Sol_140P2026R0064_Amd_0001.pdf
PDF 227 KB Posted
- Attached to
- HAFE 242454, Pavement Preservation Project Federal contract opportunity
- Solicitation number
- 140P2026R0064
About this file
This is Amendment P00001 to Solicitation 140P2026R0064, issued by the National Park Service (NPS), Denver Service Center (DSC) Contracting Services Division on June 29, 2026. The amendment addresses 25 contractor questions and answers regarding a construction project at a federal park facility.
The amendment clarifies key project requirements and constraints: contractors must submit a Phasing Plan for government approval; all work must be completed Monday-Friday, 8:00 a.m. to 5:00 p.m., with weekend or early morning work available at contracting officer discretion; an estimated 56 linear feet of tree trimming is required at the Shipley School Parking area; the 108-calendar-day performance period may be extended for unforeseen circumstances such as natural disasters, severe weather, or government-caused delays; and contractor-proposed staging and laydown areas must comply with specifications in Section 01 10 00. The Technical Proposal (Volume I) is limited to five pages maximum, including all attachments such as resumes, project sheets, organization charts, certifications, and past performance questionnaires. Regarding staffing, dual-hatting of the Superintendent, SSHO, and QC Manager will be considered based on contractor and personnel experience. The amendment confirms no site visit is required, no soil boring reports are available, survey data is not available, no bulk water fill location exists on park grounds, no landscaping restoration is required, third-party inspections are not required (government will contract separately for construction management), and survey is not required. Permitting obligations, storm water pollution prevention plans, and public access maintenance during construction are addressed in the specifications. Construction activities are anticipated to begin in calendar year 2027, ideally in spring, with exact timing dependent on contract award and Notice to Proceed issuance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P2026R0064_Amd_0002.pdf | ||
| B08_Attachment_2_HAFE_100__Drawing_Plans.pdf | ||
| B08_Attachment_3_Wage_Determination_WV20260111.pdf | ||
| B08_Attachment_4_PriceSched_-_HAFE_242454_(PavePres).xlsx | XLSX spreadsheet | |
| B08_Attachment_7_Past_Performance_Questionnaire.docx | DOCX document | |
| B08_Attachment_8_Experience_Form.docx | DOCX document | |
| B08_Conformed_Solicitation_140P2026R0064.pdf | ||
| B08_Attachment_5_General_Refrences.pdf | ||
| Sol_140P2026R0064.pdf | ||
| B08_Attachment_6_Subcontract_Percentage_Worksheet.xlsx | XLSX spreadsheet | |
| B08_Attachment_1_HAFE_100__Specifications.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Rachel Dyer
See continuation page
NPS, DSC Contracting Services Div 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287
DOI, NPS, DSC Contracting Services 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287
PDS
PDS
140P2026R0064
06/29/2026
06/29/2026
1 6
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140P2026R0064/0001
The purpose of amendment P00001 is to answer questions provided by contractors.
Question 1: Will the Government approve contractor-proposed phasing, or are there required sequencing priorities for the various project locations?
Answer 1: Phasing to be proposed by the
Contractor via a "Phasing Plan", and submitted to the CO for approval.
Question 2: Please identify any roads or parking areas that require nighttime, weekend, or off-peak work due to visitor traffic or park operations.
Answer 2: All work to be completed
Monday-Friday, 8:00am-5:00pm. If weekend or early morning hours are needed, these can be requested and approved at the COs discretion.
Question 3: Please identify the locations and estimated quantities of tree trimming and vegetation clearing required under the contract.
Answer 3: The contract has an estimated 56 LF of tree trimming at the Shipley School Parking area, RTE 0908.
Question 4: The contract provides a
108-calendar-day performance period. If environmental restrictions, special events, or weather prevent completion of seal coat or chip seal operations, will the Government consider extending the performance period?
Answer 4: Unforeseen circumstances, such as natural disasters, severe weather, or government caused delays (such as delayed site access or slow review times) may be eligible for extensions to the period of performance.
Other circumstances shall only be approved by the CO.
Question 5: Please identify approved contractor staging and material stockpile locations within
Continued...
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) the park.
Answer 5: Staging and laydown areas have not been identified by the Government. The Staging
Plan is to be provided by the Contractor.
Reference Plans Sheet 3 Bullet 7 under General
Notes, and Specifications Section Summary of
Work, 01 10 00, 1.5 Contractor Use of Site for staging information.
Question 6: Section L states that the
Government is requesting no more than five (5) pages for the Technical Approach. Please confirm whether this five-page limitation applies only to Factor 1 (Technical Approach) or to the entire Technical Proposal (Volume
I).
Answer 6: It applies to the entire Technical
Proposal.
Question 7: Please clarify whether attachments such as resumes, project sheets, organization charts, certifications, and Past Performance
Questionnaires count toward the five-page
Technical Approach limitation.
Answer 7: Yes they count. Ensure all information the government requests is provided or missing requirements will be concluded as non-responsive and technically unacceptable.
Question 8: Do the Superintendent, SSHO and QC
Manager need to be 3 separate individuals?
Answer 8: Dual-hatting will be considered for this project contingent on Contractor and personnel experience.
Question 9: Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?
Answer 9: It will be considered but required documentation providing the increase will be required.
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Question 10: Please provide the site visit attendee sign in sheet.
Answer 10: The solicitation specifically says there is no site visit so there would be no sheet.
Question 11: Does this project require phasing?
Answer 11: Phasing to be proposed by the
Contractor via a "Phasing Plan", and submitted to the CO for approval.
Question 12: Is this project tax exempt?
Answer 12: No, federal construction projects are not sales-tax-exempt for contractors in
West Virginia. While the federal government itself is exempt from paying West Virginia
Consumer Sales and Service Tax, that immunity does not extend to the businesses contracting with it.
Question 13: When do you anticipate on site work starting?
Answer 13: We anticipate mobilization and initiation of construction activities to begin in CY 2027, ideally in the spring, weather pending. Exact start time will be determined by timing of contract award and issuance of Notice to Proceed.
Question 14: Are third party inspections required?
Answer 14: No. The government will contract with a Construction Management Representative contractor for on-site support with inspections and oversight.
Question 15: Is permitting required?
Answer 15: See Specifications Project
Management and Coordination 01 21 00 1.9
Permits Bullet C. There are three identified
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) permits likely to be needed to be obtained by the Contractor. However, depending on means and methods, this list may not be complete.
Question 16: Are soil boring reports available?
If not, it will be assumed that excavation will be clear of rocks and obstructions.
Answer 16: Soil boring reports are not available.
Question 17: Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity?
Answer 17: The park does not have a bulk water fill location.
Question 18: Is any landscaping restoration required for this project? For example;
topsoil, seeding, and fertilizer.
Answer 18: No.
Question 19: Please provide staking data points for the project.
Answer 19: Survey data for this project is not available.
Question 20: Are red, yellow, and blue tops required?
Answer 20: This is means and methods question and contingent on the Contractor.
Question 21: Can we shut down each area for the duration of construction?
Answer 21: Phasing and sequencing of work will be proposed by the Contractor and reviewed and approved by the CO. If a full closure is essential to complete the work, it will be allowed, but must be done in compliance with 01
10 00 1.6 Public Use of Site: "Contractor shall conduct operations to ensure the least inconvenience to public."
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Question 22: Can we close the roadways or must we maintain one lane of traffic?
Answer 22: See note above. In most cases, roads should be maintained as open to the public during construction operations. If a closure is essential to complete work, it will be allowed.
Question 23: Is a SWPPP required?
Answer 23: Yes. Comply with requirements specified in Section 01 57 23 "Temporary Storm
Water Pollution Prevention" and storm water permit requirements identified in Section 01 31
00 "Project Management and Coordination."
Question 24: Does the contractor need to include silt fence at the LOD for the project?
Answer 24: The Contractor is required to submit an Under-An-Acre Pollution Prevention Plan for the project. It is not anticipated that this will require perimeter silt fencing for all construction activities, but this depends on means and methods.
Question 25: Is survey required?
Answer 25: It is not required.
ALL OTHER TERMS AND CONDITIONS HEREBY REMAIN
UNCHANGED.
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .