G A M U N

f. Avoidance of accidents/safety violations E G A M U N

2. TIMELINESS:

a. Adherence to project delivery schedules E G A M U N

b. Submission of change proposals E G A M U N

c. Response to technical direction and change orders E G A M U N

d. Response to correction of identified problems E G A M U N

e. Submission of timely/accurate/complete billings E G A M U N

f. Submission of materials/other submittals E G A M U N

3. BUSINESS RELATIONS:

a. Flexibility and cooperativeness in resolving problems E G A M U N

b. Tenacity and innovativeness in resolving problems E G A M U N

c. Relationships with subcontractors, including prompt payment E G A M U N

d. End user was satisfied with services performed E G A M U N