This document is a specification section outlining requirements for temporary facilities and controls for the replacement of the historic Scotty's Castle climate control system project at Death Valley National Park. The specification requires the contractor to provide temporary utilities, support facilities, security, and protection facilities for the project. This includes temporary electric, water, sanitation, lighting and communications. The contractor must also furnish, install and maintain temporary roads, parking, debris disposal, dust control and traffic control as needed. Environmental protection, pest control, site security including fencing and barricades are also specified. The contractor must provide a temporary field office for the contracting officer if required. The document defines materials, installation and operational requirements for the various temporary facilities.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEVA - 236691 01 50 00 - 1
091015 TEMPORARY FACILITIES AND CONTROLS
SECTION 01 50 00 - TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes requirements for temporary utilities, support facilities, security, and protection facilities.
1.2 DEFINITIONS
A. Permanent Enclosure: As determined by Contracting Officer, permanent or temporary roofing is complete, insulated, and weathertight; exterior walls are insulated and weathertight; and all openings are closed with permanent construction or substantial temporary closures.
1.3 USE CHARGES
A. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.
B. Water Service: Non-potable water for construction from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs.
C. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs.
1.4 QUALITY ASSURANCE
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.
B. Environmental Protection: Provide environmental protection as required by agency(ies) with jurisdiction and as indicated in the Contract Documents. Coordinate with requirements of the following:
1. Regulatory Requirements.
2. Indoor Air Quality (IAQ) Management.
3. Noise & Acoustics Management.
4. Environmental Management.
5. Construction Waste Management.
DEVA - 236691 01 50 00 - 2
1.5 PROJECT CONDITIONS
A. Temporary Use of Permanent Facilities: Installer of each permanent service shall assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before NPS acceptance, regardless of previously assigned responsibilities.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Temporary materials may be new or used, but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.
B. Pavement: Comply with Division 32. pavement Sections.
C. Chain-Link Fencing: Minimum 2-inch (50-mm), 0.148-inch- (3.76-mm-) thick, galvanized steel, chain-link fabric fencing; minimum 6 feet (1.8 m) high with galvanized steel pipe posts; minimum 2-3/8-inch- (60-mm-) OD line posts and 2-7/8-inch- (73-mm-) OD corner and pull posts, with 1- 5/8-inch- (42-mm-) OD top rails
D. Portable Chain-Link Fencing: Minimum 2-inch (50-mm), 9-gage, galvanized steel, chain-link fabric fencing; minimum 6 feet (1.8 m) high with galvanized steel pipe posts; minimum 2-3/8-inch- (60-mm-) OD line posts and 2-7/8-inch- (73-mm-) OD corner and pull posts, with 1-5/8-inch- (42-mm-) OD top and bottom rails. Provide galvanized steel bases for supporting posts.
E. Safety Barrier Fence: Orange plastic fence, minimum height, 4 feet.
F. Barrier Tape: Yellow tape Imprinted with "CAUTION: CONSTRUCTION AREA", manufactured by Reef Industries, Inc., Houston, Texas, or approved equal.
G. Lumber and Plywood: Comply with requirements in Division 06 Section "Rough Carpentry."
2.2 TEMPORARY FACILITIES
A. Field Offices, General: Prefabricated or mobile units with serviceable finishes, temperature controls, and foundations adequate for normal loading.
B. Storage and Fabrication Sheds: Temporary weather tight sheds or other covered facilities for storage of materials subject to weather damage. Number and size of structures shall be subject to Contracting Officer's approval.
C. Toilets: Sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, sturdy enclosures with privacy locks.
1. Contractor personnel requiring ABA accessible toilet facilities are authorized to use the existing accessible toilet facilities onsite, maintained by NPS.
DEVA - 236691 01 50 00 - 3
2.3 EQUIPMENT
A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.
B. HVAC Equipment: Provide vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space thermostatic control.
1. Use of gasoline-burning space heaters, open-flame heaters, or salamander-type heating units is prohibited.
2. Heating Units: Listed and labeled for type of fuel being consumed, by a testing agency acceptable to agency(ies) with jurisdiction, and marked for intended use.
3. Permanent HVAC System: If Owner authorizes use of permanent HVAC system for temporary use during construction, provide filter with MERV of 8> at each return air grille in system and remove at end of construction.
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL
A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.
1. Locate facilities to limit site disturbance and as directed by the Contracting Officer.
B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.
3.2 TEMPORARY UTILITY INSTALLATION
A. General: Install temporary service or connect to existing service.
1. Arrange with utility company, NPS, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services. Acquire all necessary permits.
B. Storm Sewers and Drainage: Provide temporary utilities to remove effluent lawfully.
1. Connect temporary sewers to private system indicated as directed by the agency(ies) with jurisdiction.
C. Non-potable water for construction is available at the site.
D. Potable water, for drinking only, is available at Grapevine Ranger Station (approximately 2 miles away)
E. Sanitary Facilities: Provide temporary toilets, and wash facilities for use by construction personnel.
DEVA - 236691 01 50 00 - 4
1. Place in approved locations secluded from public observation and convenient to work stations. Relocate as work progress requires.
2. Maintain and clean toilet facilities at least weekly.
3. Completely remove sanitary facilities on completion of work.
F. Heating and Cooling: Provide temporary heating and cooling required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of low temperatures or high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed.
1. Use of permanent heating and cooling system will not be allowed without written authorization from Contracting Officer. When the permanent heating and cooling system is approved for use as temporary heating and cooling, pay all costs until final acceptance.
Permanent heating and cooling system must be sufficiently complete, including controls, to permit safe operation
2. Provide and maintain adequate approved facilities, as required for safety and construction requirements, during the progress of the work. Provide ample clearance around stoves and heaters and all chimney and vent connections to prevent ignition of combustible material
3. Install and maintain temporary filters when air handing equipment is used for temporary heating and cooling. Install new filters before final acceptance in addition to any extra sets of filters required. Clean coils as determined by Contracting Officer.
4. Warranties for equipment used for temporary heating and cooling shall start on date of Final Acceptance.
G. Ventilation and Humidity Control: Provide temporary ventilation required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed. Coordinate ventilation requirements to produce ambient condition required and minimize energy consumption.
H. Electric Power Service: Use of existing electric power service will be permitted, as long as equipment is maintained in a condition acceptable to the NPS.
1. When temporary connections are removed, restore existing utility services to their original condition.
2. Installation of a temporary power pedestal is the responsibility of the General Contractor.
I. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.
1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.
J. Telephone Service: No telephone service is available on site for Contractor's use. Make arrangements with Telephone Company and pay all costs.
1. No cell service is currently available at the project site. Limited texting service is currently available near/adjacent to the Grapevine Ranger Station.
DEVA - 236691 01 50 00 - 5
2. Obtaining a land line from AT&T may be possible at the time of construction, but is pending a current telecommunications project.
3. No fiber is available for internet service.
4. General Contractor shall provide/install and pay for satellite internet service. Coordinate location with Contracting Officer.
3.3 SUPPORT FACILITIES INSTALLATION
A. General: Comply with the following:
1. Provide incombustible construction for offices, shops, and sheds located within construction area or within 50 feet of building lines. Comply with NFPA 241.
2. Maintain support facilities until near Substantial Completion. Remove structures, equipment, and furnishings, and terminate services after punch list is 100 percent completed or when directed by Contracting Officer. Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to Contracting Officer.
B. The Contracting Officers Field Office:
1. Separate field office not required. Contracting Officer’s office to be located at the Cook
1. Separate field office required. Provide office space for Contracting Officer adequate to have private conversations, reliable high-speed internet of adequate speed for participating in on-line conference calls like Microsoft Teams, temperature control, reliable power, desk, chair and use of contractor provided restrooms. Contractor to pay all fees. All temporary facilities and utilities provided here shall meet other relevant parameters within this specification section. Use of park buildings will not be allowed
C. Temporary Roads and Paved Areas: Construct and maintain temporary roads and paved areas adequate for construction operations if needed. Locate temporary roads and paved areas in coordination with the Contracting Officer.
1. Provide dust-control treatment that is nonpolluting and non-tracking. Reapply treatment as required to minimize dust.
D. Traffic Controls: Erect and maintain barricades, lights, danger signals, and warning signs in accordance with Manual on Uniform Traffic Control Devices (MUTCD), Part IV, latest edition.
1. Protect existing site improvements to remain including curbs, pavement, and utilities.
2. Maintain access for fire-fighting equipment and access to fire hydrants.
3. Illuminate barricades and obstructions at night; keep safety lights burning from sunset to sunrise.
4. Adequately barricade and post open cuts in or adjacent to thoroughfares.
5. Protect pedestrian traffic by guardrails or fences.
6. When pedestrian traffic is detoured onto a roadway, provide temporary walkways with protection as required at ends and overhead. For walkways, use lumber running parallel to direction of traffic movement and provide ramps at changes of elevation.
DEVA - 236691 01 50 00 - 6
7. Cover pipes, hoses, and power lines crossing sidewalks and walkways with troughs using beveled edge boards.
8. Install Barrier Tape where directed by Contracting Officer. Keep a minimum of two rolls on site at all times
E. Parking: Use designated areas of existing parking areas for construction personnel.
F. Dewatering Facilities and Drains: Comply with requirements of the agency(ies) with jurisdiction.
Maintain Project site, excavations, and construction free of water.
1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining properties nor endanger permanent Work or temporary facilities.
2. Remove snow and ice as required to minimize accumulations.
G. Project Identification and Temporary Signs: Provide Project identification and other signs.
Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.
1. Provide temporary, directional signs for construction personnel and visitors.
2. Maintain and touchup signs so they are legible at all times.
3. Erect and maintain sufficient detour signs at road closures and along detour routes.
H. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of agency(ies) with jurisdiction.
3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
B. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area. Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material.
Disassembly of equipment components or specialized inspection tools are not required.
C. Temporary Erosion and Sedimentation Control: Refer to Section 01 57 23 “Temporary Storm Water Pollution Prevention”.
D. Tree and Plant Protection: Refer to Section 01 11 00 “Summary of Work”.
E. Pest Control: Follow NPS requirements and practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at Substantial Completion. Perform control operations lawfully, using environmentally safe materials.
1. Food items should be stored in secure location, away from ravens and other animals. Do not store food items in vehicles.
2. Feeding wildlife is strictly prohibited.
DEVA - 236691 01 50 00 - 7
F. Site Enclosure Fence: Before construction operations begin, furnish and install chain link fencing in a manner that will prevent people and animals from easily entering site except by entrance gates.
1. Extent of Fence: As required to enclose entire Project site or portion determined sufficient to accommodate construction operations.
2. Locate vehicular gates to avoid interference with traffic on public thoroughfares.
3. Locate pedestrian entrance gates as required to provide controlled personnel entry.
G. Security Enclosure and Lockup: Install substantial temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security.
H. Barricades, Warning Signs, and Lights: Comply with requirements of agency(ies) with jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.
I. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities.
Provide temporary weathertight enclosure for building exterior.
1. Where heating or cooling is needed and permanent enclosure is not complete, insulate temporary enclosures.
J. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with
NFPA 241.
1. Responsible Person: A capable and qualified person shall be placed in charge of fire protection. The responsibilities shall include locating and maintaining fire protective equipment and establishing and maintaining safe torch cutting and welding procedures.
2. Smoking: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes. Contracting Officer to locate a designated smoking location during construction.
3. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of NPS. Check with park; many require “burn permits” for welding.
4. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information.
5. Provide temporary standpipes and hoses for fire protection. Hang hoses with a warning sign stating that hoses are for fire-protection purposes only and are not to be removed.
Match hose size with outlet size and equip with suitable nozzles.
6. Hazard Control: Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in historic structures. Provide adequate ventilation during use of volatile or noxious substances.
7. Spark Arresters: Equip all gasoline or diesel powered equipment used during periods of potential fire hazards or in potential forest and grass fire locations with spark arresters approved by the USDA Forest Service.
a. Written determinations of periods and areas of potential fire hazard will be issued by Contracting Officer.
DEVA - 236691 01 50 00 - 8
8. Buildings: Furnish a minimum of one extinguisher for each 1,500 square feet of area or major fraction thereof.
a. Travel distance from any work station to the nearest extinguisher shall not exceed 75 feet.
9. Vehicles and Equipment: Provide one extinguisher on each vehicle or piece of equipment.
10. Service and Refueling Areas: Locate areas a minimum of 100 feet from buildings. Shut down equipment before refueling.
3.5 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.
B. Maintenance: Maintain facilities in good operating condition until removal.
1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.
C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.
D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.
1. Materials and facilities that constitute temporary facilities are property of Contractor. NPS reserves right to take possession of Project identification signs.
2. At Substantial Completion, clean and renovate permanent facilities used during construction period.
END OF SECTION 01 50 00