This document contains a price schedule and labor rates worksheet for a solicitation seeking recurring maintenance and minor repair services for U.S. Air Force fuel facilities supported by the Defense Logistics Agency - Energy at Incirlik Air Base in Turkey. The solicitation seeks fixed prices for tasks including contractor plans, reports, unscheduled repair service orders with estimated ceilings of $1 million for the base year and increasing amounts for subsequent option years, and annual fuel site assessments. The labor rates worksheet requires offerors to provide fully burdened hourly rates for positions such as program managers, engineers, technicians, and environmental scientists for the base year and escalating rates for four option years. Offerors must also propose an annual escalation percentage to be applied to the option year labor rates. The selection will be made in U.S. dollars.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WS A-Price Schedule

SCHEDULE OF ITEMS AND PRICES
WORKSHEET A: CONTRACT PRICE SCHEDULE
DLA-E Turkey RMMR
Offeror Name
Date
Proposed CLINDescription of Services (Base Year)Service Order Fixed FeePrice
CLIN 0001Task 1 - Contractor Plans$ - 0
CLIN 0002Task 2 - Contractor Reports$ - 0
CLIN 0003Task 3 - Unscheduled Minor Repair Service Orders *$ 1,000,000.00
Task 3 - Service Order Fixed Fee**FIXED FEE TOTAL$ - 0
CLIN 0004Task 4 - Annual Fuels Site Assessment$ - 0
CLIN 0005Task 5 - Unscheduled Minor Repair Service Orders for Mobile Pantographs and Equipment *$ 4,500.00
Task 5 - Service Order Fixed Fee**FIXED FEE TOTAL$ - 0
CLIN 0006Task 6 - Installation AccessNOT SEPARATELY PRICED
Base Year Total:$ - 0
Proposed CLINDescription of Services (Option Year 1)Service Order Fixed FeePrice
CLIN 1001Task 1 - Contractor Plans$ - 0
CLIN 1002Task 2 - Contractor Reports$ - 0
CLIN 1003Task 3 - Unscheduled Minor Repair Service Orders *$ 500,000.00
Task 3 - Service Order Fixed Fee**FIXED FEE TOTAL$ - 0
CLIN 1004Task 4 - Annual Fuels Site Assessment$ - 0
Option Year 1 Total:$ - 0
Proposed CLINDescription of Services (Option Year 2)Service Order Fixed FeePrice
CLIN 2001Task 1 - Contractor Plans$ - 0
CLIN 2002Task 2 - Contractor Reports$ - 0
CLIN 2003Task 3 - Unscheduled Minor Repair Service Orders *$ 510,000.00
Task 3 - Service Order Fixed Fee**FIXED FEE TOTAL$ - 0
CLIN 2004Task 4 - Annual Fuels Site Assessment$ - 0
Option Year 2 Total:$ - 0
Proposed CLINDescription of Services (Option Year 3)Service Order Fixed FeePrice
CLIN 3001Task 1 - Contractor Plans$ - 0
CLIN 3002Task 2 - Contractor Reports$ - 0
CLIN 3003Task 3 - Unscheduled Minor Repair Service Orders *$ 520,200.00
Task 3 - Service Order Fixed Fee**FIXED FEE TOTAL$ - 0
CLIN 3004Task 4 - Annual Fuels Site Assessment$ - 0
Option Year 3 Total:$ - 0
Proposed CLINDescription of Services (Option Year 4)Service Order Fixed FeePrice
CLIN 4001Task 1 - Contractor Plans$ - 0
CLIN 4002Task 2 - Contractor Reports$ - 0
CLIN 4003Task 3 - Unscheduled Minor Repair Service Orders *$ 530,604.00
Task 3 - Service Order Fixed Fee**FIXED FEE TOTAL$ - 0
CLIN 4004Task 4 - Annual Fuels Site Assessment$ - 0
Option Year 4 Total:$ - 0

Contract Total: $ - 0

* Estimated ceiling for Unscheduled Minor Repair Service Orders.
** Enter proposed Fixed Fee.

AWARD WILL BE MADE IN UNITED STATES DOLLARS

WS B-Labor Rates

SCHEDULE OF ITEMS AND PRICES

WORKSHEET B - Labor Rates for Unscheduled Minor Repair Service Orders
DLA-E Turkey RMMR
Offeror Name
Date
COLUMN A
Base Year* Burdened Rate**Option Year 1 Burdened Rate*Option Year 2 Burdened Rate*Option Year 3 Burdened Rate*Option Year 4 Burdened Rate*
Prime Direct LaborPrime Direct LaborPrime Direct LaborPrime Direct LaborPrime Direct Labor
Loaded rate includes the following indirects (i.e., Overhead, G&A, benefits, etc.):Loaded rate includes the following indirects (i.e., Overhead, G&A, benefits, etc.):Loaded rate includes the following indirects (i.e., Overhead, G&A, benefits, etc.):Loaded rate includes the following indirects (i.e., Overhead, G&A, benefits, etc.):Loaded rate includes the following indirects (i.e., Overhead, G&A, benefits, etc.):
Program Manager$ - 0Program Manager$ - 0Program Manager$ - 0Program Manager$ - 0Program Manager$ - 0
Project Manager$ - 0Project Manager$ - 0Project Manager$ - 0Project Manager$ - 0Project Manager$ - 0
Team Leader$ - 0Team Leader$ - 0Team Leader$ - 0Team Leader$ - 0Team Leader$ - 0
Site Supervisor/Superindendent$ - 0Site Supervisor/Superindendent$ - 0Site Supervisor/Superindendent$ - 0Site Supervisor/Superindendent$ - 0Site Supervisor/Superindendent$ - 0
Petroleum Maintenance Technician (Senior)$ - 0Petroleum Maintenance Technician (Senior)$ - 0Petroleum Maintenance Technician (Senior)$ - 0Petroleum Maintenance Technician (Senior)$ - 0Petroleum Maintenance Technician (Senior)$ - 0
Petroleum Maintenance Technician (Mid-Level)$ - 0Petroleum Maintenance Technician (Mid-Level)$ - 0Petroleum Maintenance Technician (Mid-Level)$ - 0Petroleum Maintenance Technician (Mid-Level)$ - 0Petroleum Maintenance Technician (Mid-Level)$ - 0
Petroleum Maintenance Technician (Junior)$ - 0Petroleum Maintenance Technician (Junior)$ - 0Petroleum Maintenance Technician (Junior)$ - 0Petroleum Maintenance Technician (Junior)$ - 0Petroleum Maintenance Technician (Junior)$ - 0
Engineer (Senior)$ - 0Engineer (Senior)$ - 0Engineer (Senior)$ - 0Engineer (Senior)$ - 0Engineer (Senior)$ - 0
Engineer (Mid-Level)$ - 0Engineer (Mid-Level)$ - 0Engineer (Mid-Level)$ - 0Engineer (Mid-Level)$ - 0Engineer (Mid-Level)$ - 0
Engineer (Junior)$ - 0Engineer (Junior)$ - 0Engineer (Junior)$ - 0Engineer (Junior)$ - 0Engineer (Junior)$ - 0
Environmental Scientist (Senior)$ - 0Environmental Scientist (Senior)$ - 0Environmental Scientist (Senior)$ - 0Environmental Scientist (Senior)$ - 0Environmental Scientist (Senior)$ - 0
Environmental Scientist (Mid-Level)$ - 0Environmental Scientist (Mid-Level)$ - 0Environmental Scientist (Mid-Level)$ - 0Environmental Scientist (Mid-Level)$ - 0Environmental Scientist (Mid-Level)$ - 0
Environmental Scientist (Junior)$ - 0Environmental Scientist (Junior)$ - 0Environmental Scientist (Junior)$ - 0Environmental Scientist (Junior)$ - 0Environmental Scientist (Junior)$ - 0
CADD Operator$ - 0CADD Operator$ - 0CADD Operator$ - 0CADD Operator$ - 0CADD Operator$ - 0
Translator$ - 0Translator$ - 0Translator$ - 0Translator$ - 0Translator$ - 0
Certified Surveyor$ - 0Certified Surveyor$ - 0Certified Surveyor$ - 0Certified Surveyor$ - 0Certified Surveyor$ - 0
Haz Wast Specialist$ - 0Haz Wast Specialist$ - 0Haz Wast Specialist$ - 0Haz Wast Specialist$ - 0Haz Wast Specialist$ - 0
Project Controls$ - 0Project Controls$ - 0Project Controls$ - 0Project Controls$ - 0Project Controls$ - 0
Quality Control Manager$ - 0Quality Control Manager$ - 0Quality Control Manager$ - 0Quality Control Manager$ - 0Quality Control Manager$ - 0
Database Developer$ - 0Database Developer$ - 0Database Developer$ - 0Database Developer$ - 0Database Developer$ - 0
Database Administrator$ - 0Database Administrator$ - 0Database Administrator$ - 0Database Administrator$ - 0Database Administrator$ - 0
Site Safety and Health Officer (SSHO)$ - 0Site Safety and Health Officer (SSHO)$ - 0Site Safety and Health Officer (SSHO)$ - 0Site Safety and Health Officer (SSHO)$ - 0Site Safety and Health Officer (SSHO)$ - 0

Proposed Percentage for Annual Escalation Rate: 0%

$0.00
* Complete Column A for the Base Year ONLY for the labor disciplines your firm proposes under this contract. The Option Year burdened rates will automatically populate once the Proposed Percentage for Annual Escalation Rate is entered. If awarded the contract, the burdened rates will be binding for Unscheduled Minor Repair Service Orders approved under Task 3 and Task 5 in the Performance Work Statement.

** Burdened rate for each labor category without profit

File details come from the government source that posted it. Updated .