This document outlines a water quality monitoring plan for a shoreline stabilization project at American Memorial Park in Saipan. The project involves replacing approximately 720 linear feet of an existing dilapidated concrete mattress/boulder revetment structure with a new boulder revetment along the entrance channel to Smiling Cove Marina. It also includes constructing a new 124-linear foot shoreline revetment structure along the shoreline at Outer Cove Marina. The plan details turbidity mitigation measures using silt curtains, water quality monitoring stations and protocols to ensure turbidity levels do not exceed ambient conditions by more than 1 NTU. It requests an exemption from a 21-day stoppage period during coral spawning due to the localized and contained nature of dredging activities and sediment composition.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMERICAN MEMORIAL PARK
SAIPAN, CNMI
NPS CONTRACT NO. 140P8219D0001
TASK ORDER NO. 140P2021F0096
REPLACE SHORELINE BARRIERS AT SMILING COVE AND OUTER
COVE, AMERICAN MEMORIAL PARK, SAIPAN, MP
PMIS #236143
FINAL CONSTRUCTION DOCUMENTS SUBMITTAL
SPECIFICATIONS
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
PREPARED BY:
PMB 596 Box 10000
Del Sol Building, Beach Road, Garapan, Saipan, MP 96950
Tel: (670) 234-0483
Fax: (670) 234-5615
Email: saipanghd@GHD.com http://www.GHD.com
January 2022
THIS PAGE INTENTIONALLY BLANK
AMME, PMIS No. 236143 TABLE OF CONTENTS TOC - 1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 50 00 Temporary Facilities and Controls 01 57 19.12 Noise and Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures
DIVISION 02 – EXISTING CONDITIONS
02 24 24 Unexploded Ordnance 02 41 00 Demolition
DIVISION 03 - CONCRETE
03 30 00 Cast-In-Place Concrete
DIVISION 31 - EARTHWORK
31 05 13 Soil for Earthwork 31 05 16 Aggregates for Earthwork 31 05 22 Geotextiles Used as Filters 31 22 13 Rough Grading 31 23 16 Excavation 31 25 00 Erosion and Sedimentation Controls
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 23 Aggregate Base Course 32 12 16 Asphalt Pavement 32 17 23 Asphalt Pavement Markings 32 90 00 Planting
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 31 19 Stone, Channel, Shoreline/Coastal Protection for Structures
APPENDICES
APPENDIX A – GEOTECHNICAL ENGINEERING REPORT
APPENDIX B – WAVE ANALYSIS REPORT
APPENDIX C – ANOMALY AVOIDANCE WORK PLAN FOR ARCHAEOLOGICAL
SURVEY AND SUBSURFACE TESTING
AMME, PMIS No. 236143 TABLE OF CONTENTS TOC - 2
APPENDIX D – ANOMALY AVOIDANCE REPORT FOR ARCHAEOLOGICAL
SURVEY AND SUBSURFACE TESTING
APPENDIX E – DDESB TP-18, MARCH 2018
APPENDIX F – NPS PRELIMINARY REPORT, SEPTEMBER 2017
AMME PMIS # 236143 01 11 00 - 1
012721 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Contractor Use of Site
3. Public Use of Site
4. Conduct of Operations
5. Work Restrictions
6. Special Construction Requirements
7. Soils Investigation Report
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: The project is part of the American Memorial Park in Saipan. The project is located along the West and East Causeways which serve the Smiling Cove Marina and the Outer Cove Marina, respectively.
B. The Work consists of:
1. Erosion control and water quality protection measures.
2. Completely removing approximately 730 feet of shoreline slope protection along the West Causeway and 100 feet of degraded slope along the East Causeway including existing rock, filter fabric, soil, concrete mattress, trees, abandoned fire water system, bollards, and other related miscellaneous items within the limits of removal.
3. Reconstruction of the slope, affected roadway, slope protection, and landscaping along the shoreline of the West and East Causeways located within the American Memorial Park, and the addition of a new concrete sidewalk along the West Causeway. The new rock revetment will be installed using native armor stone and underlayer rock.
C. Project will be constructed under a single prime contract.
1.3 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to areas within the Construction limits indicated on drawings. Contractor will not be able to enter nearby pago/mangrove habitat located east of the Smiling Cove Marina entrance channel site. Do not disturb portions of Project site beyond areas in which the Work is indicated.
AMME PMIS # 236143 01 11 00 - 2
B. Construction Staging Areas: Establishment of construction staging areas will be limited to the areas shown in the Plans, unless otherwise authorized by the Contracting Officer.
C. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
D. Storage of Materials: Confine storage of materials to areas shown on plans, unless otherwise authorized by the Contracting Officer.
E. Parking: Contractor shall confine parking to along the south side of Industrial Drive at the designated temporary facilities site, contractor-designated parking area within the smiling cove parking lot, and the eight southernmost parking stalls along the sheet pile wall at the end of the West Causeway, unless otherwise authorized by the Contracting Officer.
F. Stockpiling: Confine stockpiling to areas shown on plans, unless otherwise authorized by the Contracting Officer.
G. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones not designated to be removed.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
H. Biological Monitoring and Mitigation:
1. Constant vigilance shall be kept for the presence of ESA-listed species (green sea turtles and hawksbill turtles) during all aspects of the permitted action
a. The contractor shall designate a competent observer to search/monitor work sites and areas adjacent to the authorized work area for ESA-listed species;
b. Searches shall be made prior to the start of work each day, including prior to resumption of work following any break of more than one-half hour.
c. All in-water work will be postponed or halted when ESA-listed marine species are within 50 yards of the proposed work, and will only begin or resume after the animals have voluntarily departed the area.
d. Project-related personnel shall NOT attempt to disturb, touch, ride, feed, or otherwise intentionally interact with any protected species.
e. Slow moving benthic invertebrates (e.g., sea cucumbers, larger gastropods, sea urchins, etc.) will be relocated outside the active work site prior to commencement of demolition work by the Contractor.
I. Driveways and Entrances: Keep driveways and entrances serving premises, and especially the adjacent Marine Enforcement Facility, clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
AMME PMIS # 236143 01 11 00 - 3
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
J. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.4 PUBLIC USE OF SITE
A. Contractor shall conduct his operations to ensure the least inconvenience to public. Causeway road closures may be permitted, when required, upon specific approval of Contracting Officer for a maximum of 4 days (Monday thru Thursday).
1.5 CONDUCT OF OPERATIONS
A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: 8:00 a.m. to 5:00 p.m.
B. All construction activities at the site shall be suspended during events and activities associated with the various fishing tournaments such as the:
• Wahoo Fishing Derby (typically in February)
• Mahi Mahi Fishing Derby (typically in April)
• Saipan International Fishing Tournament (typically in July)
• Mariana Islands Fishing and Seafood Festival (typically in September)
Immediately prior to this period of suspended work the Contractor shall clean up all construction debris, arrange materials and equipment in orderly configurations, and ensure that the worksite is
AMME PMIS # 236143 01 11 00 - 4
secure and safe for park employees and visitors. No additional time will be added to the contract Period of Performance due this period of suspended work.
C. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
D. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two (2) business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Proposed Utility interruptions shall be no longer than four (4) hours in duration.
1.7 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by NPS will be used for purposes of managing communication and documents during construction stage.
1.8 SOILS INVESTIGATION REPORT
A. The report entitled “Geotechnical Engineering Report, NPS Smiling and Outer Cove Repair, Puerto Rico, Saipan, Commonwealth of the Northern Mariana Islands”, Reference No. 20-025, dated June 17, 2021, has been prepared by Marianas Geotech Services (MGS).
B. A copy of the report is available to all plan holders with this package.
C. In case of conflict between report and drawings or specifications, the drawings and specifications govern.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
AMME PMIS #236143 01 26 01 - 1
012721 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager (PM), Assistant Project Manager
AMME PMIS #236143 01 26 01 - 2
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
AMME PMIS #236143 01 26 01 - 3
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.
Include as a separate line item in modification proposals and provide current company bonding rates upon request.
http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank
AMME PMIS #236143 01 26 01 - 4
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal shall be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.
3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
http://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=396735|
AMME PMIS #236143 01 26 01 - 5
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
AMME PMIS #236143 01 26 01 - 6
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………15%
Profit………………….. 8%
2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 01 26 01
AMME PMIS #236143 01 27 00 - 1
012721 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 1 – West Causeway Shoreline Protection
1. This item consists of all labor, materials, and equipment required to remove and stockpile the existing 30 feet of existing transition rock slope protection adjacent to the existing concrete mattress, remove approximately 200 feet of existing concrete mattress slope protection, remove trees, remove and replace existing bollards, repair roadway in affected areas, regrade the shoreline slope including transition, and construct approximately 230 feet of new rock revetment (from Station 0+50 to Station 2+80 on the drawings), sidewalk, landscaping, fortify 50 feet of existing rock revetment and other miscellaneous work and materials necessary to complete the contract line item in accordance with the drawings and specifications.
2. Measurement for payment will be based on linear feet of rock revetment completed, overall project schedule and phasing requirements, acceptance for work, and other related items.
3. Payment will be made as a percentage of the contract lump sum price in accordance with the work completed as approved by the Contracting Officer.
B. Contract Line Item No. 2 – East Causeway Shoreline Protection
1. This item consists of all labor, materials, and equipment required to regrade approximately the shoreline slope including transitions, repair roadway in affected areas, and construct approximately 100 feet of new rock revetment from station 20+00 to 21+00 including transitions, and other miscellaneous work and materials necessary to complete the contract line item in accordance with the drawings and specifications.
2. Measurement for payment will be on a percent complete basis relative to the overall project schedule and phasing requirements, acceptance for work, and other related items.
3. Payment will be made as a percentage of the contract lump sum price in accordance with the work completed as approved by the Contracting Officer.
AMME PMIS #236143 01 27 00 - 2
012721 DEFINITION OF CONTRACT LINE ITEMS
C. Contract Line Item No. 3 – (Option 1) West Causeway – 500 feet of Additional Shoreline Rock Slope Protection
1. This item consists of all labor, materials, and equipment required to remove approximately 500 linear feet of existing concrete mat slope protection, remove trees, remove and replace existing bollards, regrade the shoreline slope including transition, and construct approximately 486 linear feet of new rock slope protection (from Station 2+80 to Station 7+50 on the drawings) including transition back to the existing concrete mat slope protection, sidewalk, landscaping, and other miscellaneous work and materials necessary to complete the contract line item in accordance with the drawings and specifications.
2. Measurement for payment will be on a percent complete basis relative to the overall project schedule and phasing requirements, acceptance for work, and other related items.
3. Payment will be made at the contract price per lineal feet in accordance with the work completed as approved by the Contracting Officer.
D. Contract Line Item No. 4 – (Option 2) New Sidewalk along West Causeway – Approximately 900 Linear Feet
1. This item consists of all labor, materials, and equipment required to remove select trees, regrade top of slope and construct approximately 900 linear feet of new concrete sidewalk and drainage swale (from Station 0+00 to Station 9+00 on the drawings) including striping of crosswalk, striping of asphalt buffer and grooving of new sidewalk.
2. Measurement and payment will be on a percent complete basis relative to the overall project schedule and phasing requirements, acceptance for work, and other related items.
3. Payment will be made as a percentage of the contract lump sum price in accordance with the work completed as approved by the Contracting Officer.
END OF SECTION 01 27 00
AMME PMIS #236143 01 31 00 - 1
012721 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. NPS/DSC Project Website
7. Project Meetings
8. Environmental Coordination
9. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.
AMME PMIS #236143 01 31 00 - 2
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
9. Commissioning activities
1.3 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan (APP)
5. A List of Subcontractors for this project
6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
8. Waste Management Plan (WMP)
9. Quality Control Plan (QCP)
10. Temporary Storm Water Pollution Prevention Plan (SWPPP)
11. In-Water Pollution Control Plan
AMME PMIS #236143 01 31 00 - 3
12. Storm Response Plan will be developed and implemented for the project. The storm plan includes a post-storm assessment identifying potential storm associated impacts to important adjacent marine resources.
13. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
B. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on NPS/DSC management software website.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. Project name
4. NPS Contract number
5. Name of Contractor
6. RFI subject
7. Specification Section number and title and related paragraphs, as appropriate.
8. Drawing number and detail references, as appropriate.
9. Field dimensions and conditions, as appropriate.
10. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract Time or Contract Sum, Contractor shall state impact in RFI.
11. Contractor's signature
12. Requested date for response
AMME PMIS #236143 01 31 00 - 4
13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete RFI Form on NPS/DSC Project Website as follows:
1. Enter general information at the top of the form.
2. Under the "Action" section at the bottom of the form, select "Question" then select "CMR" in drop-down of "Send to" box.
3. Enter details of question and attach related documents.
4. Select "Submit Form" at bottom of page.
D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.
1.5 PROJECT WEBSITE
A. Use NPS/DSC management software website for communication throughout contract period on:
1. Project directory
2. Project correspondence
3. Meeting agendas and minutes
4. Contract modifications forms and logs
5. RFI form and processing
AMME PMIS #236143 01 31 00 - 5
6. Task and issue management
7. Photo documentation
8. Baseline schedule, schedule updates and calendar management
9. Submittal form and processing
10. Payment coordination documentation
11. Drawing and specification document hosting, viewing, and updating
12. Online document collaboration
13. Reminder and tracking functions
14. Archiving functions
15. Notification of submittal and RFI statuses and current responsible party
16. Permits and addendums
B. Some documents are not suitable to be shared using the NPS/DSC management software website.
Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using NPS/DSC management software website and shall be coordinated with Project team as appropriate.
C. Submit to Contracting Officer a list of employees who will need access to the website. Users will receive an invitation to register from Department of Interior (DOI). Once registered on DOI website, user will be given access to NPS/DSC management software website.
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later.
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
4. Resolution of comments on required Division 1 documents
5. Coordination of Subcontractors
6. Labor law application
7. Modifications
8. Payments to Contractor
9. Payroll reports
10. Contract time
AMME PMIS #236143 01 31 00 - 6
11. Liquidated damages
12. Contractor Performance Evaluation
13. Display of Hotline posters
14. Notice to proceed
15. Correspondence procedures
16. NPS/DSC Project website
17. Acceptance/rejection of work
18. Progress meetings
19. Submittal procedures
20. NPS Final Accessibility Inspection
21. Environmental requirements
22. Permit requirements
23. As-constructed drawings/operation and maintenance (O&M) manuals.
24. Saturday, Sunday, holiday and night work.
25. Reference materials
26. Value engineering
27. Schedule of Values
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected, including status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings and O&M manuals.
AMME PMIS #236143 01 31 00 - 7
j. Other business relating to work.
k. Permit requirements
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
g. Submittals
h. Possible conflicts
i. Compatibility requirements
j. Time schedules
k. Weather limitations
l. Manufacturer's written instructions
m. Warranty requirements
n. Compatibility of materials
o. Acceptability of substrates
p. Temporary facilities and controls
q. Space and access limitations
r. Regulations of agency(ies) with jurisdiction
s. Testing and inspecting requirements
t. Installation procedures
u. Coordination with other work
v. Required performance results
w. Protection of adjacent work
x. Protection of construction and personnel
y. Maintaining continuous public access and visitors safety
AMME PMIS #236143 01 31 00 - 8
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
1.7 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of Waste Management Plan (WMP).
c. Implementation of Storm Water Pollution Prevention Plan (SWPPP).
d. Implementation of In-Water Pollution Control Plan
e. Implementation of Section 401, Water Quality Control Plan including turbidity monitoring.
f. Implementation of Storm Response Plan.
g. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
h. Training for Contractor personnel in accordance with position requirements.
i. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Noise and Acoustics Management
4. Temporary Storm Water Pollution Prevention Environmental Management
5. Section 31 25 00, Erosion & Sedimentation Control
6. Construction Waste Management
AMME PMIS #236143 01 31 00 - 9
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:
1. Overview of environmental issues related to building industry.
2. Overview of environmental issues related to Project.
3. Review of site-specific procedures and management plans:
a. Construction Waste Management
b. Noise and Acoustics Management
c. Temporary Storm Water Pollution Prevention
d. Section 401, Water Quality Control Plan
4. Pollution Prevention (P2) practices: Submit evidence of P2 training and participation in P2 programs.
5. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, and Storm Water Pollution Prevention Plan (SWPPP).
1.8 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. Contractor shall also be responsible for damages to persons or property that occur as a result of Contractor’s fault or negligence; and for materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract, Contractor will not be considered an agent of the Government. Contractor shall comply with appropriate Federal, State and local laws.
B. Government Furnished Permits: During development of the project’s design, consultation and permits listed below were negotiated and agreed to by the Government. Terms and provisions of these permits shall be adhered to for the duration specified in each permit.
1. U.S. Army Corps of Engineers, Section 404, Nationwide Permits #3 and #13 for Smiling Cove and Permits #13 and #16 for Outer Cove, File No. POH 2019-00227 Conditional Requirements are attached at the end of this section.
2. CNMI Division of Environmental Quality, Section 401, Water Quality Certification.
Conditional Requirements and Water Quality Control Plan and Figures are attached at the end of this Section
3. United States Fish and Wild Service Section 7, Informal Consultation;
4. National Marine Fisheries Service Section 7, Informal Consultation;
AMME PMIS #236143 01 31 00 - 10
5. National Marine Fisheries Service Essential Fish Habitat
6. CNMI Division of Coastal Resource Management, CZM Federal Consistency Determination
7. CNMI Department of Lands and Natural Resources, Submerged Land Use Permit
8. Saipan Zoning Office, Zoning Permit
C. Potential Permits: Permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist Contractor in determining which permits will be required for contract’s chosen means and methods. The list shall not be considered complete; it is the Contractors’ responsibility to determine means and methods and obtain required permits. Contractor shall obtain all permits required to legally conduct work, including:
1. Construction Trailer, Utilities Hookup Permit – Commonwealth Utilities Corporation
(CUC)
2. Saipan Department of Public Works (DPW) – Road Closure Permit
3. CNMI Division of Environmental Quality (DEQ) - CWA Section 402 Construction General Permit, Stormwater Pollution Prevention Permit (NOI)
4. CNMI Division of Environmental Quality (DEQ) - Earthmoving and Erosion Control Permit
5. Dewatering Permit – Division of Environmental Quality (DEQ)
D. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying work: Coordinate meetings, reporting requirements, inspections, and other requirements.
E. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts.
2. Supply needed information to Agency(ies) with Jurisdiction issuing permits, pay fees required and provide material needed to comply with permit’s conditions and provisions.
3. Upload permits to NPS/DSC management software website when permits are obtained.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 01 31 00
Bureau of Environmental Quality Section 401 Water Quality Certification Application
WATER QUALITY MONITORING PLAN
for the National Park Service, American Memorial Park
CNMI 401 Water Quality Certification
Prepared for:
National Park Service American Memorial Park
P.O. Box 5198 CHRB Beach Road, Garapan
Saipan, MP 96950
November 4, 2021
PROJECT OVERVIEW
Project Proponent:
U.S. National Park Service
Project Locations:
American Memorial Park, Saipan, CNMI Smiling Cove Marina Entrance Channel Outer Cove Marina
Proposed Action:
The proposed action includes two shoreline stabilization projects, one in Smiling Cove Marina entrance channel and the other at Outer Cove Marina. Brief descriptions of each project follow:
1. replace an approximate 720-linear foot section of an existing dilapidated concrete mattress/boulder revetment structure with a new boulder revetment structure along the east side of the Smiling Cove Marina entrance channel; and
2. construct a new 124-linear foot shoreline revetment structure along the shoreline at Outer Cove Marina.
National Park Service Contact:
Dr. Tim Clark, Natural and Cultural Resources Manager 135 Murray Blvd., Ste.100 Hagåtña, GU 96910
Office Phone: 671.688.9783 E-mail: timothy_clark@nps.gov
Anticipated Construction Period:
March 2022 through March 2023
Water Quality Monitoring Plan Preparation and Designated Representative:
Micronesian Environmental Services Mr. John Gourley, Owner & Principal
P.O. Box 502802 Saipan, MP 96950 Northern Mariana Islands, USA
Cellular Phone: 670.483.4000 E-mail: john.e.gourley@gmail.com mailto:timothy_clark@nps.gov mailto:john.e.gourley@gmail.com
Smiling Cove & Outer Cove Water Quality Monitoring Plan
TABLE OF CONTENTS
I. Introduction and Purpose ……………………………………………………………………. 4
II. Project Location ……………………………………………………………………….……… 4
III. Proposed Action ………………………………………………………………………...……. 5
IV. Construction Overview ……………………………………………………………….…….. . 7
V. Classification of Marine Waters at Project Site ……………………………………..….…. 8
VI. Part 400 Water Quality Criteria Analysis ………………………………………………..…10
VII. Part 500, §65-130-530(3)(i) Review – Control of Turbidity Plumes ……………….….. 14
VIII. Part 500, §65-130-530(3)(ii) (iii) and (iv) Review – Water Quality Monitoring Plan
IX. List of Required Permit Actions and Approvals ……………………………………….…. 19
I. Introduction and Purpose
The purpose of this Water Quality Monitoring Plan is to describe the mitigation measures that will be implemented to control turbidity plumes and other possible construction-associated pollutants such as oil and suspended sediment during dredging operations and the associated water quality sampling…