Attch_4_-_LittleRobberDam_SchedofItems_Final.pdf

PDF 6 KB Posted

Attached to
LITTLE ROBBER DETENTION DAM RECONSTRUCTION Federal contract opportunity
Solicitation number
140L0625B0005
Issued by
Department of the Interior Bureau of Land Management National Office

About this file

This document is a Bid Schedule for the Little Robber Dam Reconstruction project, detailing 22 line items for various construction activities. The schedule includes quantities and units for work such as mobilization, excavation, embankment, riprap replacement, outlet works, and drainage systems. Key quantitative details include 46,661 cubic yards of common excavation, 47,303 cubic yards of compacted embankment, 6,800 tons of new spillway riprap, and several lump sum (LS) items for structures and preparatory work. The schedule notes that quantities are not guaranteed, with measurement and payment defined in Section 01150, and provides spaces for unit pricing and total bid price calculation.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item

No. Description Unit Price Total Price

1 Mobilization and Preparatory Work 1 LS

2 Clearing, Topsoil Stripping & Restoration 1 LS

3 Existing Structures Demolition 1 LS

4 Common Excavation 46,661 CY

5 Muck Excavation 2,500 CY

6 Compacted Embankment 47,303 CY

7 Lime Amended Embankment 3,870 CY

8 Spillway Excavation 9,780 CY

9 Spillway Fill 2,800 CY

10 Filter Sand 4,483 CY

11 Drain Gravel 400 CY

12 Road Gravel 370 TON

13 Outlet Works Tower and Inlet Structure 1 LS

14 Outlet Works Conduit 1 LS

15 Stilling Basin 1 LS

16 Salvage and Replace Embankment Riprap 2,030 CY

17 Salvage and Replace Spillway Riprap 2,972 CY

18 New Spillway Riprap 6,800 TON

19 New Embankment Riprap 3,079 TON

20 Water Control/Dewatering 1 LS

21 Toe Drain System 1 LS

22 Geotextile Fabric 500 SY

Total Bid (words):

*Quantities are not guaranteed. Measurement and payment for each Bid Item is defined in Section 01150, Measurement and

Payment.

LITTLE ROBBER DAM RECONSTRUCTION

SCHEDULE OF ITEMS

Quantity*

TOTAL BID PRICE

\\dowl.com\j\Projects\31\28008-01\81Specs\BidForm.xlsx

BID SCHEDULE

File details come from the government source that posted it. Updated .