Attmt 1 - MACC SOW 6 August 21.pdf
PDF 546 KB Posted
- Solicitation number
- FA570225R0001
About this file
This document is a Statement of Work (SOW) for a Multiple Award Construction Contract (MACC) Indefinite Delivery Indefinite Quantity (IDIQ) contract for the 379th Expeditionary Civil Engineer Squadron (ECES) at Al Udeid Air Base (AUAB), Qatar. The contract aims to support a broad range of maintenance, repair, paving, trenching, minor construction/alteration, and renovation work on real property, including the airfield.
Key requirements include providing design and construction services with multiple design phases (35%, 65%, and 95% completion stages), preparing comprehensive documentation such as drawings, specifications, and design analyses, and adhering to strict quality management and safety standards. The contractor must have experienced program management staff, technical capabilities to prepare proposals and execute construction phases, and comply with environmental, safety, and base access regulations. The contract includes provisions for performance reviews, with contractors required to maintain at least 70% participation in Fair Opportunity Proposal Requests (FOPRs) and receive satisfactory ratings to remain in the competitive pool.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6 August 2021 FA5702-25-R-0001
Attachment 1
STATEMENT OF WORK (SOW)
MULTIPLE AWARD CONSTRUCTION
CONTRACT
(MACC)
INDEFINITE DELIVERY INDEFINITE
QUANTITY (IDIQ)
AL UDEID AIR BASE (AUAB), QATAR
379th EXPEDITIONARY CIVIL ENGINEER
SQUADRON
(ECES)
6 August 2021
6 August 2021 FA5702-21-R-0024
GENERAL PROVISIONS
FOR
MACC IDIQ
1. SCOPE OF WORK:
The required work to be performed by the Contractor consists of, but is not limited to, a broad range of maintenance, repair, paving, trenching, minor construction/alteration and renovation work on real property at Al Udeid Air Base (AUAB) Qatar, including the airfield. All work shall be in conformance with the requirements of the contract including furnishing all materials, labor, plant, tools, equipment, transportation, supervision, management, and other services (including engineering/technical design support), items, and incidentals necessary thereto.
2. DEFINITIONS:
a. 35% Basis of Design – Government Furnished Materials (GFM) Documents providing the following minimum information, as applicable to the project:
1. Statement of Work (SOW) or Statement of Objectives (SOO)
2. AF Form 66 Schedule of Material Submittals (fillable form)
3. Conceptual Drawings (will consist at a minimum all major systems and connections thereto)
b. 65% Design – The Contractor will provide, based on the Government provided 35% Basis of Design, drawings and the complete text of the specifications based upon the Unified Facilities Guide Specifications (UFGS), design analysis as identified in the Task Order (TO) for Government approval. The Preliminary Design Submittal shall reflect a 65% complete design effort including a Design Analysis, Manufacturers Information, Calculations, Drawings, and Specifications required to document the work, incorporating the Concept Design Submittal Review Comments and Responses. Major mechanical and electrical equipment items shall be shown on the drawings with single line diagrams. All utilities and structures shall be shown. Drawings shall also include the following, as applicable:
1. The drawings will show an additional 30% progress in all disciplines including site plans, floor plans, elevations, wall sections, details, and all other areas as listed in the basis of design. All cut sections and details shall also be shown on the drawings at this time. Any updated or corrected design analyses of architectural, structural, civil, electric, mechanical, and utility systems shall be included. Dimensions will be provided in metric with imperial provided in parenthesis.
2. All required controlling dimensions shall be shown. Site plan showing location of work including access from main roads and surface or subsurface drainage concepts.
3. Floor plans with dimensions and functional arrangement of all areas; including corridors, exits, stairs, and utility spaces properly related to exterior access, applicable Architectural Buildings Act requirements, life safety, roads, parking, and service areas, etc. Individual treatment shall be given items involving special design and/or deviations from accepted standards and of complex design.
Gross floor areas shall be shown for each floor and for the entire building. Floor and roof framing, and design dead/live, wind and all other applicable loadings shall be indicated. Built-in, installed, and specialized portable equipment shall be indicated to scale. Pertinent information regarding fire prevention and safety requirements shall be shown.
4. Elevations shall include story heights, fenestration, and adaptation to finished grades at the site.
5. Sections of structures, including framing, partitions, suspended ceilings, (if any), ducts, etc., shall be shown.
6. Typical detail sections shall be shown at a scale of no less than 19mm (3/4 inch) = 305mm (1 foot).
Sections shall include material and thicknesses, methods of attachment, and type of windows with relation thereof to supporting structural columns or walls.
7. For heating, air conditioning, mechanical ventilation and plumbing, and special features such as fire suppression, elevators, hoists, kitchen equipment, etc., indicate the location, capacity, and space requirements for all major items of mechanical equipment. Single line indication and riser diagrams of ducts, pipes, and equipment and their approximate location shall also be shown. Indication shall be made as to whether piping and duct work are exposed or concealed. Functional areas where pipes are exposed shall be delineated. Approximate operating range or capacity for heating, ventilation, air conditioning, and refrigeration equipment shall be clearly stated.
8. For electrical systems, indicate lighting arrangements, type of fixtures proposed, general light intensities, special electrical requirements of the user, including communications and electronic facilities where applicable, light and power service entrance and distribution arrangement. Conduits, including those to be wired by others, shall be shown together with indication as to whether conduits are exposed. Functional areas having exposed conduits shall be delineated. Riser diagrams, showing service equipment, feeders, and panels, other than branch circuits, shall be shown. Cable sizes, current demand factors and the switch and panel board descriptions are required at this time.
Location capacity and space requirements of all major items of equipment shall be shown including interior substations with service equipment and panels. Power, communication, and electronic features will be indicated in sufficient detail to identify requirements clearly and to indicate the means of satisfying the requirements.
9. Identify all Government Furnished Equipment (GFE) / GFM to be installed by the Contractor and equipment furnished and installed by the Government, if applicable.
c. 95% Design – Upon receiving 65% design approval, the Contractor will submit the refined documents for Government review. The documents will include final and complete drawings and specifications. The 95% design shall include all items identified in the TO and shall be ready for construction, requiring only final Government review.
d. Color Board – A visual presentation consisting of samples of the various finishes, grouped together based on location within the project that may be required as directed by the Contracting Officer (CO) or COTR.
Samples shall be of adequate size to show the full pattern, texture, and color of each item and shall be submitted to the CO in the standard submittal format.
e. Contracting Officer Technical Representative (COTR): The ECES representative, may also be referred to as the COR, PM or CM, performs technical surveillance and evaluation of the work under this contract. This designation in no way authorizes anyone other than the CO to commit the Government to changes in the terms of the contract. Any site conditions that impact the construction of the project and indicate the need for possible changes to the SOW must be presented to the CO in written format.
f. Conventional Design-Build – The process by which the same Contractor provides both the design and construction services for a project, completing the design before construction activity begins.
g. Design Costs – Those costs identified by the Contractor, not to exceed the 6% statutory limit, as part of the TO process which represent the portion of the overall project cost attributed to preparation of the design for a construction project.
h. Fast Track Design-Build – The process by which the same Contractor provides both the design and construction services for a project, beginning construction at a mutually agreed point prior to completion of the design and construction drawings.
i. GFE/GFM – Items of equipment or material which the Government will supply to the Contractor for use in the construction of a project.
j. Hazardous Materials – Any material that is capable of posing an unreasonable risk to health, safety, or the environment if improperly handled, stored, issued, transported, labeled, or disposed because it displays a characteristic listed in Table C5.T1., “Typical Hazardous Materials Characteristics. (See State of Qatar Final Governing Standards)
k. Professional Certification – Professional certification will be required on all drawings. The process consists of affixing a seal or statement to a drawing or design document to indicate that the work to which it is affixed has been performed by a person licensed as a professional, in that area of expertise, in the State of Qatar.
l. Statement of Objectives (SOO) - A document prepared by the Government and issued to the Contractor as part of the TO. Included in the SOO are the specific technical requirements and overall objectives for the project.
m. Statement of Work (SOW) – A document prepared by the Government and issued to the Contractor as part of the TO. Included in the SOW are the specific technical requirements for the project.
n. Sustainability: Demonstrate ability to achieve Leadership in Energy and Environmental Design (LEED) self-certification if required by the TO. The Contractor is to comply with the minimum Qatari environmental performance requirements specified herein which have been derived from the Global Sustainability Assessment System (GSAS) v4.0-2019. Air Force Sustainable Design and Development (SDD) Implementing Guidance.
Reference LEED for New Construction and Major Renovation v3.0 Reference Guide
o. Task Order (TO) – A TO is a document prepared by the Government and issued to the Contractor against the basic contract. Its purpose is to place an order for labor, materials and other associated items as necessary to complete the design and/or design-build/construction of a specific project. The TO requires the Contractor to submit cost proposal and design documents for a project. Following submittal of the proposal and at the Government’s discretion, discussions may be held with the Contractor to clarify and/or negotiate elements of the proposal.
p. Fair Opportunity Proposal Request (FOPR) – A package of documents issued to the Contractor requesting a cost proposal for construction and design documents for a project based on the TO. Following submittal of the proposal and at the Government’s option, discussions may be held with the Contractor to clarify and / or negotiate elements of the proposal. The FOPR will be issued on design or design-build TO.
3. DESCRIPTION OF WORK:
a. A FOPR issued under this contract will be issued to all MACC IDIQ Contractors and will include a SOW/SOO defining the project requirements. The project may ultimately require the Contractor to produce a full design, partial design, or no design depending on the type of TO request. For example, a new project with no, or partial, previous design accomplished will be issued as an FOPR and will include requirements to provide a 35% (minimum) design as part of the Contractor’s proposal. If awarded a TO for the project, the successful Contractor will, as necessary, complete the design to the 95% level. Conversely, a project for which a 95% design is already available will only require a cost proposal in the prescribed format.
In addition, the TO may include the following:
(1) Government prepared SOW/SOO, sketches, and any available as-builts, specifications, or design information.
(2) Design calculations requirements.
(3) Construction drawings requirements including professional certifications.
(4) Direction regarding fast-track vs. design-build.
(5) Timeframes for preparing the proposal, completing design work (if awarded), and completing construction.
(6) Contractor prepared specification sections and version required.
(7) Submittal requirements.
(8) GFM or GFE.
b. Proposals received in the FOPR format will be evaluated based on compliance with the design requirements and the proposed price. The Government reserves the right to enter into discussions with the Contractor for the purpose of requesting minor revisions to the proposals.
c. The Contractor may be required to work within controlled or restricted areas in accordance with SOW Paragraphs 25, 26 and 27.
4. PROPOSAL CLASSIFICATIONS:
Due to mission requirements, the Government can rarely wait thirty (30) calendar days to receive proposals from vendors for various projects at the TO level. To mitigate, the Government will classify projects as Routine, Urgent, or Emergency, which in turn will inform the Contractor of proposal due date times. The proposal timeline will start immediately following the site visit; however, the Government reserves the right to issue the FOPR without conducting a site visit and thus, starting the proposal timeline.
Routine: Contractors will have thirty (30) calendar days to provide a proposal.
Urgent: Contractors will have seven (7) calendar days to provide a proposal, unless otherwise specified in the
FOPR.
Emergency: Contractors will have forty-eight (48) hours to provide a proposal.
5. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK:
The Contractor shall commence work and complete the project in accordance with the time frames established in the TO and Notice to Proceed (NTP). At completion of project, the Contractor shall fill out and submit the Government provided “Transfer and Acceptance of Military Real Property (DD 1354).
The Contractor shall comply with all requirements outlined in the QCS 2014 Section 11 Part 2.3.15 Environmental Protection, AUAB Environmental Management Plan (EMP), DoD 4715.05-G Overseas Environmental Baseline Guidance Document, and State of Qatar Final Governing Standards for environmental regulations.
6. DESIGN DOCUMENTS, GENERAL:
All Contractor design documents shall comply with the following requirements:
a. The Contractor shall receive an electronic copy of the appropriate record drawings, if available, with the TO.
The Government does not guarantee the accuracy or adequacy of the existing record drawings. The Contractor is responsible to field verify all Government provided record drawings during preliminary site visits, project planning, and prior to issuance of each TO. The Contractor shall be responsible for the reproduction of these drawings.
b. When design is required by the TO, the Contractor shall develop all drawings using latest version of Auto
CAD computer aided drafting software and be prepared to utilize ANSI Standard B 279mm x 432mm (11” x 17”) drawing format. All drawings shall be in the same electronic format and shall comply with DoD A/E/C CAD Standards latest version, publication ERDC/ITL TR-09-2. The AUAB cover sheet and title blocks shall be used. Cover sheet templates will be provided to the Contractor electronically.
c. The Contractor shall prepare drawings, as specified in the TO, for Government approval prior to the start of construction or as indicated in the TO. Each sheet shall have an approved title block and border with professional certification when required by the TO. The title block shall contain project information including but not limited to Project number, TO number, Project Name, and date. Basic design criteria utilized for each discipline will be included on the appropriate drawings as required by the TO. Examples include: wind and live/dead loads assumed for structural elements, function specific conditions such as lighting levels or future use considerations for electrical systems, showing haul route, site specific climatic design conditions for mechanical systems, and Uniform Building Code analysis (performed to the same level as if being applied to a building permit process). The following is a list of drawings which might typically be required under this contract:
(1) Cover Sheet with Title and Approval Block
(2) Legend page
(3) Existing Site Plan
(4) Final Site Plan
(5) Grading Plan
(6) Underground Utility Plan and Profiles
(7) Demolition Plan
(8) Floor Plans
(9) Elevations
(10) Finish Schedule
(11) Wall and Roof Sections
(12) Window and Door Schedules
(13) Ceiling Plan
(14) Details
(15) Mechanical Plan and Schedules
(16) Plumbing and HVAC Riser Diagrams
(17) HVAC Controls Diagrams
(18) Electrical Site Plan
(19) Power Plan and Panel Schedule
(20) Electrical Plan and Lighting Plan with Schedule and details
(21) Fire Projection Plan
(22) Communications Plan
d. Perspective Drawing: When required by the TO, develop a black line concept perspective and/or an AUTO
CAD/REVIT, or otherwise specified computer programming, rendered (color) perspective of the project.
(1) The perspectives shall be approximately 355.6mm x 711.2mm (14” x 28”) size and shall be mounted on a standard presentation board, complete with a small site plan and supporting data (i.e. size, cost of landscaping, site work, building, etc.) affixed to the presentation board.
(2) The black-line concept perspective shall be provided with the Contractor’s 65% submittal. The rendered perspective shall be prepared by the Contractor and delivered with the final design submittal when requested.
e. Topographic and/or Geotechnical Surveys: Surveys/work as required for siting, grading, computation of quantities for excavation and fill, and development of a particular project site and the establishment of property lines in connection with a project shall be performed using conventional or other methods, such as a total station or Global Positioning Systems (GPS) for field data collection at an accuracy level in accordance with “Geospatial Positioning Accuracy Standards, Part 2: Standards for Geodetic Networks,” published by the Federal Geographic Data Committee (FGDC), dated July 1998. All geodetic data shall be collected using the coordinate and projection system of the installation imagery - WGS 84 / UTM 39N (EPSG4979) latitude, longitude and ellipsoid height, and orthometric height (EPSG32639). Data may also be requested in QND95 / Qatar National Grid, EPSG: 2932 and QND95 (Longitude-Latitude), EPSG: 4614 coordinates. The Contractor shall use survey grade GPS, at an accuracy level of +/- 2cm. All Survey data collected shall be provided to the Government in Compact Disc (CD) digital format with an attached Survey Report identifying survey method, equipment list, calibration documentation, survey layout, description of control points, control diagrams, and field survey data.
f. Geographic Information System (GIS): GIS data shall be provided in ESRI ArcGIS 8.x personal geodatabase format. The Contractor shall identify the horizontal and vertical order, classification, ID number, elevation, coordinate location and any other necessary attributes (specified by the Government) for all surveyed features. Entity naming conventions, attribute fields, and domain names shall be collected in the format defined by the CADD/GIS Technology Center’s Spatial Data Standards (SDS) current release, except where modified by the Government. For more information, go to http://www.sdsfie.org/.
g. Specifications:
(1) If required by the TO, the Contractor shall submit an originated design specification that, in conjunction with the drawings, demonstrates compliance with materials, equipment, execution, and field quality control requirements of the SOW/SOO. The specified products, equipment, fixtures, devices, and systems submitted by the Contractor and accepted or approved by the COTR shall be used to construct the project. For projects, the Contractor shall prepare the project specification section by using the appropriate UFGS available from the Whole Building Design Guide website, http://dod.wbdg.org/, which is current at the time of FOPR release. Modify the guide specification to fit the project. Delete portions of the guide specification that cover work not included in the project.
When portions of the work involved are not covered in a guide specification, add requirements to the project specification, as necessary, using language and format similar to that employed in the guide specification. Use guide specifications only as source documents and do not reference them in project specifications. Do not combine work covered by various UFGS into one section unless the work is of a minor nature.
(2) In addition to the technical specifications described above, the current versions of the following references, which are available on line except as noted, are to be utilized in the preparation of project designs:
Air Force Engineering Technical Letters (AFETL) Air Force Occupational Safety, Fire, & Health Standards Air Force Instructions (AFI) / Air Force Manual (AFMAN) American Society for Testing Materials (ASTM) 379 AEW Environmental Management Plan (EMP) Overseas Environmental Baseline Guidance Document (OEBGD) State of Qatar Final Governing Standards (Environmental) American Concrete Institute (ACI) http://www.sdsfie.org/ http://dod.wbdg.org/
American Society of Civil Engineers (ASCE) American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) Construction Specification Institute (CSI);
United State Army Corps of Engineering, Engineering Manuals (USACE EM) International Building Code (IBC) International Electro-technical Commission (IEC) International Fire Code (IFC) International Mechanical Code (IMC) International Plumbing Code (IPC) Energy Information Administration (EIA);
KAHRAA MAA Regulations National Electric Code (NEC)- NFPA 70 National Fire Protection Association (NFPA) Qatari Construction Specifications (QCS) Kahramaa Regulations Qatari Ministry Of Electricity And Water (MEW) Occupational Safety And Health Administration (OSHA) A/E/C Graphics Standards Unified Facilities Criteria (UFC) Unified Facility Guideline Specifications (UFGS)
Attachment 1
(3) Any applicable manufacturer or industry specifications associated with material, supplies, or systems shall be utilized. If a discrepancy exists between these documents, the Contractor shall bring this to the attention of the CO and COTR, and shall utilize the most stringent requirement(s) in the preparation of the project design.
(4) The Contractor must consider the use of locally available materials for all projects as compared to
American or even European materials, provided the minimal technical requirements are met and does not exceed the cost of American materials. Local materials can be acquired with minimal time. Specialty items, which can only be procured outside the local area, shall be identified in the 65% Design by the Contractor and shall make acquisition provisions to ensure compliance with the overall schedule.
(5) Schedule of Material Submittals: Required submittals shall be listed on a Schedule of Submittals AF
Form 66. A sample copy of the AF Form 66 is included as an attachment in each TO. Reference each submittal item on the AF Form 66 to the UFGS specification section and paragraph. Consecutively number each page of the Schedule of Submittal, e.g. “Page 1 of X”. Use all line number rows on one page before starting another page. Ensure all items requiring submittals are annotated on the Schedule of Submittals with the anticipated submission date. The COTR will review the Schedule of Submittals to ensure all required submittals are annotated and track required submittals for each construction project.
h. Design Analysis: As specified in the TO, design analysis may be required, to include Calculations, General
Description, History, Assumptions, References; Analysis of Alternatives; Energy Conservation Analysis/Life Cycle Cost Analysis, and code references, as applicable for each discipline, to show compliance. Calculations shall be provided by the Contractor and included with the appropriate design submittal. The following is a list of calculations which might typically be required under this contract:
(1) Civil/Site work:
(a) Survey: Contractor shall survey the site to locate all existing conditions on the site.
(b) Site location map and location plan showing geographic location of project relative to existing facilities, roads, streets, etc.
(c) Demolition plans at a legible scale showing quantities, locations and type of materials to be removed and added.
(d) Site plan: All roads, parking, sidewalks and loading zones
(e) Grading plan: showing all topographic and grading information
(f) Utilities Plan: showing connections, routing and capacities of all utilities
(g) Details: all civil engineering details required to complete the installation of the work
(h) Geotechnical report
(2) Structural
(a) Foundation sizes and reinforcing
(b) Superstructure framing
(c) Wind & snow loading analysis
(d) LL (live load) & DL (dead load) calculations
(e) Wall sizes and reinforcing
(f) Equipment supports
(g) Elevated platforms
(h) Floor member sizing / reinforcing
(i) Lintel sizing
(j) Sizing for roof joists & decking
(k) Seismic calculations
7.
During the progress of the work, the Contractor shall keep a detailed record of all changes and corrections from the original design layouts shown on the drawings. These red-lined drawings will be maintained at the job site, available for inspection by the Government. The Contractor shall manually and promptly enter any changes and corrections on the contract or record drawings maintained at the site. On completion of the project, the Contractor shall update the original electronic drawing files and provide the Government with a draft of the as-built drawings for approval. Upon Government approval, the Contractor shall submit as-built drawings as specified in the TO. The drawings shall indicate, in addition to all changes and corrections, the actual location of all subsurface utility lines.
In order that the location of the utility lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, the as-built drawings shall be clearly defined to show the end of each run including each change in direction. This may be accomplished, by offset dimensions to two (2)
Mechanical:
Cooling and heating load analysis.
Pump sizing and pump curves.
Pipe sizing.
Duct size.
Static pressure loss.
Control valve sizing.
Psychometric chart analysis.
Fan sizing and fan curves.
Heat exchanger selection.
Electrical:
Load calculations Short circuit calculations Lighting level calculations Branch circuit calculations Motor feed requirements Panel sizing
Fire Protection:
Sprinkler layout and pipe sizing Water supply analysis (flow test) Sizing of fire demand pipelines Sizing of fire pumps Sizing of Water Storage Tanks
Architectural:
GSAS Sustainability Checklist and Analysis IBC Code Analysis Life Safety Code Analysis
Others as applicable to a specific project and identified in the TO.
AS-BUILT DRAWINGS:
permanently fixed surface features. Valves, splice boxes, and similar appurtenances shall be located by accurate dimensions along the utility run from a reference point. The Contractor shall record the depth (below the surface of each run), in addition to the size and type of conduit or pipe used for the run.
8. SUBMITTAL REVIEWS:
The Government will review all submittal within 15 calendar days of submission. If a submittal document is disapproved and resubmitted, the Government will not take more than 10 calendar days for their review.
9. POST AWARD MEETINGS:
a. Design Charrette/Post Award Kickoff Meeting (PAK): The Contractor shall host a meeting intended to build consensus among stakeholders, develop specific design goals and solutions for each TO. Participants represent all those who can influence the project design decisions. For further information, refer to documents such as A Handbook for Planning and Conducting Charrettes for High-Performance Project, National Renewable Energy Laboratory. If mutually beneficial to the Contractor and the Government, this may be a single meeting or multiple meetings.
b. Bi-Annual Review - The Contractor shall facilitate a bi-annual review of the base contract and all subsequently awarded TOs with key personnel of ECES, ECONS and other identified Government stakeholders.
Key members of the prime and subContractors teams, including senior management, must participate. The Bi- Annual Review should be held in a Government conference room on AUAB. The Contractor is responsible for developing presentation material to articulate comprehensive status updates on all TOs, actual and projected risks and mitigations statuses, quality management concerns and base access status. The Government will present its draft and final performance evaluations. The Government is not responsible for any Contractor travel expenses.
c. Preconstruction Meeting - Meet with the CO and COTR to discuss construction items of concern to the
Government and the Contractor such as base access, quality management, dig permits, outages, storage, trailer location, disposal of construction debris, etc. at a location to be determined by the Government. The Preconstruction meeting may take place with the PAK meeting or at any time prior to mobilization and before any construction work begins.
10. PERFORMANCE REVIEW:
Ninety (90) days before the anniversary of the contract award date, the Government shall perform an assessment of each MACC Contractor’s performance based on their current and past performance on MACC task orders. For purposes of the performance, the following criteria is how each Contractor will be evaluated annually. The Government will evaluate each Contractor’s participation rate, reason(s) for non-participation, and overall work performance for TOs completed, or in progress. The Government reserves the right to implement performance evaluations into the Contractor Performance Assessment Reporting System (CPARS) for all TOs. A Contractor rated as Satisfactory* may remain in the competition pool. Failure to participate in good faith and/or a TO performance assessment rating of Marginal** or Unsatisfactory***, under the CPARS rating system, may result in the Contractor being off-ramped from the MACC. If a Contractor has failed to comply with the terms and conditions of the MACC and task order(s), the Government reserves the right to not issue future solicitations to that contractor and/or terminate their contract. This shall serve as the "Off-Ramping" process. The Off-Ramped contractor will be required to continue any active projects until completion, unless otherwise terminated.
RATING DEFINITIONS:
*Satisfactory:
To receive a Satisfactory (S) rating, Contractor must maintain 70% participation in all MACC FOPRs and maintain a Satisfactory Rating per TO.
Satisfactory (S) Rating: Performance meets contractual requirements. The contractual performance of the element, or sub-element, contains some minor problems for which corrective actions taken by the Contractor appear or were satisfactory. Additionally, to justify a Satisfactory rating, there should have been only minor problems, or major problems the Contractor recovered from without impact to the contract/order. A fundamental principle of assigning ratings is that Contractors will not be evaluated with a rating lower than Satisfactory solely for not performing beyond the requirements of the contract/order
** Marginal:
A Marginal (M) rating will be given if the Contractor has a participation rating of less than 70%, but more than
50%, of all MACC FOPRs, or a Marginal rating on any TO. Subsequently, the CO shall make a determination regarding the continuance of any Contractor receiving a Marginal (M) rating. The Contractor may provide written documentation that identifies extenuating circumstances or a performance improvement plan for consideration by the CO.
Marginal (M) Rating: Performance does not meet some contractual requirements. The contractual performance of the element, or sub-element, being evaluated reflects a serious problem for which the Contractor has not yet identified corrective actions. The Contractor’s proposed actions appear only marginally effective or were not fully implemented. A Marginal rating should be supported by referencing the management tool that notified the Contractor of the contractual deficiency (e.g., management, quality, safety, or environmental deficiency report or letter).
*** Unsatisfactory:
An Unsatisfactory (U) will be given if the Contractor has a participation rating of less than 50% in all MACC FOPRs, or an Unsatisfactory rating on any TO. The CO shall make a determination regarding the continuance of any Contractor receiving an UNSATISFACTORY (U) rating. The Contractor may provide written documentation that identifies extenuating circumstances, or a performance improvement plan, for consideration by the CO.
Unsatisfactory (U) Rating: Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element, or sub-element, contains a serious problem(s) for which the Contractor’s corrective actions appear or were ineffective. An Unsatisfactory rating should be supported by referencing the management tools used to notify the Contractor of the contractual deficiencies (e.g., management, quality, safety, or environmental deficiency reports, or letters).
11. PROGRESS OF WORK:
Once awarded a TO, the Contractor shall submit, for approval, all work schedules to the CO within ten (10) calendar days after start of work unless otherwise specified. The reports contemplated by the clause titled “Schedules for Construction Contracts” shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, Contract Progress Schedule, and AF Form 3065, Contract Progress Report.
12. MATERIAL APPROVAL SUBMITTAL FORM:
(AF FAR SUP 5336.290): All material and articles requiring approval, as contemplated by the Materials and Workmanship Clause, shall be submitted by the Contractor. All wall covering, carpet and other fabric type submittals will show the full pattern of material as a minimum. All applicable submittals shall be grouped in color boards as installed, i.e. carpet, paneling, chair-rail, wall covering and ceiling tile. Contractor is responsible for identifying and locating required materials for submittals to include matching any existing materials.
13. PROGRAM MANAGEMENT:
The Contractor shall provide a program manager and staff for executing TOs awarded under this contract. The program management staff shall have project design oversite, quality control, and construction and financial management capability. The program manager shall have a minimum of five (5) years experience as a program manager, and shall have the authority to negotiate TOs and modifications thereto and obligate the company for TOs.
The program manager shall have the authority to hire subcontractors. The program manager must be experienced in subcontract management.
14. QUALITY MANAGEMENT PLAN:
The Contractor shall designate on-staff personnel as project superintendents to document and resolve all quality problems and accomplish daily quality control inspections. The Contractor shall establish a method to identify poor performance and specify appropriate corrective action. Quality personnel will interface with Government personnel to ensure that quality is maintained at the highest level.
15. SUBCONTRACTING SUPPORT CAPABILITY:
The Contractor shall provide subcontractor management including surveillance, quality control, base access, and scheduling. Subcontractors must be available to ensure quick response times. The Contractor must have the ability to manage and control multiple subcontracts at multiple job locations. The Contractor must ensure subcontractors are competent and capable of handling all tasks assigned to them and shall ensure that each subcontractor is not assigned more work than they can satisfactorily accomplish.
16. PROJECT EXECUTION AND TECHNICAL CAPABILITY:
Contractor shall have a support staff that includes clerical, quality control, project superintendent, drafting and design personnel as necessary to prepare proposals and execute the construction phase of all TOs.
IDENTIFICATION REQUIREMENTS
a. Personnel: The Contractor and subcontractor personnel shall present a neat appearance and be easily recognized as Contractor employees when they are on AUAB. This shall be accomplished by providing each employee with a picture identification badge to be worn at all times.
b. Contractor Office/Storage Area: Any storage yards or office trailers shall have the following sign posted:
(1) Size: 0.9144m x 1.2192m (3’ x 4’).
(2) Color: Sahara tan sign and posts with cocoa brown letters.
(3) Letters: Stenciled 101.6mm (4”) high letters for first line of sign.
(4) Stenciled 76.2mm (3”) high letters for middle of sign.
(5) Stenciled 50.8mm (2”) high letters for last line of sign.
(6) Information:
c. Storage Yard: Upon Contractor request, reasonable space will be provided if permanent outdoor storage is required; however, the Contractor will be required to provide and install a Government approved fence to secure the area. The fence shall have a screen attached to conceal the materials inside in compliance with AUAB Installation Facility Standards and approved by the COTR.
d. Office and Storage Facilities: The Contractor is not required to have offices or storage facilities on AUAB.
If the Contractor chooses to have an office or storage facility on AUAB, the Government will provide a 15.24m x 30.48m (50’ x 100’) lot within a reasonable distance of utilities. The Contractor shall be responsible for any costs associated with their on-site office and storage facilities to include mobilization, demobilization, trailers, skirting, utility lines, connections and site restoration. The on-site office and storage facility must conform to AUAB Installation Facility Standards. The Contractor shall restore the site to its original condition within thirty (30) days of contract completion. The Government will provide thirty (30) days notice and an alternate site if the current Contractor site is reallocated for Government purposes.
e. Available Utilities: Subject to available supply, the Government will provide reasonable access to electricity, gas, water and sanitary sewer capacity from existing outlets and supplies. The Contractor shall conserve the utilities. The CO at their discretion, can charge the Contractor for utilities if the Contractor is using poor conservation practices. The Contractor shall install, maintain and remove any necessary temporary connections and distribution lines at their own expense. If temporary lines are associated with a specific TO, they shall be removed prior to the final acceptance meeting. Communications access is not available to the Contractor and the Contractor will be required to use wireless communications.
AIR FORCE MACC CONTRACT
Contractor Name Contract Number Contract Duration
Emergency Contractor Phone Number Contracting Officer Technical Representative (COTR) can be reached at XXX-XXXX
f. Construction Project Sign: At commencement of construction the Contractor will establish (in consultation with the COTR) one construction sign at a prominent location at or near the construction site per the following guidance and specifications.
1. The prime Contractor shall furnish and install a construction sign for identification of the project. The sign shall be constructed in accordance with the guidelines, specifications, and drawing below. No other Contractor or subcontractor or material signs will be permitted on the site.
2. The cost of preparation and erection of the sign shall be at no additional cost to the Government. On rare occasions, and at the discretion of the CO, the dimensions or other features of the sign may be changed, or the sign omitted altogether, at no additional cost to the Government.
3. The construction sign for identification of the project will be installed prior to commencement of construction at a location which is near the project site and amenable to public viewing.
4. The sign will be adequately supported with regard to site conditions and will be an adequate distance above the prevailing grade to permit public viewing. The Contractor should exercise care when installing the sign to minimize disruption to the grounds/landscaping. Upon final acceptance of the project, the Contractor shall be responsible for restoring the grounds/landscaping to its original condition.
5. The sign will be constructed of a 1.2192m x 1.2192m (4’ x 4’) exterior type high density overlaid plywood or other sign material of equivalent quality and framed with nominal 50.8mm x 101.6mm (2” x 4”) wood of suitable grade. The sign surface shall be minimum 12mm thick Exterior Grade Plywood fastened to 2 each 89mm x 89mm pressure treated posts. Posts shall be buried a minimum 1000mm into the ground. The sign will be painted with black lettering on a matt white background. Lettering will be of professional quality and in accordance with the drawing detail below; all lettering will be in proportion to the sizes shown and centered on the sign.
6. A draft sign will be rendered, submitted and reviewed by the COTR prior to production. Any additional information displayed on the sign will not detract from or displace the information required in the drawing.
Changes must be approved by the COTR.
7. The sign will be maintained in good condition by the Contractor until completion of the construction project. The sign will be removed and appropriately disposed of when the construction is complete and accepted by the Government.
8. Below is the drawing detail/template for the sign. The Contractor shall update appropriate information such as the contract #, TO #, phone #s, etc., as required.
17. GOVERNMENT FURNISHED EQUIPMENT/MATERIALS:
a. The Government reserves the right to provide GFE and/or GFM if it is available and can be used by the Contractor to complete a TO. The GFE/GFM shall be transported by the Contractor, from the Government storage area, to the work site indicated on the TO.
b. The Contractor assumes the risk and responsibility for the loss or damage to GFE/GFM once the Contractor receives possession of the GFE/GFM.
c. The Contractor shall follow the instructions of the COTR regarding the disposition of all GFE/GFM not consumed in performance of a TO.
18. GOVERNMENT EQUIPMENT ON THE SITE:
a. The Contractor shall relocate all property on-site that the Government retains title to as specified in the TO or follow the instructions of the CO or his/her representative.
b. The Contractor is required to cover equipment that is to remain in place within the area of contract operations and protect it against damage or loss. Where directed, the Contractor will store equipment that is removed in performance of work or return equipment for reuse in work as required by drawings and specifications.
Equipment temporarily removed shall be protected and returned to the site in an equal condition to its original condition prior to starting work at no additional expense to the Government. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the Contractor.
19. DISPOSAL OF WASTE:
a. All construction debris will be taken off base to an approved landfill. Upon request, the Contractor shall submit all trip tickets from the landfill facility to show all debris is being disposed of in an approved landfill and in accordance with all Host Nation and Federal requirements.
b. All trucks containing loose debris shall ensure that upon leaving the site, the debris is loaded in such a manner that shall prevent dropping materials on streets and conform to local ordinances/laws. The Contractor shall fasten suitable cover, such as a tarpaulin, over the load before entering surrounding streets. The Contractor shall be responsible for cleaning up any materials that fall from trucks and be held liable for any resulting damages.
20. CONSTRUCTION SITE MAINTENANCE:
Contractor shall store all supplies and equipment on project site so as to preclude theft or damage from the elements. Maintain site in a neat and orderly manner. Protection and security for materials and equipment on site is the sole responsibility of the Contractor.
21. INSTALLATION PERIMETER ACCESS CONTROL:
All Foreign Nationals are required to register at the North Gate Pass and ID Office per AFMAN 31-113. The Contractor shall adhere to local policy and instructional guidance for entry requirements onto AUAB (See Contract Attachment 5). The Contractor shall submit base passes under the base contract and not individual TOs. The Contractor shall provide all required documentation, and ensure face-to-face meetings required for the badging process are attended. If appointments are missed, or documentation is not timely submitted, the Contractor is liable for any performance delays.
22. ESCORTING:
Government shall provide all escorts required for Contractor access to restricted/controlled areas, while working on construction projects at AUAB. The Contractor shall comply with submitting escort request in accordance with Contract Attachment 5.
23. LOCAL AND FEDERAL HOLIDAYS:
Contractors shall not work on U.S. or Qatari holidays. U.S. holidays may be observed on a separate date than the one listed as observation. Recognized holidays are below.
Qatari:
National Day (18 Dec)
National Sports Day (9 Feb) Ramadan April 23-May 23* Eid al Fitr (3 days following Ramadaan)* Eid al Adha (20-22 July but subject to change based on moon sightings)*
U.S.**:
New Year’s Day (1 Jan) MLK Day (third Monday in Jan) Presidents Day (third Monday in Feb) Memorial Day (last Monday in May) Juneteenth (19 June) Independence Day (4 July) Labor Day (first Monday in Sep) Columbus Day (second Monday in Oct) Veteran’s Day (11 Nov) Thanksgiving Day (last Thursday in Nov) Christmas Day (25 Dec)
*These dates are approximate since they change year to year.
**The 379 AEW Commander will determine the actual day of observance.
24. QATAR MID-DAY SUMMER LABOR LAWS:
a. The contractor shall follow all local labor laws, including any labor restrictions placed upon work hours during summer months. It is imperative that the contractor familiarize itself with all laws and restrictions and ensure their work schedule takes into account the effect of any law on the overall performance or schedule of the contract. For schedule submission purposes, please beware that the USG will still consider summer days as full working days.
25. DELAYS IN ENTERING AND LEAVING WORK AREA:
If the work site is located in a restricted or controlled area, the Contractor may experience delays due to compliance with entrance/exit requirements of the restricted/controlled areas. The Contractor shall not be compensated for reasonable delays in accessing the site. Also, due to the nature of restricted areas, the Contractor may be requested to leave the restricted area at any given time. The CO may extend the contract performance time when unreasonable delays occur.
26. SAFETY AND HEALTH:
a. General:
(1) In order to provide safety controls for protection to the life and health of employees and other persons, for prevention of damage to property, materials, supplies, and equipment, and for avoidance of work interruptions in the performance of this contract, the Contractor shall comply with all pertinent provisions of the Qatar Construction Specifications, (QCS 2014, Section 11, Part 1.02), entitled “Occupational Health and Hygiene (Regulatory Document)” as amended, and will also take or cause to be taken any additional measures as the CO, or COTR may determine to be reasonably necessary for the purpose.
(2) The Contractor shall report exposure data and all accidents resulting in death, traumatic injury, occupational disease, and damage to property, materials, supplies, and equipment incident to work performed under this contract. The Contractor shall maintain an accurate record of, and will report to CO or COTR as requested.
(3) The CO or COTR will notify the Contractor of any noncompliance with the foregoing provisions and the action to be taken. The Contractor shall, after receipt of such notice, immediately take corrective action. Such notice, when delivered to the site of the work, shall be deemed sufficient for this purpose. If the Contractor fails or refuses to comply promptly, the CO may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such stop orders shall be made the subject of claim for extension of time or for excess costs or damages by the Contractor.
(4) The Prime Contractor will be responsible for the safety and health compliance of all subcontractors.
b. Standards are applicable to all work covered by this contract:
(1) Applicable Publications:
i. Qatar Construction Specifications, (QCS 2014, Section 11, Part 1.02), entitled “Occupational
Health and Hygiene (Regulatory Document)” as they relate to construction safety and health.
ii. Standards for Hazardous Air Pollutants.
c. AUAB Environmental Standards:
(1) Material Data Sheets, Preparation and the Submission to the CEI environmental office on this installation.
(2) Use of Asbestos Containing Material or any Class 1 ozone depleting chemical compounds are prohibited.
27. COORDINATION REQUIREMENTS:
a. Excavation Requirements:
(1) Work Clearance Request: Forty-five days prior to commencing work on an individual TO, the Contractor shall prepare and coordinate an AF Form 103, Work Clearance Request, with drawings indicating where the existing subsurface improvements are in the area and specific excavation and trenching locations widths and depths. The Government will provide information on which offices on AUAB must coordinate on the AF Form 103.
The Contractor shall hand carry the AF Form 103 to the coordinating offices and get their approval signatures. A copy of the completed AF Form 103 shall be provided to the Government prior to the Contractor requesting utility locates. A copy of the completed AF Form 103 shall be on the TO site for the duration of the TO.
(2) Utility Locates: The Contractor must contact each office on the approved AF Form 103 at least five (5) working days (WDs) prior to initiating excavation and trenching to arrange appointments to get utility spots at the site.