B08-2 QASP PM Support for AFRIMS ENTO IDIQ FINAL.pdf
PDF 660 KB Posted
- Attached to
- Project Management Support for Armed Forces Research Institute of Medical Sciences (AFRIMS) Entomology
- Solicitation number
- W81XWH21R0057
- Issued by
-
Department of the Army Medical Command
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE AND SURVEILLANCE PLAN
For AFRIMS Project Management Entomology Support Services
Contract Number: < upon award, enter contract number>
Contract Description: < enter contract description >
Contractor’s name: < upon award, enter contractor name > (hereafter referred to as the contractor).
Contents
1. PURPOSE
2. GOVERNMENT ROLES AND RESPONSIBILITIES
3. CONTRACTOR REPRESENTATIVES
4. PERFORMANCE REQUIREMENTS SUMMARY MATRIX
5. METHODS OF SURVEILLANCE ................................................ Error! Bookmark not defined.
PERFORMANCE REPORT
CONTRACT DISCREPENCY REPORT (CDR)
1. PURPOSE
This Quality Assurance Surveillance Plan (QASP) provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:
What will be monitored
How monitoring will take place
Who will conduct the monitoring; and
How monitoring efforts and results will be documented.
This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance. In addition, the
QASP should recognize that unforeseen and uncontrollable situations may occur.
This QASP is a “living document” and the Government may review and revise it on a regular basis. However, the
Government shall coordinate changes with the contractor. Updates shall ensure that the QASP remains a valid, useful, and enforceable document. Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.
The following FAR clauses may apply depending on contract type:
52.246-4 Inspection of Services – Fixed-Price
2. GOVERNMENT ROLES AND RESPONSIBILITIES
The following personnel shall oversee and coordinate surveillance activities.
Contracting Officer (KO) - The KO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The KO shall also assure that the contractor receives impartial, fair, and equitable treatment under this contract. The KO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.
Assigned KO: Jennifer Jackson
Organization or Agency: USAMRAA
Telephone: (301) 619-2054
Email: jennifer.c.jackson18.civ@mail.mil
Contract Specialist (CS) - The CS acts as an acquisition consultant and serves as liaison between the contract office and Walter Reed Army Institute of Research (WRAIR).
Assigned CS: Jaclyn Svincek
Organization or Agency: USAMRAA
Telephone: 301-619-2189
Email: Jaclyn.p.svincek.civ@mail.mil
Contracting Officer’s Representative (COR) - The COR is responsible for technical administration of the contract and shall assure proper Government surveillance of the contractor’s performance. The COR shall keep a “QASP and
Performance” file. At the conclusion of the contract or when requested by the KO, the COR shall provide documentation to the KO. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf. The contractor shall refer any changes they deem may affect contract price, terms, or conditions to the KO for action.
Assigned TBD mailto:jennifer.c.jackson18.civ@mail.mil
Other Key Government Personnel -
Title: Technical POC
TBD
3. CONTRACTOR REPRESENTATIVES
The following employees of the contractor serve as the contractor’s Program Manager and Task Manager for this contract. <Communication should occur with them during QASP development. It will help if they review the draft
QASP and accept the final version. You may delete the stated roles or change the naming convention if applicable. >
Program Manager - <upon award, enter name>
Telephone: <enter number>
Email: <enter address>
Task Manager - <upon award, enter name>
Other Contractor Personnel - <upon award, enter name or delete these lines if not applicable>
Title: <enter title>
4. PERFORMANCE REQUIREMENTS SUMMARY MATRIX
PWS
Ref.
Performance
Objective Performance Measurement Acceptable Quality Level
Method of
Surveillance Incentive
1 5.2 Holiday Calendar
Deliverable at the beginning of each task order, submitted complete and on-time
<Exceeds: >95%.
Meets: 94.5 – 90.0%.
Does Not Meet: <89.9%>
Monitored via Remedy and After Action
Reports.
Frequency: within 30 days of task order or scientific project award
Past Performance
2, 6.2.A., 6.2.5a Plans
Deliverable at the beginning of each task order or scientific project award, submitted complete and on-time
<Exceeds: >95%.
Meets: 94.5 – 90.0%.
Does Not Meet: <89.9%>
Monitored via Remedy
Frequency: Weekly
Past Performance
3 6.2.1a Kickoff Meetings
Deliverable at the beginning of each task order, agenda provided at least a week in advance and meeting notes within a week after the meeting
Exceeds - project starts one week early with budget, management, and control plans in place
Meets – Project starts project starts on-time with budget, management, and control plans in place
Does not meet – meeting late or major questions unanswered
Monitored via Remedy
4 6.2.1b Routine calls
Deliverable monthly or quarterly, agenda provided at least a week in advance and meeting notes within a week after the meeting
Exceeds- calls occur routine and facilitate discussion of science, and summary notes provided within 3-4 days of call
Meets- calls occur routinely, summary notes provided within one week of the call
Does not meet - calls not at specified frequency or scheduled so that partners are frequently unable attend, or summary notes not provided
5, 6, 7, 8
6.2.2c, 6.3, 6.2.3a
6.2.4a, 6.2.4c
Reports, monthly Deliverable monthly submitted complete and on-time
Exceeds – within first week of month, minimal edits
Meets – on time, with minimal edits
Does not meet – past due OR major edits
Monitored via Remedy
9 6.2.4d Reports, Quarterly Deliverable quarterly submitted complete and on-time
Exceeds – within first week of month, understandable without
Meets – on time, with minimal
Does not meet – past due OR
Monitored via Remedy
10 6.2.4e Final, data Final deliverable, submitted complete and on-time
Exceeds – provided prior to Q6 if GEIS-funded or within last
30 days of project, minimal edits required, understandable without edits
Meets – on time, with minimal edits for clarity and understanding
Does not meet – past due OR major edits OR data missing
Monitored via Remedy
12 6.3 Quality Control
Plan
Final deliverable, submitted complete and on-time
At a minimum, the QCP must include a self-inspection plan, an internal staffing plan, and an outline of the procedures that the Contractor will use to maintain quality, timeliness, responsiveness, and customer satisfaction.
Monitored via Remedy
13 6.3
Service Contract
Reporting
Application
Final deliverable, submitted complete and on-time
The contractor shall complete and deliver the SCRA
Monitored via Remedy
14 6.3
CPAR
Concurrence/Non-concurrence
The contractor shall provide concurrence or non-concurrence with the CPARS assessment
The contractor shall provide concurrence or non-concurrence with the CPARS assessment
Monitored via Remedy
15, 9.1
9.2
Transition in and out plans
As required for transitions, submitted complete and on-time
Exceeds- Provided at 60 days
(30 day prior to initiation of 30 day transition, covers all major topics and provides best practices
Meets- Provided at 45 days
(30 day prior to initiation of 30 day transition, covers all major topics
Does not meet- Provided at start of 30 days transition, incoming contractor has many questions after transition
Frequency: Weekly.>
17 9.2 Final report to be submitted with Transition-Out
Plan submitted complete and on-time
Exceeds – within first week of month, minimal edits
Meets – on time, with minimal edits
Does not meet – past due OR major edits OR data missing
< Monitored via
Remedy and After
Action Reports.
18 11.2 Trip Reports Submitted within 7 days of travel, submitted complete and on-time
Exceeds- early and no edits
Meets- on-time and minor edits
Does not meet- past due OR
19 14.1.2 OSHA by February 1 of each year
Exceeds – 7 days early
Meets-on time
Does not meet -late
Monitored via Remedy
16.11.1
TARP
This training shall be completed within 60 calendar days after the contract award or after new employees commence performance, and annually thereafter.
Exceeds – 14 days early
Meets-on time
Does not meet -late
Monitored via Remedy
21 16.12 InfoSec
Training shall be complete not later than 30 calendar days after contractor personnel begin performance under this contract and annually thereafter
Exceeds – 7 days early
Meets-on time
Does not meet -late
Monitored via Remedy
22 16.15 HIPAA
Within 30 days after contract award, and then annually thereafter for the remainder of the contract.
Exceeds – 7 days early
Meets-on time
Does not meet -late
< Monitored via
Remedy and After
Action Reports.
23 16.18
Continuous
Cybersecurity
Risk
Management
Provides all security management deliverables on time [applicable for vendors providing systems or devices]
Meets: >99.9
Does Not Meet: <99.9%
Monitored via review of reports by
Government-appointed third party specialist
Frequency: Weekly
Past Performance
24 16.18 Close discovered cybersecurity vulnerabilities
Close all discovered vulnerabilities or submit detailed explanations for inability to do so; provide vulnerability scan and SCAP scan results [applicable for vendors providing systems or devices]
Meets: >99.9
Does Not Meet: <99.9%
Monitored via review of reports and scan results by Government-appointed third party specialist
Frequency: Monthly
25 16.18
Maintain
Government-approved cybersecurity policies, plans, and procedures documentation
Obtain approval from Government on all changes of cybersecurity policies, plans, and procedures [applicable for vendors providing systems or devices]
Meets: >99.9
Does Not Meet: <99.9%
Monitored via review of reports by
Government-appointed third party specialist
Frequency: Annual
26 16.11.2
Installation
Access -
Contractor shall follow installation access procedures.
Sum of all incidents in which contractor personnel did not follow installation access procedures
< 1 incident per month
Direct observation by
COR and installation security.
27 16.11.4 iWATCH
Training -
Contractor shall provide iWATCH training to all personnel within
30 calendar days of contract award.
(Sum of all contractor personnel who have completed iWATCH training within 30 calendar days of contract award) / (total number of contractor personnel supporting the contract)
>90%
Review of Training report from the contractor.
Past Performance
16.11.1
OPSEC SOP –
Contractor shall submit OPSEC
SOP that meets minimum quality standards.
Number of calendar days after contract award that the contractor submits the OPSEC SOP to the COR
< 90 calendar days after contract award
COR receipt of OPSEC
SOP
Past Performance
29 16.11.9
Information
Assurance –
Contractor information assurance workforce personnel are trained in accordance with
DoD and Army policy
Number of calendar days after contract award in which the contractor submits training certifications for all personnel requirement information assurance training
< 30 calendar days COR receipt of all certifications
PERFORMANCE REPORT
Contract Number: <insert number>
Prepared by: (Name of COR) <insert name>
Date and time of observation: <insert date>
Observation:
<Examples of items to include in a report are:
- Method of surveillance.
- How frequently you conducted surveillance.
- Surveillance results (Exceeds, Meets, Does Not Meet).
- Number of observations.>
Prepared by: <Enter COR’s name>
COR’s Signature Date
CONTRACT DEFICIENCY REPORT (CDR)
< The COR may initiate a CDR at any time, including whenever the number of monthly recorded defects for a performance standard exceeds the allowable number of defects; anytime unacceptable performance is determined critical in nature and requires formal corrective action; and whenever an unfavorable trend is detected in contractor performance.>
Contract Number: <insert number>
Contractor Project Manager: <insert name>
From: <insert name of COR>
Date and time observed discrepancy:
Contract Discrepancy:
<Describe in detail. Identify any attachments.>
Corrective action plan:
A written corrective action plan < is / is not > required.
< If a written corrective action plan is required include the following. > The contractor shall provide the COR with the Corrective Action Plan not later than < # days after receipt of this CDR. >
Prepared by: <Enter COR’s name>
COR’s Signature Date
Received by: <Enter contractor project manager’s name>
Contractor Project Manager’s Signature Date