B.08.02 Appendix A - Schedule of Items and Prices 7 JAN 2021.xlsx
XLSX spreadsheet 30 KB Posted
- Attached to
- RMMR Services for USAF Fuel Facilities Supported by DLA-Energy at Incirlik Air Base, Turkey
- Solicitation number
- W912GB21R0004
- Issued by
-
Department of the Army European Command
About this file
This document contains a price schedule and labor rates worksheet for a solicitation seeking recurring maintenance and minor repair services for U.S. Air Force fuel facilities supported by the Defense Logistics Agency - Energy at Incirlik Air Base in Turkey. The solicitation seeks fixed prices for tasks including contractor plans, reports, unscheduled repair service orders with estimated ceilings of $1 million for the base year and increasing amounts for subsequent option years, and annual fuel site assessments. The labor rates worksheet requires offerors to provide fully burdened hourly rates for positions such as program managers, engineers, technicians, and environmental scientists for the base year and escalating rates for four option years. Offerors must also propose an annual escalation percentage to be applied to the option year labor rates. The selection will be made in U.S. dollars.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B.08.03 W912GB21R0004 Amend 0001.pdf | ||
| B.08.02 RFP W912GB21R0004_Conformed thru Amend 0001.pdf | ||
| B.08.02 PWS Attachment F - SO SSJ Form.pdf | ||
| B.08.02 RFP W912GB21R0004.pdf | ||
| B.08.02 PWS Attachment E - Sample SO Submission Form.xlsx | XLSX spreadsheet | |
| B.08.02 PWS Attachment B - Bulk Fuel Facilities.xlsx | XLSX spreadsheet | |
| B.08.02 Appendix D - PPQ.pdf | ||
| B.08.02 PWS Attachment D- Sample SO Request Form.docx | DOCX document | |
| B.08.02 PWS Attachment A - Operational Fuel Facilities.xlsx | XLSX spreadsheet | |
| B.08.02 Appendix C - Past Performance Information Sheet.pdf | ||
| B.08.02 Appendix B - Letter of Commitment Sample.docx | DOCX document | |
| B.08.02 PWS Attachment C - Incirlik AB EBS List 07-MAY-2020.xlsx | XLSX spreadsheet |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WS A-Price Schedule
| SCHEDULE OF ITEMS AND PRICES |
| WORKSHEET A: CONTRACT PRICE SCHEDULE |
| DLA-E Turkey RMMR |
| Offeror Name |
| Date |
| Proposed CLIN | Description of Services (Base Year) | Service Order Fixed Fee | Price |
| CLIN 0001 | Task 1 - Contractor Plans | $ - 0 | |
| CLIN 0002 | Task 2 - Contractor Reports | $ - 0 | |
| CLIN 0003 | Task 3 - Unscheduled Minor Repair Service Orders * | $ 1,000,000.00 | |
| Task 3 - Service Order Fixed Fee** | FIXED FEE TOTAL | $ - 0 | |
| CLIN 0004 | Task 4 - Annual Fuels Site Assessment | $ - 0 | |
| CLIN 0005 | Task 5 - Unscheduled Minor Repair Service Orders for Mobile Pantographs and Equipment * | $ 4,500.00 | |
| Task 5 - Service Order Fixed Fee** | FIXED FEE TOTAL | $ - 0 | |
| CLIN 0006 | Task 6 - Installation Access | NOT SEPARATELY PRICED | |
| Base Year Total: | $ - 0 |
| Proposed CLIN | Description of Services (Option Year 1) | Service Order Fixed Fee | Price |
| CLIN 1001 | Task 1 - Contractor Plans | $ - 0 | |
| CLIN 1002 | Task 2 - Contractor Reports | $ - 0 | |
| CLIN 1003 | Task 3 - Unscheduled Minor Repair Service Orders * | $ 500,000.00 | |
| Task 3 - Service Order Fixed Fee** | FIXED FEE TOTAL | $ - 0 | |
| CLIN 1004 | Task 4 - Annual Fuels Site Assessment | $ - 0 | |
| Option Year 1 Total: | $ - 0 |
| Proposed CLIN | Description of Services (Option Year 2) | Service Order Fixed Fee | Price |
| CLIN 2001 | Task 1 - Contractor Plans | $ - 0 | |
| CLIN 2002 | Task 2 - Contractor Reports | $ - 0 | |
| CLIN 2003 | Task 3 - Unscheduled Minor Repair Service Orders * | $ 510,000.00 | |
| Task 3 - Service Order Fixed Fee** | FIXED FEE TOTAL | $ - 0 | |
| CLIN 2004 | Task 4 - Annual Fuels Site Assessment | $ - 0 | |
| Option Year 2 Total: | $ - 0 |
| Proposed CLIN | Description of Services (Option Year 3) | Service Order Fixed Fee | Price |
| CLIN 3001 | Task 1 - Contractor Plans | $ - 0 | |
| CLIN 3002 | Task 2 - Contractor Reports | $ - 0 | |
| CLIN 3003 | Task 3 - Unscheduled Minor Repair Service Orders * | $ 520,200.00 | |
| Task 3 - Service Order Fixed Fee** | FIXED FEE TOTAL | $ - 0 | |
| CLIN 3004 | Task 4 - Annual Fuels Site Assessment | $ - 0 | |
| Option Year 3 Total: | $ - 0 |
| Proposed CLIN | Description of Services (Option Year 4) | Service Order Fixed Fee | Price |
| CLIN 4001 | Task 1 - Contractor Plans | $ - 0 | |
| CLIN 4002 | Task 2 - Contractor Reports | $ - 0 | |
| CLIN 4003 | Task 3 - Unscheduled Minor Repair Service Orders * | $ 530,604.00 | |
| Task 3 - Service Order Fixed Fee** | FIXED FEE TOTAL | $ - 0 | |
| CLIN 4004 | Task 4 - Annual Fuels Site Assessment | $ - 0 | |
| Option Year 4 Total: | $ - 0 |
Contract Total: $ - 0
| * Estimated ceiling for Unscheduled Minor Repair Service Orders. |
| ** Enter proposed Fixed Fee. |
AWARD WILL BE MADE IN UNITED STATES DOLLARS
WS B-Labor Rates
SCHEDULE OF ITEMS AND PRICES
| WORKSHEET B - Labor Rates for Unscheduled Minor Repair Service Orders |
| DLA-E Turkey RMMR |
| Offeror Name |
| Date |
| COLUMN A | |||||||||
| Base Year* Burdened Rate** | Option Year 1 Burdened Rate* | Option Year 2 Burdened Rate* | Option Year 3 Burdened Rate* | Option Year 4 Burdened Rate* | |||||
| Prime Direct Labor | Prime Direct Labor | Prime Direct Labor | Prime Direct Labor | Prime Direct Labor | |||||
| Loaded rate includes the following indirects (i.e., Overhead, G&A, benefits, etc.): | Loaded rate includes the following indirects (i.e., Overhead, G&A, benefits, etc.): | Loaded rate includes the following indirects (i.e., Overhead, G&A, benefits, etc.): | Loaded rate includes the following indirects (i.e., Overhead, G&A, benefits, etc.): | Loaded rate includes the following indirects (i.e., Overhead, G&A, benefits, etc.): | |||||
| Program Manager | $ - 0 | Program Manager | $ - 0 | Program Manager | $ - 0 | Program Manager | $ - 0 | Program Manager | $ - 0 |
| Project Manager | $ - 0 | Project Manager | $ - 0 | Project Manager | $ - 0 | Project Manager | $ - 0 | Project Manager | $ - 0 |
| Team Leader | $ - 0 | Team Leader | $ - 0 | Team Leader | $ - 0 | Team Leader | $ - 0 | Team Leader | $ - 0 |
| Site Supervisor/Superindendent | $ - 0 | Site Supervisor/Superindendent | $ - 0 | Site Supervisor/Superindendent | $ - 0 | Site Supervisor/Superindendent | $ - 0 | Site Supervisor/Superindendent | $ - 0 |
| Petroleum Maintenance Technician (Senior) | $ - 0 | Petroleum Maintenance Technician (Senior) | $ - 0 | Petroleum Maintenance Technician (Senior) | $ - 0 | Petroleum Maintenance Technician (Senior) | $ - 0 | Petroleum Maintenance Technician (Senior) | $ - 0 |
| Petroleum Maintenance Technician (Mid-Level) | $ - 0 | Petroleum Maintenance Technician (Mid-Level) | $ - 0 | Petroleum Maintenance Technician (Mid-Level) | $ - 0 | Petroleum Maintenance Technician (Mid-Level) | $ - 0 | Petroleum Maintenance Technician (Mid-Level) | $ - 0 |
| Petroleum Maintenance Technician (Junior) | $ - 0 | Petroleum Maintenance Technician (Junior) | $ - 0 | Petroleum Maintenance Technician (Junior) | $ - 0 | Petroleum Maintenance Technician (Junior) | $ - 0 | Petroleum Maintenance Technician (Junior) | $ - 0 |
| Engineer (Senior) | $ - 0 | Engineer (Senior) | $ - 0 | Engineer (Senior) | $ - 0 | Engineer (Senior) | $ - 0 | Engineer (Senior) | $ - 0 |
| Engineer (Mid-Level) | $ - 0 | Engineer (Mid-Level) | $ - 0 | Engineer (Mid-Level) | $ - 0 | Engineer (Mid-Level) | $ - 0 | Engineer (Mid-Level) | $ - 0 |
| Engineer (Junior) | $ - 0 | Engineer (Junior) | $ - 0 | Engineer (Junior) | $ - 0 | Engineer (Junior) | $ - 0 | Engineer (Junior) | $ - 0 |
| Environmental Scientist (Senior) | $ - 0 | Environmental Scientist (Senior) | $ - 0 | Environmental Scientist (Senior) | $ - 0 | Environmental Scientist (Senior) | $ - 0 | Environmental Scientist (Senior) | $ - 0 |
| Environmental Scientist (Mid-Level) | $ - 0 | Environmental Scientist (Mid-Level) | $ - 0 | Environmental Scientist (Mid-Level) | $ - 0 | Environmental Scientist (Mid-Level) | $ - 0 | Environmental Scientist (Mid-Level) | $ - 0 |
| Environmental Scientist (Junior) | $ - 0 | Environmental Scientist (Junior) | $ - 0 | Environmental Scientist (Junior) | $ - 0 | Environmental Scientist (Junior) | $ - 0 | Environmental Scientist (Junior) | $ - 0 |
| CADD Operator | $ - 0 | CADD Operator | $ - 0 | CADD Operator | $ - 0 | CADD Operator | $ - 0 | CADD Operator | $ - 0 |
| Translator | $ - 0 | Translator | $ - 0 | Translator | $ - 0 | Translator | $ - 0 | Translator | $ - 0 |
| Certified Surveyor | $ - 0 | Certified Surveyor | $ - 0 | Certified Surveyor | $ - 0 | Certified Surveyor | $ - 0 | Certified Surveyor | $ - 0 |
| Haz Wast Specialist | $ - 0 | Haz Wast Specialist | $ - 0 | Haz Wast Specialist | $ - 0 | Haz Wast Specialist | $ - 0 | Haz Wast Specialist | $ - 0 |
| Project Controls | $ - 0 | Project Controls | $ - 0 | Project Controls | $ - 0 | Project Controls | $ - 0 | Project Controls | $ - 0 |
| Quality Control Manager | $ - 0 | Quality Control Manager | $ - 0 | Quality Control Manager | $ - 0 | Quality Control Manager | $ - 0 | Quality Control Manager | $ - 0 |
| Database Developer | $ - 0 | Database Developer | $ - 0 | Database Developer | $ - 0 | Database Developer | $ - 0 | Database Developer | $ - 0 |
| Database Administrator | $ - 0 | Database Administrator | $ - 0 | Database Administrator | $ - 0 | Database Administrator | $ - 0 | Database Administrator | $ - 0 |
| Site Safety and Health Officer (SSHO) | $ - 0 | Site Safety and Health Officer (SSHO) | $ - 0 | Site Safety and Health Officer (SSHO) | $ - 0 | Site Safety and Health Officer (SSHO) | $ - 0 | Site Safety and Health Officer (SSHO) | $ - 0 |
Proposed Percentage for Annual Escalation Rate: 0%
| $0.00 | |
| * Complete Column A for the Base Year ONLY for the labor disciplines your firm proposes under this contract. The Option Year burdened rates will automatically populate once the Proposed Percentage for Annual Escalation Rate is entered. If awarded the contract, the burdened rates will be binding for Unscheduled Minor Repair Service Orders approved under Task 3 and Task 5 in the Performance Work Statement. |
** Burdened rate for each labor category without profit
File details come from the government source that posted it. Updated .