B.08.02 RFP W912GB23R0011 DC-23-0012 Increase POL Capacity Hungary.pdf
PDF 1 MB Posted
- Solicitation number
- W912GB23R0011
- Issued by
-
Department of the Army European Command
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THIS IS A REQUEST FOR PROPOSAL (RFP) PHASE ONE FOR THE DESIGN AND CONSRUCTION FOR EDI POL INCREASE CAPACITY AT
KECSKEMET AIR BASE, HUNGARY.
THE GOVERNMENT CONTEMPLATES THAT THIS SOLICITATION WILL RESULT IN SINGLE FIRM FIXED-PRICE DESIGN-BUILD CONTRACT
AWARD USING A BEST VALUE TRADE-OFF ACQUISITION METHOD.
NON-PRICE PROPOSALS ARE REQUESTED ONLY AT THIS TIME FOR THIS RFP PHASE ONE. DO NOT SUBMIT PRICE PROPOSALS. SEE
SECTION 00 21 00 AND 00 22 00 FOR MORE INFORMATION.
A. The estimated Magnitude of Construction is betw een $15,000,000 and $35,000,000.
B. This RFP is solicited under full and open competition (unrestricted).
C. Aw ard of this contract w ill be made in Euro (EUR).
NOTE: PHASE TWO PRICE PROPOSALS WILL NEED TO BE HELD FOR SIX (6) MONTHS AS THE GOVERNMENT WILL WORK ON
REPROGRAMMING.
LORRAINE Q LAURENTE
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
09-Feb-2023
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______7 calendar days and complete it w ithin ________1225 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________16 Mar 2023 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
CONTRACTING DIVISION
US ARMY CORPS OF ENGINEERS
KONRAD ADENAUER RING 39
D-65187 WIESBADEN GERMANY
WIESBADEN 65187
W912GB
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
10:00 AM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W912GB23R0011 61
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912GB23R0011
Section 00 01 10 - Table of Contents
ATTACHMENTS
ATTACHMENTS (Incorporated herein by reference)
1. Past Performance Information Sheet
2. Past Performance Questionnaire (PPQ)
3. Sample Commitment Letter
4. Bank Letter of Assurance (BLA) Template
5. Bank Letter Guarantee (BLG) Template
6. Base Access List – Kecskemet AB KTR Template
7. Site Visit Meeting Area and Parking Map
8. Statement of Work (A.02.17)
9. Specifications Binder (A.03.09)
10. Appendix A – Drawings
11. Appendix B - Final Geotechnical Report
12. Appendix C – Survey Report
13. Appendix D – Fire Protection System Report
14. Appendix E - Schedule
Section 00 10 00 - Solicitation
PRICE SCHEDULE
Offerors shall provide pricing for all base and option items if requested to move to Phase TWO only. Pricing shall NOT be provided in Phase ONE.
The following items include providing all labor, materials, equipment, and services necessary to complete the construction of the work identified in the attached Plans, Specifications, Statement of Work (SOW), Solicitation. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, and safety requirements. All work shall be performed in accordance with these documents. Refer to Specification Section 01 22 00 Price and Payment Procedures for additional description of the work associated with each of the items.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job POL Increase Capacity
FFP
FOB: Destination
PSC CD: Y1JZ
NET AMT
0002 1 Job OPTION Option 1: POL Increase Tank Capacity
FFP
The Contracting Officer may exercise the option via contract modification issued to the Contractor within 60 calendar days after Contractor receives Notice to Proceed (NTP) for the base line item and be completed concurrently with all other work.
0003 1 Job OPTION Opt 2: Repave Damaged Roads POL Site B
FFP
The Contracting Officer may exercise the option via contract modification issued to the Contractor within 280 calendar days after Contractor receives Notice to Proceed (NTP) for the base line item and be completed concurrently with all other work.
0004 1 Job OPTION Opt 3: Provide Fuel for Commissioning
FFP
The Contracting Officer may exercise the option via contract modification issued to the Contractor at any time during period of performance after Contractor receives Notice to Proceed (NTP) for the base line item and be completed concurrently with all other work.
0005 1 Job OPTION Opt 4: Dispose of Fuel for Commissioning
FFP
The Contracting Officer may exercise the option via contract modification issued to the Contractor at any time during period of performance after Contractor receives Notice to Proceed (NTP) for the base line item and be completed concurrently with all other work.
0006 10 Cubic
Meter
OPTION Opt 5: Dispose of Contaminated Soil
FFP
Opt 5: Dispose of Contaminated Soil - 10 CM. The Contracting Officer may exercise the option via contract modification issued to the Contractor at any time during period of performance after Contractor receives Notice to Proceed (NTP) for the base line item and be completed concurrently with all other work.
0007 10 Cubic
Meter
OPTION Opt 6: Dispose of Contaminated Soil
FFP
Opt 6: Dispose of Contaminated Soil - 10 CM to 100 CM. The Contracting Officer may exercise the option via contract modification issued to the Contractor at any time during period of performance after Contractor receives Notice to Proceed (NTP) for the base line item and be completed concurrently with all other work.
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 1225 dys. ANP 1 U.S. ARMY CORPS OF ENGINEERS, EUROPE
CENAU-CT
KONRAD-ADENAUER RING 39
WIESBADEN 65187
(+49)611-9744-2600
WK4SF6
0002 1225 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0003 1225 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0004 1225 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0005 1225 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0006 1225 dys. ANP 10 (SAME AS PREVIOUS LOCATION)
0007 1225 dys. ANP 10 (SAME AS PREVIOUS LOCATION)
Section 00 21 00 - Instructions
INSTRUCTIONS TO OFFERORS
Section 00 21 00 Instructions to Offerors
A. INTRODUCTION
1. Summary. The US Army Corps of Engineers (USACE) Europe District (NAU) intends to award a single Design-Build construction contract resulting from this solicitation. To assure timely and equitable evaluation of proposals, Offerors must follow the instructions contained herein. Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors. Copies of the solicitation are available by INTERNET ACCESS ONLY. All solicitation documents will made available for viewing under Contracting Opportunities within the SAM website (https://www.sam.gov). All amendments will be made available for viewing within SAM.
It shall be the Offeror’s responsibility to check the website for any amendments. NOTE:
When the word “Offeror” is encountered in the RFP, it is intended to mean a company seeking to do business with the Government that submits a proposal in response to this Solicitation. When the word “Government” is encountered, it is intended to mean USACE NAU. “Request for Proposal,” “RFP” and “Solicitation” are used synonymously throughout.
2. General Description of the Construction Project. Please note the following is a general description of the construction project; it is not the final description: This RFP is for a Design-Build construction contract for construction of the POL Increase Capacity which consist of two cut-and-cover fuel storage tanks. Support facilities include a fuels operations building, site development, utilities and connections, lighting, lightning protection, paving, markings, storm drainage, landscaping, and signage. Facility design will be permanent construction in accordance with DoD Unified Facilities Criteria (UFC) 1-202-01, Host Nation Facilities in Support of Military Operations; Bi-Strategic Commands (Bi-SC) Directive 85-5, NATO Approved Criteria and Standards for Airfields;
USAFE/NATO Airfield Standard Design for Jet Fuel Storage/Dispensing Systems, including Standard Specifications B, E, an M; AC/4-M(96)001, NATO Approved Technical Criteria and Standards for POL Facilities; and UFC 1-200-02, High Performance and Sustainable Building Requirements. This project will comply with DoD antiterrorism (AT) requirements per UFC 4-010-01.
The POL Increase Capacity is located at the Kecskemet Air Base, Hungary, which is northeast of the town of Kecskemet in the county of Bács-Kiskun in central Hungary. The POL Increase Capacity will accommodate two NATO-equivalent Tactical Fighter Aircraft (TFA) and Strategic Transport Aircraft (STA). With limited airspace windows, all aircraft need to be fueled and ready for takeoff at the commencement of their respective flying schedules. The jet fuel storage facility will support the simultaneous refueling of TFA and STA. This facility will increase the frequency of sortie generation, directly improving airfield operations for greater responsiveness during bilateral and multilateral exercises and training with allies and partners. This project will boost airfield presence and improve airfield capability and readiness response to support Operation Atlantic Resolve.
3. Two-Phase Design-Build Selection Procedures. For the purposes of this
Solicitation, the Government will utilize the Two-Phase Design-Build Selection Procedures in accordance with FAR 36.303.
(i) In Phase ONE of the TWO phase design-build selection procedures, interested firms or joint venture entities (collectively referred to in the Solicitation as “Offerors”) submit certain specified performance capability proposals, demonstrating their capability to successfully execute the design-build construction contract resulting from this solicitation. The Government will evaluate the performance capability proposals in accordance with the criteria described herein and select the most highly qualified Phase ONE Offerors to compete for the design-build contract in Phase TWO.
The most highly qualified Offerors selected to participate in Phase TWO will be notified by the Contracting Officer. The Government intends to select a target of five Offerors from Phase ONE to compete in Phase TWO, however the Government may elect to allow more than five if determined to be necessary and if in the best interest of the Government by the Contracting Officer and if approved in accordance with agency procedures. Additionally, the Contracting Officer may select fewer than five offerors to advance to phase two, or none at all. The Contracting Officer reserves the right to reject any and all offers.
(ii) In Phase TWO, the Offerors selected to participate will submit proposals in accordance with Section 00 22 00. Phase TWO utilize the Tradeoff Source Selection Process (see FAR 15.101-1). This process allows for a tradeoff between non-cost factors and cost/price and allows the Government to accept other than the lowest priced proposal or other than the highest technically rated proposal to achieve a best-value contract award. It is the intent of the Government to award off initial offers without discussions. Proposal revisions may not be possible and the best proposal should be submitted initially.
(iii) The evaluation methodology consists of five factors. See Section 00 22 00 for further details on the Government’s evaluation approach.
Phase ONE Factor 1: Past Performance Factor 2: Management Approach
Phase TWO
Factor 3: Technical Approach Factor 4: Design Approach Factor 5: Price
B. PRE-PROPOSAL CONFERENCE
1. Summary. The Government intends to hold a pre-proposal conference with site visit for Phase ONE.
2. Phase ONE pre-proposal conference details:
(i) Purpose: The purpose of the Phase ONE pre-proposal conference is two-fold. First, the US Government will present a summary of the project SOW and proposal instructions/evaluation approach. Secondly, Offerors will be given the opportunity to walk through one of the buildings so they can visually assess the site conditions. NOTE: The Government may host a virtual pre-proposal conference to further discuss the proposal instructions and evaluation approach. Further details are to be announced.
(ii) Location:
Offerors should meet at the Marriott Budapest hotel located Apaczai Csere Janos u. 4 1052 Budapest, Hungary for the pre-proposal conference. The pre-proposal site visit will take place on the following day and the offerors should meet at the front gate of Kecskemet Air Base, Hungary (GPS coordinates 46.9086°N 19.7528°E).
(iii) Individuals must submit a base access request through USACE for processing at least 14 days in advance. See further instructions below. In either case, all attendees should arrive 30 minutes early and come prepared with a passport for identification. No opportunity for Base access request the day of. After entering the base, the base personnel will escort the participants into a bus which will drive us to the POL site.
(iv) Time/Date:
- Preproposal conference Budapest Marriott: 01MAR2023 from 0830 to 1230 local time
- Site visit Kecskemet Air Base: 02MAR2030 starting 0930 local time. Offerors will meet at the gate no later than 0900 AM. The entire visit should last no longer than three to four hours. Please reference site visit map (solicitation attachment) for location information.
(v) Registration Instructions: Offerors must pre-register their attendees no later than at 1000 Central European Time. To Pre-Register, complete the site visit attendee information sheet (solicitation attachment 6) submit via email to USACE Project Manager, Richard Leroy at richard.p.leroy@usace.army.mil and Contract Specialist, Lorraine Laurente at lorraine.q.laurente@usace.army.mil. IMPORTANT:
Any individuals planning to attend must register in advance with their full name, organization name, job title, or they may not be permitted access to the sites— please use the attendee information sheet attached to the RFP. Individuals that complete and submit the access roster information timely may show up at the gate on the day of the visit, show their passport/ausweis, and tell the guard they are on an access roster. Individuals that do NOT complete the access roster information timely cannot participate at the site visit.
(vi) Space Limitations. Space may be limited at the pre-proposal site visit, and as a result the number of attendees per company may be limited. Offerors are advised to register no more than four individuals, and space may be limited to less than that.
Phase TWO Offerors will be given another, more thorough opportunity to walk through the buildings at a later date.
(vii) Project Questions. All project questions should be submitted via ProjNet (see instructions below). Any answers given at the site visit are strictly unofficial.
C. PROPOSAL SUBMISSION
1. To assure timely and equitable evaluation of proposals, Offerors must follow the instructions contained herein. Offerors are required to meet all Solicitation requirements, including terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors. The Offeror shall submit in the proposal all requested information specified in this section of the Request for Proposal (RFP) at or before the exact time specified. Failure to meet a requirement may result in an Offeror being ineligible for award. Copies of the RFP are available by INTERNET ACCESS ONLY. All RFP documents will be made available for viewing at the SAM website (http://www.sam.gov). All amendments will be made available for viewing in SAM. It shall be the Offeror’s responsibility to check the website for any amendments.
2. Inquiries. Offerors with technical inquiries and any other questions shall submit their inquiries via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet. The project number is: W912GB23R0011. The bidder inquiry key is: ZRF7C3-52BAY5.
Offerors are requested to review the plans and specifications in their entirety and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
The Government reserves the right to decline addressing certain questions. Further, no questions, unless in the Government’s interest, will be answered any later than 10 business days prior to the stated deadline for offers. All Offerors are encouraged to register on ProjNet for alerts to stay abreast of Q&A’s that are posted in reference to this Solicitation. Only self-registered users on ProjNet can submit and review inquiries.
To self-register, go to the webpage, click BID tab, select Bidder Inquiry, select agency USACE, enter the key for this Solicitation listed above, and your email address. After initial login, enter all the required information to create your user ID. Verify the information on the next screen and from there you may submit and view inquiries.
Those submitting inquiries will receive a system generated email notification when their inquiry has been processed and answered. It is the Offeror’s responsibility to monitor for inquiries and responses.
3. General Proposal Submission Requirements.
a. Electronic Proposals. In an effort to reduce paperwork and costs, ALL
RESPONSES TO THIS ANNOUNCEMENT SHALL BE SUBMITTED
ELECTRONICALLY. Hand carried delivery or USPS/UPS/Fedex delivery of hard copies and/or CD-ROMs are not authorized. Facsimile submission is not authorized. Electronic submissions shall be via email to both the Contract Specialist, Lorraine Laurente, at lorraine.q.laurente@usace.army.mil and the Contracting Officer, Christopher Brackett, at christopher.brackett@usace.army.mil. It is the responsibility of the Offeror to ensure receipt.
b. File Size Limitations. Offerors are advised that the file size limitation is
10MB due to email server restrictions. If needed, Offerors are advised to break the files down into smaller sections and deliver in separate emails. In such cases, please divide the sections as logically as possible and be sure to clearly name the files as specified below.
c. File Names. To ensure your submission is received and processed appropriately, it is important that interested parties CAREFULLY ensure their electronic files adhere to the following naming convention. Each filename shall begin with the Solicitation Number, followed by the word “RESPONSE,” followed by your firm’s name, and finally a brief file description. EXAMPLES:
(1) “W912GB23R0011 RESPONSE Firmname Volume I.pdf”
(2) “W912GB23R0011 RESPONSE Firmname Volume I Part 1.pdf”
(3) “W912GB23R0011 RESPONSE Firmname Volume I Part 2.pdf”
(4) “W912GB23R0011 RESPONSE Firmname Volume I diagrams, figures.pdf”
(5) “W912GB23R0011 RESPONSE Firmname Volume II.pdf”
d. File Organization, Formatting, and Other Instructions. Although hard copies are not accepted, each file shall be clearly indexed, and logically assembled. Font size shall be 10 point or larger and font text shall be legible. Pages shall be letter or A4 sized--larger page sizes (such as 11x17 foldouts, etc.) will be counted as two pages. Offerors shall prepare proposals in the English language. Proposals shall be in a narrative format, organized and titled so that each section of the proposal follows the order and format of the factors. Information presented should be organized so as to pertain to only the evaluation factor in the section that the information is presented. Proposals shall completely and adequately address the requirements of this Solicitation. Offerors are reminded that elaborate corporate marketing information, formatting, special reproduction techniques, etc., are not necessary. Failing to submit attachments or failing to complete the proposal properly may result in rejection of the offer without further evaluation. Information pertaining to more than one evaluation factor should be repeated in each section for each factor. Electronic files shall be Microsoft Windows compatible. Files shall be submitted in their native format (i.e., doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text. If the electronic files are of a size at which they must be compressed (zipped), they shall be compressed into one zipped folder.
e. Upload Completion & Deadline. Interested parties shall submit responses no later than the date specified on the solicitation document. The time and date of proposal receipt will be the delivery time and date recorded of email receipt on the Government’s server. Do not assume that electronic submission will occur instantaneously. Offerors should time their submission with prudence by not waiting until the last day—this will allow for unexpected delays in the transmittal process and troubleshooting. Offerors are encouraged to keep a copy of the delivery and/or read confirmation for their record but should also request confirmation. It is the responsibility of the Offeror to ensure receipt. Be advised that proposals received after the submission deadline will be considered late and as such will be processed in accordance with FAR 15.208.
f. Proprietary Information. Any information, presented in a proposal that the
Offeror wants safeguarded from disclosure to other parties must be identified and labeled in accordance with the requirements of Provision “FAR 52.215-1, Instructions to OfferorsCompetitive Acquisition (Jan 2004),” subparagraph (e). The Government will endeavor to honor the restrictions against release requested by Offerors, to the extent permitted under United States law and regulations.
g. SAM Registration: SAM Registration: In order to do business with the US
Government as a contractor, a company must be registered with the System for Award Management (SAM, www.sam.gov). In order to register on SAM, a company must obtain a NCAGE code and a UEI number. You can apply for an NCAGE code and a UEI number simultaneously, but both must be obtained in order to register on SAM. Specific instructions how to obtain a NCAGE code and a SAM Registration are as follows:
(i) NCAGE Code. An NCAGE code is a five-character ID number used by the US Government to identify international companies. All non- US firms must obtain an NCAGE code. How does your company obtain an NCAGE Code? If you are a vendor located outside the United States, one can be obtained at no cost by visiting https://eportal.nspa.nato.int/AC135Public/CageTool/home. Further information about NCAGE codes is available at:
https://eportal.nspa.nato.int/AC135Public/Docs/US%20Instructions% 20for%20NSPA%20NCAGE.pdf. Generally it takes approximately 24-48 hours to obtain an NCAGE code.
(ii) SAM Registration. The System for Award Management (SAM) is a registration database required for all US Federal Government Contracts and where you will find contract opportunities all over the world. You can register on SAM at:
https://www.sam.gov/SAM/pages/public/loginFAQ.jsf. For help with SAM registration, see the SAM Quick Start guide at:
https://www.sam.gov/SAM/transcript/Quick_Guide_for_International _Entity_Registration.pdf. For additional help at no cost, contact the Federal Service Desk at www.fsd.gov or by telephone at +1-866- 606-8220 (toll free) or +1-334-206-7828 (internationally). Generally it takes approximately two weeks to for SAM to activate a registration, from the date it receives a completed registration. Please take notice that SAM has an entity registration requirement that firms submit an "original, signed notarized letter before the registration will be activated." Instructions for international entities (not located in the U.S. or its outlying areas) can be found at:
https://www.fsd.gov/fsd-gov/answer.do?sysparm_kbid=dbf8053adb119344d71272131f9619 46&sysparm_search=KB0013221.
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.215-1 Instructions to Offerors--Competitive Acquisition NOV 2021 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014
CLAUSES INCORPORATED BY FULL TEXT
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm Fixed Price construction contract resulting from this solicitation.
(End of provision)
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.
The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be ten percent (10%) of the bid price.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
US ARMY CORPS OF ENGINEERS
CONTRACTING DIVISION (CENAU-CT)
KONRAD ADENAUER RING 39
65187 WIESBADEN GERMANY
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits may be arranged during normal duty hours by contacting:
See Section 00 21 00 for pre-proposal conference and site visit information.
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/dfars https://www.acquisition.gov/afars
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
Section 00 22 00 - Supplementary Instructions
PHASE 1 OF 2 DB PROCEDURES
Section 00 22 00 Phase ONE of TWO – Design-Build Selection Procedures
A. PHASE ONE SPECIFIC PROPOSAL INSTRUCTIONS
1. Summary. The Government Source Selection Team (SST) will evaluate proposals according to the factors listed below. Offerors are required to provide data addressing all stated factors in a clear and understandable format. Proposals that do not clearly address all factors may be considered unacceptable and may not receive further consideration. The following Factors will be evaluated in Phase ONE:
Factor 1: Past Performance Factor 2: Management Approach
2. Specific Submission Requirements, Phase ONE, Volume I, Non-Price Proposal:
Volume I should include a section for each Non-Price factor. Volume I should be organized as follows:
(i) Factor 1, Past Performance. Offerors shall provide a completed performance record for up to five construction projects that have been completed by the Offeror (or substantially completed) within the last six (6) years (from the RFP issue date) that are similar to this project in size, scope, and complexity. Substantially completed is defined as “the Contractor has completed the work and related contract obligations in accordance with the contract documents, such that the Government may enjoy the intended access, occupancy, possession, and use of the entire work without impairment due to incomplete or deficient work, and without interference from the Contractor's completion of remaining work or correction of deficiencies in completed work.” Projects submitted that were completed beyond six years will be evaluated, but may be considered less relevant.
Offerors may also provide a completed performance record for up to five design projects that have been completed by the Offeror (or the Offeror’s separate designer if applicable and the Offeror has selected a design firm to partner with). The Government will evaluate a maximum of ten projects (with at least two construction projects and two design projects).
Offerors shall complete the Past Performance Information sheet, which is provided by RFP attachment 1. The experience Information sheet is limited to three pages per project, minimum 10 point size font. Offerors must specifically cite the work they were responsible for under each project (i.e., if the Offeror was a JV on a prior project but not submitting as a JV for this project or if it utilized subcontractors to perform work on prior projects, the Offeror must provide a description of only the work that the Offeror performed). Separate contracts (or IDIQ task orders) may not be combined in order for the project to be considered similar. Additionally, Offerors are cautioned to provide enough detail for an assessment to be made by the evaluators.
If available, a completed record from the Contractor’s Performance Assessment Reporting System (CPARS) will be accepted for evaluation under this factor. An interim completed CPARS rating will be considered if a final record is not available.
If a completed CPARS record is not available at all, Offerors shall complete and provide a Past Performance Questionnaire (PPQ). A blank PPQ form is provided as a solicitation attachment 2. Offerors shall provide a copy of any Cure Notices or Show Cause Letters received by the offeror for each submitted project and a description of any corrective action implemented by the offeror. The offerors shall indicate if any of the contracts listed were terminated and the type and reasons for the termination.
PPQ Instructions: If a CPARS record is unavailable, the Offeror shall complete Blocks 1-4 of the provided PPQ and have the Contracting Activity and the Technical Representative responsible for the past/current contract complete the remainder of the PPQ. Offeror shall ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQs shall be submitted with the proposal, and shall not exceed four (4) pages each. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact via email no later than the closing date of this solicitation. If an offeror has no relevant past performance history, the offeror must affirmatively state that it possesses no relevant directly related or similar past performance. Offerors are encouraged to request narratives to support PPQ ratings.
(ii) Factor 2, Management Approach. The Offeror shall provide a plan that describes the Offeror’s Management Approach to executing the project. The Management Approach shall not exceed twenty pages. If more than twenty pages are submitted, only the first twenty pages will be reviewed and evaluated. Only the title page, organization chart, and table of contents will not be counted toward the page count. The Offeror shall provide a Management Approach, which shall include at a minimum, the following:
(a) A graphical description (organizational chart) and narrative of its planned organization structure for successful execution of the contract. This should include a description of the Offeror’s overall structure and management of the project team from the Offeror’s Headquarters to the Offeror’s site office(s). The chart and narrative must:
identify all offices involved in this contract identify all positions by title, organization, and physical location, including subcontractors and consultants include lines of reporting and technical areas of responsibility under the contract clearly show the lines of authority of the Offeror’s Project Manager, Quality Control and Safety Organization, including all JV Partners and subcontractors, when applicable
(b) A narrative discussion of how the Offeror will ensure quality consistently across the team and discuss quality control lines of authority between subcontractors and prime.
(c) A narrative discussion of how the Offeror will ensure safety consistently across the team and discuss safety lines of authority between subcontractors and prime.
(d) A narrative discussion of the Offeror’s plan to obtain, retain, coordinate, and manage subcontractors. Include any established relationships with organizations qualified for work within the scope of this RFP, including number of projects that have been completed together and/or number of years of partnering.
Identify the significant aspects of the work that are to be self-performed and those that will be subcontracted. Identify the nature and overall percent of work that will be performed by the Offeror and all key sub-contractors. Offerors are reminded of the requirements of 52.236-1, Performance of Work by the Contractor.
(e) A narrative discussion of the Offeror’s criteria for selection of the
Designer(s) of Record for types of work to be accomplished under this contract.
(f) A narrative discussion of the Offeror’s knowledge of engineering and design in Hungary to include coordination with Hungarian authorities (to include any certification or registration requirements) and the ability to communicate in Hungarian and English.
(g) A narrative discussion of any additional and/or unique management advantages contracting with their firm provides to the Government, if applicable.
2. Specific Submission Requirements, Phase ONE, Volume II – Administrative
Matters. Volume II should be organized as follows
(a) Cover Letter. Offerors shall submit a cover letter in accordance with FAR 52.215-1(c)(2), including:
(1) The Solicitation number.
(2) The Offeror’s name, address, and phone/email contact information.
(3) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the Solicitation and agreement to furnish any or all items upon which prices are offered.
(4) Names, titles, and telephone / email contact information of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this Solicitation.
(5) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority.
(b) Completed Solicitation Form (and amendments). Offerors shall submit a completed Standard Form (SF) 1442 included in this Solicitation. If applicable, Offerors may also submit a completed SF 30 for each Solicitation amendment, acknowledging all the amendments or use the SF1442 Block 19.
(c) SAM Registration, Representations & Certifications. Offerors shall submit the following:
(1) A completed clause FAR 52.204-8(d).
(2) A copy of their current “Entity Registration” in the System for
Award Management (SAM) as recorded at www.sam.gov, showing the following sections: “core data, “assertions”, and “POCs”.
(3) A copy of their current “FAR & DFARS Report” that demonstrates all their completed representations and certifications as recorded at www.sam.gov.
(d) JV agreements. If the Offeror is a joint venture (JV), it must provide evidence of a legally binding JV agreement, which creates legal responsibility on the part of all members of the JV. A searchable copy of the JV Agreement in English and signed by all JV members shall be provided as part of the proposal in Factor 1 Past Performance. The JV Agreement shall include the following:
(1) A detailed statement outlining the following in terms of percentages, where appropriate:
i. The relationship of the JV parties in terms of business ownership, capital contribution, and profit distribution or loss sharing.
ii. The management approach of the JV in terms of who will conduct, direct, supervise and control the project and have custody and control of the assets of the JV and perform the duties necessary to complete the work.
iii. The structure of the JV and decision-ranking responsibilities of the JV parties in terms of who will control the manner and method of performance of the work.
iv. Identification of the key personnel having authority to legally bind the JV to subcontracts and state who will provide or contract for the labor and materials for the JV.
v. Identification of party maintaining the JV bank accounts for the payment of all expenses and the deposits of all receipts, keep the books and records, and pay applicable taxes for the JV.
vi. Identification of party furnishing the facilities, such as office supplies and telephone service.
vii. Identification of party having overall control of the JV.
viii. A statement that the JV partners are jointly and severally liable under the contract.
(2) Other sections of the proposal shall identify, where appropriate, whether key personnel are either employees of the individual JV parties and identify the party, or hired as employees of the JV.
(3) If one of the JV parties possesses relevant experience and/or past performance, the experience and/or past performance of that firm will be considered as the experience and/or past performance of the JV. Each member of the JV may submit project examples for Factor 1, but the total submitted by the individual JV members shall not exceed three such examples. In addition to the JV Agreement, the Factor 1 proposal of a JV Offeror shall clearly address the experience of each of the JV members and the division of the members' responsibilities/duties on any ongoing or previous projects. The proposal shall also include the DUNS numbers of each JV partner.
(e) Team arrangements. As described in FAR Subpart 9.6, it is the
Government’s policy to recognize the integrity and validity of contractor team arrangements. The Offeror may be credited with the experience, expertise and/or past performance of a JV member, a team member, a subcontractor, or an affiliate (collectively referred to in this RFP as “Team Members”) if that experience/past performance relates to the services described for that party in the team arrangement agreement or the letter of commitment. Consistent with FAR 9.104-4 the Government also may consider the responsibility of such entities or persons when it may adversely affect the prospective prime contractor’s responsibility or when it is in the Government’s interest to do so. Offerors are reminded that regardless of any teaming arrangements, the prime contractor will be fully responsible for contract performance. Also, in the event that the Offeror is awarded the resultant contract, there can be no substitution of any proposed team member, subcontractor, or key personnel identified in a teaming agreement or letter of commitment without prior written approval of the Contracting Officer. Approval or disapproval of a substitute entity or person is a matter within the sole discretion of the contracting officer, who will consider factors such as whether the proposed substitute appears to be equally qualified and whether the substitution is the best interests of the Government and project execution. In approving a substitution, the contracting officer may impose such conditions on the substitution as he/she deems appropriate in the exercise of his/her sole discretion. Teaming agreements and sub-contractor commitment letters are not required, but when they are not provided with the proposal, the experience and/or past performance of any affiliate, team members or subcontractors will not be considered for purposes of source selection evaluation:
(1) Teaming Agreements. For a teaming agreement to be recognized for purposes of source selection evaluation and the application of non-price factors, the proposal must include a searchable teaming agreement in English that reflects a binding commitment from all parties and that has been signed by all team members. The Teaming Agreement must have full disclosure of the teaming arrangement and include a narrative that explains the major or critical aspects of the work to be performed by each team member (to include identification of team members, a full delineation of roles and responsibilities of team members, and the duration of the agreement). Each non-Offeror member of a team may submit project examples for Factor 1, but the total submitted by such team members shall not exceed three (3) such examples. Furthermore, past performance of such team members will be considered only to the extent it is similar to what they will perform on this Contract.
(2) Key Subcontractor Commitment Letters. For a prime-subcontractor arrangement to be recognized for purposes of source selection evaluation and the application of non-price factors, the proposal must have a commitment letter signed by both the prime and the subcontractor that includes all of the substantive portions of the sample provided in the RFP Attachment. The proposal must also reflect that the Offeror as the prime contractor is vested with control and responsibility for the daily management of the work, and that it remains responsible for contract performance, including those items allocated to a subcontractor. Furthermore, past performance of committed subcontractors will be considered only to the extent it is similar to what the subcontractor commits to perform on this Contract.
(3) Affiliates. The term “affiliate” is defined in FAR 2.101. For an affiliate’s past experience/past performance to be recognized for purposes of source selection evaluation and the application of non-price factors, the proposal must demonstrate a firm commitment that the affiliate will participate meaningfully (e.g., roles, responsibilities, etc.) in the performance of the contract resulting from this solicitation.
This commitment, the nature of each entity’s relationship and meaningful participation on this Contract shall be described in a document signed by authorized representatives of both the Offeror and its affiliate. The requirements of in sub-paragraph 1 above for teaming agreements shall also apply to such affiliate agreements.
B. PHASE ONE EVALUATION APPROACH
1. General. The Source Selection Team (SST) will evaluate the non-price proposals in order to determine the most highly qualified Offerors from Phase ONE.
Offerors are cautioned to put forth their best efforts for the Phase ONE submission, and to furnish all information clearly to allow the Government to determine their performance capability. Offerors should not assume that they will have an opportunity to clarify or correct anything in their proposal after submitting it in response to Phase ONE.
However, the Government reserves the right to allow proposal corrections, if deemed necessary to determine the most highly qualified Offerors to shortlist for Phase TWO.
The Contracting Officer, independently exercising prudent business judgment, will select the most highly qualified Offerors and request that only those Offerors submit phase TWO proposals.
Selecting only the most highly rated offerors to advance to phase two is not equivalent to establishing a competitive range pursuant to FAR Part 15. Under FAR Part 36 procedures, the evaluation of phase one proposals does not permit the consideration of cost or price as an evaluation factor. Rather, the contracting officer selects the most highly qualified offerors--based only on non-price factors--to submit phase two proposals. Consistent with these procedures, price proposals are submitted by offerors and evaluated by the agency at phase two. Only phase two of a design-build procurement is conducted in accordance with FAR part 15, including the evaluation of technical and price proposals. In other words, the selection of a limited number of offerors from phase one of a FAR subpart 36.3 competition to continue to phase two does not constitute, and is not equivalent to, the establishment of a competitive range.
2. Relative Importance of Evaluation Factors. Of the non-price factors (Factors 1-
2), Factor 1 - Past Performance is approximately equal to Factor 2 - Management Approach.
3. Definitions. The following definitions are provided to assist evaluators in the evaluation process:
a.…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .