B08_Attachment_1_SOW_Rehab_Jacob_RIIS_Rail_GATE.pdf
PDF 354 KB Posted
- Attached to
- GATE-REHAB JACOB RIIS SHIP RAIL
- Solicitation number
- 140P4525R0030
About this file
This is a Request for Proposal (RFP) from the National Park Service (NPS) for replacing historic ship's rails on the Riis Park Boardwalk at Gateway National Recreation Area in Brooklyn, New York. The project involves removing approximately 1,800 linear feet of existing corroded ship's rails on the dune side of the boardwalk, excavating sand and vegetation, and installing new rails matching the historic design. The work includes careful vegetation management, with specific requirements to protect endangered plant species like seabeach amaranth, and replacement of removed vegetation with American beach grass. Material specifications include K-Alloy T6 uncoated posts, 1-21/32" anodized aluminum tubing, and pressure-treated Douglas fir, with a qualified botanist required to inspect the site before and during work. The project emphasizes environmental preservation, wildlife protection, and maintaining the historic character of the boardwalk, with strict guidelines for construction practices, quality control, and site restoration.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GATEWAY NATIONAL RECREATION AREA
BROOKLYN, NEW YORK
GATE 245541
REPLACE HISTORIC SHIP’S RAIL ON THE RIIS
PARK BOARDWALK
Request for Proposal (RFP)
NATIONAL PARK SERVICE (NPS)
1.0 PROJECT INTRODUCTION
Project Identification: GATE 245541 Project Title: Replace Historic Ship’s Rail on the Riis Beach Boardwalk In accordance with terms and conditions of the Contract, the Contractor shall perform the work of this Request for Proposal (RFP) for the National Park Service (NPS) as described below.
1.1 LOCATION
This project is located at Gateway National Recreational Area, Jacob Riis Beach in the Jamaica Bay Unit. See sheet C2.
1.2 BACKGROUND
This project will restore a portion of boardwalk rail system, a key component of the historic cultural landscape. Approximately 1,800 lineal feet of ship’s rails on the dune side of the boardwalk to the west of the Wise Clock at Jacob Riis Park needs replacement. The rails have been subject to repeated storm damage and sea spray. The metals are corroded, and the timber is rotted. The corresponding rails on the beach side of the boardwalk have already been replaced.
The rails outlined in this project will also set the boundary limits of the boardwalk and prevent the visiting public from disturbing the dune and natural area bordering the boardwalk.
1.3 DESCRIPTION OF WORK
The work involves dismantling the existing ship's rails on the dune side, excavating sand and vegetation encroaching on the footings, and clearing vegetation around the rail footings. New rails will be fabricated and installed to match the historic design. Work also includes plantings to stabilize dune.
1.4 DATA AND MATERIALS PROVIDED BY NPS
1. Detail of replacement ships rails (sheet C5)
2. Project location map and rail section outlines (Sheets C1, C2, C3 & C4,)
3. List of protected plant species.
2.0 PROJECT REQUIREMENTS
2.1 SCOPE OF WORK
BASE BID: Sections A, B, C, D
Treatment for Sections A, B, C & D
1. Remove Existing Ship's Rails
• Secure the work area to ensure safety for both workers and the public.
• Detach rails from their concrete footings.
• Contractor is responsible for removal of refuse from the site and disposal in an appropriate and legal manner (at a dump or recycling center).
2. Excavation of Dunes
• Qualified botanist inspects vegetation area for protected or endangered species. If seabeach amaranth (Amaranthus pumilus), or any other federal or state listed species, is found, stop work and report to Resource Stewardship Division Manager. See Specifications for acceptable botanist qualifications and list of endangered species.
• Remove the encroaching vegetation to expose 8” of sand behind the concrete footing from around the rail footings, using tools that minimize damage to surrounding plants.
Plants with wooded stems may be trimmed back but not removed altogether.
• Transport excess sand to the designated disposal or redistribution site, ensuring minimal impact on the surrounding environment.
• Any vegetation removed must be replaced with American beach (Ammophila breviligulata) grass according to specifications and as outlined on sheet C5.
3. Installation of Ship's Rails
• Install new ship’s rails matching drawing C5.
• Restore any spalled or cracked concrete footings for consistency along the full stretch of railing, from the start to the end of the section.
• Position new K-Alloy T6 in the holes where old posts used to be. Then, thread the transverse anodized aluminum tube through the holes in the posts.
• Conduct a final inspection with the NPS project manager to ensure that all connections are secure, and the rail installation meets safety and quality standards.
OPTION A: Sections E, F, G
Treatment for Sections E, F & G
1. Remove Existing Ship's Rails
• Secure the work area to ensure safety for both workers and the public.
• Detach rails from their concrete footings.
• Contractor is responsible for removal of refuse from the site and disposal in an appropriate and legal manner (at a dump or recycling center).
2. Excavation of Dunes
• Qualified botanist inspects vegetation area for protected or endangered species. If Sseabeach amaranth, amaranth (Amaranthus pumilus), or any other federal or state listed species, is found, stop work and report to Resource Stewardship Division Manager See Specifications for acceptable botanist qualifications and list of endangered species.
• Remove the encroaching vegetation to expose 8” of sand behind the concrete footing from around the rail footings, using tools that minimize damage to surrounding plants.
Plants with wooded stems may be trimmed back but not removed altogether.
• Transport excess sand to the designated disposal or redistribution site, ensuring minimal impact on the surrounding environment.
• Any vegetation removed must be replaced with American beach grass (Ammophila breviligulata) according to specifications and as outlined on sheet C5.
3. Installation of Ship's Rails
• Install new ship’s rails matching drawing C5.
• Restore any spalled or cracked concrete footings for consistency along the full stretch of railing, from the start to the end of the section.
• Position new K-Alloy T6 in the holes where old posts used to be. Then, thread the transverse anodized aluminum tube through the holes in the posts.
• Conduct a final inspection with the NPS project manager to ensure that all connections are secure, and the rail installation meets safety and quality standards.
OPTION B: Section H
1. Remove Existing Ship's Rails
• Secure the work area to ensure safety for both workers and the public.
• Detach rails from their concrete footings.
• Contractor is responsible for removal of refuse from the site and disposal in an appropriate and legal manner (at a dump or recycling center).
2. Excavation of Dunes
• Qualified botanist inspects vegetation area for protected or endangered species. If seabeach amaranth is found, stop work and report to Resource Stewardship Division Manager. See Specifications for acceptable botanist qualifications and list of endangered species.
• Remove the encroaching vegetation to expose 8” of sand behind the concrete footing from around the rail footings, using tools that minimize damage to surrounding plants.
Plants with wooded stems may be trimmed back but not removed altogether.
• Transport excess sand to the designated disposal or redistribution site, ensuring minimal impact on the surrounding environment.
• Any vegetation removed must be replaced with American beach grass (Ammophila breviligulata) according to specifications and as outlined on sheet C5.
3. Installation of Ship's Rails
• Install new ship’s rails matching drawing C5.
• Restore any spalled or cracked concrete footings for consistency along the full stretch of railing, from the start to the end of the section.
• Position new K-Alloy T6 in the holes where old posts used to be. Then, thread the transverse anodized aluminum tube through the holes in the posts.
• Conduct a final inspection with the NPS project manager to ensure that all connections are secure, and the rail installation meets safety and quality standards.
2.3 MATERIAL LISTS
Submittals are required for all materials intended for use in this Contract.
The following materials will be used for the replacement of the ship's rails at Riis Beach:
Metals
• K-Alloy T6 (Uncoated) Post o Description: High-strength aluminum alloy known for its corrosion resistance and durability.
o Dimensions: [Specify dimensions based on design specifications]
• 1-21/32" Anodized Schedule 80 Aluminum o Description: Heavy-duty anodized aluminum tubing, offering additional corrosion resistance and aesthetic appeal.
o Dimensions: 1-21/32" diameter, Schedule 80 thickness
Wood
• Pressure Treated Douglas Fir o Description: Durable and rot-resistant wood, pressure treated for enhanced longevity in outdoor environments.
o Dimensions: [Specify dimensions based on design specifications]
Installation Accessories
• Fasteners and Hardware o Stainless steel bolts, nuts, and washers o No submittal necessary
Plants
• Ammophila brevigulata – American beach grass
• Spaced 18" on center in alternating rows
• 3 culm per hole
• Contractor responsible for successful establishment of grasses and stabilization of dune.
o Contractor to guarantee at least one surviving culm per 18” on center hole, not on average, for a period of 2 years.
2.4 BOTANIST QUALIFICATIONS
Minimum requirements for a botanist should be consistent with USOPM job series standards for at least a GS7 Botanist (Botany Series 0430):
Basic Requirement: 0430 Series
Degree: botany; or basic plant science that included at least 24 semester hours in botany.
Ccourses in basic botany, plant anatomy or morphology, cytology, histology, genetics, taxonomy or systematics, algology, mycology, ethnobotany, and those dealing with specific problems of a botanical nature or with specific groups of plants are qualifying.
https://www.opm.gov/policy-data-oversight/classification-qualifications/general-schedule-qualification-standards/0400/botany-series-0430/
-OR-
Combination of education and experience: courses equivalent to a major in botany or basic plant science that included at least 24 semester hours in botany, as shown above, plus appropriate experience or additional education.
In addition to meeting the basic requirement, you must also possess experience and/or directly related education in the amounts listed below.
Specialized Experience Requirement for the GS-7 level:
Applicants must have one year of graduate-level education. One year of full-time graduate education is considered to be the number of credit hours that the school attended has determined to represent 1 year of full-time study. If that number cannot be obtained from the school, 18 semester hours should be considered an academic year of graduate study. Part-time graduate education is creditable in accordance with its relationship to a year of full-time study at the school attended.
-OR-
One year of specialized experience equivalent to at least the GS-5 grade level. Specialized experience is defined as experience that equipped the applicant with the particular knowledge, skills, and abilities to perform successfully the duties of the position, and that is typically in or related to the work of the position to be filled. To be creditable, specialized experience must have been equivalent to at least the next lower grade level in the normal line of progression for the occupation in the organization.
-OR-
Combination of Graduate Education and Professional Experience: Combinations of successfully completed graduate level education and specialized experience may be used to meet total experience requirements.
2.5 BUILDING CODES
1. Work shall conform to the 2024 International Building Code.
2. Work shall conform to the 2024 NFPA 70 (National Electric Code).
2.5 DEFINITION OF CONTRACT LINE ITEMS
See attached Contract Price Schedule
2.3 BUILDING CODES
3. Work shall conform to the 2024 International Building Code.
4. Work shall conform to the 2023 NFPA 70 (National Electric Code).
2.4 DEFINITION OF CONTRACT LINE ITEMS
See attached Contract Price Schedule
3.0 RESOURCE PRESERVATION
3.1 NATURAL RESOURCE PRESERVATION
Implement the following mitigation measures to minimize impacts of construction activities:
Soil: Intact native topsoil from the project area shall be retained whenever feasible.
Should additional fill be needed, all fills must be of quality suitable for use in a National Park Unit. Any substructure fill should be tested/inspected to ensure radionuclides are not present in a concentration that decay will result in release of radon gas in a concentration that would be a health concern. Any fill materials required for the project must be obtained from a park-approved source. Such materials are to be clean of contaminants and free of exotic seeds and spores. Written verification of such should be provided to the CO and COR prior to delivery of material. Soils should not be amended.
Any new soils/sediment brought on site must be tested and meet New York State Department of Environmental Conservation standards for general fill (6 CRR-NY 360.13).
• Soil Erosion: Protect against erosion and topsoil depletion. Seed-free straw bales must be deployed for sediment/erosion control. Seed-free straw is required for compliance with Federal Noxious Weed Control Act and Executive Order 13112.
• Exotic Vegetation and Noxious Weeds: Prevent introduction and minimize spread of exotic vegetation and noxious weeds. Incorporate following procedures if site next to buildings is impacted due to construction activities:
• Vegetation: Vegetation may not be trimmed, removed, sprayed, or otherwise damaged to accommodate ladders or other equipment to conduct the work around the buildings. If such modification of vegetation is later determined to be necessary, then NPS/park Resource Stewardship Division must be contacted through the contracting officer’s representative (COR) to conduct an inspection of the work area prior to initiating the proposed vegetation modification. The Contractor shall protect tree trunks and root systems of trees in, or adjacent to, work areas.
o Plant Material: Contractor will use native plant species that are as closely related genetically and ecologically as possible to park populations. For GATE, the operational definition for closely related native species is plant material from seeds or cuttings that were collected from native plant species within 10 miles of the ocean anywhere along the coasts of New Jersey, Staten Island, and western
Long Island are considered suitable. Substitution of plant material will be made only on the basis of proof of unavailability.
• Wildlife: Project must be implemented consistent with outcome of Endangered Species
Act Section 7 consultation. This could include time of year restrictions and/or monitoring requirements. No more than 90 days prior to project implementation, a review is required to determine if there are any changes in the proposed or listed species under the Endangered Species Act (ESA) that are potentially present within the project area that would alter Section 7 consultation and/or no effect determinations. Changes in the proposed or listed species may result require additional ESA consultation. Do not intentionally disturb wildlife nesting, breeding, or other activities. If exterior project work will be implemented during period of March 15 to September 1, park Natural Resource Stewardship must be contacted to conduct an inspection of the work area prior to initiating work to determine if there is any nesting activity that could be impacted by the project. If nest building begins, birds must not be harassed in any manner to deter nesting activity. Park approval is required prior to placement of any structures to deter osprey nesting and any such structure may only be put in place between September 2 and March 14.
It is the Contractor responsibility to check any bird nest on buildings and notify the Contracting Officer in writing. If nests are found, all work should be suspended in that building and no work should proceed until Park Natural Resource Stewardship approval is obtained. The contractor shall adhere to a seasonal restriction on the use of heavy construction equipment/machinery within 300 meters of any active osprey nest along the project limit of disturbance from April 1 through August 31 of each calendar year.
• Visitor Experience: Provide the Project Manager with the project schedule as soon as it is known and provide periodic updates of project work.
Should closure or rerouting of visitors be necessary, contractor must submit a proposal including detour route and signage. Closures would be for the minimal time required to complete the work activity or correct the problem.
• Air and Water Pollution Control:
Minimize tailpipe emissions, do not leave construction equipment idling longer than 3 minutes in accordance with The Rules of the City of New York Section 39.
Minimize construction dust by applying water to problem areas. Limit equipment to fenced project area to minimize soil disturbance and dust generation.
Take necessary reasonable measures to reduce air and water pollution with material or equipment used during construction. Keep volatile wastes in covered containers.
All machinery containing fuels and oils shall have a spill kit available to immediately use in the event of a spill. In the event of a fuel or oil leak or spill, the work shall cease immediately, spill containment deployed, and Gateway NRA Dispatch (718) 354-4700 shall be called immediately.
• Construction Debris:
Construction debris shall be collected in appropriate containers and controlled such that the forces of nature cannot spread it beyond the collection point.
All construction debris and removed material shall be transported outside the park and properly disposed of at an approved off-site location(s) in accordance with federal, state, and local regulations.
• Light Pollution If lighting is proposed, project shall comply with NPS and park lighting guidelines to reduce impacts to the night sky and wildlife. This will include, but is not limited to, warm color hue, low-lumens, and minimized glare. Fixtures shall be downward focused with full shielding. They shall have adaptive technology controls such as timers, motion detectors, hue adapters, and dimmers.
• Wheel Ruts and Divots Any wheel ruts, holes or divots in lawn areas caused by the work shall be repaired by the contractor. Any bare soil areas created by the work shall be seeded with annual ryegrass and a native grass seed mix designed for the Northeast US region, where needed to restore area to pre-construction condition. Seed shall be applied at a rate of ½ pound per 1,000 square feet unless otherwise required for compliance with applicable standards. The park’s Resource Stewardship Division must approve all plant selections before they are purchased.
3.2 CULTURAL RESOURCE PRESERVATION
Ground Disturbance
If ground disturbance is anticipated, an Archeological Monitor will need to be present at work site. If an inadvertent discovery is made of cultural material, architectural debris or foundations, or human remains during the project, work in the area must stop and the Cultural Resources Program Manager must be notified immediately.
Any of the work being performed at this historic site must retain and preserve the historic character of the buildings in compliance with the Secretary of the Interior’s Standards for the Treatment of Historic Properties.
4.0 CONTRACT ADMINISTRATION
4.1 PROGRESS PAYMENTS
Progress payments will be based on percentage of work completed on items listed in approved schedule of values. Actual construction completed and in place will form basis for payment. The Contractor shall verify percent complete under direction of the Contracting Officer Representative unless Contracting Officer waives this requirement in a specific instance.
Contractor shall make computations for payment based on Government’s verification of work completed and in place for periods which progress payments are requested. Update currently accepted construction schedule monthly. If the Contractor fails to provide monthly updates or revisions to currently accepted construction schedule, a portion of monthly payment may be retained until updates/revisions made.
4.2 PROJECT MEETINGS
Preconstruction Meeting and Division One Submittals Submit following deliverables a minimum of one week prior to Preconstruction Meeting.
• Accident Prevention Program (APP)
• Site Plan with storage area, trailers and buildings boundaries.
• Evidence of liability insurance coverage and workman’s compensation for the Contractor and Subcontractors
• Historic Preservation Treatment Plan
• Letters designating Project Manager, Project Superintendent, CQC Manager, and Safety
Manager. Submit resumes for each key personnel.
• List of required permits.
• List of Subcontractors (same as proposal).
• Project Baseline Schedule.
• Schedule of Values shall be part and integrated in the Project Schedule.
• Quality Control Plan
• Storm Water Pollution Prevention Plan (SWPPP)
• Waste Management Plan
• Written statements from Subcontractors certifying compliance with applicable labor standard clauses
Progress Meetings The Contractor shall participate in Bi-Weekly virtual conference calls with Contracting Officer Representative, Contracting Officer and other project team members with updates to following meeting agenda items:
• Approval of minutes of previous meetings.
• Modifications
• Review of off-site repair and delivery.
• Requests for Information (RFI) and issues.
• Schedule update. (Provide updated CPM (Critical Path Method) schedule.)
• Submittal status.
• Work in progress and projected.
• Other business relating to work.
4.3 PROJECT SCHEDULE
General Requirements:
• Project schedule shall cover entire contract period. Late finish date is same as contract’s established completion date.
• The Contractor shall provide a pdf and native file of the project baseline schedule.
• A two-week lookahead schedule shall be submitted weekly and discussed at the Bi-
Weekly virtual conference call. Update the project schedule monthly throughout contract period until project substantial completion. The period of performance can only be changed with a contract modification issued by the Contracting Officer. Status date of each schedule update shall be 10 days before progress payment request date.
• Construction work cannot begin until Government approval is obtained for the work plan for each building, schedule, safety plan, materials and/or any Contractor certifications to be utilized for the work involved in this Contract.
• The Contractor shall ensure project schedule includes own work and Subcontractor work.
Required Software:
Latest version of Microsoft Project, Primavera Project Planner, SureTrak, or equal.
Schedule Development The Contractor shall use Critical Path Method (CPM) with limited use of lead or lag durations between schedule activities. The Contractor's project schedule shall consist of procurement activities (including mobilization, submittal, and fabrication and delivery of key and long-lead procurement items) and construction activities.
The Contractor's project schedule shall consist of, but not be limited to:
• Identify activities and numbers numerically (maximum 5-digit). Number activities in increments of 10.
• Concisely describe work represented by activity (maximum 48 characters). Avoid using non-standard abbreviations. Limit work related to each activity to one work trade.
• Activity duration shall be in whole working days with maximum duration 15 workdays each, unless otherwise approved by Contracting Officer, except for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing.
Project schedule shall show sequence and interdependence of activities required for complete performance of work and shall be cost and resource loaded. The Contractor shall ensure work sequences are logical and project schedule shows a coordinated work plan. Proposed durations assigned to each activity shall be the Contractor's best estimate of time required to complete activity, considering scope and resources planned. Resource loading of each activity shall list personnel by labor category and equipment type, and capacity proposed to complete activity in duration shown. Include permit requirements and constraints. Consider and include seasonal weather conditions in planning and scheduling of work influenced by high or low ambient temperatures and wind and/or precipitation, to ensure completion of work within contract time.
Project Schedule Updates Monthly updates of project schedule shall be an integral part and basic element of estimate upon which progress payments shall be made under this contract. If, in judgment of Contracting Officer, the Contractor fails or refuses to provide schedule of values and complete schedule update or revision as specified hereinafter, the Contractor shall be deemed to have not provided required information upon which progress payment may be made and shall be subject to retainage of a portion of the payment.
Each project update shall include a narrative consisting of, but not be limited to:
• Brief description actual progress made during update period.
• Actual and potential delaying activities.
• Impediments to progress.
• Issues related to inclement weather.
• Progress toward established milestones.
• Project float.
• Brief description of work anticipated to be performed in next month.
• Identify minor revisions to schedule for evaluation and accepted or rejected.
As work progresses, indicate Actual Completion percentage for each activity. If schedule update shows late finish date after contract completion date, at a minimum, include the following in narrative with submission:
• Known delays.
• Actions taken to get back on schedule.
• Pending modifications.
• Impediments or constraints affecting progress.
4.4 TIME IMPACT ANALYSIS REQUIREMENTS FOR CONTRACT MODIFICATIONS,
CHANGES, DELAYS, AND CONTRACTOR REQUESTS
When contract modifications or changes are initiated, delays are experienced, or the Contractor revises project schedule, the Contractor shall submit to Contracting Officer a written time impact analysis illustrating influence of each modification, change, delay, or Contractor’s request on the contract time.
Time Extensions
Activity delays shall not automatically mean an extension of contract time is warranted or due to the Contractor. It is possible that modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of available total float that may exist within an activity chain of the project schedule, thereby not effecting the contract time. Time extensions will be granted according with terms of contract.
Float
Float is not for exclusive use or benefit for NPS or Contractor. Extension of contract time is granted only to extent the equitable time adjustments to activity or activities affected by modification, change, or delay exceeds total (positive or zero) float available on a particular activity.
4.5 CONSTRUCTION SUPPORT
Staging Areas Limit construction sites to smallest feasible area. Equipment and material staging must be limited to hard surfaces. Carefully control ground disturbance and site management to prevent undue damage to vegetation, soils, and archeological resources, and to minimize air, water, soil, and noise pollution.
• Consult with Contracting Officer and develop standards and methods for determining standards.
• Structures such as trailers, storage, field offices, sheds must be approved by Contracting Officer
• Staging areas should be coordinated and approved by NPS prior to any mobilization.
• Staging is limited in or near construction area for a construction office or trailer.
• Locate construction equipment and material storage in previously disturbed areas near construction site preferably on hard surfaces such as pavement.
• Once construction is complete, return staging areas to pre-construction conditions.
Construction Camps Establishment of construction camps will not be permitted.
Construction Zones Before construction activity, use construction barrier, plastic, or portable fencing, approved by Contracting Officer, to define construction zone/minimum area required for construction. Clearly state protection measures in the staging plan and instruct workers to avoid conducting activities beyond construction zone.
Protection of Public Use freestanding fence, barricade, or other means to block immediate work area and prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs according to current version of Manual on Uniform Traffic Control Devices (MUTCD).
Reporting Crime The Contractor is required to report all incidents of crimes committed on the job site to GATE Dispatch (718) 354-4700, and the Project Manager, regardless of the magnitude.
4.6 SUBMITTAL TYPES
There are two primary types of submittals. Action Submittals require Government approval prior to construction. Informational Submittals are either accepted or rejected.
Action Submittals Written, graphic information, and physical samples that require Government’s responsive action.
• Product Data: Collect information in single submittal for each element of construction and type of product or equipment.
• Samples: Submit Samples of kind, color, pattern, and texture for reviewing characteristics with other elements and comparing between submittal and actual component as delivered and installed.
• Construction Materials: The Contractor is encouraged to submit, for approval, products made of recycled or environmentally responsible material. NPS will make every effort to approve these materials.
Informational Submittals Written information not requiring Government’s responsive action. Submittals may be rejected for not complying with requirements.
• Key Personnel
• Insurance and Bonds
• Project Schedule
• Submittal List
• List of Subcontractors
• Accident Prevention Program
• Quality Control Management Plan
• Site and Staging Plan
• Waste Management Plan
Contractor’s Review Review each submittal for coordination with other work of contract and compliance Contract Documents. Note corrections to field dimensions and actual conditions.
• Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities requiring sequential activity.
• Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.
Processing Time
1. Action Submittals: Allow 15 days for initial review of each submittal. Allow 10 days if coordination with subsequent submittals is required. Allow 15 days for review of submittal resubmission.
2. Informational Submittals: Allow 15 days for review of each submittal.
Contracting Officer’s (CO) Review Contracting Officer will review each submittal, generate comments on corrections or modifications required, and indicate appropriate action:
Action Submittals
1. Approved: Acceptable with no corrections required.
2. Approved with Notations: Minor corrections or clarifications required. Comments are clear and no further review required. The Contractor shall address review comments when proceeding with work.
3. Disapproved – Resubmit: Rejected for not according with contract or requiring major corrections or clarifications. Contracting Officer will identify reasons for disapproval.
The Contractor shall revise and resubmit with changes clearly identified.
Informational Submittals
4. Accepted
5. Rejected
Use for Construction Use only final submittals marked with Approved or Approved with Notations. Ensure notations are incorporated and, at a minimum, keep one copy of final approved submittal on site during construction.
4.7 CONSTRUCTION COORDINATION
The Contractor shall work with Park Project Team and develop communication plan.
Notifications Contracting Officer provides necessary written notification and/or direction to the Contractor.
On-site Contracting Officer’s Representative from the Park coordinates the Contractor’s construction efforts with daily operations and transmits/receives correspondence.
4.8 QUALITY CONTROL
The Contractor is responsible for quality of work. Independent testing laboratory is responsible for testing. Inspect and test work as needed to ensure quality of materials, workmanship, construction, and finish, and to ensure functional performance is in compliance with applicable scope of work.
The Contractor accepts ultimate responsibility, liability and duty to control quality of services provided to the Government as stipulated in FAR Part 36.609-2. Contractor shall be responsible for professional quality, technical accuracy and other services furnished by the Contractor, their Employees, Agents, Assignees, and Subcontractors under the contract. Contractor shall, without additional compensation, correct or revise any errors or deficiencies.
The Contractor shall maintain a record of CQC Daily Reports, Daily Test Report Information Sheets, and Accessibility Inspection Reports of quality control activities and tests. CQC Daily Reports may not be substituted for other written reports required under clauses of the contract such as disputes, differing site conditions, or changes
The Contractor shall demonstrate existence of a Quality Control (QC) system used for work submitted to NPS. Contractor and Subcontractors shall use this QC system and, at a minimum, include:
• Coordination of all construction work required for each building.
• Verification that documents to be submitted are accurate and correct.
• Checklists for internal review of construction work, and cost estimates.
o Required documents for each submission are included and complete per contract requirements.
o Required documents have been through a QC review. NPS requires documentation and submittal of QC work performed.
• CQC Supervisor will complete CQC Daily Reports.
Testing Laboratory and Equipment:
• Person performing tests will complete test reports.
• Contracting Officer may designate test locations.
Quality Control Staff Requirements
• CQC Manager, designated by the Contractor, shall be on project site whenever contract work is in progress.
• Contractor's job supervisory staff may assist CQC Manager, as necessary, by adding certified testing technicians.
Testing Laboratory and Equipment:
• Employ certified independent laboratories to perform sampling and testing. Testing laboratory organization shall be certified for type of testing work.
• Calibrate measuring devices, laboratory equipment, and instruments at established intervals against certified standards according to National Bureau of Standards (NBS) requirements.
Quality Control Submittals:
Quality Control Plan Prior to Preconstruction meeting, submit written CQC plan for approval.
If plan requires revisions or corrections, the Contractor shall resubmit plan within 10 days.
Government reserves right to require changes to the plan during contract period as necessary to obtain quality specified.
No change in the approved plan may be made without written concurrence by Contracting Officer.
The plan shall include:
• A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.
• A copy of a letter of direction to CQC Manager outlining assigned duties.
• Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
• Methods of performing, documenting, and enforcing quality control of work.
• Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.
Daily Reports Submit and include inspections and tests on first workday following date covered by report.
Test Reports Submit Test Information Sheets with CQC Daily Reports.
• Submit failing test results and proposed remedial actions within four hours of noted deficiency.
• Submit electronic copies of complete test results no later than one calendar day after test performed.
• If CQC plan and CQC Daily Reports are not submitted as specified, Contracting Officer may retain payments until a plan is accepted and implemented. Or Contracting Officer may retain payments for work completed on days with no CQC Daily Reports.
Off-Site Inspection Reports Submit prior to shipment
Execution of Quality Control Notify Contracting Officer at least 24 hours in advance of initial and follow-up phases.
Off-Site-Control Items fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.
On-Site Control Notify Contracting Officer at least 48 hours in advance of preparatory phase meeting.
Quality Control Phases Preparatory Phase: Perform before beginning each feature of work.
• Review control submittal requirements with personnel directly responsible for quality control work. At a minimum, CQC Manager and Superintendent responsible for the feature of work shall attend.
• Ensure copies of referenced standards, related to sampling, testing, and execution for the feature of work, are available on site.
• Ensure provisions were made for field control testing.
• Examine work area to ensure preliminary work completed.
• Verify field dimensions and advise Contracting Officer of discrepancies with contract documents.
• Ensure necessary equipment and materials are at project site and comply with approved shop drawings and submittals.
• Document preparatory phase activities and discussions on CQC Daily Report.
Initial Phase: As soon as work begins, inspect and test a representative portion of a particular feature of work for quality of workmanship.
• Review control testing procedures to ensure compliance with contract requirements.
• Document initial phase activities and discussions on CQC Daily Report.
Exact location of initial phase shall be indicated for future reference and comparison with follow-up phases.
Follow-Up Phase: Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.
Additional Preparatory and Initial Phases: May be required on the same feature of work for the following reasons:
• Quality of on-going work is unacceptable.
• Changes occurred in applicable quality control staff, on-site production supervision, or work crew.
• Work on a particular feature of work is resumed after a substantial period of inactivity.
Enforcement Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by quality control staff or Contracting Officer.
4.9 WORKING HOURS
Limit work and deliveries to weekday hours of 7:00 AM to 5:00 PM unless otherwise approved by Contracting Officer. Any requested work on holidays or weekends requires approval from the Contracting Officer.
4.10 TEMPORARY SERVICES
Temporary materials may be new or used but must be adequate in capacity for required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.
• Fire Protection Equipment: Observe and enforce standards of fire prevention. No open fires allowed.
• Vehicles and Equipment: Provide one fire extinguisher on each vehicle or piece of equipment. Extinguishers shall have a minimum UL (Underwriters Laboratory) rating of 2-A:10-B:C. A capable and qualified person shall be placed in charge of fire protection.
Responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.
• Hazard Control: Take necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in existing structures. Provide adequate ventilation during use of volatile or noxious substances.
• Spark Arresters: Equip gasoline or diesel-powered equipment, used in potential forest or grass fire locations, with spark arresters approved by U. S. Forest Service. Contracting Officer will issue written determinations of areas and periods of potential fire hazard.
Locate internal combustion equipment so exhausts discharge well away from combustible materials. Locate service areas a minimum of 50 feet from buildings. Shut down equipment before refueling.
• Smoking and Tobacco Use: Smoking within buildings or temporary storage sheds is prohibited. Tobacco use including vaping is prohibited.
• Welding: Cutting by torch or welding shall be performed only when adequate fire protection is provided. Submit a Hot Work Permit to Park Law Enforcement and Contracting Officer for approval.
• Electricity and Lighting: Make arrangements with utility company for metered connection to existing utility and pay costs. Coordinate work with Contracting Officer.
Temporary electrical work shall meet requirements of current version of NFPA 70 NEC Article 590 (National Fire Protection Association (NFPA), National Electrical Code (NEC)). When temporary connections are removed, restore existing utility services to original condition.
• Telephone: Contractor shall make arrangements with local telephone company and pay costs for job-site telephone service.
• Water: Contractor shall provide potable water and pay costs.
• Heating and Cooling: Furnish temporary heating and cooling. Do not use permanent heating and cooling system without written authorization from Contracting Officer.
When permanent heating and cooling system is approved for use as temporary heating and cooling, pay costs until final acceptance. Install new filters before final acceptance.
Equipment warranties start on date of final acceptance.
• Sanitary Facilities: Provide and maintain temporary toilet facilities according to State Health Department and NPS regulations. Provide separate accessible facilities for men and women with privacy locks. Enclosures shall be weatherproof, sight proof, and of sturdy construction. Completely remove sanitary facilities on completion of work.
4.11 ACCESS
Coordinate construction efforts with Contracting Officer towards minimal impact to the work of NPS personnel and to the visiting public.
During construction of scheduled facilities, the Contractor shall have continuous access to the site.
4.12 PRESERVATION OF ADJACENT FEATURES
Confine operations to work limits of project. Prevent damage to natural surroundings. Restore damaged areas outside work limits, repair or replace damaged trees and plants, at no additional expense to NPS.
Provide temporary barriers to protect existing trees, plants, and root zones that will remain in place. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove roots and branches interfering with construction. To prevent damage, carefully supervise excavation, grading, backfilling, and other construction operations near trees and plants.
4.13 EXISTING UTILITIES
Contractor is responsible to locate utilities in each building and protect them. Minimize service disruptions. Contractor shall coordinate with local utility companies and NPS of any affected utility by construction work. Arrange disruptions at least 48 hours in advance with NPS and get approval from Contracting Officer.
Construction procedures shall include preventing accidental disruptions to facilities outside project limits by investigating existing utilities and protection during construction. Accidental disruptions shall be remedied at no cost to NPS.
4.14 ENCOUNTERING UNEXPLODED ORDINANCE
Be advised, Gateway National Recreation Area (GATE) is home to former active military sites and there could be unexploded ordnance (UXO) contained within the ground and/or waters of the park. If a UXO is discovered, extreme caution is warranted, and it should be treated as a live/active munition until proven otherwise. If a UXO is discovered or suspected, immediately cease operations and notify the GATE Dispatch Center (24/7) by calling 718-354-4700. Advise all personnel to clear the area and do not touch the item(s). Emergency response officials will respond and investigate.
4.15 HAULING RESTRICTIONS
Comply with legal and local load restrictions. For delivery material and equipment coordinate with NPS and Park for routes, access, and escort to delivery site. Arrange delivery at least 48 hours in advance with NPS and get approval from Contracting Officer.
4.16 ACCIDENT PREVENTION
Accident Prevention Program Prior to Preconstruction Meeting, submit accident prevention program. Program must be accepted by NPS before work on site begins and shall comply with Occupational Safety and Health Administration (OSHA) and project requirements. Include:
• Name of responsible Safety Manager to carry out the program. Submit a complete resume.
• Monthly safety meetings.
• First aid procedures.
• Outline of each phase of work, hazards associated with each phase, and methods proposed to ensure property protection and safety of the public, NPS staff, and DB Construction Contractor employees.
• Training
• Planning for possible emergency situations.
• Housekeeping and fire protection.
Accident Reporting: Report incidents to GATE Dispatch
• Any accident resulting in injury to contractor’s personnel, NPS employees, or the public regardless of severity
• Any incident that causes damage to property or equipment
• Fires shall be reported immediately.
Complete DSC Contractor Accident/Property Damage Report (CM-22) and forward to
Quality Assurance Ensure employees are physically qualified to perform assigned duties safely. Do not allow employees to work if their abilities are impaired. Operators of equipment shall be able to understand signs, signals and operating instructions, and capable of operating such equipment.
Accident Prevention Products
• First aid facilities.
• Personnel protective equipment shall meet requirements of NIOSH and MSHA (National
Institute for Occupational Safety and Health and Mine Safety and Health Administration).
• Emergency instructions including telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and park police. Place in conspicuous locations at work site.
• Adequate egress at all times according to Standard for Safeguarding Construction, Alteration, and Demolition Operations (NFPA 241).
• Hard hats for employees and for up to six visitors.
• Designate and post signs in hard hat areas.
Training Provide training for first aid and hazardous material handling and storage.
4.17 CONTRACTOR PROVIDES EQUIPMENT AND SERVICES
The contractor shall provide all personnel, services, vehicles, transportation, tools, equipment, materials, supplies, facility supervision, administration supervision and any other item(s) necessary to perform and accomplish this service. The contractor shall be familiar with all the terms, conditions, and requirement herein contained. All work must comply with federal, state and local regulations.
4.18 TEMPORARY CONTROLS
• Housekeeping: Keep project neat, orderly, and in safe conditions at all times.
• Weather Protection: When inclement weather is expected, provide temporary protection for areas where roofing, siding, windows, doors, or other enclosing elements have been removed or have not been installed. Inspect protective coverings frequently to ensure proper function.
• Hurricane Season: Begins May 15 and terminates November 30. If hurricane threatens area, secure and close project site at least 24 hours before anticipated storm landfall. The 8a Contractor should follow Park and state guidance.
4.19 PROJECT CLOSE-OUT
Project Record Documentation Maintain one complete record of all construction documentation. Clearly mark changes, deletions and additions, using NPS standards to show actual constructed conditions. Certification of accuracy and completeness are required for monthly payment requisitions. On completion of total project, submit complete project documentation.
Cleaning Before scheduling final inspection, remove tools, equipment, surplus materials, and rubbish. For surfaces damaged due to work performed under this contract, restore or refinish to original condition. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces.
Remove construction debris from site. At time of final inspection, project shall be thoroughly clean, and all construction debris disposed outside of the park.
Before submitting request for final inspection, submit:
• Project Documentation: As specified above.
• Guarantees and Bonds: As specified in Performance Requirements.
• Operation and Maintenance (O&M) Data: As specified below
Operation and Maintenance (O&M) Data Prior to final inspection, provide one three-ringed binder with O&M data to Contracting Officer for review. Data shall include manufacturer’s standard literature, vendor-furnished as-built drawings, custom written data not included in manufacturer’s standard literature, schedules, warranties, parts lists, test results, and Subcontractor list.
After NPS completes review, incorporate comments. Submit three final sets of O&M data to
4.20 SUBSTANTIAL COMPLETION
Submit written certification to Contracting Officer indicating project, or designated portion of project, is substantially complete, and request inspection. Upon receiving certification, Contracting Officer and Contracting Officer’s Representative will proceed with inspection within
10 days or advise the Contractor of items preventing project from being designated as substantially complete.
When work is determined substantially complete, Contracting Officer will prepare a list of deficiencies (Punch List) for corrections before final acceptance and issue a Letter of Substantial Completion. If work is not determined substantially complete, Contracting Officer will notify the Contractor in writing. After completing work, the Contractor shall resubmit certification and request new final inspection.
Following final inspection, if work is determined substantially complete, Contracting Officer will prepare list of deficiencies for corrections before final acceptance and issue a Letter of Substantial Completion. Contractor shall complete work described on list of deficiencies within 30 calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, Contracting Officer may either replace or correct the work with an appropriate reduction in contract price or charge for re-inspection costs according to the contract’s Inspection of Construction clause.
Acceptance of the work: After deficiencies corrected, Contracting Officer will issue a Letter of Final Acceptance.
| 1.0 PROJECT INTRODUCTION |
| 1.1 LOCATION |
| 1.2 BACKGROUND |
| 1.3 DESCRIPTION OF WORK |
| 1.4 DATA AND MATERIALS PROVIDED BY NPS |
| 1. Detail of replacement ships rails (sheet C5) |
| 2. Project location map and rail section outlines (Sheets C1, C2, C3 & C4,) |
| 3. List of protected plant species. |
| 2.0 PROJECT REQUIREMENTS |
| 2.1 SCOPE OF WORK |
| BASE BID: Sections A, B, C, D |
| Treatment for Sections A, B, C & D |
| 1. Remove Existing Ship's Rails |
| 2. Excavation of Dunes |