B08_ATTACH_1_DEVA_236691_Specification_Manual.pdf
PDF 14 MB Posted
- Attached to
- DEVA 236691 Replace Historic Scotty's Castle Clima Federal contract opportunity
- Solicitation number
- 140P2022R0103
About this file
This federal solicitation requests proposals to replace the climate control system at Scotty's Castle in Death Valley National Park. The National Park Service seeks proposals under solicitation number 140P2022R0103 by July 15, 2022 to replace aging HVAC equipment at the historic castle. Proposals should address replacing all HVAC components to restore climate control and prevent further deterioration of the landmark building. The replacement system must be compliant with historic preservation standards and ensure visitor and collection protection. The award is expected by September 30, 2022 to complete installation before peak visitation season.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Death Valley National Park
Replace Scotty’s Castle Climate Control System
CD FINAL
Project Specifications
December 5, 2019
PMIS 236691
TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT & CONTRACTING
00 01 07 – Seals Page
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 – Summary of Work
01 26 01 – Contract Modification Procedures
01 27 00 – Definition of Contract Line Items
01 31 00 – Project Management & Coordination
01 32 16 – Construction Schedule
01 32 33 – Photographic Documentation
01 33 23 – Submittal Procedures
01 35 13.22 – Archeological Protection
01 35 23 – Safety Requirements
01 35 43 – Environmental Procedures
01 35 91 – Historic Preservation Treatment Procedures
01 40 00 – Quality Requirements
01 42 00 – Reference Standards
01 50 00 – Temporary Facilities and Controls
01 57 19.11 – Indoor Air Quality Management
01 57 19.12 – Noise & Acoustics Management
01 57 23 – Under an Acre Pollution Prevention
01 67 00 – Product Requirements
01 73 29 – Cutting and Patching
01 73 40 – Execution
01 74 19 – Construction Waste Management and Disposal
01 77 00 – Closeout Procedures
01 78 23 – Operation and Maintenance Data
01 79 00 – Demonstration and Training
01 81 13 – Sustainable Design Requirements
01 91 14 – Total Building Commissioning
DIVISION 02 – EXISTING CONDITIONS
02 41 13 – Selective Site Demolition
02 41 91 – Selective Historic Demolition
02 82 13 – Asbestos Abatement
DIVISION 03 – CONCRETE
03 01 30.71 – Rehabilitation of Cast-in-Place Concrete
03 20 00 – Concrete Reinforcing
03 30 00 – Cast-in-Place Concrete
03 31 00 – Normal Weight Structural Concrete
03 40 00.10 – Concrete Jersey Barriers
DIVISION 04 – MASONRY
04 20 00 – Unit Masonry
DIVISION 05 – METALS
05 50 00 – Metal Fabrications
DIVISION 06 – WOOD & PLASTICS
06 05 73 – Wood Treatment
06 10 00 – Rough Carpentry
06 16 00 – Sheathing
06 41 00 – Architectural Wood Casework
DIVISION 07: THERMAL AND MOISTURE PROTECTION
07 32 13 – Clay Tiles
07 62 00 – Sheet Metal Flashing and Trim
07 92 00 – Joint Sealants
DIVISION 8: OPENINGS
08 11 13 – Hollow Metal Doors and Frames
08 71 00 – Door Hardware
DIVISION 9: FINISHES
09 01 20.91 – Lime Plaster Restoration
09 24 23 – Portland Cement Stucco
09 90 00 – Painting and Coating
DIVISION 10: SPECIALITIES
10 14 00 – Signage
10 44 00 – Fire Protection Specialties
10 81 19 – Rodent Control
DIVISION 11: EQUIPMENT
Not Used
DIVISION 12: FURNISHINGS
12 93 00 – Site Furnishings
DIVISION 13: SPECIAL CONSTRUCTION
DIVISION 14: CONVEYING EQUIPMENT
DIVISION 21: FIRE SUPPRESSION
DIVISION 22: PLUMBING
22 05 00 - Common Work Results for Plumbing
22 05 23 - General-Duty Valves for Plumbing Piping
22 05 29 - Hangers and Supports for Plumbing Piping and Equipment
22 05 48 - Vibration and Seismic Controls for Plumbing Piping and Equipment
22 05 53 - Identification for Plumbing Piping
22 07 19 - Plumbing Piping Insulation
22 11 16 - Domestic Water Piping with Designer Notes
22 11 19 - Domestic Water Piping Specialties
22 13 16 - Sanitary Waste and Vent Piping
22 13 19 - Sanitary Waste Piping Specialties
22 45 00 – Emergency Plumbing Fixtures
DIVISION 23: HEATING, VENTILATING, AND AIR CONDITIONING
23 01 30.52 - Existing HVAC Air Distribution System Cleaning
23 05 00 - Common Work Results for HVAC
23 05 13 - Common Motor Requirements for HVAC Equipment
23 05 17 - Sleeves and Sleeve Seals for HVAC Piping
23 05 18 - Escutcheons for HVAC Piping
23 05 23.12 - Ball Valves for HVAC Piping
23 05 23.13 - Butterfly Valves for HVAC Piping
23 05 23.14 - Check Valves for HVAC Piping
23 05 29 - Hangers and Supports for HVAC Piping and Equipment
23 05 48 - Vibration and Seismic Controls For HVAC
23 05 53 - Identification for HVAC Piping and Equipment
23 05 93 - Testing, Adjusting, And Balancing for HVAC
23 07 13 - Duct Insulation with Designer Notes
23 08 00 – Commissioning of HVAC
23 09 23 - Direct Digital Control (DDC) System for HVAC
23 09 23.11 - Control Valves
23 09 23.14 - Flow Instruments
23 09 23.23 - Pressure Instruments
23 09 23.27 - Temperature Instruments
23 11 26 - Facility Liquefied-Petroleum Gas Piping
23 21 13 - Hydronic Piping with Designer Notes
23 21 13.13 – Underground Hydronic Piping
23 21 16 - Hydronic Piping Specialties
23 21 23 - Hydronic Pumps
23 31 13 - Metal Ducts
23 51 23 - Gas Vents
23 52 16 - Condensing Boilers
23 64 23.16 - Water-Cooled, Scroll Water Chillers
23 65 14.16 - Closed-Circuit, Induced-Draft, Counterflow Cooling Towers
23 82 19 - Air Handling Units
DIVISION 26: ELECTRICAL
26 05 00 – Common Work Results for Electrical
26 05 19 – Low-Voltage Electrical Power Conductors and Cables
26 05 26 – Grounding and Bonding for Electrical Systems
26 05 29 – Hangers and Supports for Electrical Systems
26 05 33 – Raceway and Boxes for Electrical Systems
26 05 44 – Sleeves and Sleeve Seals for Electrical Raceways and Cabling
26 05 48 – Vibration and Seismic Controls for Electrical Systems
26 05 53 – Identification for Electrical Systems
26 05 73 – Electrical System Studies
26 08 00 – Commissioning of Electrical Systems
26 09 23 – Lighting Control Devices
26 24 16 – Panelboards
26 27 13 – Electricity Metering
26 27 26 – Wiring Devices
26 28 16 – Enclosed Switches and Circuit Breakers
26 29 13 – Enclosed Controllers
26 41 13 – Lightning Protection for Structures
26 43 13 – Transient-Voltage Suppression for Low-Voltage Elect
26 51 00 – Lighting Fixtures
DIVISION 28: ELECTRONIC SAFETY AND SECURITY
• Not Used
DIVISION 31: EARTHWORK
31 10 00 – Site Clearing
31 22 19 – Finish Grading
31 23 16.10 – Imported Soils & Fill Materials
31 23 17 – Watering
31 23 33 – Utility Excavation & Backfill
31 23 33.20 – Restoration of Surfaces
31 25 00 – Erosion & Sediment Control
31 36 19 – Gabion Revet Mattress
DIVISION 32: SITE WORK
32 12 16 – Asphalt Paving
32 93 00 - Plants
DIVISION 33: UTILITIES
33 00 00 – Pipe & Pipe Fittings: General Statement
33 01 30.14 – Effluent Piping Testing
33 05 26.16 – Utility Line Marking
33 11 16 – Site Water Utility Distribution
33 31 13 – Effluent Disposal Pipe
33 36 13.13 – Precast Concrete Sediment Tank
33 39 23 - Cleanouts
APPENDIX
A. Geotechnical Engineering Investigation – dated 7/28/2017, prepared by Ninyo & Moore
B. Hazardous Material Survey Report for Scotty’s Castle Climate Control System – dated 11/8/2018, prepared by Landmark Environmental, Inc.
C. Geotechnical Investigation of Scotty’s Castle Climate Control System Effluent Discharge area – dated 01/16/2019, prepared by Golder Associates Inc.
D. Stucco Analysis for Scotty’s Castle Visitor Center, Death Valley National Park, prepared by
Atkinson-Noland and Associates, dated 11/30/2017.
DEVA 236691 00 01 07 - 1
SEALS PAGE
SECTION 00 01 07
PART 1 - GENERAL
1.1 SUMMARY
A. Professional seals by Design Professionals and others responsible for preparing Construction
Documents:
1. Civil Engineer:
2. Landscape Architect:
3. Architect:
DEVA 236691 00 01 07 - 2
4. Structural Engineer
5. Mechanical Engineer:
6. Electrical Engineer:
DEVA 236691 00 01 07 - 3
7. Effluent Disposal:
03 31 00 Normal Weight Structural Concrete
03 40 00.10 Concrete Jersey Barrier
31 10 00 Site Clearing
31 22 19 Finish Grading
31 23 16.10 Imported Soils & Fill Materials
31 23 17 Watering
31 23 33 Utility Excavation & Backfill
31 23 33.20 Restoration of Surfaces
31 25 00 Erosion & Sediment Control
31 36 19 Gabion Revet Mattress
33 00 00 Pipe & Pipe Fittings: General Statement
33 01 30.14 Effluent Piping Testing
33 05 26.16 Utility Line Marking
33 31 13 Effluent Disposal Pipe
33 36 13.13 Precast Concrete Sediment Tank
33 39 23 Cleanouts
12-5-2019
DEVA 236691 00 01 07 - 4
THIS PAGE INTENTIONALLY LEFT BLANK
DEVA - 236691 01 11 00 - 1
091015 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Government Furnished Materials.
5. Contractor use of premises.
6. Public use of site.
7. Occupancy requirements for buildings.
8. Work Restrictions.
9. Special Construction Requirements.
10. Soils Investigation Report.
11. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Death Valley National Park, Scotty’s Castle HVAC Replacement at the Main
House and Annex, Project site is located in California.
B. The Work consists of the following:
1. The Work includes the removal of the existing water source heat pump (WSHP) HVAC system at the Castle Main House and Annex and shall be replaced with a new 4-pipe boiler/chiller system with new air handling units (AHU) in the Castle Main House and
Annex. The work includes selective demolition at the Castle Main House, Annex and
Stables, installation of new HVAC and electrical systems, protection of existing historic fabric, selective site work, trenching for installation of new MEP infrastructure, modifications to existing interior partition framing at the Stables, construction of a new mechanical room at the Stables, construction of a new cooling tower and cooling tower enclosure east of the Stables, and construction of a new effluent disposal system for the cooling tower effluent.
C. Project will be constructed under a single prime contract.
1.3 WORK PHASES
A. The Work shall be conducted in one phase.
DEVA - 236691 01 11 00 - 2
1.4 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
B. Preceding Work: Government will award separate contract(s) for the following construction operations at Project site. Those contracts may be in progress when the work of this contract is underway.
1. DEVA site utility work – PMIS 227657: A separate contract will be awarded to the successful bidder (contractor TBD) for the construction required to upgrade the existing utility infrastructure at Scotty’s Castle.
C. Concurrent Work: Government will award separate contract(s) for the following construction operations at Project site. Those operations may begin or be in progress during execution of the work of this contract.
1. DEVA Flood Protection Structures – DEVA 227682 : A separate contract will be awarded to the successful bidder (contractor TBD) for the site improvement construction to add drainage swales and earthen berms to mitigate the impact of future floods on the Scotty’s
Castle complex of buildings.
2. DEVA Visitor Center Rehabilitation – DEVA 227652 : A separate contract will be awarded to the successful bidder (contractor TBD) for the rehabilitation of the flood damaged Visitor Center which includes grading improvements to the courtyard between the Visitor Center and the Castle Main House and Annex.
D. Future Work: Government will award separate contract(s) for the following additional work to be performed at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Contract.
1. DEVA 234012: Repair of telecommunications at Scotty’s Castle.
1.5 GOVERNMENT-FURNISHED MATERIALS
A. Government will furnish products indicated.
1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.
2. After delivery, Government will inspect delivered items for damage. Contractor shall be present for and assist in Government's inspection.
3. If Government-furnished items are damaged, defective, or missing, Government will arrange for replacement.
4. Contractor is responsible for receiving, unloading, and handling Government-furnished items at Project site.
5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.
6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.
DEVA - 236691 01 11 00 - 3
7. Contractor shall install and otherwise incorporate Government-furnished items into the
Work.
B. Government-Furnished Products:
1. Salvaged clay tile from park inventory for wall cap at new cooling tower enclosure – coordinate location of existing clay tiles with Contracting Officer.
1.6 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to the area as indicated on the Staging Plan included in the drawings, refer to sheet G0.4. Further, the contractor shall only have access to the Castle Main House Basement and Annex Basement to perform work. For portions of work that require access to main or upper floors of the Main House and Annex, contractor shall coordinate with Contracting Officer to schedule work for an appropriate time.
2. Limit site disturbance, including earthwork and clearing of vegetation, to 20 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.
3. Contractors shall limit the weight of vehicles at the construction site to 6,000 lbs. maximum or the drive surface must be covered with steel plates. This restriction specifically applies to driveways over top of the existing sub-grade tunnels.
B. No work will be allowed within 0.25 miles (1,320 feet) of the wetlands shown in the plan below from
April 10 to August 16. However, work may resume after June 24 if the Government determines that no Threatened or Endangered bird species is present in the area.
DEVA - 236691 01 11 00 - 4
1. No work will be allowed at any time within 50 ft of active bird nests.
2. No work will be allowed within 100 ft of active raptor nests.
3. The Contracting Officer shall be notified immediately of any bird nests discovered near the project site.
C. Site Access: Death Valley National Park restricts commercial vehicles travel on the roads accessing the site. A permit will be issued by Death Valley National Park covering contractor deliveries to the site as follows:
1. When observed by law enforcement officers, commercial vehicles will be stopped and asked to show proof of local delivery to the project.
2. Proof of local delivery shall be a document that identifies the name of the general contractor, the general contractor’s contract number, and the delivery locations of Scotty’s
Castle. Acceptable forms of proof of local delivery shall only be:
a. A business card created by the general contractor with the required information on it, provided by the general contractor to the commercial vehicle operator, or
b. A bill of lading that includes all of the required information.
3. There shall be no additional cost to the government for delivery delays caused by law enforcement stop of commercial vehicles, or failure of the delivery vehicle to have on hand require proof of local delivery.
4. Contractor shall be aware, and make all delivery companies aware, that commercial traffic on “Daylight Pass Road” from Beatty Nevada to CA190 is excluded from any permit for commercial vehicles and that route may not be utilized by commercial vehicles under any circumstance.
D. Storage of Materials: Confine storage of materials to the area as indicated on the Staging Plan included in the drawings.
E. Protection of Historic Fabric/Features:
1. Contractor is required to attend a briefing with DEVA historic preservation staff prior to commencing construction work onsite. Contractor superintendent will be provided information regarding allowable behaviors onsite as it relates to impact on historic fabric and features.
2. Contractor is required to brief each contractor and subcontractor staff member of the same information immediately upon arrival at the jobsite.
3. Contractor is required to keep a log of contractor/subcontractor employees who have been briefed including name, company, position, and briefing date. Records shall be updated and provided to the Contracting Officer bi-weekly.
F. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
DEVA - 236691 01 11 00 - 5
G. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
H. Construction Camp: Establishment of a camp within the park will not be permitted.
I. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
J. Preservation of Cultural Resources: Scotty’s Castle Main House, Annex and Stables are all contributing structures in the Death Valley Scotty Historic District, which was listed on the National
Register of Historic Places in 1978. The Main House, Annex and Stables are all constructed in the
“provincial Spanish” style which is a defining characteristic of the structures within the complex and is comprised of: textured/troweled stucco finish, antiquated redwood elements (fascia, rafter tails, gates, vertical plank doors, windows), and mission style clay roof tiles. Interior character defining features at the Main House and Annex consist of original redwood tongue and groove ceiling, highly detailed carved redwood trusses and ceiling joists, interior plaster walls (4 different finish types found throughout the Main House and Annex), tile flooring and ornate ironwork (light fixtures, railings, hardware). Interior character defining features within the work area at the Stables include original windows and large wooden trusses. Scotty’s Castle is also considered a cultural landscape with character defining features including the historic swimming pool adjacent to the Main House, wishing well, water feature (north of the Visitor Center) and the style of landscaping commonly found throughout the Castle complex. This project replaces critical HVAC, plumbing and electrical in the Castle Main House and Annex; the absolute utmost care and craftsmanship must be employed when working in any space within the Main House, Annex and Stables. All work must be conducted in accordance with the Secretary of the Interior’s Standards for Rehabilitation.
1.7 PUBLIC USE OF SITE
The site will be open to the public 7 days a week during normal business hours.
1.8 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with
Government during construction operations to minimize conflicts and facilitate
Government usage. Perform the Work so as not to interfere with Government’s operations.
Maintain existing exits, unless otherwise indicated.
DEVA - 236691 01 11 00 - 6
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).
1.9 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 72 hours in advance of the work to the
Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.10 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of
6:00 a.m. to 4:30 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Not allowed unless approved in advance by Contracting Officer. Submit requests 72 hours in advance to the Contracting Officer for approval.
2. Early Morning Hours: Will be allowed with prior approval from Contracting Officer
3. Hours for core drilling or other noisy work: No restrictions
4. The site is to be locked outside of normal business hours. Contractor shall ensure the site is locked if contractor leaves after normal business hours.
5. It is anticipated that construction activities will be restricted for certain months of the year due to the Migratory Bird Treaty Act. Coordinate with Contracting Officer regarding specific requirements and restrictions.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours for Utility Shutdowns: 8 hours maximum.
DEVA - 236691 01 11 00 - 7
D. Designated Smoking Location: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1. Contracting Officer to locate a designated smoking location during construction.
E. Maximum Vehicular Weight: Contractors shall limit the weight of vehicles at the construction site to 6,000 lbs. maximum or the drive surface must be covered with steel plates. This restriction specifically applies to driveways over top of the existing sub-grade tunnels.
1.11 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
1.12 SOILS INVESTIGATION REPORT
A. A soils investigation report entitled Geotechnical Evaluation dated 07/28/2017 has been prepared by
Ninyo & Moore
B. A copy of the report is available to all plan holders with this package and is in the appendix.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
1.13 ADDITIONAL REPORTS
A. A report entitled Hazardous Material Survey Report for Scotty’s Castle Climate Control System dated 11/8/2018 has been prepared by Landmark Environmental, Inc., and is included in the appendix.
B. A report entitled Geotechnical Investigation of Scotty’s Castle Climate Control System Effluent
Discharge area dated 01/16/2019 has been prepared by Golder Associates Inc, and is included in the appendix.
C. A report entitled Stucco Analysis for Scotty’s Castle Visitor Center, Death Valley National Park dated 11/30/2017 has been prepared by Atkinson Noland and Associates and is included in the appendix.
D. A copy of the reports are available to all plan holders with this package.
E. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
DEVA - 236691 01 11 00 - 8
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
DEVA - 236691 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
DEVA - 236691 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating
General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
DEVA - 236691 01 26 01 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General
Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct
DEVA - 236691 01 26 01 - 4
own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction
Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the
Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
DEVA - 236691 01 26 01 - 5
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.
Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the
US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10%
Profit………………6.7%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
DEVA - 236691 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
DEVA - 236691 01 27 00 - 1
082714 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No.01: Base Project – HVAC Replacement
1. This item consists of the base project as illustrated in the DEVA 236691 Contract
Documents. Work includes, but is not limited to complete replacement of the HVAC system at the Castle Main House and Annex, installation of a new 4-pipe boiler/chiller system with new air handling units in the Main House basement and Annex first floor, modifications/expansion to the existing electrical room at the northeast corner of the
Stables to provide a central heating and cooling plant with chillers and boilers, site trenching for heating and cooling water piping and electrical conduit between Stables and the subterranean tunnels adjacent to the Hacienda, piping continues in tunnels to the Castle
Main House basement. A new cooling tower and cooling tower enclosure shall be constructed east of the Stables building. A new leach field shall be provided south of the cooling tower for effluent from the cooling tower. New plantings will be provided around the cooling tower to screen the tower and enclosure from the public view. Preservation of all historic fabric/finishes is required, the utmost care shall be taken while working around historic fabric. Scope of work includes Architectural, Civil, Landscape, Leach Field, Structural, Mechanical and Electrical. Work under this contract line item does not include
Bid Options 1 and 2.
2. No separate measurement for payment will be made.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No.02: Bid Option #1 – Lightning Protection System
1. This item consists of the installation of a lightning protection system in accordance with the risk assessment that was performed. Refer to applicable specification system for performance requirements.
2. No separate measurement for payment will be made.
3. Payment will be made at the contract lump sum price.
DEVA - 236691 01 27 00 - 2
082714 DEFINITION OF CONTRACT LINE ITEMS
C. Contract Line Item No. 03: Bid Option #2 – Concrete Encased Ductbank
1. This item consists of the installation of a concrete encased ductbank for the buried utilities feeding the cooling tower at the cross over wash #5 at the east side of the Stables.
2. No separate measurement for payment will be made.
3. Payment will be made at the contract lump sum price.
D. Contract Line Item No. 4: Unit Cost #1 – Unit Cost for Stucco Repair
1. This item consists of minor exterior stucco repair in areas impacted by the scope of work, most notably, at the north side of the Stables where the existing sash will be retrofitted to include a new mechanical louver.
2. No separate measurement for payment will be made.
3. Payment will be made at the contract unit price per square foot for plaster repair. Assume
50SF of repair.
E. Contract Line Item No. 5: Unit Cost #2 – Unit Cost for Repair of Concrete Floor
1. This item consists of concrete floor patching, as necessary, after the WSHP are removed from the Castle and Annex basement. Concrete patching shall match the existing adjacent concrete in composition and color.
2. No separate measurement for payment will be made.
3. Payment will be made at the contract unit price per square foot for concrete repair. Assume
400SF of repair.
F. Contract Line Item No. 6: Unit Cost #3 – Unit Cost for Repair of Plaster Walls
1. This item consists of patching historic plaster walls, as necessary, after the removal of the
WSHP’s in the Castle and Annex basement. Plaster patching shall match the existing adjacent in composition, color and tooling.
2. No separate measurement for payment will be made.
3. Payment will be made at the contract unit price per square foot for plaster wall repair.
Assume 400SF of repair.
G. Contract Line Item No. 7: Unit Cost #4 – Unit Cost for Repair of Plaster Ceiling
1. This item consists of patching historic plaster ceilings, as necessary, after the removal of the WSHP’s in the Castle and Annex basement. Plaster patching shall match the existing adjacent in composition, color and tooling.
2. No separate measurement for payment will be made.
3. Payment will be made at the contract unit price per square foot for plaster ceiling repair.
Assume 400SF of repair.
END OF SECTION 01 27 00
DEVA - 236691 01 31 00 - 1
091015 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on
Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Coordination Drawings.
5. Requests for Information (RFIs).
6. NPS/DSC SharePoint Project Website.
7. Project meetings.
8. Environmental Coordination.
9. Permits
B. Related Requirements:
1. Section 01 11 00 “Summary of Work” for description of project, work restrictions, work under other contracts, contractor use of site, preservation of cultural resources.
2. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
3. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
4. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
5. Section 01 91 14 “Total Building Commissioning” for coordinating the work with Owner’s
Commissioning Authority.
1.2 DEFINITIONS
A. Link: Agency with Jurisdiction
B. Link: Construction Permits – Contractor Provided
C. Link: Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm
DEVA - 236691 01 31 00 - 2
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
9. Commissioning activities.
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base
Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
e. Indicate required installation sequences.
DEVA - 236691 01 31 00 - 3
2. Sheet Size: Submittals shall be formatted such that they are legible when printed at 11x17 size, but no larger than 30x42 paper size.
3. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Section
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.
2. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.
3. Structural Penetrations: Indicate penetrations and openings required for all disciplines.
4. Mechanical and Plumbing Work: Show the following:
a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.
b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.
c. Fire-rated enclosures around ductwork.
5. Electrical Work: Show the following:
a. Runs of vertical and horizontal conduit 1-1/4 inches (32 mm) in diameter and larger.
b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.
c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.
d. Location of pull boxes and junction boxes, dimensioned from column center lines.
6. Fire-Protection System: Show the following:
a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.
7. Review: Contracting Officer (CO) will review coordination drawings to confirm that the
Work is being coordinated, but not for the details of the coordination, which are
Contractor's responsibility. If CO determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, CO will so inform
Contractor, who shall make changes as directed and resubmit.
8. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."
C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
DEVA - 236691 01…
This is the start of the file's text. The full file is on GovTribe.