AttachmentM_CI5702_ConceptualDesign_251024.pdf
PDF 3 MB Posted
- Attached to
- Power Backup at Lang Ranch Pump Station
- Solicitation number
- CI 5702
- Issued by
- Ventura County, California
About this file
This document is a Conceptual Design attachment for the City of Thousand Oaks' CI 5702 Power Backup project at the Lang Ranch Pump Station. The project involves upgrading the electrical infrastructure with new power backup systems, including a 200kW/250kVA standby diesel generator, a 500kWh Battery Energy Storage System (BESS), and a new 600A switchboard. The design aims to ensure continuous electrical power for the pump station by implementing redundant power sources and improving the existing electrical distribution system.
The conceptual design includes removing existing electrical cables and infrastructure, installing a new switchboard with remote close/open capabilities, and integrating a standby generator and battery storage system. The project will require coordination with Southern California Edison (SCE) for closed-transition and islanding requirements. The design-builder will be responsible for determining the precise kilowatt ratings to ensure proper pump operation and developing a functional design based on the conceptual drawings. The single-line diagrams provide technical details of the existing and proposed electrical system, highlighting the integration of new power backup equipment at the Lang Ranch Pump Station.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT M – CONCEPTUAL DESIGN
CI 5702 – POWER BACKUP AT LANG RANCH PUMP STATION
rr======:--, \ I r- -- , \ / Q __ ---- 1r-----lJ I
\ I \ I \ I \ I \ - 1- \ I\ I \ I \ I
I \
Know what's below.
Call before you dig.
CALL 811
AT LEAST TWO DAYS
BEFORE YOU DIG
UNDERGROUND SERVICE ALERT OF SOUTHERN CALIFORNIA
I
I
I
I
I
I
I
I
I
I
I
I
I
I
' ' RESEJ..,.VOIR '
' \-<: I
', I ', I
', I ' ,_ i I
' , I-------------------------------------------------------------------------➔f------------------------------------------------------------------------- ----
,/ I
I
I
/ I
/ I
/ I
/ I
/ I
/ I
(E) MET E
) cc
DATE_-_ _ PREPARED BY
DESIGNED
DATE_-__ KEWO
l----+---+------------------------1-------+-----1-------+------1 DRAFTED BY -IK:C ENGINEERING
CORPORATION
0 CONCEPTUAL DESIGN NOT FOR CONSTRUCTION
REV. SYMBO DESCRIPTION OF CHANGE
DATE_-__
10110/25
R.C.E. DATE C.T.O. DATE CHECKED
CITY OF THOUSAND OAKS
REVIEWED BY:
PROJECT ENGINEER
REVIEWED BY:
ENGINEERING DIVISION MANAGER
APPROVED BY:
TED GERBER, CITY ENGINEER
DATE
DATE
DATE
(E) SCE TRANSFORMER
(N) SWITCHBOARD
(N) BESS
(N) DIESEL GENERATOR
� 1�
''°----210
____....,_ SCALE: 1" = 10'
CITY OF THOUSAND OAKS
Cl 5702 POWER BACKUP AT LANG RANCH PUMP STATION
EQUIPMENT LAYOUT
CITY OF THOUSAND OAKS DWG. __ _ SHEET 2 OF 4
I
Know what's below.
Call before you dig.
CALL 811
AT LEAST TWO DAYS
BEFORE YOU DIG
UNDERGROUND SERVICE ALERT OF SOUTHERN CALIFORNIA
'- ' ------- - - ------- - --- - ------- - --------- - - ----- ----- ------➔f--
DESIGNED
DATE_-__
L_J_ __ L---------------------+------11----t---l---- DRAFTED BY
0 CONCEPTUAL DESIGN NOT FOR CONSTRUCTION
REV. SYMBO DESCRIPTION OF CHANGE
DATE_-__
10110/25
R.C.E. DATE C.T.O. DATE CHECKED
-IK:C
KEWO
ENGINEERING
CORPORATION
REVIEWED BY:
PROJECT ENGINEER
REVIEWED BY:
ENGINEERING DIVISION MANAGER
APPROVED BY:
TED GERBER, CITY ENGINEER
DATE
DATE
DATE
) S:22.[[C BOARD
Cl 5702 POWER BACKUP AT LANG RANCH PUMP STATION
EQUIPMENT LAYOUT
CITY OF THOUSAND OAKS DWG. SHEET 3 OF 4
Know what's below.
Call before you dig.
CALL 811
AT LEAST TWO DAYS
BEFORE YOU DIG
UNDERGROUND SERVICE ALERT OF SOUTHERN CALIFORNIA
SCE UTILITY SERVICE
16.34 KV
SCE XFMR -----1
150KVA , I
16.34KV-480/277V I
Z=3.1%
#5574025
'------� --- G)
SCE UTILITY SERVICE
16.34 KV
0 (N) SWBD, 600A, 480/277V, 3PH-4W, 65KAIC
SCE XFMR -----· ----1
150KVA ,
16.34KV-480/277V
Z=3.1% #5574025
- I
'------- ____ _j r·-·-·-·7·------------T·---------------------------------------·-·r·-·-·---uGPs , MTR & MAIN , DISTRIBUTION , I
300A
3P , I I I
300A
3P
I
1·-· - ■-
. I ! MPG j ! 1201208V j I , 1:.11:::i: ! ·-- _ _I
(E) MCC, 600A, 480/277V, 3PH-4W, 65KAIC
- , r --------------------------------
I I
MOBILE r·-··;·---.
GENERATOR i ) i
277/480V, 3PH 4W �©-!
! G !
I I
(E) MCC, 600A, 277/480V, 3PH-4W, 65KAIC
AIR
COMP.
PUMP
P-1
PUMP
P-2
------,----------r-----------------------------------------------
I I r-·-·-·:, l���K )
L)1: ! j KEY JOOA r-· ·-
I , INTLK 3P 3KVA �r,�.� • I
• I XFMR ' v v ' ! PNL A j ! j '------
480V-120/240V ! 1201240V j I • 1 PHASE · I I j I.-· __ _,: I
15A 3P
'125A ) 3P
125A
3P
@ EQUIPMENT
1. (E) MCC, 600A, 480/277V, 3PH-4W, 65KAIC
2.
- REMOVE NEUTRAL-GROUND BONDING JUMPER.
- SCE TO REMOVE EXISTING METER.
(E) GENERATOR PLUG
ARKTITE #AP40458, 400A, 4W, 4P
- UTILIZE PORTABLE GENERATOR TO MAINTAIN
ELECTRICAL POWER TO FACILITY DURING
CONSTRUCTION.
@ CONDUITS & CABLES
1. REMOVE EXISTING CABLES BETWEEN SCE
TRANSFORMER AND MCC. INTERCEPT CONDUITS
FOR NEW SWITCHBOARD.
DEMOLITION SINGLE LINE DIAGRAM 1
@ EQUIPMENT
1. (N) SWITCHBOARD
600A, 480/277V, 3PH-4W, 65KAIC
- REMOTE CLOSE/OPEN MAIN CIRCUIT BREAKER
- COORDINATE WITH SCE FOR
CLOSED-TRANSITION AND ISLANDING
REQUIREMENTS.
2. (N) STANDBY DIESEL GENERATOR
200KW/250KVA, 0.8PF, 480/277V, 3PH-4W
- DESIGN-BUILDER SHALL DETERMINE KW RATING
AND ENSURE PUMPS CAN BE STARTED ON WITH
GENERATOR
- WEATHER PROTECTED ENCLOSURE
SEISMIC BRACING.. ____ ·-·- -·-·-·- j.i_B_·-·-·-··""·-·-·-·-·-·-·-·-·-·-·-·-·-·-•-·-·-·-·- -·-
----__ : _____ -b ---- -------------------------------------------
,. 1 60 60
PARALLELING CONTROLS
- MOTORIZED CIRCUIT BREAKER
SYNCHRONIZING
.• 'r-----------J ----------, 7 r-'-··-i @ , , , ,. . ,-{ 1' I '
: I , • • ,6. �©-: (N)STANDBY GENERATOR
I i I . . DIESEL : • ----,-----' ! G ! 200KW/250KVA ·-·---1-·, ·-·-·-· ,., ___ ,_ I I 277/480V 3PH 4W I • I • • '
I j PROT. & , j , MICROGRID i- - - � ! CONT. j L _______ .
(N) BESS
500KWH
DATE_· _ _
DESIGNED
DATE_-__
l----+---+------------------------1-------+-----1-------+------1 DRAFTED BY
0 CONCEPTUAL DESIGN NOT FOR CONSTRUCTION
RE V. SYMBOL DESCRIPTION OF CHANGE R.C.E. DATE C.T.O.
DATE_-__
10110/25
DATE CHECKED
PREPARED BY
-IK:C
MOBILE r·-·-0 ----.
GENERATOR i ) !
277/480V, 3PH 4W
•@I
KEWO
ENGINEERING
CORPORATION
! G !
I I
CITY OF THOUSAND OAKS
REVIEWED BY:
PROJECT ENGINEER
REVIEWED BY:
ENGINEERING DIVISION MANAGER
APPROVED BY:
TED GERBER, CITY ENGINEER
HP HP HP
AIR PUMP PUMP
COMP. P-1 P-2
DATE
LOAD SHARING
3. (N) BATTERY ENERGY STORAGE SYSTEM
S00KWH, 480/277V
- DESIGN-BUILDER SHALL DETERMINE KW RATING
AND ENSURE PUMPS CAN BE STARTED WITH BESS.
NOTES:
1. SINGLE LINE DIAGRAM IS CONCEPTUAL AND SHALL
BE USED ONLY FOR REFERENCE. DESIGN-BUILDER
IS RESPONSIBLE FOR DEVELOPING FUNCTIONAL
DESIGN.
NEW SINGLE LINE DIAGRAM 2
CITY OF THOUSAND OAKS
DATE
Cl 5702 POWER BACKUP AT LANG RANCH PUMP STATION
SINGLE LINE DIAGRAM
DATE CITY OF THOUSAND OAKS DWG. __ _ SHEET 4 OF 4
File details come from the government source that posted it. Updated .