Attch 19 Rapid Response and Special Projects Guidance.pdf

PDF 140 KB Posted

Attached to
Manufacturing Technology (ManTech) Composites Manufacturing Technology Center 6 (CMTC 6)
Solicitation number
N0001425R7004
Issued by

About this file

This document is a Rapid Response and Special Projects Guidance document for the Navy ManTech Program, outlining procedures for short-term, low-dollar value technology projects within the Office of Naval Research (ONR) Center of Excellence (COE) prime contracts. The guidance establishes criteria for two project types: Rapid Response and Special Projects, each with specific requirements including a maximum funding level of $200,000, duration of 6 months or less, and written authorization from the Program Officer/Contracting Officer Representative.

The document details the submission process for these projects, requiring both a technical proposal (including background, objectives, statement of work, project schedule, and deliverables) and a cost proposal using ONR cost spreadsheet formats. Projects will be tracked at the ManTech project level, with the Contracting Officer adding the project to the appropriate Task Order via contract modification. Notably, these projects are designed to address unplanned manufacturing, sustainability, or repair issues, offer rapid technology insertion, and provide a mechanism to leverage existing expertise without initiating a separate contract action.

View the file

Other files

File Type Posted
Solicitation - N0001425R7004.pdf PDF
Attch 21 Technology Transition Plan Guidance.pdf PDF
Attch 23 CDRL Instructions for Distribution.pdf PDF
Attch 22 Trip Report Guidance.pdf PDF
Attch 7 COE Transition Implementation Guidance.pdf PDF
Attch 15 Project Quad Chart Guidance.pdf PDF
Attch 24 Cost Proposal Cost Plus Fixed Fee.xlsx XLSX spreadsheet
Attch 17 Public Release Request Tool Guidance.pdf PDF
Attch 14 Project Briefing Guidance.pdf PDF
Attch 20 Success Story Guidance.pdf PDF
RFP Exhibit B Project CDRLS.pdf PDF
Attch 12 Navy ManTech Code 33 Monthly Report Guidance.pdf PDF
Attch 6 Benefits and ROI Guidance.pdf PDF
Attch 26 Q and A Template.xlsx XLSX spreadsheet
Attch 3 Navy ManTech Program Annual Data Call.pdf PDF
Attch 25 Cost Information.pdf PDF
Attch 8 Final Report Guidance.pdf PDF
Attch 1 Statement of Work.pdf PDF
Attch 13 Project Book Guidance.pdf PDF
Attch 2 Affordability Assessment Guidance.pdf PDF
Attch 9 Funding Allocation Spreadsheet Guidance.pdf PDF
Attch 18 Quarterly Report Guidance.pdf PDF
RFP Exhibit A COE CDRLS.pdf PDF
Attch 11 Key Personnel.pdf PDF
Attch 16 Proposal Pipeline and ONR Contracts Actions Spreadsheet Guidance.pdf PDF
Attch 4 Annual Review Project Briefing Template.pdf PDF
Attch 5 Annual Portfolio Review Form.xlsx XLSX spreadsheet
Attch 10 Implementation Risk Assessment Guidance.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Navy ManTech Program

REV G OCT24

Rapid Response and Special Projects Guidance

Attachments:

1. None.

A. PURPOSE

The purpose of the Rapid Response and Special Projects guidance is to establish a framework to address individual projects under the Office of Naval Research (ONR) Center of Excellence (COE) prime contracts that can be delivered within a shortened timeframe. Both Rapid Response and Special Projects efforts enable a problem to be addressed through access to existing expertise without expending the time and effort to initiate a separate contract action.

Of shorter duration and lower dollar value than standard ManTech projects, Rapid Response projects offer increased potential for rapid technology insertion to meet Department of Navy (DON) platform needs in accordance with Department of Defense (DoD) Directive 4200.15. With minimal time and funding, a COE should be able to resolve an issue in a timely manner. Special Projects are other short-term, low-dollar value efforts, not necessarily connected with an acquisition or repair Program Office, to further evaluate technical issues related to DON manufacturing.

B. CRITERIA

A Rapid Response effort should address unplanned manufacturing, sustainability, or repair issues from fleet or production programs that can benefit from the expertise of the COEs.

In general, a proposed Rapid Response project should satisfy the following criteria:

• Acknowledgement of the problem by the appropriate stakeholder

• Clearly defined statement of work

• Implementation strategy by the stakeholder if the project is successful

• Funding level of $200K or less

• Duration of 6 months or less

• The project should be coordinated with the applicable Program Executive Office or Program Office prior to authorization.

• Written authorization is required from the Program Officer (PO) / Contracting Officer Representative

(COR) to the COE to pursue the issue of the project.

A Special Project should satisfy the following criteria:

• Clearly defined statement of work

• Address a legitimate manufacturing technology issue which will ultimately benefit the Navy but does not need to have a direct transition at this time

• Funding level of $200K or less

• Duration of 6 months or less

• Written authorization is required from the PO / COR to the COE to pursue the issue of the project.

• Examples include, but are not limited to, manufacturing trade studies, benchmarking activities, build strategy development, etc.

Rapid Response / Special Project funds should not be used to accomplish the initial phase of a typical or normal project, or be used for a normal project simply because it does not require a large budget. In addition, Rapid Response / Special Project funding is not intended to be a catch-all accounting line to be used for a variety of different charges.

Navy ManTech Program

REV G OCT24

C. RAPID RESPONSE / SPECIAL PROJECTS SUBMITTAL AND PROCESSING

The instructions below outline the submission requirements and process for a Navy ManTech Rapid Response or Special Project effort.

1. Technical Proposal:

• Background

• Objective

• Requirements and Timelines for Transition

• Statement of Work

• Contract Data Requirements List (CDRL)

• Project Schedule

• Project Specific Deliverables

• Statement on how the COE will ensure completion without an increase in scope, schedule, or cost

2. Cost Proposal:

• Cost Spreadsheets in the ONR format is required for prime and subcontractors (if utilized).

The COE will submit individual project proposals to the respective ONR PO / COR. The PO / COR will review the proposal, ensure that it meets the requirements to establish a Rapid Response or Special Project and validate that the scope, cost, and period of performance are within the requirements of the applicable Task Order statement of work. The PO / COR will email the documents to the CO and indicate his concurrence to initiate the Rapid Response or Special Project effort. It is expected that these efforts will have an appropriate award type (i.e., Firm Fixed Price, Cost Plus Fixed Fee, etc.). The CO will add the Rapid Response or Special Project to the appropriate Task Order via contract modification.

D. REPORTING

Rapid Response, Repair Technology Rapid Response, and Special Project efforts are to be tracked at a ManTech project level for reporting purposes. Projects should fulfill all applicable ManTech Data Call Requirements (see the Project Types - Data Call Requirements table) at an appropriate level for the level of effort and at the discretion of the PO / COR. Note that Rapid Response and Repair Technology Rapid Response projects do not require Technology Transition Plans or risk assessments.