B08_Attach_1_Specifications.pdf

PDF 3 MB Posted

Attached to
YOSE 228193, 228205, 228214, Tuolumne Meadows Elec
Solicitation number
140P2022R0110
Issued by

About this file

This solicitation is for electrical distribution replacement work at the Ranger Camp West, Ranger Camp East, and Bug Camp locations within Tuolumne Meadows in Yosemite National Park. The work includes removal and replacement of overhead and underground electrical lines, conduits, wiring, panels and equipment. Additional scope involves installation of new underground infrastructure, building electrical upgrades, and coordination with Southern California Edison for transformer replacements and meter installations. The period of performance is approximately June 15 through October 15 annually over multiple seasons, depending on weather and road conditions. The solicitation number is 140P2022R0110 and was issued by the National Park Service. Interested parties should monitor the Federal Business Opportunities website for additional details and response requirements.

View the file

Other files

File Type Posted
B09_Question_Tracker_140P2022R0110_Amd3_-YOSE_Electrical__0003.pdf PDF
Sol_140P2022R0110_Amd_0003.pdf PDF
Sol_140P2022R0110_Amd_0002.pdf PDF
B09_Question_Tracker_140P2022R0110_Amd2-YOSE_Electrical__0002.pdf PDF
B09_Question_Tracker_140P2022R0110_-YOSE_Electrical__0001.pdf PDF
B11_Site_Visit_Minutes_0001.docx DOCX document
B09_Amd1_Exp_YOSE_TM_Elec_Dist_0001.docx DOCX document
B09_Amd1_GenRefs_0001.doc DOC document
B09_Amd1_Tribal_Monitor_Fieldnotes_Daily_Rpt_Form_0001.docx DOCX document
B09_Amd1_Yosemite_Camps_E115_Mark-up_0001.pdf PDF
B09_Amd1_Yosemite_Camps_E212_Mark-up_0001.pdf PDF
B09_Amd1_Yosemite_Camps_E118_Mark-up_0001.pdf PDF
B09_Amd1_Yosemite_Camps_E124_Mark-up_0001.pdf PDF
B09_Amd_1_Site_Visit_Tri_Fold_YOSE_TM_Elec_Distribution_Replacement_0001.docx DOCX document
B09_Amd1_Yosemite_Camps_E102_Mark-up_0001.pdf PDF
B09_Amd1_TM_Electric_Pre-Bid_Sign-In_8_8_2022_0001.pdf PDF
Sol_140P2022R0110_Amd_0001.pdf PDF
B09_Amd1_Yosemite_Camps_E123_Mark-up_0001.pdf PDF
B09_Amd1_32_01_18_Asphalt_Patch_Specs_0001.docx DOCX document
B08_Attach_2_Yosemite_Camps_062322_22x34_reduced.pdf PDF
B08_Attach_4_Vaccination_Cert_Notification.pdf PDF
B08_Attach_5_Certification_of_Vaccination_Form_(3).pdf PDF
B08_Attach_6_Past_Performance_Questionnaire.docx DOCX document
B08_Attach_7_LmtOnSubcon.xlsx XLSX spreadsheet
Sol_140P2022R0110.pdf PDF
B08_Attach_1b_Asb_and_Lead_Rpt_Ranger.pdf PDF
B08_Attach_1c_SoCa_Edison_Inv_Rpt.pdf PDF
B08_Solicit_140P2022R0110_package.pdf PDF
B08_Attach_3__CA20220018_WD.pdf PDF
B08_Attach_1a_C99-21_Asb_and_Lead_Rpt_Bug.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Yosemite National Park

Replace Secondary Electrical System, Bug Camp and Ranger Camp, Toulumne Meadows

Construction Documents Project Manual

Revised Final 100% CD Submittal

June 15, 2022

HDR Project No. 10309975

This page intentionally left blank.

YOSEMITE NATIONAL PARK

CALIFORNIA

Replace Secondary Electrical System, Bug Camp and Ranger Camp, Tuolumne Meadows

YOSE

PMIS NO. 228214

PMIS NO. 228193

PMIS No. 228205

PROJECT SPECIFICATIONS

Revised Final 100% CD Submittal

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

June 2022

Engineer’s Certification

Preparation of this document for Replace Secondary Electrical System, Bug Camp and Ranger Camp, Tuolumne Meadows project was done by HDR Engineering, Inc. under the responsible charge of the following:

HDR Engineering, Inc.

YOSE-228214, 228193, 228205 00 01 10-1

June 2022 TABLE OF CONTENTS

REPLACE SECONDARY ELECTRIC SYSTEM, BUG CAMP AND RANGER CAMP,

TUOLUMNE MEADOWS PMIS #228214, 228193, AND 228205

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 14 16 Coordination with Owner’s Operations 01 27 00 Definition of Contract Line Items 01 29 42 Schedule of Values 01 31 00 Project Management & Coordination 01 32 16 Project Schedule 01 33 23 Submittal Procedures 01 35 13 YNP Natural, Cultural, and Physical Resource Protection 01 35 23 Safety Requirements including Hantavirus Information 01 35 60 Tribal Cultural Monitoring 01 35 91 Historic Preservation Treatment Procedures 01 40 00 Quality Requirements 01 42 00 References 01 50 00 Temporary Facilities and Controls 01 57 19.12 Noise & Acoustics Management 01 57 23 Storm Water Pollution Prevention (SWPPP) for Linear Utility-State Permit Exempt 01 57 60 Asbestos and Lead Abatement 01 61 03 Equipment – Basic Requirements 01 67 00 Product Requirements 01 73 20 Openings and Penetrations in Construction 01 73 29 Cutting and Patching 01 73 40 Execution 01 74 00 Cleaning 01 75 00 Checkout and Start-up Procedures 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 01 79 00 Demonstration and Training

DIVISION 02 - EXISTING CONDITIONS

02 41 00 Demolition

DIVISION 03 - CONCRETE

03 00 05 Concrete 03 15 19 Anchorage To Concrete

DIVISION 05 – METALS

05 50 00 Metal Fabrications

YOSE-228214, 228193, 228205 00 01 10-2

June 2022 TABLE OF CONTENTS

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

06 10 00 Rough Carpentry 06 20 00 Finish Carpentry

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 31 30 Wood Shakes 07 46 29 Plywood, Board, and Bead Siding and Paneling 07 92 00 Joint Sealants & Flexible Flashing

DIVISION 09 - FINISHES

09 29 00 Gypsum Board 09 91 10 Architectural Painting

DIVISION 10 - SPECIALTIES

10 14 00 Identification Devices

DIVISION 26 - ELECTRICAL

26 05 00 Electrical Basic Requirements 26 05 19 Wire and Cable – 600 Volt and Below 26 05 26 Grounding and Bonding 26 05 33 Raceways and Boxes 26 05 43 Electrical – Exterior Underground 26 05 48 Electrical Seismic Restraint Systems 26 08 13 Acceptance Testing 26 24 13 Switchboards 26 24 16 Panelboards 26 27 26 Wiring Devices 26 28 00 Overcurrent and Shor Circuit Protective Devices 26 43 13 Surge Protection Devices For Low-Voltage Electrical Power Circuits 26 50 00 Interior and Exterior Lighting

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 46 00 Fire Detection and Alarm

DIVISION 31 – EARTHWORK

31 10 00 Site Clearing 31 23 00 Earthwork 31 23 33 Trenching, Backfilling, and Compacting for Utilities & Structures

APPENDICES

Appendix A – SCE Mounting Details

D I V I S I O N 0 1

GENERAL REQUIREMENTS

YOSE – 228214, 228193, 228205 01 11 00 - 1

June 2022 SUMMARY OF WORK 10309975

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work Covered by the Contract Documents.

2. Contractor Use of Site

3. Government Use of Site

4. Conduct of Operations

5. Work Restrictions

6. Special Construction Requirements

7. Additional Reports (Hazardous Materials)

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Tuolumne Meadows, Tioga Road (CA Highway 120), Yosemite National Park, CA. The project is located at the Ranger and Bug NPS Employee Camps in the NPS employee housing area of the Tuolumne Meadows developed area, on the north side of the road to the Tuolumne Lodge, approximately 1 mile east of the Tuolumne Meadows Store & Grill, and 19 miles west of Lee Vining, CA 95341. The camp buildings are heavily used daily as employee housing and operations, including the mule barn, Ranger Station, Search & Rescue Office, AT&T Telephone Equipment, and other operations facilities during the summer months. Additionally, a Winter Cabin is occupied by a team of winter rangers who snow plow and ski the area for monitoring and patrolling purposes. During winter months the Tioga Road is closed to all vehicles and becomes Wilderness, therefore, there is no access to the project site during winter. Seasonal closure dates vary based on snow conditions and weather. The construction season is generally three to five months. Refer to Specification Section 01 50 00 for additional road closure information.

B. The Work consists of the following:

1. Removal and disposal of existing electrical distribution equipment, including overhead and underground lines, conduit, wire, handholes, distribution and service panels, and associated equipment, and installation of new underground lines, conduit, wire, handholes, distribution and service panels, installation of all meters with the exception of the SCE meters on the meter mains, and associated equipment. Work includes installation of new conduit, cabling, and grounding from new Southern California Edison (SCE) transformers to new contractor installed meter main panels, installation of new transformer pads, hand holes, and coordination with and payment of fees directly to SCE for required inspections, transformer installation, cabling, hot taps, and meter main installation. The Contractor is

YOSE – 228214, 228193, 228205 01 11 00 - 2

10309975 required to comply with all SCE requirements for work involving transformer and meter main modifications, in addition to the requirements of the contract documents. The Contractor is responsible for paying all SCE fees directly to SCE for the SCE transformer installation, hot taps, inspections, meter installation, and activation fees required for a complete and operational system. See SCE design drawing 1516474_0.01 for additional requirements. Contractor shall provide and install all components shown as “Customer Installed” and “Customer Furnished”, acting as the “Customer Contractor” for the Government.

2. Removal, replacement, and testing of existing electrical panels, conduit, wiring, receptacles, switches, lights, and associated components in NPS buildings as shown on the contract documents for a complete and operational system. Work shall include patching of existing building materials as required to seal all penetrations with like materials and finishes, which vary by building. See Specification Sections 01 35 91 Historic Preservation Treatment Procedures and 01 73 29 Cutting and Patching for more information. Some surfaces contain lead based paint. See C99-21 Asbestos and Lead Report by Leon Environmental, Bug Camp, June 2022, and C100-21 Asbestos and Lead Report by Leon Environmental, Ranger Camp, June 2022, included in this contract by reference. Rehabilitation of surfaces containing lead based paint shall be performed by workers certified for this work.

3. Removal and replacement of service lines and street lights on existing wood poles as shown on the contract drawings.

4. Installation of new 2” underground conduit and pull cord, extension up the exterior building walls and termination in the buildings, for installation of future data cables by park crews, as shown on the contract drawings. Coordination is required with the NPS COR and Telecom Shop for termination requirements.

5. Re-landing of AT&T, telecom, and IT equipment services on new contractor installed panels, extension of and replacement of conduit and installation of new cabling as required.

Contractor coordination with AT&T and park telecom and IT is required.

6. Provision, operation, monitoring, and maintenance of temporary power to maintain continuous service to park facilities per these specifications.

7. Providing and coordinating tribal cultural monitoring and reporting services for ground disturbance activities required to perform this work, in accordance with Specification Section 01 35 60. All ground disturbance is required to be monitored.

C. The work to be performed under this Contract shall consist of furnishing all tools, equipment, materials, supplies, and manufactured articles, and furnishing all labor, transportation, and services, including fuel and essential communications, and performing all work or other operations required for the fulfillment of the Contract in strict accordance with the Contract Documents. The work shall be complete, and all work, materials, and services not expressly indicated or called for in the Contract Documents that may be necessary for the complete and proper construction of the work in good faith shall be provided by the Contractor as though original so indicated, at no increase in cost to the Government.

YOSE – 228214, 228193, 228205 01 11 00 - 3

10309975

D. All work shall be performed in accordance with the latest versions of the California Building Code, California Electrical Code, California Mechanical Code, the National Fire Protection Association, and Southern California Edison requirements.

E. Project will be constructed under a single prime contract.

1.3 CONTRACTOR USE OF SITE

A. General: The Contractor shall have limited use of the site for construction operations. The Contractor shall at all times conduct his operations to ensure the least inconvenience to the building occupants.

Building closures and closures or blockage of doors, driveways, and roads will not be permitted, except for short term durations and approved schedules per Section 01 32 16. Continued operation of all buildings and functions in the camps is required.

B. The Contractor is required to provide temporary power to maintain operations.

1. Continuous operation of the Search & Rescue Facility, Ranger Office, and the AT&T and

Telecom equipment is especially critical and shall not be interrupted for periods exceeding one hour.

2. Access to employee housing, restrooms, barn, stables, shower houses, and kitchens are also critical for park operations and power shall not be interrupted for more than four hours.

3. Advance notice of power interruptions is required a minimum of 10 working days, with notices posted by the Contractor on each affected building with weather resistant signage.

C. Park escorts shall be required inside buildings in use unless otherwise allowed by the CO and occupants.

D. Limits: Confine constructions operations to rooms and spaces where work as drawings indicate.

E. Storage of Materials: Confine storage of materials to preapproved areas as directed by the Contracting Officer. An outdoor staging area will be designated at the project site by the Contracting Officer. The staging area will be approximately 50’ x 20’ in the Dog Lake Parking Area. There will be park visitors, park maintenance, employees, and truck traffic around and near this area during construction. The Contractor shall submit a Staging Plan and Map for approval showing the desired locations of dumpsters, hazardous materials enclosures, clean areas, materials storage, equipment, and debris removal schedules. The Staging Plan shall be reviewed and subject to approval by building users and the CO. The Contractor shall return all storage and staging areas to the same condition that they found them at the start of construction.

F. A Contractor’s office trailer and two small travel trailers are allowed in the old Dog Lake Parking Lot. The trailers shall be self-contained, as there is no power, water, sewer, or telephone at this location. The contractor shall have no access for use of NPS facilities such as the showers, laundry, or restrooms. The Contractor shall locate his trailers and staging area to allow vehicle and pedestrian circulation and parks for public use access to the Dog Lake Trailhead and to ensure NPS staff and maintenance access to Bug Camp. The Contractor shall take documentary photos prior to staging and restore the site to its original condition at the end of the project. Trailers or equipment shall not remain over the winter. Design snow levels for this area are 375 pounds per square foot and 10 feet of snow is not uncommon over the winter. Contractor will be required to perform snow removal as required for construction access when access is allowed by Yosemite CO, which may be possible during shoulder seasons when the camps are being set up or shut down, and park plowing operations are not occurring (contractor traffic on roads being actively plowed pose an unacceptable safety risk

YOSE – 228214, 228193, 228205 01 11 00 - 4

10309975 to all parties and will not be allowed). Winter access will not be allowed at any time as the area reverts to Wilderness by law and vehicular access is not permitted.

G. Preservation of Natural & Cultural Features (see also Sections 01 35 13 YNP Natural, Cultural, and Physical Resource Protection, 01 35 60 Tribal Cultural Monitoring, and 01 35 91 Historic Preservation Treatment Procedures):

1. Project building is included in the Tuolumne Meadows Historic District. Building surfaces shall be considered historic and not disturbed unless specifically noted in the Contract Documents. All modifications are subject to the review and approval of the Yosemite Historic Architect and/or Yosemite Historic Preservation Shop.

2. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

3. Provide temporary barriers to protect existing trees and plants and root zones.

4. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer and remove agreed-on roots and branches that interfere with construction.

5. Do not fasten ropes, cables, or guys to existing trees.

6. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

7. Do not remove native soils except as shown on the Contract Drawings.

8. Provide archeological and tribal monitoring and reporting for ground disturbance activities, including trenching, required to complete the work of this project.

H. Driveways and Entrances: Keep driveways, access roads and entrances serving premises clear and available to the Government at all times with the exception of the preapproved storage and staging areas as within the limits as shown and/or as directed by the Contracting Officer. The area is not fenced or locked. The Contractor shall provide his/her own security while keeping access open for park operations. The Contractor shall provide a construction key to the COR and the park Fire Department for access in the event of a fire or other emergency.

1. Do not use these areas for parking or storage of materials.

2. Schedule deliveries to minimize use of driveways and entrances.

3. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

I. Construction Camp: Establishment of a camp consisting of two small self-contained travel trailers shall be permitted at the older Dog Lake Parking Lot. Contractor crews shall observe all park rules and regulations, including quiet hours (9 PM to 7 AM) and food storage requirements.

J. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Consult with, and receive written permission from, the Contracting Officer prior to bringing any vehicles or equipment requiring Caltrans special permits for size or weight. Permission is not guaranteed. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment. Wide loads require permits and escorts from the park traffic management and law enforcement office, with a minimum two week notice, and transport is required to occur during normal work hours when escort staff are available.

1. All park roads are subject to snow and icy conditions. It is required that you carry Caltrans approved tire chains or cables when visiting Yosemite as a sudden snowstorm could make

YOSE – 228214, 228193, 228205 01 11 00 - 5

10309975 them mandatory. Vehicles with a gross vehicle weight (GVW) of greater than 6000 pounds must use tire chains/cables when chain controls are activated at any level.

2. The primary access to Tuolumne Meadows is via CA Highway 120 (Tioga Pass Road) from either the east or west sides of the park. The Contractor is responsible for knowing and complying with any/all vehicle restrictions imposed by Caltrans or Yosemite National Park on this or any other highway utilized for access to the Project location.

3. The Tioga Pass Road portion of CA Highway 120, which includes the Project location in Tuolumne Meadows, is a seasonal highway which is closed each winter. Refer to Specification Section 01 50 00 for additional road closure information. There is no access to the Project location when Tioga Pass Road is closed, either by the park, or by Caltrans at the access points outside of the park. It is the Contractor’s responsibility to monitor weather conditions and the most up to date information regarding the road status and to plan the work accordingly. During the shoulder seasons temporary closures are common due to periodic snow storms.

a. If seasonal closure of the Tioga Pass Road occurs during the performance period of this contract, the Contracting Officer will work with the Contractor to institute a seasonal suspension of the work under conditions acceptable to both parties. The Contractor shall not make any claims for regular seasonal closure of Tioga Pass Road.

4. Aside from the seasonal closure of Tioga Pass Road, other delays or intermittent closures may occur on any park roads or any highways providing access to the park at any time due to rockslides, road washouts, and related issues. These shut downs occur with little to no notice. Heavy visitor traffic and road construction will cause delays, especially during peak travel times. The Contractor shall not make any claims for traffic delays or intermittent closures of any park road or any highway providing access to the park. The Contractor shall include five (5) work days of temporary shut down of Tioga Pass Road during each construction/summer season for weather or other events for which he will not be compensated. These temporary shut down days shall be dispersed throughout the schedule.

5. It is the Contractor’s responsibility to obtain the most up to date information on road restrictions and closures, and to comply with all rules and regulations for vehicular traffic to and from the project site. The Contractor shall perform snow removal at the camps if required for construction. Yosemite crews perform snow plowing operations of the Tioga Pass Road when conditions permit during the spring opening, but do not plow the camp areas and will not perform plowing for Contractor access.

6. Access to Hwy 120 on the west end of Tioga Road via the El Portal Road, a continuation of SR-140 from the Mariposa/Merced, CA. Restrictions on SR-140 are as follows.

a) Maximum vehicle length: Currently, the maximum vehicle length allowed is 45 feet for any vehicle, due to restrictions at the one-way bridge at the Ferguson Slide area.

b) Height restrictions: 12 feet 10 inches

c) Seasons: Open all year (chains may be required in winter).

YOSE – 228214, 228193, 228205 01 11 00 - 6

10309975

d) Delays or intermittent closures may occur due to rockslides and related issues. Heavy visitor traffic will cause delays during peak travel times.

e) The Contractor shall not make any claims for traffic delays or intermittent closures of El Portal Road.

2. Access to Tioga Road is also available from Wawona Road, a continuation of SR- 41 from the Oakhurst/Fresno, CA area. Vehicle restrictions on the Wawona Road are as follows.

a) Maximum vehicle length: 45 feet for single vehicle.

b) Height restrictions through the Wawona Tunnel into Yosemite Valley - 10 feet 2 inches at curb; from Yosemite Valley - 13 feet 6 inches. The height of the tunnel at the white fogline is higher and California-legal vehicles are able to drive through the tunnel while remaining in their lane.

c) Seasons: Open all year (chains may be required in winter).

d) Delays or closures may occur due to rockslides, snow storms, and related issues. Closures are more frequent in winter. Closures may be long-term.

e) The Contractor shall assume that Wawona Road may experience full closures of up to two months in length, at any time. The Contractor shall not make any claims for traffic delays or closures of Wawona Road.

7. Access to Tioga Road via the Big Oak Flat Road from the northwest, a continuation of SR- 120 from the Manteca/Stockton, CA area:

f) Maximum vehicle length: 45 feet for single vehicle, 60 feet for combination vehicle.

g) Height restrictions through the Big Oak Flat Tunnel: Into Yosemite Valley - 10 feet 3 inches at curb; from Yosemite Valley - 13 feet 8 inches at curb.

The height of the tunnel at the white fogline is higher and California-legal vehicles are able to drive through the tunnel while remaining in their lane.

h) Seasons: Open all year (chains may be required in winter).

i) Delays or closures may occur due to rockslides, snow storms, and related issues. Closures are more frequent in winter. Closures may be long-term.

j) The Contractor shall assume that Big Oak Flat Road from El Portal (hwy

140) to Crane Flat may experience full closures of up to two months in length, at any time. The Contractor shall not make any claims for traffic delays or closures of the Big Oak Flat Road.

K. PUBLIC USE OF SITE

L. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and park staff. Road closures within the camps will be permitted, when required, upon specific approval of Contracting Officer for a maximum of 4 hours with advance notice and approval (two weeks minimum), and access accommodation for Law Enforcement, Search and Rescue, and Barn operations and employee occupants.

YOSE – 228214, 228193, 228205 01 11 00 - 7

10309975

1.4 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Full Government Occupancy: Government will occupy the buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts. Maintain existing exits and entrances.

a. The Contractor must maintain a CO approved means of egress from buildings at all times.

b. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.

c. Maintain existing buildings in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

B. Existing Utility Service: The Contractor is required to provide temporary power to all buildings in the project area.

1.5 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 5 p.m.

B. Construction shall not be permitted during weekends, holidays, or evening hours without prior written consent from the Contracting Officer. Submit requests to the Contracting Officer for approval ten (10) working days in advance of the requested dates. Requests for work which will generate noise or disturbance disruptive to residents or building occupants during evening hours will not be considered. Inspection services by Yosemite staff will not be available, therefore requests for work items requiring inspection will not be considered.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Submit schedule for projected utility interruptions per Para D below and Section 01 14 16.

Update plan once road opening date is known. Update every Monday with Three Week Look Ahead Schedule per Section 01 32 16 Project Schedule.

2. Submit plan for utility interruptions according to Section 01 33 23, Submittal Procedures, and 01 14 16 Coordination with Owner. Provide a minimum of fifteen (15) working days for park utility review. Do not interrupt utility until plan has been approved by COR in writing.

3. Allow time for resubmittals in schedule. Include 30 day initial review period and at least one resubmittal with a 15 day Yosemite review period.

4. Notification: After plan is approved, confirm shutdown dates with Contracting Officer and Contracting Officer’s Representative not less than five (5) working days in advance of proposed utility interruptions. Post advance notification signs on doors of all affected offices/functions at least one week in advance.

YOSE – 228214, 228193, 228205 01 11 00 - 8

10309975

5. Hours for Utility Shutdowns: Contractor to obtain approval for length of utility shutdown from the COR and the Utilities Branch of Facilities Maintenance. Interruptions shall generally be limited to one (1) hour in duration for essential facilities (SAR, Ranger Office & AT&T/Telecom) and four (4) hours for all other facilities. Longer utility shutdowns will require the Contractor to provide temporary utility service.

D. Maximum parallel construction activities shall be limited to four occupied residential cabins within a single period of time. One week shut downs for buildings scheduled for complete replacement of electrical systems, i.e. the Tent Cabins, shall be allowed and shall occur in groupings of a maximum of four cabins concurrently. Schedules shall be provided by February 1st of the year prior to the construction season, adjusted slightly once the camp opening date is determined based on snow conditions, to allow adequate time for staff relocations to be planned. Four (4) hour shutdowns shall be allowed for buildings requiring only panel replacements and replacements of limited items such as GFCI installation, additional outlets, or light replacements, with advance scheduling approval and notices to CO and residents . Contractor shall detail the workplan showing the sequence of construction and buildings affected, in the detailed schedule submitted to NPS for occupancy coordination.

E. The construction season shall be approximately from June 15th to October 15th depending on weather conditions and road clearing operations by NPS and Cal Trans. Historic opening and closing dates are available on Historical Seasonal Opening and Closing Dates - Yosemite National Park (U.S.

National Park Service) (nps.gov)

F. It is anticipated the schedule will be phased as follows;

1. Season 1: West Ranger Camp and replacement of the West Ranger camp transformer and the addition of the East Ranger Camp transformer. All work within West Ranger Camp.

2. Season 2: East Ranger Camp and demo of overhead feed from Bug Camp to East Ranger cabins once service has been connected from the new service from West Ranger Camp.

All remaining work within East Ranger Camp.

3. Season 3: Bug Camp and all work within Bug Camp.

4. The contractor shall submit a detailed schedule for each season by February of each year as noted above to facilitate park cabin assignments.

5. By the end of each construction season power shall be restored to all facilities.

G. The contractor shall coordinate work within the Barn with Stable Operations to not restrict stable operations or cause distress to mules and horses. These mules and horse supply the back country park and concession trails and High Country Camps in the wilderness.

H. Common facilities such as the Shower and Restrooms shall be limited to a maximum shutdown of four hours. Shutdown of showers and restroom buildings shall not be concurrent so that at least one multiple shower/toilet facility is available at all times in each location.

I. Work within hard-roofed cabin structures shall be coordinated with the NPS and existing occupants and scheduled in advance as noted above.

J. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes at any time. In addition, during fire season, smoking is not permitted in the park at any location.

K. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

YOSE – 228214, 228193, 228205 01 11 00 - 9

10309975

1.6 SPECIAL CONSTRUCTION REQUIREMENTS

A. Third party software/programs such as Procore are not allowed to be used by Government personnel.

All communication and documents shall be provided to the CO and COR via email. Each email shall include a single subject or document, stated in the Subject Line of the email.

1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.

B. A residential community and horse and mule stables exists within the project site and noise levels shall be in accordance with Specification Section 01 57 19.12, NOISE & ACOUSTICS

MANAGEMENT.

C. Hantavirus Risk: Infection with Hantavirus can progress to Hantavirus Pulmonary Syndrome (HPS), which can be fatal. Several Hantaviruses that are pathogenic to humans have been identified in the United States, including Yosemite National Park (see Yosemite National Park Directive #9:

Hantavirus Risk Reduction Program). The Contractor must protect their employees from the hazards associated with Hantavirus exposure. Upon undertaking any work, the Contractor must become fully informed of all hazards associated with hantavirus exposure and must provide all protective measures necessary to avoid illness associated with hantavirus exposure. The Contractor’s Accident Prevention Plan (See Section 01 35 23 – Safety Requirements) must provide measures to be undertaken by the Contractor to provide work conditions necessary to prevent illness associated with Hantavirus exposure.

1.7 ADDITIONAL REPORTS

A. Asbestos and lead-based paint testing reports have been conducted on several of the buildings by Leon Environmental Services, which are included in this contract by reference and will be provided to the Contractor. Several of the buildings contain lead based paint. See

1. C99-21 Asbestos and Lead Report- Bug Camp, Tuolumne Meadows, Yosemite, CA, be Leon Environmental, June 2022

2. C100-21 Asbestos and Lead Report- Ranger Camp, Tuolumne Meadows, Yosemite, CA, be Leon Environmental, June 2022

B. Hantavirus Risk Reduction Requirements:

1. I: Yosemite National Park Directive #9: Hantavirus Risk Reduction Program

2. II: Hantavirus Risk Reduction, Worker Protection, Updated April 2013

C. Southern Cal Edison (SCE) Design Drawing #1516474_0.01 and SCE standards and requirements.

D. The above listed documents and the recommendations included in them are considered a part of this contract by reference. A copy of the above reports and SCE design drawing is available to all plan holders with this package.

E. If conflicts occur between the report and drawings or specifications, the more restrictive requirements govern.

YOSE – 228214, 228193, 228205 01 11 00 - 10

10309975

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION

YOSE- 228214, 228193, 228205 01 14 16 - 1

June 2022 COORDINATION WITH OWNER’S OPERATIONS 10309975

SECTION 01 14 16 – COORDINATION WITH OWNER’S OPERATIONS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Requirements for coordinating with Owner’s operations during the Project.

2. Requirements for tie-ins and shutdowns necessary to complete the Work without impact on

Owner’s operations except as allowed in this Specifications section.

B. Scope:

1. Contractor shall provide all labor, materials, equipment, tools, and incidentals shown, specified, and required to coordinate with Owner’s operations during the Work in accordance with this Specifications section.

2. Except for shutdowns specified in this Specifications section, perform the Work such that Owner’s facilities remain in continuous, satisfactory operation during the Project. Schedule and perform the Work such that the Work does not: impede Owner’s production or processes, create potential hazards to operating equipment and personnel, cause odors or other nuisances, does not affect the public health, safety, welfare, and convenience, and does not adversely affect the environment resulting in violation of Laws or Regulations.

3. Work not specifically addressed in this Specifications section or in referenced sections may, in general, be performed, to be completed within the Contract Times, at any time during regular working hours in accordance with the Contract Documents, subject to the requirements in this section.

C. Related Requirements: Include but are not necessarily limited to:

1. Section 01 11 00 - Summary of Work.

2. Section 01 73 29 - Cutting and Patching.

3. Section 01 75 00 - Checkout and Startup Procedures.

4. Section 01 27 00 - Definition of Contract Line Items

5. Section 01 31 00 - Project Management and Coordination

6. Section 01 32 16 - Project Schedule

7. Section 01 50 00 - Temporary Facilities and Controls

1.2 REFERENCES

A. Terminology:

1. Terminology indicated below are not defined terms and are not indicated with initial capital letters, but when used in this Specifications section have the meaning indicated below:

a. The term “Owner” is used throughout this section. When the facility is operated or managed by an entity other than Owner, references in this section to “Owner” as the operator or manager of the facility will be interpreted as referring to the facility manager.

b. A “shutdown” is when a portion of the normal operation of Owner’s facility, whether equipment, systems, conduit (including piping and ducting), has to be temporarily suspended or taken out of service to perform the Work.

c. A “tie-in” is a connection of new Work to existing facilities, including connecting to existing conduits (including piping and ducting), electrical systems, structural elements, process/mechanical elements, and other physical connections. Some tie-ins may require that the tie-in be made without an associated shutdown.

1.3 ADMINISTRATIVE REQUIREMENTS

A. Coordination:

1. Refer to Work Restrictions Section 01 11 00 Para 1.5 for work hour restrictions and shutdown planning and scheduling.

YOSE- 228214, 228193, 228205 01 14 16 - 2

10309975

2. Review construction procedures under other Specifications sections and coordinate Work that will be performed with or before the Work indicated in this Section.

B. Sequencing and Scheduling:

1. Refer to this Specification and Section 01 11 00 for sequencing, tie-ins, and shutdowns.

1.4 SUBMITTALS

A. Informational Submittals: Submit the following:

1. Shutdown Planning Submittal:

a. For each shutdown, submit an inventory of labor, materials, and equipment required to perform the shutdown and tie-in tasks, an estimate of time required to accomplish the complete shutdown including time for Contractor to take down and start up existing equipment, systems, or conduits, and written description of steps required to complete the Work associated with the shutdown.

b. Furnish submittal to CO not less than February prior to proposed shutdown start date.

Do not start shutdown until obtaining CO’s acceptance of shutdown planning Submittal. See Section 01 11 00 Para 1.5.

2. Shutdown Notification:

a. After CO’s acceptance of shutdown planning Submittal and prior to starting the shutdown, submit written notification to CO of date and time each shutdown is to start.

Submit notification not less than three weeks in advance of each shutdown.

1.5 GENERAL CONSTRAINTS

A. Indicated in the Contract Documents are the sequence and shutdown durations, where applicable, for Owner’s equipment, systems, and conduits that are to be taken out of service temporarily for the Work. New materials and equipment may be used by Owner after the specified field quality control activities are successfully completed and the materials or equipment are substantially complete in accordance with the Contract Documents.

B. The following constraints apply to coordination with Owner’s operations:

1. Operational Access: Owner’s personnel shall have access to equipment and areas of the facility that remain in operation.

2. Schedule and perform equipment and system start-ups in accordance with Section 01 75 00

- Checkout and Startup procedures. Equipment and systems shall not be placed into operation on Friday, Saturday, Sunday, or holidays without prior approval of Owner

3. Dead End Conduits:

a. Provide blind flanges, watertight bulkheads, or valve at temporary and permanent terminuses of conduits, including piping.

b. Blind flanges and bulkheads shall be suitable for the service and braced and blocked, as required, or otherwise restrained as necessary or as required by CO.

c. Temporary valves shall be suitable for their associated service. Where valve is provided at permanent terminus of conduit, including piping or ducting, also provide on downstream side of valve a blind flange with drain/flushing connection.

1.6 SEQUENCE OF WORK

A. Perform the Work in the indicated sequence. Stages specified in this article are sequence-dependent.

1. Phase I - Season 1: West Ranger Camp distribution system, replacement of the West Ranger camp transformer and the addition of the East Ranger Camp transformer. Replacement of all tent cabin interior electric circuits, conduits, and devices. Modifications to all West Ranger Camp buildings as shown in the contract drawings.

2. Phase II - Season 2: East Ranger Camp distribution system and demo of overhead feed from Bug Camp to East Ranger cabins once service has been connected from the new service transformer at West Ranger Camp. Replacement of all tent cabin interior electric circuits, conduits, and devices. Modifications to all East Ranger Camp buildings as shown in the contract drawings.

YOSE- 228214, 228193, 228205 01 14 16 - 3

10309975

3. Phase III - Season 3: Bug Camp distribution system. Replacement of all tent cabin interior electric circuits, conduits, and devices. Modifications to all Bug Camp buildings as shown in the contract drawings.

4. By the end of each construction season, power shall be restored to all facilities.

1.7 TIE-INS

A. Table 01 14 16-A in this Specifications section lists connections by Contractor to existing facilities. Table 01 14 16-A may not indicate all tie-ins required for the Work; Contractor shall perform tie-ins necessary and required to complete the Work as shown or indicated in the Contract Documents, regardless of whether tie-in is indicated in Table 01 14 16-A. For tie-ins not indicated in Table 01 14 16-A, obtain requirements for tie-ins from CO by requesting an interpretation or clarification.

1.8 SHUTDOWNS

A. Shutdowns shall be in accordance with Table 01 14 16-B of this Specifications section and per approved schedules required per these Specification, including Section 01 11 00. Work requiring service interruptions for tie-ins shall be performed during approved scheduled shutdowns.

B. Provide maps detailing locations and dates of specific components of work. Show corresponding trenching locations and building service disruptions.

C. Work that may interrupt normal operations shall be accomplished at times convenient to Owner unless otherwise indicated in the Contract Documents.

D. If Contractor’s operations cause an unscheduled interruption of Owner’s operations, immediately re-establish satisfactory operation for Owner.

PART 2 - PRODUCTS - (NOT USED)

PART 3 - EXECUTION

3.1 SUBSTITUTE PROCEDURES

A. Proposal of Substitute Sequencing, Shutdowns, and Tie-Ins:

1. As a substitute to the phasing indicated in this Specifications section, Contractor may propose providing additional temporary facilities that can eliminate or mitigate a constraint without additional cost to Owner, provided such additional temporary facilities: do not present hazards to the public, personnel, structures, and equipment; that such additional temporary facilities do not adversely affect Owner’s operations or ability to comply with Laws and Regulations, permits, and operating requirements; that such temporary facilities do not generate or foster the generation of disruptive noise, odors and other nuisances; and that requirements of the Contract Documents are fulfilled.

2. CO will consider proposals for substitute phasing after the Effective Date of the Contract.

All Bids shall be based on the requirements of the Contract Documents, including this section.

3. Substitution Requests:

a. When proposing a substitute phasing or procedure for a tie-in or shutdown or other requirements of this section, comply with the requirements of the General Conditions and Supplementary Conditions (regarding substitutes) and Section 01 33 23 Submittal Procedures.

b. When deviation from specified sequence or procedures is proposed, Contractor’s proposal shall explain in detail the proposed sequence and procedures and associated effects, including evidence that Owner’s operations will not be adversely affected, to an extent greater than originally contemplated in the Contract Documents, by proposed substitution. List benefits of proposed substitution, including benefits to Progress Schedule.

YOSE- 228214, 228193, 228205 01 14 16 - 4

10309975

3.2 GENERAL PROVISIONS FOR COORDINATING WITH OWNER’S OPERATIONS

A. When possible, combine multiple tie-ins into a single shutdown to reduce impacts on Owner’s operations and processes.

B. Operation of Existing Systems and Equipment during the Work:

1. Do not shut off or disconnect existing operating systems or equipment, unless accepted by

CO in writing.

2. Operation of existing systems and equipment will be by Owner unless otherwise specified or indicated.

3. Provide temporary watertight plugs, bulkheads, and line stops as necessary and as required.

After completing the Work, remove seals, plugs, bulkhead, and line stops to satisfaction of Engineer.

C. Performing the Work of this section constitutes Contractor’s approval of underlying work and field conditions prevailing at the time of the Work.

3.3 PREPARATION

A. Coordinate preparations for removals with requirements of Section 01 73 29 - Cutting and Patching and Section 02 41 00 - Demolition, as applicable.

B. Shutdowns - General Preparation:

1. Coordinate shutdowns with Owner and CO

2. Submit shutdown planning Submittals and shutdown notification Submittals in accordance with this Specifications section’s “Submittals” Article and Specification 01 11 00.

3. Provide maps detailing locations and dates of specific components of work. Show corresponding trenching locations and building service disruptions.

4. Furnish at the Site, in close proximity to the shutdown and tie-in work areas, tools, materials, equipment, spare parts, both temporary and permanent, necessary to successfully perform the shutdown. Complete to the extent possible, assemblies prior to commencing the associated shutdown. Demonstrate to CO’s satisfaction that Contractor has complied with such requirements before commencing the shutdown.

5. CO shall have no duty to Contractor to advise Contractor of inadequate preparations by Contractor; Contractor is solely responsible for the means, methods, procedures, techniques, and sequences of construction.

C. Shutdowns of Electrical Systems:

1. Comply with Laws and Regulations, including the National Electric Code.

2. Contractor shall lock out and tag circuit breakers and switches operated by Owner and shall verify that affected cables and wires are de-energized to ground potential before starting other Work associated with the shutdown.

3. Upon completion of shutdown Work, remove the locks and tags and advise CO that facilities are available for use.

3.4 DETAILED SHUTDOWN REQUIREMENTS

A. Shutdown: Contractor shall provide a detailed shutdown request that provides the following information in a procedure submittal for approval. Shutdown schedule shall be provided to CO each February prior to the construction season, and updated once the seasonal opening date is known. See notification and scheduling requirements in related specification sections, including Sections 01 11 00 Summary of Work, 01 27 00 Definition of Contract Line Items, 01 31 00 Project Management and Coordination, 01 32 16 Project Schedule, and 01 50 00 Temporary Facilities and Controls.

1. General:

a. Affected Equipment Operating Prior to Shutdown:

b. Equipment Operating During Shutdown:

c. Equipment Out of Service During Shutdown

d. Impact on Other Equipment and Processes:

e. Procedure:

YOSE- 228214, 228193, 228205 01 14 16 - 5

10309975

f. Dates: Shutdown shall be accomplished.

g. Time: Shutdown shall be performed: indicate time of day/hours or operating shift.

2. Provide maps detailing locations and dates of specific components of work. Show corresponding trenching locations and building service disruptions.

3. Prior to Shutdown:

a. Obtain CO’s acceptance of proposed shutdown planning Submittal and shutdown notification Submittal.

b. Bring necessary piping, couplings, valves, equipment, and appurtenances to the work areas.

c. Coordinate other tie-ins to be performed simultaneously.

d. Post notifications on buildings per Specification 01 11 00 Para 1.5.

4. During Shutdown:

a. Place temporary electrical system into operation.

b. Remove existing conduit and wire as required.

c. Provide all materials and temporary power sources for the tie-ins.

d. With Owner, return equipment and system to operation.

5. Following Shutdown:

a. Verify functionality of equipment and systems.

b. Verify operation of new equipment and systems and verify that joints in conduits

(including piping and ducting) are watertight or gastight as applicable.

c. Repair joints that are not watertight or gastight, as applicable.

d. Remove temporary pumping system and appurtenances.

3.5 TABLE OF TIE-INS

A. The following list outlines the minimum major tie-ins required for each Phase. Additional tie’s may be required by the contractor’s detailed schedule that provide minimal disturbance or power disruptions to the camps in order to accomplish the replacement work.

1. Phase I

a. West Ranger Camp temporary power.

b. West Ranger Camp transformer

c. East Ranger Camp transformer

d. West Ranger Camp demo and distribution lines

e. West Ranger Camp Service Panel terminations

f. West Ranger Camp electrical modifications in buildings.

g. West Ranger Camp West temporary power removal.

2. Phase II

a. East Ranger Camp temporary power.

b. East Ranger Camp demo and distribution lines

c. East Ranger Camp Service Panel terminations

d. East Ranger Camp electrical modifications in buildings.

e. East Ranger Camp temporary power removal

3. Phase III

a. Bug Camp temporary power

b. Bug Camp demo and distribution lines

c. Bug Camp Service Panel terminations

d. Bug Camp electrical modifications in buildings.

e. Bug Camp temporary power removal

YOSE- 228214, 228193, 228205 01 14 16 - 6

10309975

Table 01 14 16-A

Schedule of Line Replacements and Tie-Ins

Tie-In No.

New Line

Size and Service

Existing (Connecting) Line

Size & Service Tie-In

Building/Location Construction

Stage

Proposed Start Date

Proposed End Date Remarks

YOSE- 228214, 228193, 228205 01 14 16 - 7

Table 01 14 16-B

Schedule of Shutdowns

Shut-down No.

Building and Service Lines

Out-of-Service During Shutdown

Building and Equipment

In Operation During Shutdown Tie-In Nos.

Shut Down Start Date

Shut Down End Date

A

B

C

D

YOSE – 228214, 228193, 228205 01 27 00 - 1

June 2022 DEFINITION OF CONTRACT LINE ITEMS 10309975

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item Number 1: Mobilization & Demobilization – Phase 1 Ranger Camp West

1. This item includes mobilizing and demobilizing all required equipment to the site. For Schedule of Value purposes, the mobilization cannot exceed 60% of this CLIN. This CLIN does not include payment for materials. The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid. Measurement for payment shall be by lump sum.

2. Payment will be at the contract lump sum price. Progress payments will be based on percentage of the work item that is completed, or as outlined in the approved Schedule of Values.

B. Contract Line Item Number 2: Mobilization & Demobilization – Phase II Ranger Camp East

1. This item includes mobilizing and demobilizing all required equipment to the site. For Schedule of Value purposes, the mobilization cannot exceed 60% of this CLIN. This CLIN does not include payment for materials. The Contracting Officer may require the Contractor to furnish cost data to justify this portion

2. Payment will be at the contract lump sum price. Progress payments will be based on percentage of the

C. Contract Line Item Number 3: Mobilization & Demobilization – Phase III Bug Camp

1. This item includes mobilizing and demobilizing all required equipment to the site. For Schedule of Value purposes the mobilization cannot exceed 60% of this CLIN. This CLIN does not include payment for materials. The Contracting Officer may require the Contractor to furnish cost data to justify this portion

2. Payment will be at the contract lump sum…