B08_Attachment_1_Scope_of_Services.docx

DOCX document 703 KB Posted

Attached to
COLO 253093 - York River Shoreline Stabilization Federal contract opportunity
Solicitation number
140P2021R0066
Issued by
Department of the Interior National Park Service National Office

About this file

This request for proposal from the National Park Service solicits design-build services for the York River Shoreline Stabilization project at Colonial National Historical Park in Yorktown, Virginia. The scope of work includes repairing and stabilizing eroded portions of the York River shoreline along Reaches 1 and 2 to prevent further loss and protect the alignment of Colonial Parkway. Services will include rehabilitating existing rock revetments and constructing new rock sills, breakwaters, and a sheet pile slope stabilization. The contractor will provide design and permitting services, and construction is to be completed within 550 workdays of award. The pre-proposal site visit will be held on September 14, 2021, and proposals are due by September 30, 2021. The contract is to be awarded by October 15, 2021. Payment will be made for design, permitting and construction deliverables according to the schedule of values and contract line items in the proposal.

View the file

Other files for this federal contract opportunity

Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Colonial National Historical Park Yorktown, Virginia

SOLICITATION 140P2021R0066

York River Shoreline Stabilization

COLO 253093- 316317

23 August 2021

DESIGN-BUILD (DB) PROJECT SCOPE

(DB Request for Proposal (RFP))

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

TABLE OF CONTENTS

1 PROJECT INTRODUCTION1
1.1 Project Location1
1.2 Project Description1
1.3 NPS Points of Contact1
1.4 Data and Materials to be Provided by NPS2
1.5 Schedule for Design and Construction2
2 GENERAL REQUIREMENTS5
2.1 Definition of Contract Line Items5
2.2 Progress Payments7
2.3 Project Meetings7
2.4 Construction Coordination9
2.5 Project Website9
3 DESIGN REQUIREMENTS12
3.1 Denver Service Center (DSC) Design-Build (DB) Workflows12
3.2 Design Principles and Processes12
3.3 Sustainability in Design14
3.4 Codes and Authorities15
3.5 Technical Requirements15
3.6 Permitting and Compliance15
4 CONSTRUCTION REQUIREMENTS17
4.1 Construction Support17
4.2 Access18
4.3 Working Hour Restrictions18
4.4 Environmental and Sustainability Requirements for Construction18
4.5 Quality Control20
4.6 Temporary Materials, Equipment, and Services21
4.7 Preservation of Adjacent Features22
4.8 Maintaining Existing Utilities22
4.9 Hauling Restrictions22
4.10 Accident Prevention22
4.11 House Keeping23
4.12 Field Engineering23
4.13 Project Closeout23
4.14 Substantial Completion and Final Inspection23
4.15 Acceptance of Work24
5 DELIVERABLES AND SUBMITTALS25
5.1 Design and Construction Schedule25
5.2 Schedule of Values25
5.3 Design and Construction Documents25
5.4 Technical Specifications and Submittals26
5.5 Pre-Construction Deliverables27
5.6 Digital Images29
5.7 Quality Control Submittals29
5.8 Project Closeout Submittals30
6 ATTACHMENTS31

1 PROJECT INTRODUCTION

Project Name: York River Shoreline Stabilization

Project Number: COLO 253093 & 316317

Park Name & Address:Colonial National Historical Park
P.O. Box 210

Yorktown, VA 23690

1.1 Project Location

The project is in York County Virginia, a few miles northwest of Yorktown. This work is located along the York River shoreline parallel to Colonial National Historical Parkway in Colonial National Historical Park (COLO). The segment of work for this project is identified as Reaches 1 & 2 of the shoreline. Reach 1 extends from Felgates Creek on the west to Indian Field Creek to the east, a distance of approximately 1.7 miles. Reach 2 extends from the mouth of Indian Field Creek on the west to the pier of the Yorktown Naval Weapons Station to the southeast, a distance of approximately 1.4 miles. Government furnished draft design drawings provide more detail.

1.2 Project Description

This project will repair and stabilize portions of the York River shoreline in Reaches 1 and 2 that have been severely eroded. This stabilization is essential to prevent loss to the current alignment of Colonial Parkway due to shoreline erosion. The project includes a combination of shoreline stabilization and marsh protection in both reaches. The work will generally consist of adding rock to increase the revetment height, installing new rock sills and breakwaters, enhancing or adding wetland and marsh habitat, and slope stabilization. Sheet pile wall will be installed to stabilize the steep slope, reduce erosion, and protect the parkway alignment proximate to distance marker K5 (delineated in the plans), northwest of the Yorktown Naval Weapons station pier. Other steep slopes and erosion will be stabilized utilizing geotextile materials and/or native plantings. This slope stabilization is expected to protect shoreline slopes from stormwater runoff above as well as undercutting below. Note that project site access limitations require most material and equipment delivery and some installation of the work from the York River by barge.

1.3 NPS Points of Contact

Contractual:

Contract Officer (CO):Kevin Lommer
Contract Specialist (CS):Jennifer Braaten

Technical:

Project Manager (PM):Jason Himick
Project Specialist (PS):Jennifer Baker

Park:

Facility Manager:Matt Henderson
Civil Engineer:Tim McLean

1.4 Data and Materials to be provided by the NPS

The following data and materials will be provided to the Contractor by the National Park Service (NPS), including but not limited to:

· Bridging Documents

· 95% draft plans and specifications prepared by U.S. Army Corps of Engineers (in native drawing and document formats), and NPS review comments; geotechnical report

· 100% construction drawings (dwg format) and permit application from 2021 revetment rehabilitation project

· Virginia Institute of Marine Sciences (VIMS) – Shoreline Management Plan: Phase II Report, July 2006

· Environmental Assessment – Repair and Stabilize the York River Shoreline to Protect the Colonial Parkway, June 2012

· Colonial National Historical Park – Wetland Delineation Report, May 2011

· GIS Data – Wetland Delineation, 2015; COLO known archaeological sites

· Colonial National Historical Park – General Management Plan

· Cultural Landscape Reports (CLRs)

1.5 Schedule for Design and Construction

The Contractor has ten (10) workdays after award to provide Performance and Payment Bonds and a preliminary project schedule. Once Performance and Payment bonds are approved the Notice to Proceed for design and construction will be issued. The Contractor shall determine and provide a schedule for completion of the design and construction deliverables listed in Section 5. The project shall be fully designed and permitted before the start of construction. The performance period for design and construction shall be 550 workdays from the date of contract award to substantial completion of the improvements.

The NPS will negotiate the project schedule with the contractor. The NPS aspires to complete the work in this RFP in accordance with the following schedule:

Task
Days from previous task
Days from Contract Award

Performance & Payment Bonds

Preliminary Schedule

Notice to Proceed

Pre-Design Meeting

70% Draft Design Development Documents Submittal
45
55
NPS 70% Draft Review
10
65
70% Compliance and Permitting Documents Submittal
10
75

Submit Permit Application(s) - Contractor

Initiate NHPA Section 106 Review - NPS

95% Construction Documents Submittal
30
105
NPS 95% Review
10
115
100% Construction Documents Submittal
20
135
NPS 100% Review
10
145
Complete Stamped and Signed Construction Documents
10
155
Pre-Construction Meeting
15 - or upon compliance and permit approval, whichever comes later
170

Permitting Preparation:

Upon notice to proceed, Contractor shall begin all activities and preparation of information needed for permit application(s). This activity will be conducted concurrently with preparation of 70% design development documents.

70% Design Development (DD) Documents:

70% draft design development documents submitted no later than forty (45) workdays after notice to proceed.

NPS review shall be completed no later than fifteen (15) workdays after submission of draft design development documents.

70% ‘Compliance & Permitting’ documents and written responses to the NPS draft 70% design development document review comments submitted no later than ten (10) workdays after receipt of NPS review comments. NPS comments shall be reviewed with the NPS (as needed) and incorporated in the compliance and permitting documents.

70% ‘Compliance & Permitting’ documents shall be used by the contractor to support federal, state, and local permitting applications.

70% ‘Compliance & Permitting’ documents will be submitted to Virginia Department of Historic Resources (also referred to as State Historic Preservation Office – SHPO) by NPS for compliance with Section 106 of the National Historical Preservation Act (NHPA). This review is expected to take no less than thirty (30) calendar days after submission. If the SHPO requests additional information the NPS may request additional edits / revisions to the 70% plans to be incorporated into the 95% documents.

95% Construction Documents (CD):

Work on 95% Construction Documents shall begin upon submittal of the 70% ‘Compliance & Permitting’ documents.

95% Construction Documents submitted thirty (30) workdays after submission of 70% ‘Compliance & Permitting’ documents, or as based on compliance and permit review timelines.

NPS review shall be completed no later than ten (10) workdays after receipt of 95% Construction Documents.

100% Complete Construction Documents (CD):

100% Complete DB Construction Documents and written responses to the NPS 95% Construction Documents Review Comments submitted no later than twenty (20) workdays after submission of NPS 95% review comments.

NPS will review 100% submittal for compliance with contract requirements and approve or reject submittal no later than ten (10) workdays after receipt of 100% Complete Construction Documents.

Stamped and signed Construction Documents submitted no later than ten (10) workdays after receipt of NPS 100% CD approval.

Construction:

Construction shall not begin until compliance requirements are met and permits are received, the Pre-Construction Meeting is complete, and the Contract Officer has issued authorization to start construction.

Construction completed no later than 390 workdays after start of construction.

As-Constructed Drawings:

As-Constructed Drawings completed no later than twenty (20) workdays after Substantial Completion.

2 GENERAL REQUIREMENTS

This Section defines components of the project and Contract Line Items, and outlines progress payments and required project meetings.

Unit Price Payment Items: The unit price and payment made for each item listed shall constitute full compensation for furnishing all labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, safety requirements, tests and reports, and all other work required.

2.1 Definition of Contract Line Items

The intent of this Section is to explain, in general, what is included in each contract line item and to clarify limits or cut-off points where one item ends and another begins. If a portion of the work is not explicitly covered in any line item below but is a part of the project, include the costs for that work in a related line item.

2.1.1 Contract Line Item No. 1 – Design & Permitting

This item consists of the preparation, submission, and completion of design and construction documents, and permits as described in sections 5.3 and 4.15, respectively. The Contractor is responsible for determining and obtaining all necessary permits.

Measurement for payment will be made at the contract lump sum price.

2.1.2 Contract Line Item No. 2 – Revetment Area 1 – Revetment Rehabilitation This item consists of all work required to construct Rock Revetment 1, including but not limited to the rehabilitation of the existing rock revetment structures (repositioning the existing rock, placing new geotextile and/or subgrade material, placing new armor rock), wetland planting and/or revegetation, and all access and staging between approximately stations 08+00 to 72+00 delineated in the bridging documents.

Measurement for payment will be made at the contract unit price per linear foot.

2.1.3 Contract Line Item No. 3 – Revetment Area 1 – Slope Stabilization This item consists of all work required for vegetated slope stabilization in Revetment Area 1, including but not limited to site preparation, clearing vegetation, stockpiling of specific materials, hauling, placing, surveying work, erosion and sediment control measures.

Measurement for payment will be made at the contract lump sum price.

2.1.4 Contract Line Item No. 4 – Revetment Area 2 – Revetment Rehabilitation This item consists of all work required to construct Rock Revetment 2, including but not limited to the rehabilitation of the existing rock revetment structures (repositioning the existing rock, placing new geotextile and/or subgrade material, placing new armor rock), wetland planting and/or revegetation, and all access and staging between approximately stations 131+00 to 142+00 delineated in the bridging documents.

Measurement for payment will be made at the contract unit price per linear foot.

2.1.5 Contract Line Item No. 5 – Revetment Area 2 – Slope Stabilization This item consists of all work required for vegetated slope stabilization in Revetment Area 2, including but not limited to site preparation, clearing vegetation, stockpiling of specific materials, hauling, placing, surveying work, erosion and sediment control measures.

Measurement for payment will be made at the contract lump sum price.

2.1.6 Contract Line Item No. 6 – Sheet Pile Slope Stabilization This item consists of work required for sheet pile slope stabilization including but not limited to driving of steel sheets, installing anchoring systems, placing of granular fill, and all access and staging between approximately stations 128+00 and 132+00 delineated in the bridging documents. The work also includes vegetated slope stabilization of the slopes landward of the steel sheet stabilization (may include geotextile reinforcement and rock revetment at the toe of the slope as shown in the construction drawings).

Measurement for payment will be made at the contract lump sum price.

2.1.7 Contract Line Item No. 7 – Option A – Rock Sill Section 1 This item consists of all work required to construct Rock Sill Section 1 including but not limited to construction of the rock sill structure (placing new geotextile, new core rock, and new armor rock), the fill, grading, and wetland planting, and all access and staging between stations 0+00 to approximately station 08+50 delineated in the bridging documents.

Measurement for payment will be made at the contract lump sum price.

2.1.8 Contract Line Item No. 8 – Option B – Rock Sill Section 2 This item consists of all work required to construct Rock Sill Section 2 including but not limited to the rehabilitation of the existing rock sill structures (repositioning the existing rock, placing new geotextile, placing new armor rock) and all access and staging between approximately stations 91+75 to approximately station 96+00.

Measurement for payment will be made at the contract lump sum price.

2.1.9 Contract Line Item No. 9 – Option C – Rock Sill Section 3 This item consists of all work required to construct Rock Sill Section 3 including but not limited to the construction of the new rock sill structures (placing new geotextile, new core rock, and new armor rock) approximately between stations 96+50 to 103+75, the fill, grading, and wetland planting areas (approximately between stations 94+00 to 105+00) delineated in the bridging documents, and all access and staging.

Measurement for payment will be made at the contract lump sum price.

2.1.10 Contract Line Item No. 10 – Option D – Rock Sill Section 4 This item consists of all work required to construct Rock Sill Section 4 including but not limited to the rehabilitation of the existing rock sill structures (repositioning the existing rock, placing new geotextile, placing new armor rock and all access and staging between approximately stations 103+75 to approximately station 113+50. This work includes a new rock sill extension from approximately 103+75 to 104+75 delineated in the bridging documents.

Measurement for payment will be made at the contract lump sum price.

2.1.11 Contract Line Item No. 11 – Option E – Rock Sill Section 5 This item consists of all work required to construct Rock Sill Section 5 including but not limited to the construction of the new rock sill structures (placing new geotextile, new core rock, and new armor rock) approximately between stations 113+50 to 116+75, the fill, grading, and wetland planting areas (approximately between stations 113+00 to 117+00), and all access and staging delineated in the bridging documents.

Measurement for payment will be made at the contract lump sum price.

2.1.12 Contract Line Item No. 12 – Option F – Rock Sill Section 6 This item consists of all work required to construct Rock Sill Section 6 including but not limited to the rehabilitation of the existing rock sill structures (repositioning the existing rock, placing new geotextile, placing new armor rock) and all access and staging between approximately stations 116+75 to approximately station 121+50 delineated in the bridging documents.

Measurement for payment will be made at the contract lump sum price.

2.1.13 Contract Line Item No. 13 – Option G – Breakwaters

This item consists of all work required to rehabilitate the existing breakwater including but not limited to the repositioning of the existing structures, placing new geotextile and armor rock, and all access and staging between approximately stations 122+00 to approximately station 129+50 delineated in the bridging documents. The work under this item also includes the fill, grading, and wetland planting areas (approximately between stations 120+75 to 131+00).

Measurement for payment will be made at the contract lump sum price.

2.2Progress Payments
2.2.1Design Phase

Progress payments during the design phase of the work will be based on submission, review, and acceptance of design deliverables.

2.2.2 Construction Phase

Progress payments during construction will be based on the percentage of work completed on items listed on the approved Schedule of Values (Section 5.2) or by Contract Line Item. Actual construction completed and in place will form the basis for payment. Verification of the percentage (%) complete shall be initiated by the Contractor for approval by the Contract Officer’s Representative (COR). The Contractor shall make the computations for payment based on the government’s verification of work completed and in place for any periods for which progress payments are requested.

The Contractor shall furnish the originals of all field notes, invoices and payroll reports, and all other records relating to the basis for payment, to the Contract Officer (CO), who shall use them as necessary to determine the final amount of progress payments. The Contractor shall retain copies of all such material furnished to the CO.

2.3Project Meetings
2.3.1Pre-Design Meeting

After the award of the contract and acceptance of the Performance and Payment bonds and schedule, the CO will arrange a pre-design meeting with the Contractor. The Contractor shall prepare and distribute a meeting agenda at least five (5) workdays prior to the scheduled meeting. Notes of the meeting will be recorded by the Contractor and distributed to attendees no later than five (5) workdays after the meeting. The meeting agenda shall include the following as a minimum:

· Review and emphasize the park needs and design objectives

· Environmental and sustainability requirements

· Design and construction schedule (Section 5.1)

· Schedule of Values (Section 5.2)

· Modifications during design

· Submittals during design

· Site safety and park access requirements

· Natural and cultural resource protection

· Minimum drawing and information requirements for NHPA Section 106 review

· Permit requirements – Clean Water Act Section 404, VA joint permit

· Payments to the Contractor

2.3.2 Pre-Construction Meeting

After 100% complete Construction Documents are approved and prior to the start of construction, the CO will arrange an on-site pre-construction meeting with the Contractor and prepare the agenda. Notes of the meeting shall be recorded by the Contractor and will be distributed no later than five (5) workdays after the meeting. Deliverables required in advance of the meeting are listed in Section 5.5. The meeting agenda will include the following as a minimum:

· Park rules and regulations

· Correspondence procedures

· Progress meetings

· Lines of authority

· Roles and responsibilities

· Coordination of subcontractors

· Submittal process

· Distribution of or access to digital images of construction progress

· Final construction schedule

· Weekly work schedule

· Progress payments

· Acceptance/rejection of the work

· Liquidated damages

· Labor standards and labor law application

· Payroll reports

· Modifications

· Accident Prevention Plan and accident reporting

· Contractor’s Quality Control Plan

· Waste Management and Recycling Plan

· Medical emergency processes, availability, emergency numbers, and contacts

· Park permits, burning construction waste, rules of the road, alcohol use, housekeeping, firearms, pets, natural and cultural resource concerns

· Bridge, access road and site constraints

· Traffic control

· Visitation and public relations

· Environmental and sustainability requirements for the project

· Archeological resources protection requirements

· Value engineering

2.3.3 Progress Meetings

The Contractor shall participate in weekly progress meetings with the CO and other project team members. Notes shall be kept by the Contractor and distributed to participants, and each agenda shall contain the following meeting agenda items at a minimum:

· Approval of minutes of previous meetings

· Safety

· Submittal status

· Review of off-site fabrication and delivery

· Requests for Information (RFI’s) and issues

· Modifications

· Work in progress

· Schedule update – two week look ahead

· Status of Project Record Drawings and O&M Manuals

· Other business relating to work

2.4 Construction Coordination

The CO will provide all necessary written notification and/or direction to the contractor. An on-site independent Construction Management Representative (CMR) will oversee the contractor’s construction efforts and coordinate with the park staff’s daily operations and will transmit and receive correspondence between the Denver Service Center and the Contractor. However, the CMR will have no authority to accept or reject work, or to authorize changes to the terms and conditions of the contracts, or to obligate the NPS for time or money.

2.5 Project Website

The Contractor shall provide a project management program that has real-time work management features that support Task Management, Team Collaboration, and Document Management. The project management program shall be a secure web-based application that does not require a subscription or software downloads by NPS staff or partners. Acceptable programs include but are not limited to: Procore; PlanGrid; Bluebeam; Microsoft Teams; etc. At a minimum program features shall include:

a) Project File Directory

b) Project Document Management:

i) Unlimited Storage;

ii) Document Tracking;

iii) Document and Folder Permissions.

c) Project Schedule:

i) Provide ability to upload PDF schedules from but not limited to Primavera and Microsoft Project;

ii) Provide ability to view in Gant and calendar view Baseline and Monthly Schedule Updates.

d) Meeting Minutes:

i) Track attendance, meeting notes and attachments;

ii) Distribute meeting agendas prior to meeting;

iii) Track assignment and completion of meeting generated tasks.

e) Photographs:

i) Store, organize, and display digital images and videos;

ii) Allow attachment of photos to drawings, punch list items, and other records;

iii) Support the capture and upload of photos from mobile devices;

iv) Automatically aggregate project photos captured in other record types, such as daily logs into the photo album.

f) Submittals:

i) Collect, workflow and distribute project submittals;

ii) Submittal register shall be created from project specifications;

iii) Distribute approved packages to project participants.

g) Daily Log:

i) Record and view daily job site activities provided by the Contractor;

ii) Record and view observation and inspection reports provided by the Construction Management Representative;

iii) Allows for submission by multiple project collaborators with an approval process.

h) RFI Tool:

i) Include responsibility assignment, automatic routing and reminder notifications as well as the ability to respond into the system via email;

ii) System shall have ability to track author, addressee(s), when files are sent, received and read;

iii) System shall have ability to document and track review comments and responses;

iv) Permissions shall be granted at the folder and document level.

i) Record Linking:

i) Ability to link project critical information such as RFI’s, Submittals, Observations and photo to locations on the drawing. Allow for the search of names, description and contents of documents within the documents tool.

Access to the website, from any internet-connected device, 24 hours a day, 7 days a week, is required for all project participants and collaborators at no additional costs.

The COR shall determine permission and access for each party.

The Contractor shall establish and submit personnel security requirements for Project Management Program staff to the Government for review and approval.

Data Ownership: The Government shall retain ownership of all data. The system shall permit stakeholders the ability to download a copy of the data at any time. Within 14 days of Substantial Completion the Contractor shall provide secure file transfer or download all stored data to a Flash Drive and provide to the COR. In addition, the Government shall be able to access the site up to 3 months after issuance of Substantial Completion.

3 DESIGN REQUIREMENTS

This Section provides information on Design Imperatives that help ensure compatibility of the project with NPS goals, and general Environmental and Sustainability Requirements for designing the proposed improvements.

3.1 Denver Service Center (DSC) Design-Build (DB) Workflows

Website: https://www.nps.gov/dscw/designbuild.htm

Listed on the DB homepage are links to the design phases which describe the required workflow process from Predesign (PD) through Construction Documents (CD). Each design phase webpage contains hypertext links to definitions, forms, templates, samples and guidelines.

The DB homepage also includes links to the Design Standards and Design Deliverables sections which provide design requirements and criteria that shall be used for completing the work of this contract:

· Design Standards (https://www.nps.gov/dscw/dstandards.htm): Design Standards arranged by discipline and/or specialty.

· DB Design Deliverables (https://www.nps.gov/dscw/del_designbuild.htm): Design phase submission requirements for technical content and submission format (hard-copy and electronic)

In addition, there is an Information section (https://www.nps.gov/dscw/information.htm) with links directly to the following sections:

· Definitions (https://www.nps.gov/dscw/definitions.htm): A list of terms relevant to design and construction in national parks.

· Forms/Templates/Samples/Guidelines (https://www.nps.gov/dscw/publicforms.htm): A listing of forms/templates/samples/guidelines used for a typical project.

· Laws/Regulations/Policies/Guidance (https://www.nps.gov/dscw/laws-policies.htm): A listing of sources for retrieving laws/regulations/policies/guidance applicable to NPS projects.

· Quality Assurance Guideline & Review Checklists (https://www.nps.gov/dscw/qaguideline.htm): Overview of the DSC Quality Assurance (QA) Process for reviewing Design Documents.

In case of conflict between this RFP and the DSC DB Workflows website, https://www.nps.gov/dscw/designbuild.htm, this RFP will take precedence over and will be used in lieu of such conflicting portions.

The A/E remains fully responsible for determining if the standards or provisions cited on the DSC DB Workflows website, https://www.nps.gov/dscw/designbuild.htm, have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the CO requesting direction.

3.2 Design Principles and Processes

Utilize the following design principles and processes throughout all stages of design and construction.

3.2.1 Appropriate Design Solutions for Park Use and Maintenance Capabilities Employ design solutions that are:

· Appropriate for the proposed use of the park

· Appropriate for the location of the project (Contextual Design)

· Easily and economically operated and maintained by the park staff

3.2.2 Integration of Facilities into the Park Environment

The NPS will provide visitor and administrative facilities that are necessary, appropriate, and consistent with the conservation of park resources and values. Facilities will be harmonious with park resources, compatible with natural processes, esthetically pleasing, functional, energy- and water-efficient, cost-effective, universally designed, and as welcoming as possible to all segments of the population. NPS facilities and operations will demonstrate environmental leadership by incorporating sustainable practices to the maximum extent practicable in planning, design, siting, construction, and maintenance. (See Section 9.1.1.2 within the 2001 Management Policies available at http://www.nps.gov/policy/mp/chapter9.htm)

3.2.3 Compliance Consistency Reviews

The ongoing processes utilized by the design and construction teams to ensure that the evolving design, including design alternatives, and details, are consistent with those that were evaluated within the Environmental Assessment (EA) and Finding of No Significant Impact (FONSI).

3.2.4 Constructability Strategies

The ongoing processes utilized by the design and construction teams to ensure that the evolving design, including design alternatives, and details, are constructible.

3.2.5 Quality Assurance

The process of ensuring the technical accuracy, completeness, and correctness of the design, cost estimate and all architectural, landscape architectural, and engineering aspects and details, including coordination of all disciplines with each other and with the specifications.

3.2.6 Risk Analysis

Risk Analysis is a technique to identify and assess factors that may jeopardize the success of a project or achieving a goal. This technique also helps define preventive measures to reduce the probability of these factors from occurring and identify countermeasures to successfully deal with these constraints when they develop.

3.2.7 Scope and Budget Consistency Reviews

The ongoing processes utilized by the design and construction teams to ensure that the evolving design and design details are consistent with the approved project, and within the available construction funds.

3.2.8 Integrated Design Principles

Integrated Design Principles shall be employed. Use a collaborative, integrated design process that initiates and maintains an integrated project team in all stages of a project and considers all stages in the lifecycle of the project.

3.3 Sustainability in Design

The NPS promotes as a design imperative Sustainable Design Practices which apply the principles of ecology, economics, and ethics to the business of creating necessary and appropriate places for people to visit, live, and work. Development that has been sustainably designed sits lightly upon the land, demonstrates resource efficiency, and promotes ecological restoration and integrity, thus improving the environment, the economy, and society. Sustainable Design Practices include those choices, decisions, actions and ethics that will best achieve ecological/ biological integrity; protect qualities and functions of air, water, soil, and other aspects of the natural environment; and preserve human cultures. Sustainable Design Practices allow for use and enjoyment by the current generation, while ensuring that future generations will have the same opportunities.

3.3.1 Environmental and Sustainability Requirements for Design The NPS has established the following general environmental and sustainability requirements for the project. Notify the CO if conflicts arise between performance of the work and environmental and sustainability requirements. The NPS does not intend to limit alternative means of achieving these requirements.

· Avoid Scarce, Irreplaceable, or Endangered materials

· Select materials that come from abundant resources

· Select materials that are replaceable, renewable or can be replenished where possible

· Select materials that minimize damage to natural habitats

· Select materials that generate the least amount of pollution. Consider pollution and toxins generated during harvesting, mining, manufacturing, transport, installation, use and disposal.

· Select durable materials that can be reused or recycled or materials with a significant percentage of recycled content. Avoid recycled content materials that are difficult to recycle.

· Use Durable Materials

· Select materials with the longest usable life

· Select materials that can be reused

· Select materials or equipment that use less energy or save energy over their life span

· Consider the embodied energy in each phase of the complete life cycle of the material:

· Harvesting, extraction

· Manufacturing, processing

· Transportation, distribution: Choose local materials

· Installation, use, maintenance

· Recycling, disposal

3.3.2 Project-Specific Sustainability Requirements

Sustainability requirements for NPS projects are found in federal legislation and Executive Orders, and depend on type of work and size of the project that must be met. There are also DOI and NPS policies that apply. An updated list of laws, regulations, policies and background data is available at: http://www.nps.gov/dscw/ds-sustainability.htm. The NPS Project Sustainability Checklist Template provides a mechanism for identifying project specific sustainability requirements and a means to document continued compliance with those requirements Building and non-building projects with estimated gross construction costs greater than $2 million must comply with all Federal requirements listed in the NPS checklist. Under $2 million, some Federal Requirements still apply. The checklist can be found at: http://www.nps.gov/dsc/workflows/publicforms.htm.

This project shall follow all applicable laws, regulations and policies related to sustainability and environmental practices in design, which include:

· Obtain an NPDES Storm Water Pollution Prevention permit

· Complete Natural Hazards Checklist

3.4 Codes and Authorities

All work performed shall comply with applicable laws, regulations, and NPS policies and guidelines. The following links provide access to some of these policies and guidelines:

· NPS Office of Policy: http://home.nps.gov/applications/npspolicy/index.cfm

· NPS Management Policies 2006: http://www.nps.gov/policy/mp/policies.html

· NPS Legislative and Congressional Affairs: http://www.nps.gov/legal/

All units, structures and components must be constructed based on the following codes and authorities, depending upon application:

· The Code of Federal Regulation, including 10 CFR Part 435 – Energy Performance Standards for Federal buildings and 10 CFR Part 436 – Federal Energy Management and Planning Programs (view at http://ecfr.gpoaccess.gov/)

· International Building Code (IBC), latest edition

· American Society for Testing Materials (ASTM) specifications as applicable

· American National Standards Institute (ANSI)

· Americans with Disabilities Act and Architectural Barriers Guidelines

· American Concrete Institute publications, latest editions

3.5 Technical Requirements

The Design-Build Contractor shall utilize the ‘Shoreline Management Plan: Phase II’ report prepared by Virginia Institute of Marine Science (2006), US Army Corps of Engineers (USACE) Coastal Engineering Manual (latest edition), USACE Design of Coastal Revetments, Seawalls, and Bulkheads (latest edition), and the Bridging Documents as the basis for the design and proposal. The design should be in conformance with USACE, VDEQ, Virginia Marine Resources Commission (VMRC), York County local wetlands board regulations as well as the Code of Virginia for tidal wetlands. The USACE calculations, assumptions, and design elements provided in the bridging documents should be reviewed and verified. Any performance requirements not identified in these documents are flexible items for the design build contractor to resolve per NPS and Federal requirements.

3.6 Permitting and Compliance

The proposed work will be along the shoreline and within the tidal zone of the York River. The project is expected to require authorization from the U.S. Army Corps of Engineers (USACE), Virginia Department of Environmental Quality (VDEQ), Virginia Marine Resources Commission (VMRC) and York County local wetlands board under Sections 408, 404 and 401 of the Clean Water Act as well as Section 28.2 of the Code of Virginia for tidal wetlands. A Joint Permit Application (JPA) will be prepared by the Contractor (for Park signature) and submitted to these agencies for review and approval. The JPA will identify the purpose and need of the project, alternatives considered, quantify impacts to jurisdictional resources and identify any proposed mitigation, if required. Based on the defined scope of work, the project is not expected to require an Individual Permit and may likely be authorized under a Regional Permit (RGP) by the USACE. Attendance at public hearings will be required, and payment of any permit fees and public notice fees should be included in this task. Information on the Tidewater Joint Permit Application (JPA) permit can be found at:

https://www.nao.usace.army.mil/Missions/Regulatory/JPA.aspx.

The project area and appropriate buffers shall be delineated to identify environmental resources under the potential jurisdiction of the USACE and/or VDEQ. The mapped delineation shall be based on surveyed topographic contours as provided by the NPS in GIS or CADD format. Surveyed locations of mean high water and mean low water shall also be provided and referenced to the applicable state plane coordinate system. The project area has been previously delineated in 2011; however, the delineation does not appear to be covered under a current, valid confirmation. The delineation shall include flagging of the limits of wetlands and stream channels onsite, data forms, a hardcopy map and request for a Preliminary Jurisdictional Determination to the USACE if needed.

As a Federal applicant, the NPS will be the designated lead agency on applicable Section 106 and Section 7 coordination that is required for the Section 404 authorizations. Section 106 coordination under the National Historic Preservation Act shall be completed by NPS and is not included in this scope of work. NPS shall be responsible for initiating the required Section 7 Endangered Species Act coordination with NOAA, NMFS and USFWS. The preparation of letters, documents and materials to be used for the purposes of review and compliance under Section 7 will be completed by the Contractor and provided to NPS for review and submittal.

4 CONSTRUCTION REQUIREMENTS

4.1Construction Support
4.1.1Staging Areas

Construction sites will be limited to the smallest feasible area. Ground disturbance and site management will be carefully controlled to prevent undue damage to vegetation, soils, and archeological resources and to minimize air, water, soil, and noise pollution.

Confine storage of construction materials and equipment to the paved surfaces of designated areas and project site, unless directed otherwise by the CO. All staging areas shall be returned to pre-construction conditions once construction is complete. Standards for this, and methods for determining when the standards are met, shall be developed in consultation with the CO. If used, all temporary water, sewer, sanitary facilities, electric and other utilities and utility connections shall be completely removed upon project completion.

The location of trailers, storage, field offices, sheds and staging areas will require CO approval.

4.1.2 Construction Zones

Do not disturb portions of project site beyond areas in which the Work is indicated. Construction zones shall be fenced with CO approved construction barrier fencing, chain link, plastic or portable fencing before any construction activity. The fencing shall define the construction zone and confine activity to the minimum area required for construction. Where the limit of work is adjacent to or over top of known archaeological resources, no posts can be driven into the ground – fence and sign posts shall be free-standing. All protection measures shall be clearly stated in the construction documents, and workers will be instructed to avoid conducting activities beyond the construction zone as defined by the construction zone fencing. The Contractor shall protect tree trunks and root systems of trees in or adjacent to work areas.

4.1.3 Protection of Public

The Contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs in accordance with the Manual of Uniform Traffic Control Devices (MUTCD). Where adjacent to or over top of known archaeological resources, no posts can be driven into the ground – fence and sign posts shall be free-standing.

4.1.4 Parking of Construction Vehicles

Parking of vehicles shall be limited to existing roads, in legally designated areas, and within approved staging area(s).

4.1.5 Special Construction Conditions and Requirements

In-Water Work Restrictions: The York River has been designated as and Anadromous Fish Use Area, and the federal and state endangered Atlantic sturgeon (Acipenser oxyrinchus) is identified by Virginia Fish and Wildlife Information Service (VAFWIS) as occurring within the river. As such, a time-of-year restriction (TOYR) on in-stream work is typically required from February 15 to June 30, particularly for activities that may generate excessive noise or increase turbidity.

Weight limitations and commercial vehicle restrictions exist for Colonial Parkway and associated bridges. Check requirements prior to shipping materials on these roadways. Rock and heavy equipment required to complete the work will be delivered via barge or other seaworthy vessel. Potential barge access points have been identified on the design drawings provided.

The hurricane season begins June 1 and terminates November 30. Should a hurricane threaten the area, the park shall be secured and closed at least 24 hours before anticipated storm landfall.

Any previously abandoned construction debris (not including trash washed ashore) discovered in the course of the project work that is clearly within the project area work zones shall be removed and disposed of properly. Known debris includes rusted steel ‘I’ beams adjacent to Felgates Creek, rusted steel buoys on the shoreline, and a beached log fender (aka log camel).

4.2 Access

Coordinate construction efforts with the CO such that there is minimal impact to the work of NPS personnel, the visiting public, and other contract work in the park. During construction of the scheduled facilities, the Contractor shall have continuous access to the site.

4.3 Working Hour Restrictions

All work and deliveries shall be limited to the weekday business hours of 7:00am to 5:00pm unless otherwise approved by the CO. No work shall occur on Federal holidays or weekends without prior approval.

4.4 Environmental and Sustainability Requirements for Construction The following are general environmental and sustainability requirements during construction, designed to minimize construction impacts.

4.4.1 Air

Employ construction practices that minimize dust production and combustion byproducts.

4.4.2 Water

Avoid materials that can leach toxic chemicals into the ground water. Do not allow toxic chemicals to enter sewers or storm drains. Submit a Storm Water Pollution Prevention Plan (Section 5.5.2) to the CO prior to Construction which meets local, state, federal requirements, and obtain all necessary permits. Apply Best Management Practices, including vehicle wash-down areas, protection of equipment storage and maintenance areas, and sweeping of roadways related to hauling activities.

4.4.3 Soil

Protect against erosion, contamination, and topsoil depletion.

4.4.4 Exotic Vegetation and Noxious Weeds

Prevent the introduction and minimize the spread of exotic vegetation and noxious weeds. Any fill, rock, or additional topsoil needed shall be obtained from a Government approved source. All areas disturbed by construction shall be re-vegetated using approved native seed and/or plants.

4.4.5 Vegetation Salvage and Re-vegetation Plan

A Salvage and Re-vegetation Plan shall be required for this project. Any re-vegetation efforts shall use approved native species and/or native seed, and park policies regarding vegetation and site restoration shall be incorporated into the plan. The plan shall consider, among other things, the use of native species, plant salvage potential, the avoidance of exotic vegetation and noxious weeds, and the use of pedestrian barriers.

4.4.6 Habitats

Protect natural habitats and ecological systems on facility site.

4.4.7 Special Status Species

To protect any unknown or undiscovered threatened, endangered, or special status species, the construction contract will include provisions for the discovery of such. The Contractor should contact the park for direction for evaluation of any special species at the site.

4.4.8 Noise

Minimize noise generation during construction. Operate power equipment in accordance with local noise restrictions.

4.4.9 Materials

Use resources efficiently. Select materials and use construction practices that achieve the most efficient use of resources and materials.

4.4.10 Waste Management Goals

Employ processes that ensure the generation of as little waste as possible. Minimize waste generation due to over-packaging, poor planning, breakage, mishandling, contamination, error or other factors. Of the waste generated, as much as is economically feasible shall be reused, salvaged or recycled. Waste disposal in landfills shall be minimized. All material unsuitable for recycling must be disposed of, in a legal manner, at public or private dumping areas outside the park.

Materials that may be recycled include but are not limited to the following:

· Cardboard, paper, packaging

· Clean dimensional wood, pallet wood

· Beverage containers

· Concrete

· Concrete Masonry Units

· Metals from banding, ductwork, piping, rebar, roofing, etc.

· Glass

· Plastics

4.4.11 Air and Water Pollution Control

Air quality impacts are expected to be temporary and localized. All necessary and reasonable measures shall be taken to reduce air and water pollution by any material or equipment used during construction. To reduce tailpipe emissions, construction equipment shall not be left idling any longer than is necessary for safety and mechanical reasons. Volatile wastes shall be stored according to best industry practices and in covered containers.

4.4.12 Cultural Resources

Colonial National Historical Park contains subsurface archeological resources. If archeological resources (including human remains) are discovered at the project site, all work in the vicinity of the discovery must stop immediately, and the discovery must be reported to the CO. Work may not continue in the aera without explicit approval from the Park cultural resource staff and CO. While NPS does not anticipate the Contractor uncovering subsurface cultural resources in the project area, the potential exists.

4.5Quality Control
4.5.1General

The quality of all work shall be the responsibility of the Contractor. Inspect and test all work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings. Quality Control Daily Reports shall be completed by the Quality Control Supervisor. Test reports shall be completed by person performing the test.

4.5.2 Quality Control Staff

The Contractor's Quality Control Supervisor may also perform the duties of Project Superintendent.

The Contractor's designated Quality Control Supervisor shall be on the project site whenever contract work is in progress. The Contractor's job supervisory staff may be used to assist the Quality Control Supervisor, supplemented, as necessary, by additional certified testing technicians.

Required Quality Control Submittals are listed in Section 5.7.

4.5.3Quality Control Phases
4.5.3.1Preparatory Phase

Perform before beginning each element of work.

· Review quality control submittal requirements with personnel directly responsible for the quality control work.

· Review all applicable specifications sections and drawings related to the feature of work.

· Ensure that copies of all referenced standards related to sampling, testing and execution for the feature of work are available on site.

· Ensure that provisions have been made for field control testing.

· Examine the work area to ensure that all preliminary work has been completed.

· Verify all field dimensions and advise the CO of discrepancies with contract documents.

· Ensure that necessary equipment and materials are at the project site and that they comply with approved shop drawings and submittals.

· Document all preparatory phase activities and discussions on the Contractor's Quality Control Daily Report.

4.5.3.2 Initial Phase

As soon as work begins, inspect and test a representative portion of a particular element of work for quality of workmanship.

· Review control testing procedures to ensure compliance with contract requirements.

· Document all initial phase activities and discussions on the Contractor's Quality Control Daily Report. Exact location of initial phase shall be indicated for future reference and comparison with follow-up phases.

4.5.3.3 Follow-Up Phase

Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.

4.5.3.4 Additional Preparatory and Initial Phases

Additional preparatory and initial phases may be required on the same element of work for the following reasons:

· Quality of on-going work is unacceptable.

· Changes occur in the applicable quality control staff, on-site production supervision, or work crew.

· Work on a particular element of work is resumed after a substantial period of inactivity.

4.5.4Execution
4.5.4.1Off-Site-Control

Items that are fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.

4.5.4.2 On-Site Control

Notify the CO at least 48 hours in advance of the preparatory phase meeting, and notify the CO at least 24 hours in advance of the initial…