B.08 Att 8 Period of Performance Clause Medical Storage, Chad.docx
DOCX document 30 KB Posted
- Solicitation number
- W912GB25RA003
- Issued by
-
Department of the Army European Command
About this file
The attached document is a Period of Performance Clause for a medical storage facility construction project in N'Djamena, Chad, associated with Solicitation Number W912GB25RA003. The project requires the contractor to commence work within 7 calendar days of receiving the Notice to Proceed, prosecute the work diligently, and complete the entire project within 450 calendar days, including final cleanup.
The project involves demolishing an existing 260 m2 warehouse, clearing and grading the site, and constructing a new pre-manufactured warehouse facility with specific requirements including a PV power system, concrete access ramp, loading/unloading dock, and climate control systems maintaining internal temperatures at or below 27 degrees Celsius. A pre-proposal site visit is scheduled for 25 April 2025, with mandatory pre-registration by 21 April 2025. The project is being managed by the Department of the Army European Command, and contractors must be SAM registered to be eligible for the contract.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TCD MEDICAL STORAGE FACILITY
N’DJAMENA, CHAD
20-November-2024
COMMENCEMENT PROSECUTION AND EXECUTION OF WORK (52.211-10)
The Contractor shall be required to (a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use no later than 450 calendar days after the contractor receives the Notice to Proceed. Any options, if awarded, shall be completed concurrently with the associated work.
The time stated for completion shall include final cleanup of the premises. The Government intends to issue a single Notice to Proceed for all work.