GLEN CANYON
NATIONAL RECREATION AREA (GLCA)
LAKE POWELL, UTAH
SOLICITATION 140P2026R0010
GLEN CANYON LOW WATER RAMPS (BULLFROG DISTRICT)
GLCA 318882
DESIGN-BUILD (DB) SCOPE of WORK (SOW)
NATIONAL PARK SERVICE (NPS)
DENVER SERVICE CENTER (DSC)
DB SOW GLCA 318882 | Page 2 of 54
TABLE OF CONTENTS
1.0 PROJECT INTRODUCTION
1.1 SCOPE
1.2 PROJECT WEBSITE
1.3 LOCATION
1.4 BACKGROUND
1.5 DESCRIPTION
1.6 SCHEDULE
1.6.1 POST AWARD SITE EVALUATION
1.6.2 DB DESIGN DEVELOPMENT (DD) DOCUMENTS:
1.6.3 100% DRAFT DB CONSTRUCTION DOCUMENTS (CD):
1.6.4 100% COMPLETE DB CONSTRUCTION DOCUMENTS (CD):
1.6.5 COMPLETE STAMPED AND SIGNED DB CONSTRUCTION DOCUMENTS (CD): .9
1.6.6 CONSTRUCTION:
1.6.7 AS-CONSTRUCTED DRAWINGS:
1.7 NPS CONTACTS & ADDRESS:
1.8 DATA AND MATERIALS PROVIDED BY NPS
2.0 PROJECT REQUIREMENTS
2.1 GENERAL REQUIREMENTS
2.1.1 SCOPE OF WORK AND PROJECT SUMMARY/REQUIREMENTS
2.1.2 DEFINITION OF CONTRACT LINE ITEMS
2.1.3 PROGRESS PAYMENTS
2.1.4 PROJECT MEETINGS
2.1.5 PROJECT SCHEDULE
2.2 DESIGN REQUIREMENTS
2.2.1 DESIGN DOCUMENTS
2.2.2 DB DESIGN DEVELOPMENT (DD) DOCUMENTS AND DB CONSTRUCTION
DOCUMENTS (CD)
2.2.3 ENVIRONMENTAL, REGULATORY COMPLIANCE, PERMITTING, AND
SUSTAINABILITY REQUIREMENTS FOR DESIGN
2.3 CONSTRUCTION REQUIREMENTS.................... ERROR! BOOKMARK NOT DEFINED.
2.3.1 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS .................. ERROR!
BOOKMARK NOT DEFINED.
2.3.2 SCHEDULE OF VALUES
2.3.3 CONSTRUCTION SUPPORT
2.3.4 SUBMITTALS DURING CONSTRUCTION
2.3.5 CONSTRUCTION COORDINATION
2.3.6 OTHER CONTRACTS, WORK AND EVENTS
2.3.7 DIGITAL IMAGES
2.3.8 QUALITY CONTROL
2.3.9 WORKING HOUR RESTRICTIONS
2.3.10 TEMPORARY SERVICES
2.3.11 ACCESS
2.3.12 PRESERVATION OF ADJACENT FEATURES
2.3.13 EXISTING UTILITIES
2.3.14 HAULING RESTRICTIONS
2.3.15 ACCIDENT PREVENTION
DB SOW GLCA 318882 | Page 3 of 54
2.3.16 TEMPORARY CONTROLS
2.3.17 FIELD ENGINEERING
2.3.18 PROJECT CLOSE-OUT
2.3.19 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
2.4 FORMS
2.5 APPENDIX A
2.6 APPENDIX B
3.0 PERFORMANCE REQUIREMENTS
3.1 DESIGN IMPERATIVES
3.2 SUSTAINABILITY
3.3 INTEGRATED DESIGN PRINCIPLES
3.4 FACILITY PERFORMANCE
3.5 ELEMENTS AND PRODUCTS
4.0 TECHNICAL REQUIREMENTS
4.1 OVERALL PERFORMANCE CRITERIA
4.2 DESCRIPTION
4.3 FIXED DESIGN REQUIREMENTS
4.4 TECHNICAL CONTENTS
SECTION 01 11 00 - SUMMARY OF WORK
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
SECTION 01 32 33 – PHOTO DOCUMENTATION
SECTION 01 33 23 - SUBMITTAL PROCEDURES
SECTION 01 35 13.22 – ARCHEOLOGICAL PROTECTION
SECTION 01 35 23 - SAFETY REQUIREMENTS
SECTION 01 35 25 - EXPLOSIVES
SECTION 01 40 00 - QUALITY REQUIREMENTS
SECTION 01 42 00 – REFERENCE STANDARDS
SECTION 01 50 00 - TEMPORARY FACILITIES AND CONTROLS
SECTION 01 57 19.12 – NOISE AND ACCOUSTICS MANAGEMENT
SECTION 01 57 23 - TEMPORARY STORM WATER POLLUTION PREVENTION
SECTION 01 67 00 - PRODUCT REQUIREMENTS
SECTION 01 73 29 - CUTTING AND PATCHING
SECTION 01 73 40 - EXECUTION
SECTION 01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
SECTION 01 74 19B - STANDARD SOLID WASTE CONVERSIONS
SECTION 01 77 00 - CLOSEOUT PROCEDURES
SECTION 01 78 23 - OPERATION AND MAINTENANCE DATA
SECTION 01 79 00 - DEMONSTRATION AND TRAINING
5.0 ATTACHMENTS ............................................................ ERROR! BOOKMARK NOT DEFINED.
DB SOW GLCA 318882 | Page 4 of 54
1.0 PROJECT INTRODUCTION
Park Acronym and PMIS Number: GLCA 318882B
Project Title: GLEN CANYON LOW WATER RAMPS (BULLFROG DISTRICT)
Project Drawing Number: 608 186913
1.1 Scope
In accordance with terms and conditions of the Contract, the Design-Build (DB) Contractor shall perform the work of this Request for Proposal (RFP) for the National Park Service (NPS) as described below.
Architect-Engineer (A/E) Services required in this RFP shall be performed and sealed by an appropriately licensed Architects and Engineers registered in the State of Utah (as required).
Complete this task order using requirements and criteria on Denver Service Center (DSC) Design-Build (DB) Workflows website.
The DB home page includes links to design phases that describe required workflow processes from Predesign (PD) through Construction Documents (CD). Each design phase web page contains links to definitions, forms, templates, samples, and guidelines.
The DB home page also includes links to the Design Standards and Design Deliverables sections, which provide design requirements and criteria that will be used for completing the work of this contract, as follows:
• Predesign (PD) through Construction Documents (CD) design phase requirements with definitions plus forms, templates, samples, and guidelines used for a typical project.
• Division 1 Specifications Templates: These templates represent standard information that may need clarification and addition to the DB RFP template on some projects.
• Design Standards are arranged by discipline and/or specialty.
• DB Design Deliverables - Content and Format Requirements o Design phase submission requirements for:
Technical content Submission format
• In addition, the Information section has links directly to the following:
o Definitions: A list of terms relevant to design and construction in National Parks.
o Forms/Templates/Samples/Guidelines: A list of forms, templates, samples, and guidelines used for a typical project.
o Law/Regulations/Polices/Guidance: A list of sources for retrieving laws, regulations, policies, and guidance applicable to NPS projects.
o Quality Assurance (QA) Guideline & Review Checklists: Overview of the DSC QA process for reviewing design documents.
In case of conflict between this contract and the DSC DB Workflows website, this contract shall take precedence and shall be used in lieu of conflicting portions.
DB SOW GLCA 318882 | Page 5 of 54
The Design-Build (DB) Contractor remains fully responsible for determining if the standards or provisions cited on the DSC DB Workflows website have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the Contracting Officer (CO).
1.2 Project Websites
Use the Government provided website to host and manage project communication and documentation until Final Completion. The project website will be used for:
• Project directory
• Project correspondence
• Meeting agendas and minutes
• Contract modifications documentation and logs
• RFI (Request for Information) form and processing
• Task and issue management
• Photo documentation
• Baseline schedule, schedule updates and calendar management
• Submittal form and processing
• Drawing and specification document hosting, viewing, and updating
• Online document collaboration
• Reminder and tracking functions
• Archiving functions
• Notification of submittal and RFI statuses and current responsible party
Submit to the CO a list of employees needing access to the Government provided website. The Department of Interior (DOI) will send these users an invitation to the site. Users are required to have Internet Explorer version 7 or later and Adobe Acrobat Professional version 9 or later.
DB Contractor to provide a website for public information and project status. Provide website layout for review and approval by the CO within the first 21 days after contract award.
1.3 Location
This project is located at Glen Canyon National Recreation Area (GLCA), Bullfrog District, in Utah.
1.4 Background
Glen Canyon National Recreation Area (GLCA) is predicting that within the near future North Lake Powell will have no operable boat launch ramps due to historically low water levels. The area currently has two marinas, Bullfrog and Halls Crossing, which are operated and maintained primarily by Aramark, a concessioner of the National Park Service. The area also has many land-based structures which include lodging facilities, campgrounds, boat rentals and boat storage while the marinas are the two floating structures that have fuel pumps, stores, snack bars and covered boat slips for storing vessels. Utilities servicing the local need are operated by both Aramark and NPS as there are no independent power, sewer, water companies in this area. .
Facilities at Halls Crossing are currently open although these services vary seasonally and based on launch ramp water levels. A ramp extension at Bullfrog was completed this spring and provides access to 3529’ for houseboats and to 3525’ for smaller vessels. As of November 21, 2022, the elevation of Lake Powell is 3528.6’.
DB SOW GLCA 318882 | Page 6 of 54
Bullfrog remains the only low-water access to North Lake Powell. Constructing an additional low-water ramp at Bullfrog would provide continued lake access to an elevation of 3450’.
This project will address low water lake access for the Bullfrog District based upon the relocation of the launch ramp to a new deep pool location. The work includes a new access road, water, wastewater, power, and telecom utility extensions, parking lot, and launch ramp.
1.5 Description
The specific purpose of the project is to ensure long term sustainable lake access at Antelope Point by designing and constructing a new high and low water launch ramp. The ramp will be designed to accommodate lake elevations between 3,450 and 3,700 feet. Due to funding limitations, construction will match the full design grade, but the actual service elevation will depend on the awarded bid option. This approach ensures that any future extensions can be built without reconstructing any of the ramp completed under this project. Facilities supporting the new ramp include new boat and passenger vehicle parking areas.
Boat Ramp Water Surface Elevation Performance and Risk Balancing
Baseline Condition for Construction Planning
For purposes of construction planning, sequencing, and risk allocation, the Government establishes a baseline lake surface elevation of 3,520 feet as the assumed water surface elevation during design development and construction.
The Design-Builder shall base its construction approach, sequencing, temporary works, and cost assumptions on this baseline condition.
Normal Fluctuations (No Adjustment)
The Design-Builder shall accommodate normal lake surface elevation fluctuations between 3,495 feet and 3,545 feet (±25 feet from the baseline) through reasonable design and construction means, without entitlement to adjustment in contract price or time.
Seasonal Construction Assumption
For purposes of construction planning and risk allocation, the Design-Builder shall assume that in-water construction activities will occur during the Fall and Winter seasons.
The Design-Builder shall plan sequencing, access, temporary works, and means and methods accordingly.
Seasonal conditions typical of Fall and Winter operations including reduced daylight, colder temperatures, precipitation, and expected seasonal lake surface elevation trends, shall not, by themselves, constitute a changed condition.
Any in-water work performed outside the seasonal construction assumptions described above shall be undertaken at the Contractor’s sole risk and shall not constitute a basis for a change condition, time extension, or additional compensation.
Changed Condition Evaluation Trigger
DB SOW GLCA 318882 | Page 7 of 54
Notwithstanding the design performance requirements above and the seasonal construction assumptions herein, a lake surface elevation shall be considered eligible for evaluation as a changed condition only if the following threshold is met:
• The lake surface elevation exceeds 3,545 feet or falls below 3,495 feet for a continuous period of seven
(7) consecutive calendar days.
Short-term fluctuations, seasonal trends, or conditions reasonably anticipated during Fall and Winter in-water work shall not constitute a changed condition.
Higher Water Levels (Government Risk)
If the lake surface elevation exceeds 3,545 feet and meets the changed condition evaluation trigger during construction, the Government will consider this a changed condition.
The Government may issue a contract modification to reduce, adapt, or modify the ramp to maintain functional performance, with an equitable adjustment in time and/or price for the benefit of the Design-Builder.
Lower Water Levels (Government Benefit)
If the lake surface elevation falls below 3,495 feet and meets the changed condition evaluation trigger during construction, the Government will consider this a changed condition.
The Government may issue a contract modification for credit, or other adjustment for the benefit of the Government.
Risk Clarification
Notwithstanding the requirement to design the ramp to function across elevations 3,700 feet to 3,450 feet, contractual risk for lake surface elevation during construction is directly tied to the 3,520-foot baseline and the fluctuation limits and triggers defined above.
To align the project with available funding, a base schedule and optional betterments will be evaluated as follows:
BASE SCHEDULE:
• CLIN 1 BASE – DESIGN
o 150-foot-wide low water boat ramp servicing elevation 3700 to 3450-ft, a 2,419-ft length on the horizontal along a 10.5% grade.
o 8.3 Acre asphalt boat parking area connected to the top of the ramp o 0.7 Acre asphalt passenger vehicle parking area o Includes supplemental design effort supporting the awarded construction base + scalable options and NPS support needs for NEPA/Permitting.
• CLIN 2 BASE - CONSTRUCTION - ACCESS ROAD/UTILITIES
o Construct a two-lane gravel access road connecting US 276 to the parking area.
o Construct utilities (potable water, wastewater, power, and communications) servicing the top of the launch ramp.
DB SOW GLCA 318882 | Page 8 of 54
• CLIN 3 BASE - CONSTRUCTION - PARKING AREA (8 ACRE)
o Construct an 8-acre gravel parking area.
• CLIN 4 BASE - CONSTRUCTION - 90-FOOT WIDE LOW WATER RAMP (3700 to 3570)
(matching the 3450 design in CLIN 1)
• CLIN 5 BASE - CONSTRUCTION - 90-FOOT WIDE LOW WATER RAMP (3570 to 3545)
• CLIN 6 BASE - CONSTRUCTION - 90-FOOT WIDE LOW WATER RAMP (3545 to 3520)
• CLIN 7 BASE - CONSTRUCTION (IN WATER) - 90-FOOT WIDE LOW WATER RAMP (3520
to 3490) (matching the 3450 design in CLIN 1)
BID OPTIONS:
• CLIN 8 Option E - CONSTRUCTION (IN WATER) - 90-FOOT WIDE LOW WATER RAMP
(3490 to 3450) (matching the 3450 design in CLIN 1)
• CLIN 9 Option A - CONSTRUCTION - Widen from 90-FOOT to 150-FOOT WIDE LOW WATER
RAMP (3700 to 3570) (matching the 3450 design in CLIN 1)
• CLIN 10 Option A - CONSTRUCTION - Widen from 90-FOOT to 150-FOOT WIDE LOW
WATER RAMP (3570 to 3545) (matching the 3450 design in CLIN 1)
• CLIN 11 Option A - CONSTRUCTION - Widen from 90-FOOT to 150-FOOT WIDE LOW
WATER RAMP (3545 to 3520) (matching the 3450 design in CLIN 1)
• CLIN 12 Option A - CONSTRUCTION (IN WATER) - Widen from 90-FOOT to 150-FOOT WIDE
LOW WATER RAMP (3520 to 3490) (matching the 3450 design in CLIN 1)
• CLIN 13 Option F - CONSTRUCTION (IN WATER) - Widen from 90-FOOT to 150-FOOT WIDE
LOW WATER RAMP (3490 to 3450) (matching the 3450 design in CLIN 1)
• CLIN 14 OPTION B - PARKING AREA (CONSTRUCTION)
o Expand the 8-acre gravel parking area (Base) to a 16-acre gravel parking area.
• CLIN 15 Option C - ACCESS ROAD PAVING (CONSTRUCTION) o Add asphalt surfacing to the gravel access road (Base).
• CLIN 16 Option D - PARKING AREA PAVING (CONSTRUCTION) o Add asphalt surfacing to the 16-acre gravel parking area (Option G).
1.6 Schedule
DB SOW GLCA 318882 | Page 9 of 54
Complete work in this SOW according to following schedule, with a total of 730 days for design and construction:
1.6.1 Post Award Site Evaluation
The DB Contractor will meet with NPS onsite to review the proposed solution presented in the proposal package.
This site visit is to occur no later than 21 calendar days after award. It is expected that a 3-day visit will be required. A pre-visit teleconference meeting will be conducted with NPS and the Park at least 14 calendar days before the site visit, such that logistics can be coordinated before the visit.
1.6.2 DB Design Development (DD) Documents:
Submit DB DD Documents no later than (to be defined by Design Build Contractor proposed scheduled) calendar days after award.
Allow no less than 15calendar days for NPS Review after submitting DB DD Documents.
1.6.3 100% Draft DB Construction Documents (CD):
Continue work on 100% Draft DB CD during DB DD Documents review. After receiving DB DD review comments, address and incorporate comments in 100% Draft DB CD.
Submit 100% Draft DB CD and responses to NPS Review form with responses to DB DD Documents no later than (to be defined by Design Build Contractor proposed scheduled) calendar days after receiving NPS Review comments of the DB DD Documents.
Allow no less than 15calendar days for NPS Review after submitting 100% Draft DB CD.
1.6.4 100% Complete DB Construction Documents (CD):
Submit 100% Complete DB CD and NPS Review form with responses to 100% Draft DB CD review comments no later than (to be defined by Design Build Contractor proposed scheduled) calendar days after submitting 100% Draft DB CD.
Allow no less than 15 calendar days for NPS Review after submitting 100% Complete DB CD.
1.6.5 Complete Stamped and Signed DB Construction Documents (CD):
Submit Complete Stamped and Signed DB CD and NPS Review form with responses to 100% Complete DB CD review comments no later than 15 calendar days after receiving NPS review comments.
1.6.6 Construction:
Construction begins when CO issues DB On-site Notice to Proceed (NTP) – authorizing ground disturbing activities.
DB SOW GLCA 318882 | Page 10 of 54
Complete design and construction no later than 710 calendar days following issuance of the NTP . Actual contract completion date will be established based on the proposer’s schedule. Site mobilization is to begin before construction start. Refer to Section 2.1.5 Project Schedule.
1.6.7 As-Constructed Drawings:
As constructed plans of the completed construction project are needed to provide a historic record of all work accomplished on this project. These plans are used as future references for needed repairs, maintenance, and construction projects.
Maintain one record copy of all design documentation at the site, in good order and regularly updated to show all changes made during construction. Make these documents, along with all other submittals made by the DB Contractor, available to the CO during construction.
Submit Final As-Constructed Drawings no later than 21 calendar days after Substantial Completion to the CO for review and approval.
Submit DB DD Documents, DB CD, and As-Constructed Drawings to the NPS Construction Management Representative (CMR), the NPS Project Manager (PM), and the NPS Project Specialist.
Include within Division 1 Specifications, regular updates, and submittals of the as constructed drawings to keep current and accurate record.
A retention amount of $500k will held by the Government until final acceptance of the as-constructed drawings by the CO.
1.7 NPS Contacts & Address:
Contractual:
Contracting Officer (CO): Tony Jasper, 303-969-2789, anthony_jasper@ios.doi.gov Contract Specialist (CS): None
Technical:
Project Manager (PM) and Contracting Officer’s Representative (COR): Michael Will, PE, 303-956-5054, mike_will@nps.gov Project Specialist (PS) and Alternate Contracting Officer’s Representative: Travis Kraft,, 303-918-9997, travis_kraft@nps.gov
Address:
National Park Service - Denver Service Center 12795 West Alameda Parkway Post Office Box 25287 Denver, Colorado 80225
1.8 Data and Materials Provided by NPS
DB SOW GLCA 318882 | Page 11 of 54
Schematic Design (SD) dated January 2023 has been performed for the site. The initial engineering documents and concepts will be provided as reference documents by the government; however, these reference documents are not considered design-build bridging documents and may be used at the discretion of the DB Contractor.
The Bullfrog Launch Ramp SD package includes the following ultimate full build elements (base schedule plus options):
• Approximate 3.1 mile, 2-lane asphalt access road with 3ft asphalt shoulders to new boat launch location.
• Approximate 700,000 SF asphalt parking area
• 150ft wide concrete launch ramp serving water elevations 3,450’ to 3,700’
• New utility service to the top of ramp including water, wastewater, electrical and communications lines that terminate and capped at the top of the ramp.
NPS will provide to DB Contractor the following data and materials:
• Project Program
• NPS Design Build Workflow o Design-Build (DB) - (U.S. National Park Service) (nps.gov) o Design Build Deliverable Requirements o Quality Assurance Guidelines
• SD Basis of Design Report (BDR)
• Visitor Use Study
• Approved Schematic Design Preferred Alternative Full Build – Plan
• NPS Project Sustainability Checklist
• Field Mapped Utility survey data
• Topographic (arial and bathymetric) survey data
• Geotechnical Subsurface Investigation Information
• Wetlands delineation
• *NEPA compliance authorization (in process)
*NPS is in process of securing NEPA compliance approvals. Approvals are expected no later than June 1, 2023.
No ground disturbance is permitted prior to NEPA approvals. Current documents include anticipated NEPA compliance requirements, however final approval has not been received.
2.0 PROJECT REQUIREMENTS
2.1 General Requirements
2.1.1 Scope of Work and Project Summary/Requirements
The project will consist of the design and construction of a new access road, which is approximately 3.1 miles long, from US 276 to the new launch ramp location. A new parking area will be designed and constructed that is between 6 and 16-acre of area with a houseboat turnaround at the top of the ramp. A new launch ramp between 90 and 150 ft wide will be designed and constructed accommodating lake access between elevations 3445 and 3700. New water, wastewater, power, and telecom utilities will be installed servicing the top of the new launch
DB SOW GLCA 318882 | Page 12 of 54 ramp.
The project will include, but not be limited to:
• Design and Construction of roadway, parking area, utilities (water, wastewater, electric, communications), and a launch ramp system including associated incidental work.
• Review Schematic Design preferred alternative provided in the RFP package
• Review site data.
• Submit DB Design Development and DB Construction Documents for review and approval, as required.
• Secure all permits necessary to support construction in accordance with all local, state, and federal requirements. Refer to Section 2.2.3.
• Project Management
• Geotechnical investigation/analysis as necessary to complete the work.
• Survey as necessary to complete the work.
• Lifecycle cost analysis
• Provide, manage, and update schedule of design and construction work.
• Quality Control
• Materials Sampling and Testing
• Maintenance during construction including but not limited to erosion management, traffic management, etc.
• Conduct Paleontological monitoring during ground disturbance.
• Provide for continued access to existing facilities.
• Provide new construction GIS data supporting updates to the NPS GIS database
• Provide as-constructed drawings.
The DB Contractor will identify any previously undefined deficiencies or failures that are uncovered as part of their due diligence.
2.1.2 Definition of Contract Line Items
In general, explain what is included in each contract line item, limits or cut-off points where one item ends, and another begins. If no item exists for a portion of the work, include costs in a related line item.
See subsection 1.5 above.
2.1.3 Progress Payments
Design Phase - Progress payments will be based on submission, review, and acceptance of design deliverables.
Construction Phase - Progress payments will be based on percentage of work completed on items listed in approved schedule of values. Actual construction completed and in place will form basis for payment. DB Contractor shall verify percent complete under direction of the COR unless CO waives this requirement in a specific instance. DB Contractor shall make computations for payment based on Government’s verification of work completed and in place for periods which progress payments are requested.
DB Contractor shall furnish to the CO originals of field notes and other records relating to basis for payment.
The CO shall use as necessary to determine final amount of progress payments. DB Contractor shall retain copies of material furnished to CO.
DB SOW GLCA 318882 | Page 13 of 54
2.1.4 Project Meetings
Kickoff and Design Meeting
After award of the contract and acceptance of Performance and Payment bonds, the CO will arrange a kickoff and design meeting with DB Contractor. Meeting agenda shall include the following as a minimum:
• Areas available for use by DB Contractor
• Access requirements of the Park
• Design schedule including dates each required permit will be secured (minimum two color hard copies).
• Environmental and sustainability requirements
• Natural and Cultural Resource Protection
• Payments to DB Contractor
• Review and emphasize Park needs and design objectives.
• Modifications during design
• Schedule of Values
• Submittals during design
• Site Visit
• Utility connection/outages
Preconstruction Meeting
Submit following Part 2 Project Requirement deliverables a minimum of one week prior to Preconstruction Meeting.
• Accident Prevention Program (APP)
• Evidence of liability insurance coverage and workman’s compensation for DB Contractor and
Subcontractors
• Letter designating your Project Superintendent
• List of obtained and required construction permits
• List of Subcontractors for project (same as proposal)
• Project Schedule with construction portion fully developed
• Quality Control Plan
• Comprehensive breakdown of the Schedule of Values for all elements of work
• National Pollutant Discharge Elimination System (NPDES) permit application forms including Storm
Water Pollution Prevention Plan (SWPPP)
• Waste Management Plan
• Written statements from Subcontractors certifying compliance with applicable labor standard clauses
After 100% Complete DB CD are approved (or completed portions of DB Construction Documents necessary for fast tracking the project), and before start of construction, The CO will arrange on-site Preconstruction meeting with DB Contractor. Meeting agenda will include the following as a minimum:
• Accident reporting
• Construction schedule (provide electronic copy in software it was created in and a Portable Document
File [PDF] copy)
• Correspondence procedures
• Jobsite safety
DB SOW GLCA 318882 | Page 14 of 54
• Labor standards
• Lines of Authority
• Modifications
• Government provided project website
• Park Rules and Regulations
• Payroll reports
• Progress Payments
• Resolution to comments provided by NPS on the Part 2 Project Requirements
• Roles and responsibilities
• Schedule of Values
• Submittal process
• Access and site constraints.
• Medical emergency processes, availability, emergency numbers, and contacts.
• Park permits, burning construction waste, rules of the road, alcohol use, housekeeping, firearms, pets, natural and cultural resource concerns.
• Public relations.
• Archeological Resources Protection Requirements
• Environmental and sustainability requirements for the Project, required tracking for sustainability (related submittals), and use of NPS Project Sustainability Checklist.
• Saturdays, Sundays, holidays and night work.
• Traffic control.
Progress Meetings
DB Contractor shall participate in weekly telephone conference calls with CO and other project team members with updates to following meeting agenda items:
• Approval of minutes of previous meetings.
• Review of off-site fabrication and delivery.
• Requests for Information (RFI) and issues.
• Schedule update to include the following:
o Provide updated CPM (Critical Path Method) schedule o Provide hard copies for all on-site meetings o Three week lookahead o Work in progress and projected o Three Phase Meeting Schedule
• Status of Project Record Drawings and O&M (Operation & Maintenance) Manuals.
• Submittal status.
• DB Contractor website updates
• Project Risk and Opportunity Identification and Monitoring
• Safety Debrief
• Other business relating to work.
Over-the-Shoulder Reviews
Over-the-Shoulder reviews are strongly encouraged to enhance the partnering efforts between the DB Contractor and the Government. The intent of Over-the-Shoulder reviews is to provide guidance to the DB Contractor during the project. Over-the-Shoulder reviews will be conducted for informal review of designs only and do not
DB SOW GLCA 318882 | Page 15 of 54 replace the Overall Project Submittals. Over-the-Shoulder reviews may be scheduled by the DB Contractor or NPS. Requests for reviews must be in writing and allow at least 7 calendar days-notice prior to the proposed review. The number and timing of the reviews will be discussed at the Project Kick-off Meeting. Reviews will be held at a location approved by the CO.
2.1.5 Project Schedule
The DB Contractor must ensure construction materials, supplies, and equipment are procured with sufficient time to start construction without delay.
General: DB Contractor shall upload project schedule to Government provided project website and provide two
(2) color copies after award and before the design kick-off meeting. Schedule shall include detailed design phase with design deliverable submission dates, review periods, and summary construction schedule with important milestones included for both phases.
Fully develop construction portion of project schedule and submit to CO. Update the full project schedule monthly throughout contract period until project substantial completion. Status date of each schedule update shall be 10 days before the progress payment request date.
Construction work cannot begin until Government approval is obtained for any of the following or as described otherwise:
• Entire set of 100% Complete DB CD.
• Fast track construction: 100% Complete DB CD affecting work to be constructed.
• DB Contractor obtains required permits as listed in Section 2.2.3
• CO issues DB Start Work Notice
• DB Contractor provided project website
• CO may authorize a limited NTP for any portion of the project or for purchasing or stockpiling of approved material.
o Early construction may begin on any approved Specific Element Submittal at the sole risk of the
DB Contractor. Do not start work prior to approval or acknowledgement by the CO. The extent, acceptability, and schedule for early construction reviews will be mutually agreed as requested based on information contained in the Schedule and its approval. The CO will stop any work that does not comply with environmental, legal, standard or permitting requirements of the contract or project.
Purpose: Project schedule ensures adequate planning, coordinating, scheduling, and reporting of DB Contractor’s design and construction activities. Project schedule will assist DB Contractor and CO to monitor work progress, evaluate proposed changes, and process DB Contractor's monthly progress payment requests.
Software: Latest version of Microsoft Project, Primavera Project Planner, SureTrak, or approved equal.
Schedule Development: Project schedule shall cover entire contract period. Late finish date is same as contract’s established completion date.
DB Contractor shall use Critical Path Method (CPM) with limited use of lead or lag durations between schedule activities. DB Contractor's project schedule shall consist of procurement activities (including mobilization, submittal, and fabrication and delivery of key and long-lead procurement items) and construction activities.
DB SOW GLCA 318882 | Page 16 of 54
DB Contractor's project schedule shall consist of, but not be limited to, the following for each activity:
• Identify activities and numbers numerically (maximum 5-digit). Number activities in increments of 10.
• Concisely describe work represented by activity (maximum 48 characters). Avoid using non-standard abbreviations. Limit work related to each activity to one work trade.
• Activity duration shall be in whole working days with maximum duration 15 workdays each, unless otherwise approved by the CO, except for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing.
DB Contractor shall ensure project schedule includes own work and Subcontractor work.
Follow all Federal, state, and local labor laws. Schedule at least 2 non-work days out of every 14 calendar days.
The selected non-work days do not need to be consecutive, but they must be scheduled.
Project schedule shall show sequence and interdependence of activities required for complete performance of work and shall be cost and resource loaded. DB Contractor shall ensure work sequences are logical and project schedule shows a coordinated work plan. Proposed durations assigned to each activity shall be DB Contractor's best estimate of time required to complete activity, considering scope and resources planned. Resource loading of each activity shall list personnel by labor category and equipment type, and capacity proposed to complete activity in duration shown. Include permit requirements and constraints. Consider and include seasonal weather conditions in planning and scheduling of work influenced by high or low ambient temperatures and wind and/or precipitation, to ensure completion of work within contract time.
Project Schedule Updates
Monthly updates: Monthly updates of project schedule shall be an integral part and basic element of estimate upon which progress payments shall be made under this contract. If, in judgment of the CO, the DB Contractor fails or refuses to provide schedule of values and complete schedule update or revision as specified hereinafter, the DB Contractor shall be deemed to have not provided required information upon which progress payment may be made and shall be subject to retainage of a portion of the payment.
Narrative: Include in report:
• Brief description actual progress made during update period.
• Actual and potential delaying activities.
• Impediments to progress.
• Issues related to inclement weather.
• Progress toward established milestones.
• Project float.
• Brief description of work anticipated to be performed in next month.
• Identify minor revisions to schedule for evaluation and accepted or rejected.
As work progresses, indicate Actual Completion percentage for each activity. If schedule update shows late finish date after contract completion date, at a minimum, include the following in narrative with submission:
• Known delays.
• Actions taken to get back on schedule.
DB SOW GLCA 318882 | Page 17 of 54
• Pending modifications.
• Impediments or constraints affecting progress.
Progress Payments: Update currently accepted construction schedule monthly. If DB Contractor fails to provide monthly updates or revisions to currently accepted construction schedule, a portion of monthly payment may be retained until updates/revisions made.
Time Impact Analysis for Contract Modifications, Changes, Delays, and DB Contractor Requests Requirements: When contract modifications or changes are initiated, delays are experienced, or DB Contractor revises project schedule, DB Contractor shall submit to the CO a written time impact analysis illustrating influence of each modification, change, delay, or DB Contractor’s request on the contract time.
• Time Extensions: Activity delays shall not automatically mean an extension of contract time is warranted or due to DB Contractor. It is possible that modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of available total float that may exist within an activity chain of the project schedule, thereby not effecting the contract time. Time extensions will be granted according with terms of contract.
• Float: Float is not for exclusive use or benefit for NPS or DB Contractor. Extension of contract time is granted only to extent the equitable time adjustments to activity or activities affected by modification, change, or delay exceeds total (positive or zero) float available on a particular activity.
2.2 Design Requirements
2.2.1 Design Documents
2.2.1.1 Design Basis
The proof of concept for the project is defined by the BDR documents, SD drawings, and RFP documents. These documents demonstrate the ultimate build concept for the following project elements:
o Access Roadway alignment o Parking lot layout and location o Utility Services o Launch ramp size, location, and alignment.
2.2.2 DB Design Development (DD) Documents and DB Construction Documents (CD)
Prepare DB Design Development Documents and DB Construction Documents using English System of Weights and Measurements and according to DSC Design Standards and DSC Design Deliverables - Content and Format Requirements for DB Design Development Documents and DB Construction Documents.
List salient characteristics for products and materials specified. Refer to Guide for Specifiers.
Deliverables
• Submit documents in native and PDF (Portable Document Format) file formats.
• PDF files shall be unlocked to allow printing and saving.
DB SOW GLCA 318882 | Page 18 of 54
• See DB Submittal Requirements, Design Deliverables.
The following deliverables are required (refer to Section 1.6 for schedule):
• Submit DB DD Documents for Review o Draft DB Design Development Drawings o Divisions 2 through 49 Outline Specifications o Product File o Statement of Structural Tests and Special Inspections o Design Calculations
• Submit 100% Draft DB CD for Review o 100% Draft DB CD o Divisions 2 through 49 Construction Specifications (Construction Specifications Institute (CSI)
MasterFormat 04 Edition). A/E shall utilize and modify their own Divisions 2 through 49 Construction Specifications templates.
o Product File o Statement of Structural Tests and Special Inspections o Design Calculations o Checklists for internal review of drawings, specifications, calculations, and cost estimates
Required documents for each submission are included and complete per contract requirements.
Required documents have been through a Quality Control (QC) review. NPS requires documentation and submittal of QC work performed.
o NPS Review form with responses to DB DD Documents review comments
• Submit 100% Complete DB CD for Final Approval o 100% Complete DB Construction Drawings o Divisions 2 through 49 Construction Specifications o Product File o Statement of Structural Tests and Special Inspections o Design Calculations o Checklists for internal review of drawings, specifications, calculations, and cost estimates
Required documents for each submission are included and complete per contract requirements.
Required documents have been through a Quality Control (QC) review. NPS requires documentation and submittal of QC work performed.
o NPS Review form with responses to 100% Draft DB Construction Documents review comments
• Submit Complete Stamped and Signed DB CD o Upon final approval of 100% Complete DB CD, submit the complete stamped and signed DB CD in accordance with Table 2.1 for construction, NPS archiving, and general use. For format and media submission requirements, refer to Design Deliverables – Content and Format Requirements DB Hard Copy and Electronic Submittal Requirements.
DB SOW GLCA 318882 | Page 19 of 54
TABLE 2.1. Deliverables
Complete Stamped and Signed DB CD Electronic Formats[a]
Hard Copy Formats
DB Construction Drawings AutoCAD and PDF N/A
Divisions 2 through 49 Construction Specifications PDF and MS (Microsoft) Word
N/A
Product File PDF N/A Statement of Structural Tests and Special Inspections PDF and MS Word N/A Supplemental Design Reports PDF N/A Design Calculations PDF N/A Checklists for Internal Review of Drawings, Specifications, Calculations, and Cost Estimate PDF and MS Excel N/A
NPS Review Form with Responses to 100% Complete DB CD Review Comments PDF and MS Excel N/A
[a] The recipient of the electronic files is TIC (Technical Information Center).
DB Construction Drawings printed from secondary software (e.g., Adobe.pdf) are not acceptable as they often result in off-scale product.
The DB Contractor will provide electronic copies of the DD and Draft CD drawings to the PM, project specialist, and the Park for each review.
Changes to CD documents. The DB Contractor may initiate design changes at any time during the process.
(a) Design Changes Prior to CD Submission. If the proposed design change occurs after a scheduled intermediate review, notify the CO in writing. In the notification, provide the following regarding the change: a general overview, reasons and justifications, and schedule impacts. Incorporate the change into the Final Submittal after receiving written approval from the CO.
(b) Design Changes After Final Design Submission. If the proposed design change occurs after a final design submission, submit a revised final design submittal for the affected segment of the project.
Conform with the technical requirements specified for that submittal type. In addition, provide the following regarding the change: a general overview, reasons and justifications, and schedule impacts.
The Government turn-around time for changes to approved CD documents is 21 calendar days, from the day the submittal is received to the day it is sent back to the DB Contractor.
2.2.3 Environmental, Regulatory Compliance, Permitting, and Sustainability Requirements for Design
NPS established environmental and sustainability requirements for the project. Notify the CO if conflicts arise between performance of work and environmental and sustainability requirements. NPS does not intend to limit alternative means of achieving these requirements.
For sustainability requirements for design, see Part 3 Performance Requirements and NPS Project Sustainability Checklist. Complete checklist by concisely explaining how each credit/requirement will be met.
DB SOW GLCA 318882 | Page 20 of 54
National Environmental Policy Act Compliance
NPS is in process of securing authorizations for compliance with the National Environmental Policy Act (NEPA). Compliance authorizations are anticipated no later than (June 1, 2023). No ground disturbance is permitted prior to NEPA approvals.
Permits:
Table 2.2 summarizes the environmental regulatory compliance and permitting requirements for the project, along with identifying relevant legal citations, typical associated time frames, and NPS and the DB contractor’s roles and responsibilities in relation to the development of the document for each.
TABLE 2.2. Permits
Item Legal Citation(s) NPS Role DB Role Time Frame
Sec. 404/10 Sec. 401 State Water Quality Certification (if necessary)
Clean Water Act
(CWA) § 404,
Executive Order (EO) 11990, 33 U.S.C.
1344, 33 U.S.C. 403
(R&HA 1899 §§9-10),
CWA § 401
Lead
Support Permit authorizations secured prior to initiating in-water work.
Utah Pollutant Discharge Elimination System (UPDES) General Construction (Storm Water)
CWA § 402, Utah Administrative Code R317-8-3.9
Support Lead Permit authorizations secured prior to initiating ground-disturbance work.
NOTE: Other regulatory compliance and permitting actions for construction and operation of the system may be required. The Contractor is responsible for obtaining any other Federal, State, or local authorizations not listed above, as required by law.
Clean Water Act
Section 404 Permit; Section 401 Water Quality Certification
The Government will be responsible for securing authorization and complying with Clean Water Act approvals and provisions.
UPDES Storm Water General Permit for Construction
A UPDES General Permit authorizing discharges of storm water associated with construction activity will be required for the project. The DB contractor will lead all actions related to requesting coverage under the state’s existing UPDES permit program, and will apply as the operator on the permit.
Construction activities that disturb one or more acres of land must be authorized under the Utah Pollutant Discharge Elimination System (UPDES). Owners and general contractors are required to obtain a Storm Water Permit, UPDES Construction General Permit Number UTRC00000 effective July 8, 2020. This permit may cover all types and sizes of construction activity. Utah Administrative Code R317-8-3.9 requires UPDES construction storm water permits for soil disturbances of an acre or more, including less than an acre if it is part
DB SOW GLCA 318882 | Page 21 of 54 of a common plan of development or sale (that is over an acre). Soil disturbance is described as clearing, grading, or excavating. A Notice of Intent (NOI) must be filed for this permit and an SWPPP must be developed and submitted to the state as well as the payment of a fee. There is no automatic coverage under the permit.
The DB contractor will be responsible for identifying and obtaining all required UPDES permits and permit requirements (including NOI, SWPPP, Notice of Termination [NOT], and any other requirements) for construction of the project.
Noise Permit or Variance
The DB contractor will be responsible for obtaining all necessary noise permits or variances.
2.3 Construction Requirements
2.3.1 Environmental and Sustainability Requirements
The National Park Service Contracting Officer will oversee the construction of the project to ensure all environmental commitments detailed in the plans and special contract requirements are met. Provide immediate corrective measures as directed by the CO when notification is given that the work is out of compliance.
Specific sustainability requirements generated in design will dictate more stringent environmental requirements for this project. Refer to Part 3 Performance Requirements, Part 4 Technical Requirements, and NPS Project Sustainability Checklist. General requirements:
• Site Disturbance: Minimize construction limits of project to reduce impact on site.
• Toxic Chemicals: Avoid materials that can leach toxic chemicals into ground water. Do not allow toxic chemicals to enter sewers or storm drains or contaminate land or any body of water. Refer to NPS Project Sustainability Checklist for additional requirements.
• Soil Erosion: Protect against erosion and topsoil depletion according to Stormwater Pollution Prevention Plan (SWPPP).
• Habitats: Protect natural habitats and ecological systems on facility site as identified in the biological assessment.
• Noise: Minimize noise during construction. Operate power equipment according to local noise restrictions.
• Waste Management: Employ processes ensuring minimal waste output and in landfills. Recycling is a requirement of this project. Legally dispose materials unsuitable for recycling at public or private dumping areas outside the Park.
• Hazardous Materials: Preliminary analysis indicated there are no contaminated sites. However, if the DB contractor identifies any hazardous materials, they should notify NPS and develop a plan for correct handling and disposal.
DB Contractor shall designate an on-site party (or parties) responsible for instructing workers and overseeing environmental and sustainability requirements of this project. Distribute copies of environmental and sustainability requirements to Job Site Foreman and each Subcontractor.
Waste Management Plan: Prior to scheduled Preconstruction meeting, DB Contractor shall submit draft Waste Management Plan to CO for approval. Develop and implement according to ASTM E1609 and as required in contract documents. Plan shall include, but not be limited to:
DB SOW GLCA 318882 | Page 22 of 54
• List of recycling facilities, reuse facilities, municipal solid waste landfills, and other disposal area(s) to be used. Include name, location, and phone number.
• List of proposed materials to be reused or recycled.
• List of materials that cannot be recycled or reused with explanation or justification.
• Storage and collection methods of waste and recyclables, handling procedures, and means of keeping recyclables free of contamination.
• Describe means of transporting recyclable materials and estimate frequency of emptying bins.
• Identity person or persons responsible for ensuring project recycling goals are achieved.
• Revise and resubmit Plan per Contracting Officer. Approval of DB Contractor’s Plan does not relieve DB
Contractor of complying with applicable environmental regulations.
Progress Documentation: Supplemental to Waste Management Plan; document solid waste disposal, diversion, and cost/revenue analysis, and submit completed worksheet when waste is removed from the Park. Use Appendix A – Project Waste Management Plan Worksheet and report totals to date for column headings. Use Appendix B for solid waste volume to weight conversions
Prior to commencement of work, schedule and conduct meeting with CO. Discuss proposed Waste Management Plan and develop mutual understanding of details of environmental protection.
Minimize Construction Impacts
Implement following mitigation measures to minimize impacts of construction activities:
Soil Erosion: Protect against erosion and topsoil depletion. An UPDES General Permit and SWPPP is required.
Exotic Vegetation and Noxious Weeds: Prevent introduction and minimize spread of exotic vegetation and noxious weeds. Incorporate following procedures:
• Obtain fill, rock, or additional topsoil needed from a Government-approved source.
• Imported commercially sourced materials must be certified weed free before entering the Park.
• Prevent propagation of nuisance weeds: Wash equipment if moving between sites within the Park and if working in a weedy area.
• All vehicles/vessels, machinery, tools, and equipment used to implement project will be cleaned (dirt, weed/seed free or cleaned, drained, and dried) and inspected prior to entering the park to ensure they do not introduce or spread non-native species (terrestrial or aquatic).
Revegetation: The National Park Service is responsible for revegetation activities on this project. Notify the CO and its representative when sites will be available for revegetation treatments.