B08_Att_01_Scope_GLCAAntelopePoint-DB-RFP_250722.pdf
PDF 1 MB Posted
- Solicitation number
- 140P2025R0021
About this file
This is a Design-Build Request for Proposal (RFP) for the Glen Canyon Low Water Ramps project at Antelope Point in Glen Canyon National Recreation Area, Arizona. The National Park Service (NPS) is seeking a contractor to design and construct a new 150-foot-wide boat launch ramp, an 8.3-acre boat trailer parking lot, and a 0.7-acre passenger vehicle parking lot. The project will accommodate lake elevations between 3,445 and 3,700 feet, with a 10.5% ramp slope. The total planned contract time is 820 days, with construction to be completed within 580 calendar days after the Notice to Proceed. The project includes multiple contract line item options for different ramp widths and water elevation ranges, allowing flexibility in the final implementation. Key requirements include compliance with numerous design standards, environmental regulations, and National Park Service guidelines, with a focus on sustainable design, accessibility, and minimal environmental impact.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GLEN CANYON
NATIONAL RECREATION AREA (GLCA)
LAKE POWELL, ARIZONA
SOLICITATION 140P2025R0021
GLEN CANYON LOW WATER RAMPS (ANTELOPE POINT
DISTRICT)
GLCA 318876
DESIGN-BUILD (DB) PROJECT SCOPE
(DB Request for Proposal (RFP))
NATIONAL PARK SERVICE (NPS)
DENVER SERVICE CENTER (DSC)
DB RFP GLCA 318876 | Page 2 of 61
TABLE OF CONTENTS
1.0 PROJECT INTRODUCTION
1.1 SCOPE
1.2 NPS/DSC SHAREPOINT PROJECT WEBSITE
1.3 LOCATION
1.4 BACKGROUND
1.5 DESCRIPTION
1.6 SCHEDULE
SITE EVALUATION
DB DESIGN DEVELOPMENT (DD) DOCUMENTS:
100% DRAFT DB CONSTRUCTION DOCUMENTS (CD):
100% COMPLETE DB CONSTRUCTION DOCUMENTS (CD):
COMPLETE STAMPED AND SIGNED DB CONSTRUCTION DOCUMENTS (CD):
CONSTRUCTION:
AS-CONSTRUCTED DRAWINGS:
1.7 NPS CONTACTS & ADDRESS:
1.8 DATA AND MATERIALS PROVIDED BY NPS
2.0 PROJECT REQUIREMENTS
2.1 GENERAL REQUIREMENTS
2.1.1 SCOPE OF WORK AND PROJECT SUMMARY/REQUIREMENTS
2.1.2 DEFINITION OF CONTRACT LINE ITEMS
2.1.3 PROGRESS PAYMENTS
2.1.4 PROJECT MEETINGS
2.1.5 PROJECT SCHEDULE
2.2 DESIGN REQUIREMENTS
2.2.1 EVALUATION OF SCHEMATIC DESIGN DOCUMENTS
2.2.2 DB DESIGN DEVELOPMENT (DD) DOCUMENTS AND DB CONSTRUCTION
DOCUMENTS (CD)
2.2.3 ENVIRONMENTAL, REGULATORY COMPLIANCE, AND PERMITTING,
REQUIREMENTS FOR DESIGN
2.3 CONSTRUCTION REQUIREMENTS
2.3.1 ENVIRONMENTAL REQUIREMENTS
2.3.2 SCHEDULE OF VALUES
2.3.3 CONSTRUCTION SUPPORT
2.3.4 SUBMITTALS DURING CONSTRUCTION
2.3.5 CONSTRUCTION COORDINATION
2.3.6 OTHER CONTRACTS, WORK AND EVENTS
2.3.7 DIGITAL IMAGES
2.3.7 QUALITY CONTROL
2.3.8 WORKING HOUR RESTRICTIONS
2.3.9 TEMPORARY SERVICES
2.3.10 ACCESS
2.3.11 PRESERVATION OF ADJACENT FEATURES
2.3.12 EXISTING UTILITIES
2.3.13 HAULING RESTRICTIONS
2.3.14 ACCIDENT PREVENTION
2.3.15 TEMPORARY CONTROLS
DB RFP GLCA 318876 | Page 3 of 61
2.3.16 FIELD ENGINEERING
2.3.17 PROJECT CLOSE-OUT
2.3.18 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
2.4 FORMS
APPENDIX A
APPENDIX B
3.0 PERFORMANCE REQUIREMENTS
3.1 DESIGN IMPERATIVES
3.2 INTEGRATED DESIGN PRINCIPLES
3.3 FACILITY PERFORMANCE
3.4 ELEMENTS AND PRODUCTS
4.0 TECHNICAL REQUIREMENTS
4.1 OVERALL PERFORMANCE CRITERIA
4.2 DESCRIPTION
4.3 FIXED DESIGN REQUIREMENTS
4.4 TECHNICAL CONTENTS
SECTION 01 11 00 - SUMMARY OF WORK
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
SECTION 01 32 33 – PHOTO DOCUMENTATION
SECTION 01 33 23 - SUBMITTAL PROCEDURES
SECTION 01 35 13.22 – ARCHEOLOGICAL PROTECTION
SECTION 01 35 23 - SAFETY REQUIREMENTS
SECTION 01 35 25 - EXPLOSIVES
SECTION 01 40 00 - QUALITY REQUIREMENTS
SECTION 01 42 00 – REFERENCE STANDARDS
SECTION 01 50 00 - TEMPORARY FACILITIES AND CONTROLS
SECTION 01 57 19.12 – NOISE AND ACCOUSTICS MANAGEMENT
SECTION 01 57 23 - TEMPORARY STORM WATER POLLUTION PREVENTION
SECTION 01 67 00 - PRODUCT REQUIREMENTS
SECTION 01 73 29 - CUTTING AND PATCHING
SECTION 01 73 40 - EXECUTION
SECTION 01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
SECTION 01 74 19B - STANDARD SOLID WASTE CONVERSIONS
SECTION 01 77 00 - CLOSEOUT PROCEDURES
SECTION 01 78 23 - OPERATION AND MAINTENANCE DATA
SECTION 01 79 00 - DEMONSTRATION AND TRAINING
5.0 ATTACHMENTS
DB RFP GLCA 318876 | Page 4 of 61
1.0 PROJECT INTRODUCTION
Park Acronym and PMIS Number: GLCA 318876
Project Title: GLEN CANYON LOW WATER RAMPS (ANTELOPE POINT DISTRICT)
Project Drawing Number: GLCA 608 194758
1.1 Scope
In accordance with terms and conditions of the Contract, the Design-Build (DB) Contractor shall perform the work of this Request for Proposal (RFP) for the National Park Service (NPS) as described below.
Architect-Engineer (A/E) Services required in this RFP shall be performed by licensed Architects and Engineers registered in Arizona (as required).
Complete this task order using requirements and criteria on Denver Service Center (DSC) Design-Build (DB) Workflows website.
The DB home page includes links to design phases that describe required workflow processes from Predesign (PD) through Construction Documents (CD). Each design phase web page contains links to definitions, forms, templates, samples, and guidelines.
The DB home page also includes links to the Design Standards and Design Deliverables sections, which provide design requirements and criteria that will be used for completing the work of this contract, as follows:
Design Standards are arranged by discipline and/or specialty.
DB Design Deliverables - Content and Format Requirements o Design phase submission requirements for:
Technical content Submission format
In addition, the Information section has links directly to the following:
o Definitions: A list of terms relevant to design and construction in National Parks.
o Forms/Templates/Samples/Guidelines: A list of forms, templates, samples, and guidelines used for a typical project.
o Law/Regulations/Polices/Guidance: A list of sources for retrieving laws, regulations, policies, and guidance applicable to NPS projects.
o Quality Assurance (QA) Guideline & Review Checklists: Overview of the DSC QA process for reviewing design documents.
In case of conflict between this task order and the DSC DB Workflows website, this task order shall take precedence and shall be used in lieu of conflicting portions.
The Design Build Contractor (DB) remains fully responsible for determining if the standards or provisions cited on the DSC DB Workflows website have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the Contracting Officer (CO).
1.2 Project Websites
DB RFP GLCA 318876 | Page 5 of 61
Use the NPS/DSC provided project website to host and manage project communication and documentation until Final Completion. The project website will be used for:
Project directory;
Project correspondence;
Meeting agendas and minutes;
Contract modifications documentation and logs;
RFI (Request for Information) form and processing;
Task and issue management;
Photo documentation;
Baseline schedule, schedule updates and calendar management;
Submittal form and processing;
Drawing and specification document hosting, viewing, and updating;
Online document collaboration;
Reminder and tracking functions;
Archiving functions;
Notification of submittal and RFI statuses and current responsible party.
Submit to the CO a list of employees needing access to the NPS/DSC provided project website. The Department of Interior (DOI) will send these users an invitation to the site. Users are required to have Internet Explorer version 7 or later and Adobe Acrobat Professional version 9 or later.
DB Contractor to provide a website for public information and project status. Provide website layout for review and approval by the CO within the first 21 days after contract award.
1.3 Location
This project is located at Glen Canyon National Recreation Area (GLCA), Antelope Point District in Arizona.
1.4 Background
Glen Canyon National Recreation Area (GLCA) is predicting that within the near future North Lake Powell will have no operable boat launch ramps due to historically low water levels. Since 2021 the region is experiencing a dry cycle that has resulted in low lake elevations and at times required ramp closures, including the ramp at Antelope Point, though the marina is open. The marina business and valet ramp are also currently closed due to low water. Antelope Point provides an important access point for kayakers visiting Antelope Canyon, as well as large houseboats and other motorized vessels in South Lake Powell. Vessels are able to access this area by boating from the Wahweap Stateline Auxiliary launch ramp, which has been extended with declining water levels. However, there are periodic closures or delays for construction and boilerplate installations.
This project will address low-water lake access at Antelope Point based upon the relocation of the launch ramp to a new deep pool location. The work includes but is not limited to a new launch ramp and parking lots.
1.5 Description
The specific purpose of the project is to ensure long term sustainable lake access at Antelope Point by designing and constructing a new high and low water launch ramp. The ramp will be designed to accommodate lake elevations between 3,445 and 3,700 feet. Due to funding limitations, construction will reach the full design grade, but the actual service elevation will depend on the awarded bid option. This approach ensures that any
DB RFP GLCA 318876 | Page 6 of 61 future extensions can be built without reconstructing any of the ramp completed under this project.Facilities supporting the new ramp include new boat and passenger vehicle parking areas.
Boat Ramp Water Surface Elevation Performance Requirement
The Design-Builder shall design and construct the boat ramp to provide safe, durable, and functional service for launching and retrieving boats across the range of lake surface elevations between 3450 feet and 3700 feet. The design shall account for the geometry, slope, surface treatment, and structural considerations necessary to maintain usability and public safety within this service range.
For purposes of construction planning and risk allocation, the Government establishes a baseline lake surface elevation of 3580 feet as the assumed water surface elevation during design development and construction. The Design-Builder shall base its design, construction sequencing, and cost assumptions on this baseline condition.
Normal Fluctuations (3565–3595 feet): The Design-Builder shall incorporate into its design and construction approach all reasonable measures to accommodate normal lake fluctuations of ±15 feet around the baseline (elevations between 3565 and 3595) without entitlement to adjustment.
Higher Water Levels (>3595 feet): If the lake surface elevation exceeds 3595 feet during or after construction, the Government will consider this a changed condition. The Government may issue a contract modification to extend, adapt, or modify the ramp to maintain function, with equitable adjustment for the benefit of the Design-Builder.
Lower Water Levels (<3565 feet): If the lake surface elevation drops below 3565 feet during or after construction, the Government will consider this a changed condition. The Government may issue a contract modification for credit, scope reduction, or other adjustment for the benefit of the Government.
The Design-Builder shall demonstrate in the design submittals how the ramp geometry, slope, and length achieve safe and effective service between elevations 3450 and 3700, while recognizing that contractual risk for water elevation during construction is tied to 3580 feet as the baseline condition.
To align the project with available funding, a base schedule and optional betterments are evaluated as follows:
BASE SCHEDULE:
CLIN 1 BASE – DESIGN
o 150-foot-wide low water boat ramp servicing elevation 3450 to 3700-ft, a 2,419-ft length on the horizontal along a 10.5% grade.
o 8.3 Acre asphalt boat parking area connected to the top of the ramp o 0.7 Acre asphalt passenger vehicle parking area o Includes supplemental design effort supporting the awarded construction base + scalable options.
CLIN 2 BASE – CONSTRUCTION (Out of Water) o 120-foot-wide low water boat ramp servicing elevation 3580 to 3700-ft, along a 10.5% grade.
o 8.3 Acre asphalt boat parking area connected to the top of the ramp o 0.7 Acre asphalt passenger vehicle parking area
OPTIONS:
DB RFP GLCA 318876 | Page 7 of 61
CLIN 3 – Option 1 – Construction (In-Water) o 120-foot-wide low water ramp servicing elevation 3580 to 3555-ft, a 238-ft length on the horizontal along a 10.5% grade.
CLIN 4 – Option 2 – Construction (In-Water) o 120-foot-wide low water ramp servicing elevation 3555 to 3530-ft, a 238-ft length on the horizontal along a 10.5% grade.
CLIN 5 – Option 3 – Construction (In-Water) o 120-foot-wide low water ramp servicing elevation 3530 to 3505-ft, a 238-ft length on the horizontal along a 10.5% grade.
CLIN 6 – Option 4 – Construction (In-Water) o 120-foot-wide low water ramp servicing elevation 3505 to 3490-ft, a 143-ft length on the horizontal along a 10.5% grade.
CLIN 7 – Option 5 – Construction (Out of Water) o Widen from 120-foot to 150-foot-wide low water boat ramp servicing elevation 3450 to 3700-ft, a 2,419-ft length on the horizontal along a 10.5% grade.
CLIN 8 – Option 6 – Construction (In-Water) o Widen from 120-foot to 150-foot-wide low water ramp servicing elevation 3580 to 3555-ft, a 238-ft length on the horizontal along a 10.5% grade.
CLIN 9 – Option 7 – Construction (In-Water) o Widen from 120-foot to 150-foot-wide low water ramp servicing elevation 3555 to 3530-ft, a
238-ft length on the horizontal along a 10.5% grade.
CLIN 10 – Option 8 – Construction (In-Water) o Widen from 120-foot to 150-foot-wide low water ramp servicing elevation 3530 to 3505-ft, a 238-ft length on the horizontal along a 10.5% grade.
CLIN 11 – Option 9 – Construction (In-Water) o Widen from 120-foot to 150-foot-wide low water ramp servicing elevation 3505 to 3490-ft, a
143-ft length on the horizontal along a 10.5% grade.
1.6 Schedule
Complete work in this RFP according to following schedule: Total planned Contract Time = 820 days.
1.6.1 Post Award Site Evaluation
The DB Contractor will meet with NPS onsite to review the proposed solution presented in the proposal package.
This site visit is to occur no later than 21 calendar days after award. It is expected that a 3-day visit will be required. A pre-visit teleconference meeting will be conducted with NPS and the Park at least 14 calendar days before the site visit, such that logistics can be coordinated before the visit.
1.6.2 DB Design Development (DD) Documents:
Submit DB DD Documents no later than (to be defined by Design Build Contractor proposed scheduled) calendar days after award.
Allow no less than 15 calendar days for NPS Review after submitting DB DD Documents.
DB RFP GLCA 318876 | Page 8 of 61
1.6.3 100% Draft DB Construction Documents (CD):
Continue work on 100% Draft DB CD during DB DD Documents review. After receiving DB DD review comments, address and incorporate comments in 100% Draft DB CD.
Submit 100% Draft DB CD and responses to NPS Review form with responses to DB DD Documents no later than (to be defined by Design Build Contractor proposed scheduled) after receiving NPS Review comments of the DB DD Documents.
Allow no less than 15 calendar days for NPS Review after submitting 100% Draft DB CD.
1.6.4 100% Complete DB Construction Documents (CD):
Submit 100% Complete DB CD and NPS Review form with responses to 100% Draft DB CD review comments no later than (to be defined by Design Build Contractor proposed scheduled) after submitting 100% Draft DB
CD.
Allow no less than 15 calendar days for NPS Review after submitting 100% Complete DB CD.
1.6.5 Complete Stamped and Signed DB Construction Documents (CD):
Submit Complete Stamped and Signed DB CD and NPS Review form with responses to 100% Complete DB CD review comments no later than (to be defined by Design Build Contractor proposed scheduled) after receiving NPS review comments.
1.6.6 Construction:
Construction begins when CO issues DB On-site Notice to Proceed (NTP) – authorizing ground disturbing activities.
Complete construction no later than 580 calendar days following issuance of the On-Site NTP authorizing ground disturbance. Refer to Section 2.1.5 Project Schedule.
1.6.7 As-Constructed Drawings:
As constructed plans of the completed construction project are needed to provide a historic record of all work accomplished on this project. These plans are used as future references for needed repairs, maintenance, and construction projects.
Maintain one record copy of all design documentation at the site, in good order and regularly updated to show all changes made during construction. Make these documents, along with all other submittals made by the DB Contractor, available to the CO during construction.
Submit Final As-Constructed Drawings no later than 21 calendar days after Substantial Completion to the CO for review and approval.
Submit DB DD Documents, DB CD, and As-Constructed Drawings to the NPS Construction Management Representative (CMR), the NPS Project Manager (PM), and the NPS Project Specialist.
DB RFP GLCA 318876 | Page 9 of 61
Include within Division 1 Specifications, regular updates and submittals of the as constructed drawings to keep current and accurate record. A retention amount of $500k will held by the Government until final acceptance of the as-constructed drawings by the CO.
1.7 NPS Contacts & Address:
Contractual:
Contracting Officer (CO): J Zaira Lupidi, 720-830-7602, zaira_lupidi@nps.gov
Contract Specialist (CS): TBD
Technical:
Project Manager (PM) and Contracting Officer’s Representative (COR): Mike Will, 303-956-5054, mike_will@nps.gov
Project Specialist (PS) and Alternate Contracting Officer’s Representative: TBD
Mailing Address:
P.O. Box 25287 Denver, CO 80225-0287
Address:
1 Denver Federal Center Building 50 Denver Service Center Denver, CO 80205
1.8 Data and Materials Provided by NPS
Schematic Design (SD) dated October 2024 has been performed for the site. The initial engineering documents and concepts will be provided as reference documents by the government; however, these reference documents are not considered design-build bridging documents and may be used at the discretion of the DB Contractor.
The launch ramp, and parking areas construction described in this RFP are based on the completed SD. The Antelope Point Launch Ramp SD package includes the following full build elements:
150ft wide concrete launch ramp serving lake elevations 3450 to 3700-ft Paved Boat Trailer Parking Area Paved Passenger Vehicle Parking Area
NPS will provide to DB Contractor the following data and materials. (Add as attachments in Section 5.)
Project Program (For Information) NPS Design Build Workflow (For Information) o Design-Build (DB) - (U.S. National Park Service) (nps.gov) Design Build Deliverable Requirements o Quality Assurance Guidelines
DB RFP GLCA 318876 | Page 10 of 61
NPS Design Standards (For Information) AASHTO Standards (For Information) SD Basis of Design Report (BDR) (For Information) Approved Schematic Design Preferred Alternative Full Build Documents – Plan (For Information)
NPS GIS/CAD files with known sensitive areas (requires confidentiality agreement) (Bridging)
Topographic survey data (Bridging)
Geotechnical Evaluation Report (dated October 3, 2024) (Bridging)
GLCA Hydrologic and Hydraulic Memo (dated June 18, 2024) (Bridging)
Wetlands delineation (Bridging)
Park Design Guidelines (For Information)Categorical Exclusion (CE) (For Information) o *NEPA compliance authorization (in process)
*NPS is in process of securing NEPA compliance approvals. Approvals are expected no later than October 25, 2025. No ground disturbance is permitted prior to NEPA approvals. Current documents include anticipated NEPA compliance requirements, however final approval has not been received.
2.0 PROJECT REQUIREMENTS
2.1 General Requirements
2.1.1 Scope of Work and Project Summary/Requirements
The project will consist of the design and construction of a new parking areas of 8.3-acres and 0.7 acre with a houseboat turnaround at the top of the ramp. A new launch ramp that is 150 ft wide will be designed to service lake elevations between 3445 to 3700-ft at the selected deep pool location. The construction will be carried out based on the awarded scope (Base + Option), as outlined in the bid schedule and specified in Section 1.5 of this document.
The project will include, but not be limited to:
Design and Construction of roadway, parking area, and a launch ramp system including associated incidental work;
Review Schematic Design preferred alternative provided in the RFP package;
Review site data;
Submit DB Design Development and DB Construction Documents for review and approval, as required.
Secure all non-government provided construction permits necessary to support construction in accordance with all local, state, and federal requirements. Refer to Section 2.2.3;
Project Management;
Geotechnical investigation/analysis as necessary;
Survey as necessary;
Lifecycle cost analysis;
Provide, manage, and update schedule of design and construction work;
Quality Control;
Materials Sampling and Testing;
Maintenance during construction including but not limited to erosion management, traffic management, etc;
DB RFP GLCA 318876 | Page 11 of 61
Provide for continued access to existing facilities;
Provide new construction GIS data supporting updates to the NPS GIS database;
Provide as-constructed drawings;
Provide cultural and archeological monitoring throughout construction as a requirement and in with discussion with NPS;
Provide and conduct Aquatic Invasive Species Management along with Hazard Analysis Critical Control
Point Plan (HACCP).
Compliance with requirements from Standard Division 1 Template Specifications and this RFP
NPS is in process of securing NEPA compliance approvals. Approvals are expected prior to issuance of the On-site NTP authorizing ground disturbance. Supplemental conditions resulting from NEPA approvals not captured in the awarded contract requirements will be addressed through contract change.
The DB Contractor will identify any previously undefined deficiencies or failures that are uncovered as part of their due diligence.
2.1.2 Definition of Contract Line Items
The work for each Contract Line Item (CLIN) is listed in Section 1.5 (Description) of this RFP.
2.1.3 Progress Payments
Design Phase - Progress payments will be based on submission, review, and acceptance of design deliverables.
Construction Phase - Progress payments will be based on percentage of work completed on items listed in approved schedule of values. Actual construction completed and in place will form basis for payment. DB Contractor shall verify percent complete under direction of the Contracting Officer Representative unless CO waives this requirement in a specific instance. DB Contractor shall make computations for payment based on Government’s verification of work completed and in place for periods which progress payments are requested.
DB Contractor shall furnish to CO originals of field notes and other records relating to basis for payment. CO shall use as necessary to determine final amount of progress payments. DB Contractor shall retain copies of material furnished to Contracting Officer.
2.1.4 Project Meetings
Kickoff and Design Meeting
After award of contract and acceptance of Performance and Payment bonds, CO will arrange a kickoff and design meeting with DB Contractor. Meeting agenda shall include the following as a minimum:
Areas available for use by DB Contractor Access requirements of the Park Design schedule including dates Each required permit will be secured (minimum two color hard copies).
Environmental requirements Natural and Cultural Resource Protection Payments to DB Contractor
DB RFP GLCA 318876 | Page 12 of 61
Review and emphasize Park needs and design objectives.
Modifications during design Schedule of Values Submittals during design Site Visit Utility connection/outages
Site Visit/Onsite Meetings during Design
The DB Contractor will conduct one kickoff meeting on site with NPS within the first 21 days after contract award, and second meeting for preconstruction conference. The aim of this visit is to better understand the site risks and review the existing SD constructability based on SD design document and additional data collected (listed in Section 1.8). The review will be the top priority after award. Meeting on site will be for one day and include one day of travel each way.
Preconstruction Meeting
Submit following Part 2 Project Requirement deliverables a minimum of one week prior to Preconstruction Meeting.
Accident Prevention Program (APP) Evidence of liability insurance coverage and workman’s compensation for DB Contractor and
Subcontractors Letter designating your Project Superintendent List of obtained and required permits List of Subcontractors for project (same as proposal) Project Schedule with construction portion fully developed Quality Control Plan Schedule of Values National Pollutant Discharge Elimination System (NPDES) permit application forms including Storm
Water Pollution Prevention Plan (SWPPP) Waste Management Plan Written statements from Subcontractors certifying compliance with applicable labor standard clauses List of identified risks with mitigation plan Partnering agenda
After 100% Complete DB CD are approved (or completed portions of DB Construction Documents necessary for fast tracking the project), and before start of construction, The CO will arrange on-site Preconstruction meeting with DB Contractor. Meeting agenda will include the following as a minimum:
Accident reporting Construction schedule (provide electronic copy in software it was created in and a Portable Document
File [PDF] copy) Correspondence procedures Jobsite safety Labor standards Lines of Authority Modifications
DB RFP GLCA 318876 | Page 13 of 61
NPS/DSC provided project website Park Rules and Regulations Payroll reports Progress Payments Resolution to comments provided by NPS on the Part 2 Project Requirements Roles and responsibilities Schedule of Values Submittal process Access and site constraints.
Medical emergency processes, availability, emergency numbers, and contacts.
Park permits, burning construction waste, rules of the road, alcohol use, housekeeping, firearms, pets, natural and cultural resource concerns.
Public relations.
Archeological Resources Protection Requirements Environmental requirements for the Project.
Saturdays, Sundays, holidays and night work.
Traffic control.
Progress Meetings
DB Contractor shall participate in weekly telephone conference calls with CO and other project team members with updates to following meeting agenda items:
Approval of minutes of previous meetings.
Modifications Review of off-site fabrication and delivery.
Requests for Information (RFI) and issues.
Schedule update.
o (Provide updated CPM (Critical Path Method) schedule.)
o Provide updated CPM (Critical Path Method) schedule o Provide hard copies for all on-site meetings o Three week lookahead o Work in progress and projected o Three Phase Meeting Schedule
Status of Project Record Drawings and O&M (Operation & Maintenance) Manuals.
Submittal status.
Work in progress and projected.
Updated Risk Register Other business relating to work.
Over-the-Shoulder Reviews
Over-the-Shoulder reviews are strongly encouraged to enhance the partnering efforts between the DB Contractor and the Government. The intent of Over-the-Shoulder reviews is to provide guidance to the DB Contractor during the project. Over-the-Shoulder reviews will be conducted for informal review of designs only and do not replace the Overall Project Submittals. Over-the-Shoulder reviews may be scheduled by the DB Contractor or NPS. Requests for reviews must be in writing and allow at least 7 calendar days-notice prior to the proposed
DB RFP GLCA 318876 | Page 14 of 61 review. The number and timing of the reviews will be discussed at the Project Kick-off Meeting. Reviews will be held at a location approved by the CO.
2.1.5 Project Schedule
The DB Contractor must ensure construction materials, supplies, and equipment are procured with sufficient time to start construction without delay.
General: DB Contractor shall upload project schedule to NPS/DSC provided project website and provide two
(2) color copies after award and before design meeting. Schedule shall include detailed design phase with design deliverable submission dates, review periods, and summary construction schedule with important milestones included for both phases.
Fully develop construction portion of project schedule and submit to CO on NPS/DSC provided project website before Preconstruction meeting. Update project schedule monthly, or when schedule changes are known, throughout contract period until project substantial completion. Resubmit the schedule any time the schedule changes. Status date of each schedule update shall be 10 days before progress payment request date.
Construction work cannot begin until Government approval is obtained for any of the following:
Entire set of 100% Complete DB CD.
Fast track construction: 100% Complete DB CD affecting work to be constructed.
DB Contractor obtains required permits as listed in Section 2.2.3
CO issues DB Start Work Notice
CO may authorize a limited NTP for any portion of the project at 100% design or for purchasing or stockpiling of approved material.
o Early construction may begin on any approved Specific Element Submittal at the sole risk of the DB Contractor. Do not start work prior to approval or acknowledgement by the CO. The extent, acceptability, and schedule for early construction reviews will be mutually agreed as requested based on information contained in the Schedule and its approval. The CO will stop any work that does not comply with environmental, legal, standard or permitting requirements of the contract or project.
o Early elements of work include but not limited to clearing and grubbing, sourcing of materials, stockpiling, and advanced grading packages.
Allow no less than 15 calendar days for NPS Review after submitting early release packages.
Early release packages are limited to a total of 5 separate packages.
Purpose: Project schedule ensures adequate planning, coordinating, scheduling, and reporting of DB Contractor’s design and construction activities. Project schedule will assist DB Contractor and CO to monitor work progress, evaluate proposed changes, and process DB Contractor's monthly progress payment requests.
Software: Latest version of Microsoft Project, Primavera Project Planner, SureTrak, or approved equal.
Schedule Development: Project schedule shall cover entire contract period. Late finish date is same as contract’s established completion date.
DB Contractor shall use Critical Path Method (CPM) with limited use of lead or lag durations between schedule
DB RFP GLCA 318876 | Page 15 of 61 activities. DB Contractor's project schedule shall consist of procurement activities (including mobilization, submittal, and fabrication and delivery of key and long-lead procurement items) and construction activities.
DB Contractor's project schedule shall consist of, but not be limited to, the following for each activity:
Identify activities and numbers numerically (maximum 5-digit). Number activities in increments of 10.
Concisely describe work represented by activity (maximum 48 characters). Avoid using non-standard abbreviations. Limit work related to each activity to one work trade.
Activity duration shall be in whole working days with maximum duration 15 workdays each, unless otherwise approved by the CO, except for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing.
DB Contractor shall ensure project schedule includes own work and Subcontractor work.
Follow all Federal, state, and local labor laws. Schedule at least 2 non-work days out of every 14 calendar days.
The selected non-work days do not need to be consecutive, but they must be scheduled.
Project schedule shall show sequence and interdependence of activities required for complete performance of work and shall be cost and resource loaded. DB Contractor shall ensure work sequences are logical and project schedule shows a coordinated work plan. Proposed durations assigned to each activity shall be DB Contractor's best estimate of time required to complete activity, considering scope and resources planned. Resource loading of each activity shall list personnel by labor category and equipment type, and capacity proposed to complete activity in duration shown. Include permit requirements and constraints. Consider and include seasonal weather conditions in planning and scheduling of work influenced by high or low ambient temperatures and wind and/or precipitation, to ensure completion of work within contract time.
Project Schedule Updates
Monthly updates: Monthly updates of project schedule shall be an integral part and basic element of estimate upon which progress payments shall be made under this contract. If, in judgment of the CO, the DB Contractor fails or refuses to provide schedule of values and complete schedule update or revision as specified hereinafter, the DB Contractor shall be deemed to have not provided required information upon which progress payment may be made and shall be subject to retainage of a portion of the payment.
Narrative: Include in report:
Brief description of actual progress made during update period.
Actual and potential delaying activities.
Impediments to progress.
Issues related to inclement weather.
Progress toward established milestones.
Project float.
Brief description of work anticipated to be performed in next month.
Identify minor revisions to schedule for evaluation and if accepted or rejected.
As work progresses, indicate Actual Completion percentage for each activity. If schedule update shows late finish date after contract completion date, at a minimum, include the following in narrative with submission:
DB RFP GLCA 318876 | Page 16 of 61
Known delays.
Actions taken to get back on schedule.
Pending modifications.
Impediments or constraints affecting progress.
Progress Payments: Update currently accepted construction schedule monthly. If DB Contractor fails to provide monthly updates or revisions to currently accepted construction schedule, a portion of monthly payment may be retained until updates/revisions made.
Time Impact Analysis for Contract Modifications, Changes, Delays, and DB Contractor Requests Requirements: When contract modifications or changes are initiated, delays are experienced, or DB Contractor revises project schedule, DB Contractor shall submit to the CO a written time impact analysis illustrating influence of each modification, change, delay, or DB Contractor’s request on the contract time.
Time Extensions: Activity delays shall not automatically mean an extension of contract time is warranted or due to DB Contractor. It is possible that modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of available total float that may exist within an activity chain of the project schedule, thereby not effecting the contract time. Time extensions will be granted according with terms of contract.
Float: Float is not for exclusive use or benefit for NPS or DB Contractor. Extension of contract time is granted only to extent the equitable time adjustments to activity or activities affected by modification, change, or delay exceeds total (positive or zero) float available on a particular activity.
2.2 Design Requirements
2.2.1 Design Documents
2.2.1.1 Design Basis
The proof of concept for the project is defined by the SD drawings, and RFP documents. These documents define the expectations of NPS for the ultimate project including, but not limited to the following:
o Parking lot layout and location o Launch ramp size, location, and alignment.
2.2.2 DB Design Development (DD) Documents and DB Construction Documents (CD)
Prepare DB DD Documents and DB CD using English System of Weights and Measurements and according to DSC Design Standards and DSC Design Deliverables - Content and Format Requirements for DB Design Development Documents and DB Construction Documents.
List salient characteristics for products and materials specified. Refer to Guide for Specifiers.
Deliverables
Submit documents in native and PDF (Portable Document Format) file formats.
PDF files shall be unlocked to allow printing and saving.
See DB Submittal Requirements, Design Deliverables.
DB RFP GLCA 318876 | Page 17 of 61
The following deliverables are required (refer to Section 1.6 for schedule):
Submit DB DD Documents for Review o Draft DB Design Development Drawings o Divisions 2 through 49 Outline Specifications o Product File o Statement of Structural Tests and Special Inspections o Design Calculations
Submit 100% Draft DB CD for Review o 100% Draft DB CD o Divisions 2 through 49 Construction Specifications (Construction Specifications Institute (CSI)
MasterFormat 04 Edition). A/E shall utilize and modify their own Divisions 2 through 49 Construction Specifications templates.
o Product File o Statement of Structural Tests and Special Inspections o Design Calculations o Checklists for internal review of drawings, specifications, calculations, and cost estimates
Required documents for each submission are included and complete per contract requirements.
Required documents have been through a Quality Control (QC) review. NPS requires documentation and submittal of QC work performed.
o NPS Review form with responses to DB DD Documents review comments Submit 100% Complete DB CD for Final Approval o 100% Complete DB Construction Drawings o Divisions 2 through 49 Construction Specifications o Product File o Statement of Structural Tests and Special Inspections o Design Calculations o Checklists for internal review of drawings, specifications, calculations, and cost estimates
Required documents for each submission are included and complete per contract requirements.
Required documents have been through a Quality Control (QC) review. NPS requires documentation and submittal of QC work performed.
o NPS Review form with responses to 100% Draft DB Construction Documents review comments Submit Complete Stamped and Signed DB CD o Upon final approval of 100% Complete DB CD, submit the complete stamped and signed DB CD in accordance with Table 2.1 for construction, NPS archiving, and general use. For format and media submission requirements, refer to Design Deliverables – Content and Format Requirements DB Hard Copy and Electronic Submittal Requirements.
TABLE 2.1. Deliverables
Complete Stamped and Signed
DB CD
Electronic Formats[a] Hard Copy
Formats
DB RFP GLCA 318876 | Page 18 of 61
DB Construction Drawings AutoCAD and PDF N/A
Divisions 2 through 49 Construction Specifications PDF and
MS (Microsoft) Word N/A
Product File PDF N/A
Statement of Structural Tests and Special Inspections PDF and MS Word N/A Supplemental Design Reports – Evaluation of SD Documents
PDF N/A
Design Calculations PDF N/A Checklists for Internal Review of Drawings, Specifications, Calculations, and Cost Estimate
PDF and MS Excel N/A
NPS Review Form with Responses to 100% Complete DB CD Review Comments
PDF and MS Excel N/A [a] The recipient of the electronic files is TIC (Technical Information Center).
DB Construction Drawings printed from secondary software (e.g., Adobe.pdf) are not acceptable as they often result in off-scale product.
The DB Contractor will provide electronic copies of the DD and Draft CD drawings to the PM, project specialist, and the Park for each review.
Changes to CD documents. The DB Contractor may initiate design changes at any time during the process.
(a) Design Changes Prior to CD Submission. If the proposed design change occurs after a scheduled intermediate review, notify the CO in writing. In the notification, provide the following regarding the change: a general overview, reasons and justifications, and schedule impacts. Incorporate the change into the Final Submittal after receiving written approval from the CO.
(b) Design Changes After Final Design Submission. If the proposed design change occurs after a final design submission, submit a revised final design submittal for the affected segment of the project.
Conform with the technical requirements specified for that submittal type. In addition, provide the following regarding the change: a general overview, reasons and justifications, and schedule impacts.
The Government turn-around time for changes to approved CD documents is 21 calendar days, from the day the submittal is received to the day it is sent back to the DB Contractor.
2.2.3 Environmental, Regulatory Compliance, and Permitting Requirements for Design
NPS has established environmental requirements for the project. Notify the CO if conflicts arise between performance of work and environmental requirements. NPS does not intend to limit alternative means of achieving these requirements.
Permits:
Table 2.2 summarizes the environmental regulatory compliance and permitting requirements for the project, along with identifying relevant legal citations, typical associated time frames, and NPS and the DB Contractor’s roles and responsibilities in relation to the development of the document for each.
DB RFP GLCA 318876 | Page 19 of 61
TABLE 2.2. Permits
Item Legal Citation(s) NPS Role DB Role Time Frame
Sec. 404/10 Sec. 401 State Water Quality Certification (if necessary)
Clean Water Act
(CWA) § 404,
Executive Order (EO) 11990, 33 U.S.C.
1344, 33 U.S.C. 403
(R&HA 1899 §§9-10),
CWA § 401
Lead Support USACE permitting will be satisfied via non-notifying aspect of regional General Permit 6 (RGP-6). A memo to file will be completed by the Park after final description of the replacement dock is completed by the Contractor, including surface area.
Arizona Pollutant Discharge Elimination System (AZPDES) General Construction (Storm Water)
Arizona Administrative Code R18-9-C901
Support Lead Minimum of 30 days before anticipated ground disturbance
NOTE: Other regulatory compliance and permitting actions for construction and operation of the system may be required. The Contractor is responsible for identifying and obtaining any additional Federal, State, or local authorizations not listed above, as required by law.
Clean Water Act Section 404 Permit; Section 401 Water Quality Certification
Section 404/10 and 401 permits will be authorized via non-notifying aspect of Regional General Permit 6 (RGP- 6). The documentation of use of RGP-6 will be completed by the NPS via a memo to File within the project file under Planning, Environment and Public Comment (PEPC) project 57203. The memo to file will be completed after the final description of the replacement dock is completed and provided to NPS by the Contractor, which will include all necessary elements supporting justification, such as final surface area and Clean Water Act mitigation measures.
AZDES Storm Water General Permit for Construction
A AZPDES General Permit authorizing discharges of storm water associated with construction activity may be required for the project. The DB contractor will lead all actions related to requesting coverage under the state’s existing AZPDES permit program and will apply as the operator on the permit.
Construction activities that disturb one or more acres of land must be authorized under the Arizona Pollutant Discharge Elimination System (AZDES). Owners and general contractors are required to obtain a Storm Water Permit, AZDES Construction General Permit Number AZG2020-001 CGP effective July 1, 2020. This permit may cover all types and sizes of construction activity. There is no automatic coverage under the permit.
The DB contractor will be responsible for identifying and obtaining all required AZDES permits and permit requirements (including NOI, SWPPP, Notice of Termination [NOT], and any other requirements) for construction of the project.
National Environmental Policy Act Compliance
DB RFP GLCA 318876 | Page 20 of 61
NPS is in process of securing authorizations for compliance with the National Environmental Policy Act (NEPA); documented through a categorical exclusion (CE) determination. Compliance authorizations are anticipated no later than October 25, 2025. No ground disturbance is permitted prior to NEPA approvals.
NPS compliance staff will continue to monitor the project scope as design progresses and additional details related to the final design part of the Scope of Work being solicited within this RFP are required. The DB contractor will work with NPS and its Compliance contractor to provide required information to update a CE if needed and adjust design based on agency comments and recommendations.
Endangered Species Act(s) Compliance
California Condor
To mitigate potential impacts to the California Condor and other species, implement the following conservation measures:
NPS will provide all project personnel educational information regarding condors. Prior to beginning work on this project all personnel (prime and subcontractors) entering the project have attended training or reviewed NPS provided materials.
If a condor occurs directly within or near (≤150 feet [46 meters]) the construction site, immediately notify the CO/NPS. Construction activities will be suspended until the condor leaves or NPS and FWS permitted personnel employ techniques that result in the individual condor leaving the area.
Project workers and supervisors will avoid interaction with condors and immediately contact CO/NPS if a condor occurs in the project area. Prohibit project personnel from hazing or harassing condors.
Crews will clean up the construction site at the end of each day (e.g., trash removed, scrap materials picked up) to minimize the likelihood of condors visiting the project site.
All dead animals found within 500 feet (152 meters) of the construction site must be immediately disposed in appropriate containment and removed from the site at the end of each working day to minimize the likelihood of condors visiting the project site.
To prevent water contamination and potential poisoning of condors, the Contractor will develop and implement a spill prevention and cleanup plan.
Razorback Sucker To mitigate potential impacts to the Razorback Sucker and other species, implement the following conservation measures:
Turbidity curtains are required as a barrier around underwater construction areas to prevent suckers and other fish from entering the construction area.
Historic Preservation Act(s) Compliance
DB RFP GLCA 318876 | Page 21 of 61
The DB contractor will support all preconstruction compliance activities by providing design details, site plans, means and methods, best management practices, and so forth, and revising these work products based on agency comments and the results of consultation processes. All work associated with this project will meet the parameters set forth in the NPS Service-wide Programmatic Agreement for NHPA Section 106 Compliance.
Incidental Take License
No Incidental Take Licenses at the federal or state level are anticipated to be needed for this project.
Noise Permit or Variance
The DB Contractor will be responsible for obtaining all necessary noise permits or variances.
Aquatic Invasive Species (AIS) Management Compliance:
DB Contractor will take all prudent steps to prevent the introduction of AIS to park waters and prevent the spread of existing AIS to other waters. All equipment must be “Clean, Drained and Dried” or decontaminated prior to participation and upon completion of activities under this contract.
DB Contractor will work with the NPS AIS Coordinator (colleen_allen@nps.gov) and Alex Popores (alexandria_Popores@nps.gov) to create Hazard Analysis and Critical Control Point (HACCP) plans, determining biological risk, species identification, associated with all equipment, inspection/decontamination guidance and requirements, The HACCP plans will be agreed upon and submitted prior to any activity under this contract for all equipment that will be used in or over water in the park.
HACCP planning for control of AIS is described at Hazard Analysis and Critical Control Point Planning to Prevent the Spread of Invasive Species | U.S. Fish & Wildlife Service (fws.gov)
1. HACCP plan will address ALL equipment utilized for all stages of project from mobilization to de-mobilization and transport back to origins. It will identify the risk of new introductions and containment of existing AIS. The plan will outline legal obligations of inspection and decontamination where appropriate.
2. HACCP plan will outline AIS mitigations for legal transport and disposal of the existing dock structure, to include Certificate of Registration (COR) if transporting through or into Utah, or a variance if transporting to Arizona.
DB Contractor is responsible for informing all personnel and sub-contractors of NPS requirements, state laws regarding AIS, and of the presence of high priority AIS in Glen Canyon, including quagga mussels (Dreissena bugensis), New Zealand mud snails (Potamopyrgus antipodarum), and whirling disease in Lake Powell and the Colorado River below the Glen Canyon Dam.
DB Contractor will prevent work activities under this contract for any equipment that has been used in other waters within 30 days but not decontaminated, is not covered by an NPS approved HACCP Plan, or is in any way out of compliance with these permit requirements or state laws and immediately report the incident to the NPS.
DB Contractor will assure compliance with all laws, specifically including state AIS laws and regulations for all equipment used under this contract. Equipment can include vessels, trailers, barges, tow vehicles, DB RFP GLCA 318876 | Page 22 of 61 tools, and other items associated with the contracted activity. State AIS laws vary widely between states;
the DB Contractor should consider all the applicable requirements carefully and plan ahead.
o Determine if Dreissena mussels or larvae are present on any equipment; if mussels are found, equipment must be decontaminated prior to transport or use. Any Dreissena mussels found within the state of Utah must be reported to the Utah Division of Wildlife Resources (1-800-662-3337 or http://wildlife.utah.gov/invasive-mussels.html).
o In Utah, each vessel and launching device must be certified prior to launch that it has been decontaminated; certification options are provided in Utah R657-60-6 https://wildlife.utah.gov/r657-60.html.
o In Arizona, any watercraft or conveyance that has been in Lake Powell or the Colorado River below Glen Canyon Dam for 5 consecutive days or more is required to be decontaminated and complete dry time before launching again (Aquatic Invasive Species - Arizona Game & Fish Department (azgfd.com) o All equipment must be decontaminated and or "Cleaned, Drained, and Dried" after contacting Lake Powell or the Colorado River…