Summary: B08_Attachment_1_HAFE_100__Specifications.pdf

This is a comprehensive project specification document for the Harpers Ferry National Historical Park Pavement Preservation Project (PMIS 242454), prepared by the National Park Service Denver Service Center. The project involves pavement preservation work across multiple parking lots and facilities at Harpers Ferry National Historical Park in West Virginia, including tree trimming, seal coating, chip sealing, shoulder grading, crack sealing, asphalt patching, pavement markings, and traffic management. Work is organized into two contract line items: parking lot surface repair for public assets (23 locations) and non-public assets (5 locations), both awarded as lump-sum contracts. The contractor must conduct operations during normal business hours (8:00 a.m. to 5:00 p.m., Monday through Friday) with restrictions on work during federal holidays, special events, and specific closure dates; no work is permitted January 1st, Thanksgiving, or Christmas. Wildlife protection measures are mandatory, including prohibiting woody vegetation clearing and tree removal between April 1 and November 14 without USFWS-approved biological surveys for birds and bats, with all bridge work requiring bat surveys during the active season (April 15 to November 1).

The contractor must submit critical Division 1 documents at least one week before the preconstruction conference, including the construction schedule, schedule of values, accident prevention plan, quality control plan, waste management plan, and proof of all required permits and insurance. The construction baseline schedule must use Critical Path Method analysis with detailed activity planning, cost and resource loading, and weather considerations, submitted within 30 days of notice of award. Modification proposals must follow strict pricing guidelines with overhead capped at 6% and profit at 10% for contractor self-performed work, with total aggregate markup not exceeding 25%. Environmental coordination is required, including stormwater pollution prevention planning, invasive species surveys, and compliance with Section 7 consultation requirements. All submittals use the Government-furnished Construction Management Platform, with action submittals requiring 30 days for initial review and 10 days for re-submittal review.

View the file

Other files for this federal contract opportunity

Other files attached to HAFE 242454, Pavement Preservation Project, newest first.
File Type Posted
Sol_140P2026R0064_Amd_0002.pdf PDF
Sol_140P2026R0064_Amd_0001.pdf PDF
B08_Attachment_2_HAFE_100__Drawing_Plans.pdf PDF
B08_Attachment_3_Wage_Determination_WV20260111.pdf PDF
B08_Attachment_4_PriceSched_-_HAFE_242454_(PavePres).xlsx XLSX spreadsheet
B08_Attachment_7_Past_Performance_Questionnaire.docx DOCX document
B08_Attachment_8_Experience_Form.docx DOCX document
B08_Conformed_Solicitation_140P2026R0064.pdf PDF
B08_Attachment_5_General_Refrences.pdf PDF
Sol_140P2026R0064.pdf PDF
B08_Attachment_6_Subcontract_Percentage_Worksheet.xlsx XLSX spreadsheet
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HARPERS FERRY NATIONAL HISTORICAL

PARK,

WEST VIRGINIA

PAVEMENT PRESERVATION

PMIS 242454

PROJECT SPECIFICATIONS

100% Submittal

April 2026

NATIONAL PARK SERVICE (NPS)

DENVER SERVICE CENTER (DSC)

TABLE OF CONTENTS

DIVISION 01 GENERAL REQUIREMENTS

01 10 00 Summary of Work

01 26 01 Contract Modification Procedures

01 27 00 Definition of Contract Line Items

01 31 00 Project Management and Coordination

01 32 16 Construction Schedule

01 32 33 Photo Documentation

01 33 23 Submittal Procedures

01 35 13.22 Archeological Protection

01 35 23 Safety Requirements

01 35 91 Historic Preservation Treatment Procedures

01 40 00 Quality Requirements

01 50 00 Temporary Facilities and Controls

01 57 19.12 Noise and Acoustics Management

01 57 23 Under-An-Acre Pollution Prevention

01 67 00 Product Requirements

01 73 40 Execution

01 74 19 Construction Waste Management and Disposal

01 77 00 Closeout Procedures

DIVISION 02 EXISTING CONDITIONS

02 41 00 Selective Demolition

DIVISION 31 EARTHWORK

31 10 00 Tree Trimming

DIVISION 32 EXTERIOR IMPROVEMENTS

32 01 13.65 Chip Seal

32 01 13.75 Slurry Seal

32 12 16 Asphalt Patching and Crack Sealing

32 17 23 Pavement Markings

DIVISION 34 TRANSPORTATION

34 20 00 Maintenance of Traffic

APPENDIX

A Harpers Ferry Contact List

HAFE 242454 01 10 00 - 1

041426 SUMMARY OF WORK

NPS DSC Division 1 Specifications

HARPERS FERRY NATIONAL HISTORICAL PARK – 242454

SECTION 01 10 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Work Phases

3. Work Under Other Contracts

4. Contractor Use of Site

5. Public Use of Site

6. Conduct of Operations

7. Work Restrictions

8. Special Construction Requirements

9. Soils Investigation Report

10. Additional Reports

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: West Virginia

B. The Work consists of:

1. The pavement preservation work includes tree trimming, seal coating, chip seal, shoulder grading, crack sealing, partial and full depth asphalt pavement patching, pavement markings, traffic management and any temporary works needed for work.

C. Project will be constructed under a single prime contract.

1.3 WORK PHASES

A. The work shall be coordinated with the Contracting Officer (CO). The work can be performed in phases or done concurrently for the pavement preservation locations. Provide the CO the plan for the work with detail for what work will be completed in each phase or if concurrent the work that will be performed and what work will be completed before beginning next work element.

1.4 WORK UNDER OTHER CONTRACTS

HAFE 242454 01 10 00 - 2

a. Coincident with this contract may be other contracts within the same working vicinity.

Coordinate construction operations to minimize impacts. Coordinate with CO for other contracts information. The table below with potential projects is provided for informational purposes and may not include all projects. It is the contractor’s responsibility to coordinate work to reduce/eliminate conflicts. Need HAFE’s input on other projects.

POTENTIAL PROJECTS ESTIMATED CONSTRUCTION

1.5 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to work within the construction limits indicated on drawings. Do not disturb portions of

Project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations to contractor laydown/staging areas shown in the drawings or approved by the CO.

2. Limit site disturbance, including earthwork and clearing of vegetation, to the construction limits indicated in the drawings unless approved by the CO.

3. Laydown areas (temporary storage or working areas near work site used for short durations) shall be approved by CO.

4. The Contractor shall hold a meeting no less than seven days in advance of work with the

CO, in coordination with the Park, to review and confirm construction limits, equipment access, areas of ground disturbance and over all work procedures.

5. Contractor shall coordinate with CO for staging and storage area for traffic management set up including all materials and equipment for traffic management.

6. Contractor is responsible for restoring all staging and laydown area to pre-use conditions.

7. All emergency routes are to remain unobstructed at all times during construction.

Contractor shall pick up construction-related debris daily.

B. Storage of Materials: Confine storage of materials to contractor staging areas shown in the drawings or at a location approved by the CO.

C. Parking: Confine parking to staging area. Parking at the construction site requires CO approval.

Reduce and limit onsite parking to essential vehicles only. No less than 7 days prior to onsite work, submit an onsite parking plan with the number and type of vehicles and identify proposed laydown areas for CO approval.

D. Stockpiling: Confine stockpiling to staging area or laydown area as approved by the CO.

E. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

CO and remove agreed-on roots and branches that interfere with construction.

HAFE 242454 01 10 00 - 3

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

F. Driveways and Entrances: Keep driveways, pullouts and entrances serving premises clear and available to Government employees, and emergency vehicles at all times, unless otherwise shown as available staging area on the drawings or as approved by the CO. Do not use unauthorized areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

G. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

H. Lane and Bridge Closures: The Contractor shall submit a lane and/or closure with detour plan 3 weeks in advance of planned lane closures in accordance with 01 10 00 Subsection 1.8 to the CO for approval. No lane closures will be permitted without prior approval.

1.6 PUBLIC USE OF SITE

A. Contractor shall conduct operations to ensure the least inconvenience to public.

1.7 CONDUCT OF OPERATIONS

A. Contractor shall conduct operations in conformance with rules and regulations promulgated by the

Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays and at night may not be performed unless stated in the Work Restrictions below or without prior consent from the CO. Submit requests 5 business/calendar days in advance of the work to the CO for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the CO.

1.8 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8:00 a.m. to 5:00 p.m, Monday through Friday, except when otherwise indicated.

1. Weekend Hours: are permitted upon request and approval by the CO.

2. Early Morning Hours: are permitted upon request and approval by the CO.

3. Hours for noisy activity: are permitted during normal business working hours, upon request

HAFE 242454 01 10 00 - 4

and approval by the CO.

4. Federal Holiday, Special Events and First Amendment Activities: No lane closures are allowed on Federal Holidays, Special Events and First Amendment Activities, including the day before or after if noted. Contractor permittee to coordinate with Harpers Ferry

National Historic Park point of contact for Holidays, dates of Special Events and First

Amendment Activities, for events/holidays that require lane closures on the day before or after and for approval of lane closures. Work is permitted upon request and approval by the CO.

a. Work is not permitted on January 1st, Thanksgiving and Christmas, no exceptions.

5. No work in the event of Federal Government Closures (Weather, etc.).

6. The working hour and lane closure restrictions are as follows unless approved by CO:

a. Daytime: Monday through Friday from 8:00AM to 5:00PM.

7. The contractor shall submit a phasing plan for approval by CO for each pavement preservation area. The table below lists work restrictions for each area to be incorporated into the phasing plans:

AREA LOCATION IMPACTS WORK RESTRICTIONS NOTES

Contact information:

Add any specific contact information if needed for the parking areas

8. Wildlife - All ground disturbing work on or near bridge structures is prohibited until NPS consultation with the USFWS is complete and the Contracting Officer (CO) has

HAFE 242454 01 10 00 - 5

authorized approval for on-site work. This approval is expected no later than 15 days following pre-work submittal approvals.

A. Wildlife - Birds: Copied from GWMP verify what sections are applicable

a. The Contractor shall perform woody vegetation clearing and tree removal work between November 15 and March 31 to avoid Migratory Bird Treaty Act (MBTA) impacts. No exceptions will be permitted.

b. If structure repair is performed between April 1 and November 14, the Contractor must provide a survey by a USFWS approved biologist with findings presented to the CO for approval prior to beginning any onsite work. The Contractor shall comply with the Migratory Bird Treaty Act (MBTA) [16 USC 703]. If an active nest is encountered, the nest shall be left in place until the young hatch and depart.

Park staff must be notified and a survey by the Contractor’s biologist shall be done of the area to be impacted prior to execution; Park biologist/NR specialist will work with contractor to determine best practice on this case-by-case basis (e.g., if no nests are detected, clearing must be completed within one week of the survey, if nests are detected, clearing/execution may be held off for a period commensurate with nest stage egg incubation/hatchlings/near fledging).

c. If bird nesting activity is observed within 50' of the project site, all work in the area shall stop until after the young have fledged. Work may resume once the fledglings have left the nest.

B. Wildlife - Bats:

a. The Contractor shall perform woody vegetation clearing and tree removal work between November 15 and March 31 to avoid Threatened & Endangered Species impacts. No exceptions will be permitted.

b. All bridge work areas will need to be surveyed by a USFWS approved biologist with findings presented to the CO for approval before any work begins (including but not limited to tree clearing and bridge repairs), regardless of seasonal restrictions.

Bridge surveys shall be conducted during the active season for bats, no earlier than

April 15 and no later than November 1, and is valid for two years. Tree and bridge surveys must be conducted following the USFWS Range-Wide Indiana Bat &

Northern Long-Eared Bat Survey Guidelines: Indiana Bat and Northern Long-Eared

Bat Survey Guidelines. A list of pre-approved USFWS bat biologists can be found here. If the Contractor selects an individual not on this list to conduct habitat assessments/surveys, provide that individual’s qualifications to the USFWS

Virginia Ecological Services Field Office for review and approval 60 days prior to the start of the survey. No work is permitted with positive findings without CO approval. Immediately report positive findings to the CO.

C. Wildlife – Monarch Butterfly:

a. Fifteen days prior to vegetation clearing, the contractor will coordinate with NPS to schedule pre-work surveys for the monarch butterfly (NPS to complete).

Following the monarch butterfly survey and subsequent relocation of any findings, vegetation clearing must be completed within one week.

9. Assessment of Effect: For cultural resources protection, no disturbance of historic or cultural features shall occur; no artifacts shall be collected; and if archeological or historic resources are discovered, work shall stop at the discovery site, the discovery shall be protected as required and the Cultural Resource Specialist shall be notified as soon as possible. Information and photographs regarding the location, size, and nature of the discovery should be provided, if possible.

HAFE 242454 01 10 00 - 6

10. Vegetation – Native Plantings:

a. Soil disturbance shall be minimized to the greatest extent possible to reduce disturbance to native plants and reduce the potential for the introduction or spread of invasive non-native plant species.

b. Disturbance to existing native vegetation shall primarily be contained in previously disturbed areas or within narrow construction limits. Whenever practicable, soils and plants affected by construction shall be salvaged for reuse in site restoration.

c. Prior to construction, the project area shall be surveyed for invasive plants. A survey report shall be issued to NPS and a treatment plan developed and accepted by NPS, followed by treatment of identified species (per plan). Infestations of invasive plants within the project area shall be treated prior, during, and/or after project implementation (depending on species - as appropriate and following all protocols, labels, etc.).

d. All disturbed ground shall be reclaimed using appropriate best management practices, which may include planting or seeding with native vegetation, or, in the case of small treatment areas, allowing native vegetation to reclaim the area naturally. Project leader shall consult with the Natural Resources branch to determine the best methods for restoration.

11. Vegetation – Herbicides/Pesticides:

a. A pesticide work plan shall be submitted that will address; location, terrain, nearby waters/wetlands/intermittent streams, time of year, time of day for application, proximity to visitor use areas, number of personnel for the project, access to the work site, number of days anticipated, application techniques, and equipment to be used. Plan shall also include a safety plan that will outline the project's Personal

Protective Equipment to be used.

b. Herbicide application shall follow all federal, state, and local regulations.

12. Floodplains & Wetlands - Construction:

a. Wetlands/WOUS: Impacts to wetlands and streams are to be avoided. Incorporate

BMPs, including silt fencing and straw wattles where appropriate to limit sedimentation around wetland or stream areas.

b. Heavy equipment use in wetlands is not permitted without CO approval.

B. Existing Utilities: Utility impacts are not anticipated but it is the contractor’s responsibility to verify before any excavation work.

1. Existing Utilities: Notify CO and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be evaluated in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify CO not less than two business days in advance of proposed utility interruptions.

HAFE 242454 01 10 00 - 7

2. Do not proceed with utility interruptions without CO written permission.

3. Hours and length of Utility Shutdowns: Coordinate with CO if utility shutdowns are required.

D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted.

1.9 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A Government Furnished Construction Management Platform administered and run by the Construction Management team will be used for purposes of managing communication and documents during construction stage.

1. See Section 01 31 00 "Project Management and Coordination" for requirements on using

Project Website.

1.10 SOILS INVESTIGATION REPORT

A. A soils report is not available for this project.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 10 00

HAFE 242454 01 26 01 - 1

041426101725 CONTRACT MODIFICATION PROCEDURES

NPS DSC Division 1 Specifications

HARPERS FERRY NATIONAL HISTORICAL PARK – 242454

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager (PM), Assistant Project Manager

HAFE 242454 01 26 01 - 2

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare

3) Workers Compensation – Policy and company calculation to be made available.

HAFE 242454 01 26 01 - 3

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.

Include as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of

HAFE 242454 01 26 01 - 4

Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.

3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. Labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for work being performed.

2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.

3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

HAFE 242454 01 26 01 - 5

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.

6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.

8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………6% Profit………………10%

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

HAFE 242454 01 26 01 - 6

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 01 26 01

HAFE 242454 01 27 00 - 1

041426 DEFINITION OF CONTRACT LINE ITEMS

NPS DSC Division 1 Specifications

HARPERS FERRY NATIONAL HISTORICAL PARK – 242454

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS (See Table 01 32 16 for CLIN list with estimated quantities)

A. Contract Line Item Number 1, Parking Lot Surface Repair – Public Assets

1. This item consists of work pertaining to the Parking Lot Surface Repair as shown in the contract documents including but not limited to:

a. Mobilization

b. Traffic Control

c. Crack Sealing

d. Pavement Patching

e. Shoulder Grading

f. Tree Trimming

g. Joint Seal

h. Slurry Seal

i. Chip Seal

j. Signs

k. Pavement Markings

2. For the following assets:

a. 0010 – Hartzog Drive

b. 0012 – Shenandoah Street

c. 0014 – Shoreline Drive

d. 0015 – Public Way

e. 0300 – Whitman & Prospect Avenues

f. 0408 – Maintenance Lot Access South of Filmore St.

g. 0900 – Mather Training Center Parking

h. 0902A – Facility Maintenance Public Parking

HAFE 242454 01 27 00 - 2

041426 DEFINITION OF CONTRACT LINE ITEMS

i. 0903 – HAFC Lewis Anthony Parking

j. 0904 – Cook Hall Parking

k. 0908 – Shipley School Parking

l. 0910 – Morrell House Parking

m. 0911 – Bracket House Parking

n. 0913 – Train Station Parking

o. 0915 – Pulp Mill Parking

p. 0916 – River Access Parking

q. 0918 – Visitor Center Parking

r. 0921Z – Bolivar Heights Parking

s. 0922Z – Bolivar Heights Bus Loop

t. 0923 – Grandville School Parking

u. 0932 – HAFC Bird Brady Parking

v. 0933 – HAFC Hartzog Drive Parking

3. Measurement for payment will be lump sum.

4. Payment will be made at the contract lump sum price.

B. Contract Line Item Number 2, Parking Lot Surface Repair – Non-Public Assets

1. This item consists of work pertaining to the Parking Lot Surface Repair as shown in the contract documents including but not limited to:

a. Mobilization

b. Traffic Control

c. Crack Sealing

d. Pavement Patching

e. Shoulder Grading

f. Tree Trimming

g. Joint Seal

h. Slurry Seal

i. Chip Seal

j. Sign installation

k. Pavement Markings

2. For the following assets:

a. 0902B – Facility Maintenance Complex

b. 0906 – IDC Parking

c. 0914 – Lower Town Bus Loop Parking

d. 0919 – Visitor Center Bus loop

e. 0926 – Bus Maintenance Parking

3. Measurement for payment will be lump sum.

4. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

HAFE 242454 01 31 00 - 1

041426 PROJECT MANAGEMENT AND COORDINATION

NPS DSC Division 1 Specifications

HARPERS FERRY NATIONAL HISTORICAL PARK – 242454

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination

3. Submittals

4. Coordination Drawings

5. Requests for Information (RFIs)

6. Government Furnished Construction Management Platform

7. Project Meetings

8. Environmental Coordination

9. Permits

B. Related Requirements:

1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services.

3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.

1.2 DEFINITIONS

A. Agency with Jurisdiction: An Agency that has been granted legal authority over a location, action, or resource. This authority includes the ability to issue a permit or other legal permission document.

B. Construction Permits – Contractor Provided: Permits obtained by the Contractor based on the means and methods to conduct the work. Construction Permits are typically issued by the Agency to the Contractor and not to the National Park Service. Examples of typical Contractor

Provided Permits are: National Pollutant Discharge Elimination System (NPDES) Construction

Permit (ground disturbance), dewatering permit, permit for work in a roadway (with traffic management plan), temporary utility tap permit, etc.

C. Government Furnished Permits: Obtained by National Park Service (NPS), usually through the Architect/Engineer (A/E) or a consultant, during the design process (Predesign (PD) through

Construction Documents (CD)) and are usually concerned with impacts to resources protected by

HAFE 242454 01 31 00 - 2

federal law. However, GF permits can include other permits that are obtained for the convenience of the Government during design. GF permits are "furnished" to the Contractor in the Request for

Proposal (RFP) and as part of the final contract documents. The Contractor must comply with GF permit provisions. Examples of typical GF permits: Clean Water Act (CWA) 404 dredge and fill permit, CWA Water Quality Certification (often state administered), Highway Right-of-Way

Permit, etc.

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Make provisions to accommodate items scheduled for later installation.

3. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Coordinate with the project partners via the CO using the Harpers Ferry Contact List provided in Appendix A Such administrative activities include, but are not limited to:

1. Preparation of Contractor's Construction Schedule

2. Preparation of the Schedule of Values

3. Installation and removal of temporary facilities and controls

4. Delivery and processing of submittals

5. Progress meetings

6. Permit requirements

7. Pre-installation conferences

8. Project closeout activities

9. Commissioning activities

1.4 SUBMITTALS

A. Division 1 documents: The following items shall be submitted a minimum of one week prior to

Preconstruction Conference. Contracting Officer (CO) will notify Contractor of tentative date for

Pre-Construction Conference.

1. Letter designating Project Superintendent

2. Construction Schedule

HAFE 242454 01 31 00 - 3

3. A Comprehensive Schedule of Values

4. Accident Prevention Plan

5. A List of Subcontractors for this project

6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.

7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors

8. Waste Management Plan

9. Quality Control Plan

10. Under-An-Acre Pollution Prevention Plan (UPPP)

11. Contractors Commissioning Plan

12. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit

b. Agency(ies) with Jurisdiction issuing the permit

c. Information required from Government to complete permit application

B. Provide items listed to CO before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and CO will consider other contractual remedies.

Work shall not commence until written Notice to Proceed has been issued.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of

Contract Documents, Contractor shall prepare and submit an RFI on a form that contains the information in section B of this section or form provided by CO.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially

2. Date

3. RFI subject

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract

Time or Contract Sum, Contractor shall state impact in RFI.

8. Contractor's signature

9. Requested date for response

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

HAFE 242454 01 31 00 - 4

C. CO’s Action: CO will review each RFI, determine action required, and respond. CO will determine critical nature of each RFI and issue response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in Contract Documents.

e. Requests for adjustments in Contract Time or Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information; time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in need for a change to Contract Time or Contract Sum.

All contract changes will be processed following terms and conditions of contract.

1.6 PROJECT WEB SITE

A. Use Government Provided Construction Management Platform for communication throughout contract period. The website will be used for the following functions:

1. Project directory

2. Project correspondence

3. Meeting agendas and minutes

4. Contract modifications forms and logs

5. RFI form and processing

6. Task and issue management

7. Photo documentation

8. Baseline schedule, schedule updates and calendar management

9. Submittal form and processing

10. Payment coordination documentation

11. Drawing and specification document hosting, viewing, and updating

12. Online document collaboration

13. Reminder and tracking functions

14. Archiving functions

15. Notification of submittal and RFI statuses and current responsible party

16. Permits and addendums

B. Some documents are not suitable to be shared using website. Documents containing Personal

Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the website and shall be coordinated with Project team as appropriate.

1.7 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, CO will arrange an on-site meeting with

Contractor. Meeting agenda will include the following as a minimum:

HAFE 242454 01 31 00 - 5

1. Roles & Responsibilities / Lines of Authority

2. Park rules and regulations

3. Jobsite Safety

4. Resolution of comments on required Division 1 documents

5. Coordination of Subcontractors

6. Labor law application

7. Modifications

8. Payments to Contractor

9. Payroll reports

10. Contract time

11. Liquidated damages

12. Contractor Performance Evaluation

13. Display of Hotline posters

14. Notice to proceed

15. Correspondence procedures

16. Construction Management Website

17. Acceptance/rejection of work

18. Progress meetings

19. Submittal procedures

20. NPS Final Accessibility Inspection

21. Environmental requirements

22. Permit requirements

23. As-constructed drawings/operation and maintenance (O&M) manuals.

24. Saturday, Sunday, holiday and night work.

25. Reference materials

26. Value engineering

27. Schedule of Values

B. Progress Meetings: CO will schedule weekly meetings with Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the

Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:

a. Approval of minutes of previous meetings

b. Submittal status

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)

h. Construction Schedule update (provide updated Critical Path Method (CPM)).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

k. Permit requirements

HAFE 242454 01 31 00 - 6

l. Lane closure notification for Road Report

1) Contractor to provide lane closure notifications a minimum of 3 weeks prior to closure.

C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise CO of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:

a. Contract Documents

b. Options

c. Related RFIs

d. Related Change Orders

e. Purchases

f. Deliveries

g. Submittals

h. Review of mockups

i. Possible conflicts

j. Compatibility requirements

k. Time schedules

l. Weather limitations

m. Manufacturer's written instructions

n. Warranty requirements

o. Compatibility of materials

p. Acceptability of substrates

q. Temporary facilities and controls

r. Space and access limitations

s. Regulations of agency(ies) with jurisdiction

t. Testing and inspecting requirements

u. Installation procedures

v. Coordination with other work

w. Required performance results

x. Protection of adjacent work

y. Protection of construction and personnel

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.

HAFE 242454 01 31 00 - 7

1.8 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing

Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection. The Contractor’s Environmental Manager can be satisfied with key personnel (Superintendent, Quality Supervisor, Project Manager) working in other capacities provided they have the applicable experience.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiarity with

Environmental Management Systems (EMSs) such as International Organization for

Standardization (ISO) 14001; familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of Waste Management Plan (WMP).

c. Implementation of Under-An-Acre Pollution Prevention Plan (UPPP).

d. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.

e. Training for Contractor personnel in accordance with position requirements.

f. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements

2. Regulatory Requirements

3. Noise and Acoustics Management

4. Under-An-Acre Pollution Prevention Plan (UPPP)

5. Construction Waste Management

C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:

1. Overview of environmental issues related to Project.

2. Review of site-specific procedures and management plans:

a. Construction Waste Management

b. Noise and Acoustics Management

c. Under-An-Acre Pollution Prevention Plan (UPPP)

3. Pollution Prevention (P2) practices: Submit evidence of P2 training, participation in

P2 programs, familiarity with P2 practices.

4. Compliance with environmental regulations: As specified in Regulatory Requirements.

Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of CO.

D. Prior to any tree trimming and/or removal, Contractor shall coordinate with NPS for Section 7 process consultation.

HAFE 242454 01 31 00 - 8

1.9 PERMITS

A. General:

1. Permits and Responsibilities: Contractor shall, without additional expense to the

Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.

2. For the purpose of this contract, Contractor will not be considered an agent of the

Government. Contractor shall comply with appropriate Federal, State and local laws.

B. Government Furnished Permits: During development of the project’s design, permits listed below were negotiated and agreed to by the Government. Terms and provisions of these permits shall be adhered to for the duration specified in each permit.

1. The Government is in the process of securing the following permit:

a. United States Army Corps of Engineers (USACE) Section 404 NWP 3.

The Agency with Jurisdiction for these permits is West Virginia Department of

Environmental Protection (WVDEP). No work will be permitted on the Virginius Island

Bridge until this permit has been authorized by the regulatory agencies.

C. Potential Permits: Permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist

Contractor in determining which permits will be required for contract’s chosen means and methods. The list shall not be considered complete; it is the Contractors’ responsibility to determine means and methods and obtain required permits. Contractor shall obtain all permits required to legally conduct work.

1. Encroachment and Traffic Control permits from local municipalities and state DOT may be required for lane closures and any other work requiring traffic control.

2. Special use permit for commercial vehicle usage in park from NPS

3. Construction Stormwater NPDES Permit

It is the Contractor's responsibility to secure any and all remaining pre-construction permits prior to initiating onsite work. Demonstrated permit authorization is a condition of the quality control, preapproval phase of the three phase prework planning process.

D. Coordination with Agency(ies) with Jurisdiction Issuing Permits

1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting…