AttachmentG_ConstructionGeneralSpecifications.pdf

PDF 2 MB Posted

Attached to
Power Backup at Lang Ranch Pump Station
Solicitation number
CI 5702
Issued by
Ventura County, California

About this file

This document is a compilation of Construction General Specifications for the City of Thousand Oaks' Power Backup at Lang Ranch Pump Station project (CI 5702). The specifications cover multiple divisions and sections of construction requirements, including coordination, project meetings, scheduling, abbreviations, reference standards, quality control, temporary utilities, site access, environmental controls, materials and equipment handling, site safety, construction surveying, protection of existing facilities, construction waste management, and project closeout. The documents outline comprehensive administrative and technical requirements for the contractor, detailing expectations for project management, safety protocols, documentation, waste management, and final project completion procedures.

The specifications establish precise guidelines for contractor responsibilities, including maintaining project records, managing subcontractors, protecting existing facilities, implementing waste reduction strategies, and ensuring compliance with local and state regulations such as CalGreen and City of Thousand Oaks Municipal Codes. The documents require the contractor to develop detailed waste management plans, achieve a minimum 65% waste diversion rate, submit regular progress reports, maintain safety standards, coordinate with utility agencies, and complete extensive documentation prior to project closeout. The specifications also outline requirements for technical manual submissions, final cleanup, correction and repair protocols, and the process for release of contract retention payments.

View the file

Other files

File Type Posted
Power_Backup_at_Lang_Ranch_Pump_Station_(Addendum_#2_Revision).pdf PDF
Power_Backup_at_Lang_Ranch_Pump_Station.pdf PDF
RFPQ_CI_5702_Power_Backup_at_Lang_Ranch_Pump_Station_Notice.pdf PDF
RFPQ_CI_5702_Power_Backup_at_Lang_Ranch_Pump_Station_Notice.pdf PDF
AttachmentI_FEMA_Requirements.pdf PDF
AttachmentI_FEMA_Requirements.pdf PDF
AttachmentG_ConstructionGeneralSpecifications.pdf PDF
AttachmentN_Photos.pdf PDF
AttachmentN_Photos.pdf PDF
AttachmentB_CI5702_ScopeOfWork_.pdf PDF
AttachmentK_TechnicalSpecs.pdf PDF
AttachmentB_CI5702_ScopeOfWork_.pdf PDF
AttachmentK_TechnicalSpecs.pdf PDF
AttachmentF_DesignGuidelines_.pdf PDF
AttachmentF_DesignGuidelines_.pdf PDF
AttachmentC_AsBuiltDrawings.pdf PDF
AttachmentE_GeneralConditions_.pdf PDF
AttachmentC_AsBuiltDrawings.pdf PDF
AttachmentE_GeneralConditions_.pdf PDF
AttachmentH_SampleAgreement.pdf PDF
AttachmentH_SampleAgreement.pdf PDF
AttachmentA_CI_5702_VicinityLocationMaps.pdf PDF
AttachmentA_CI_5702_VicinityLocationMaps.pdf PDF
AttachmentM_CI5702_ConceptualDesign_251024.pdf PDF
AttachmentM_CI5702_ConceptualDesign_251024.pdf PDF
AttachmentJ_Performance_PaymentBonds.pdf PDF
AttachmentD_ElectricityBills.pdf PDF
AttachmentL_PowerIntervals.csv CSV file
AttachmentJ_Performance_PaymentBonds.pdf PDF
AttachmentL_PowerIntervals.csv CSV file
AttachmentD_ElectricityBills.pdf PDF
General_Services_Agreement_Template_Revision_9.18.23.docx DOCX document
General_Services_Agreement_Template_Revision_9.18.23.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT J – PERFORMANCE AND PAYMENT BONDS

ATTACHMENT G – CONSTRUCTION GENERAL SPECIFICATIONS

CI 5702 – POWER BACKUP AT LANG RANCH PUMP STATION

DIVISION 01 – CONSTRUCTION GENERAL SPECIFICATIONS

TABLE OF CONTENTS:

Spec # Spec Name 01 31 13 – Coordination 01 31 19 – Project Meetings 01 32 13 – CPM Schedule 01 42 13 – Abbreviations 01 42 19 – Reference Standards 01 45 00 – Quality Control 01 51 00 – Temporary Utilities 01 55 00 – Site Access and Parking 01 56 00 – Temporary Environmental Controls 01 60 00 – Materials & Equipment 01 65 00 – Delivery, Storage, and Handling 01 71 19 – Site Safety Plan 01 71 23 – Construction Surveying 01 71 33 – Protection of Existing Facilities 01 74 19 – Construction Waste Management 01 77 00 – Project Closeout

City of Thousand Oaks COORDINATION CI 5702 – Power Backup at Lang Ranch Pump Station 01 31 13

SECTION 01 31 13

COORDINATION

1.01 GENERAL

The Contractor shall be responsible for all Project coordination and the coordination of the work of all subcontractors, fabricators, utility agencies, inspectors and suppliers. Coordination, as referred to herein, shall include the establishment of on-site lines of authority and communication and the scheduling of and conducting of progress meetings between the City’s Project Manager and the Contractor and its subcontractors, fabricators, utility agencies, inspectors and suppliers. The Contractor's onsite supervisory person shall be present and shall represent the General Contractor whenever a meeting is held that involves any interface between the Engineer or the City and any subcontractors, fabricators, or suppliers.

1.02 ARRANGEMENTS FOR TEMPORARY CONSTRUCTION FACILITIES

The Contractor shall be responsible for the allocation of space for temporary structures furnished by its subcontractors; monitoring the use of temporary utilities; verification that adequate services are provided to comply with requirements for Work and climatic conditions; and the administration of traffic and parking controls. All such work shall be in strict conformance with all applicable requirements of the Contract Documents.

1.03 COST CONTROL

A. The Contractor shall review and refine the approved estimate of construction cost and shall monitor and record actual costs and estimates for uncompleted Work, including that of all subcontractors, fabricators, and suppliers. All approved changes shall be incorporated as they occur.

B. In addition, the Contractor shall be responsible for the following:

1. Maintain cost accounting records for authorized Work performed under unit costs, actual costs for labor and materials, and other basis requiring accounting records.

2. Develop and implement procedure for review and processing of applications for progress and final payments: Submit recommendations to the City’s Project Manager for certification to the City for Payment.

1.04 GENERAL COORDINATION

A. All Work covered in the Contract Documents shall be coordinated as a part of the Contractor's obligations under the Contract.

B. The Contractor shall assure timely fabrication of work, erection of work, and completion of closeout items and the timely preparation of shop drawings and other submittals in conformance with the approved construction schedule.

C. The Contractor shall coordinate the efforts of all individuals and subcontractors in the execution of the Work.

D. City shall not be responsible for any lost/waiting time costs or schedule impacts resulting from lack of timely coordination by Contractor

1.05 SPECIAL COORDINATION

A. Drawings showing the location of equipment, piping, ducts, etc., are diagrammatic only. Even though every effort has been made to provide adequate routing and placement, job conditions will not always permit their locations in the field where indicated on the drawings. Whenever this condition is encountered by the Contractor, he or she shall notify the City’s Project Manager immediately to obtain the determination of any necessary relocation.

Minor adjustments in locations, or rerouting due to ill-timed or improper sequence of trades shall be the responsibility of the Contractor and shall be performed at no additional cost to the City.

B. The Contractor shall provide advance notification to the City’s Project Manager of specific tasks and inspections specified. Failure to provide such advance notification may be cause for rejection of the Work.

C. Wherever prefabricated items are to be incorporated into the Work, the Contractor shall use templates and shall set fasteners accurately to the templates.

D. Contractor shall coordinate with the existing property owners and tenants for those properties where the Contract Documents show work to be performed on private property. The City will secure the permanent utility easements required for said locations, however it is the Contractor’s responsibility to coordinate for onsite access and scheduling to minimize impact with said properties.

E. All dimensions shall be verified to assure that all components will fit together properly. Particular care shall be exercised to assure workability, access, symmetry, and alignment of components. Whenever the Contractor is in doubt of the intended effect of the Contract Documents, a request for information or clarification shall be tendered in writing to the City’s Project Manager prior to layout of building elements.

1.06 COORDINATION OF SUBCONTRACTOR RESPONSIBILITIES

The Contractor shall be responsible for coordination of the work of each of its subcontractors and suppliers. Special attention is directed to the following obligations of the Contractor:

1. Verify that subcontractors have obtained permits for inspections.

2. Review all subcontractor shop drawings, product data, and sample submittals for compliance with Contract Documents prior to submittal to the City’s Project Manager for general review for compliance with design intent.

3. Maintain onsite documentation and keep current record drawing set at

Project site.

4. Verify that specified cleaning is done during progress of Work and at completion of each subcontract.

1.07 CLEARANCES FOR EQUIPMENT AND SYSTEMS

A. Adequate clearance shall be provided by the Contractor between architectural, structural, plumbing, fire sprinkler, HVAC, electrical, and other utility systems.

B. Drawings shall be reviewed by the Contractor for possible conflicts prior to roughing in. All access routes through concealed spaces shall be checked.

C. The Contractor shall be responsible for verification that equipment and systems will fit in the spaces provided. All conflicts shall be resolved in cooperation with the City’s Project Manager prior to rough-in.

D. Work already installed that requires re-routing or modification due to conflicts with other work shall be corrected at the Contractor's expense. Piping ducts and conduits shall be held as possible to the structure above to provide for designed ceiling heights and clearances.

END OF SECTION

City of Thousand Oaks PROJECT MEETINGS CI 5702 – Power Backup at Lang Ranch Pump Station 01 31 19

SECTION 01 31 19

PROJECT MEETINGS

A. The Contractor, along with the Contractor's Superintendent or on-site Project Manager and its safety representative, as a minimum, shall attend all meetings scheduled by the City’s Project Manager for coordination and collection and dissemination of information related to the Work.

B. The City’s Project Manager will prepare the minutes of each meeting and will distribute them to each of the participants.

C. The Contractor shall notify the City’s Project Manager of all proposed safety meetings. The City’s Project Manager will advise the Contractor about contract-related safety information, safety meetings, and safety-related issues.

1.02 PROJECT MEETINGS

A. Preconstruction Conference: Prior to the commencement of Work at the site, a Preconstruction conference will be held at a mutually agreed upon time and place which shall be attended by the Contractor, its superintendent, and its subcontractors as appropriate. Other attendees will be:

1. City’s Project Representative / Inspector.

2. Representatives of City.

3. Governmental representatives as appropriate.

4. Utility Agencies, as required

5. Others as requested by Contractor, or City.

B. Unless previously submitted to the City’s Project Manager, the Contractor shall bring to the conference one copy each of the following:

1. Tentative Construction Schedule.

2. Procurement schedule of major equipment and materials and items requiring long lead-time.

3. Shop Drawing/Sample/Substitute or "Or Equal" submittal schedule.

4. Schedule of values (lump sum price breakdown) for progress payment purposes.

City of Thousand Oaks PROJECT MEETINGS CI 5702 – Power Backup at Lang Ranch Pump Station 01 31 19

C. The purpose of the conference is to designate responsible personnel and establish a working relationship. Matters requiring coordination will be discussed and procedures for handling such matters established. The complete agenda will be furnished to the Contractor prior to the meeting date, which may include the following:

1. Contractor's tentative schedules.

2. Transmittal, review, and distribution of Contractor's submittals.

3. Processing applications for payment.

4. Maintaining of record documents.

5. Critical work sequencing.

6. Field decisions and Change Orders.

7. Use of project site, office and storage areas, security, housekeeping, and City's needs.

8. Major equipment deliveries and priorities.

9. Contractor's assignments for safety and first aid.

D. The City’s Project Manager will preside at the preconstruction conference and will arrange for keeping the minutes and distributing the minutes to all persons in attendance.

E. Progress Meetings: The Contractor shall attend and participate in regular on-site progress meetings at least weekly and at other times or frequencies as determined by City’s Project Manager. The Contractor, City’s Project Manager, and all subcontractors active and soon to be active on the site shall be represented at each meeting. Contractor may, at its discretion, request attendance by representatives of its suppliers, manufacturer's, and other subcontractors. The purpose of the meetings will be to review the progress of the Work maintain coordination of efforts, discuss changes in scheduling, and resolve other problems which may develop.

F. Contractor is required to submit the 3-week lookahead schedule no later than

24 hours prior to the weekly progress meeting. The 3-week lookahead schedule shall at a minimum show actual performance for the previous week, as well as planned work for the current week and planned work for the two successive weeks following the current week. Any changes or updates to the 3-week lookahead shall be communicated to the City, with the schedule updated 24 hours prior to the affected work sequences taking place.

City of Thousand Oaks CPM CONSTRUCTION SCHEDULE CI 5702 - Power Backup at Lang Ranch Pump Station 01 32 13

SECTION 01 32 13

CPM CONSTRUCTION SCHEDULE

A. The project management scheduling tool "Critical Path Method," a network scheduling system commonly called CPM, shall be employed by the Contractor for cost reporting, planning, and scheduling, of all work required under the Contract Documents. All schedule reports shall be in the form of electronic PDF and in native electronic format. The Contractor may elect to use bar charts (Gantt Charts) as an onsite scheduling tool; provided that all such bar charts shall be generated from the approved CPM network using the same computer program as used for the CPM network and reports submitted to the Project Manager.

B. The schedule shall clearly identify all staffing and other resources which in the Contractor’s judgment are needed to complete the Work within the Contract Time. The schedule shall clearly state the number of staff to be used on each daily segment of the Work. Schedule duration shall match the Contract Time.

C. Contractor’s schedule shall be based upon the inclusion of the required number of days of inclement weather and/or rain days to be included, within the specified overall duration of the project as stipulated in the Summary of Work 01 11 00, as well as accommodate all holidays that fall within the base contract duration.

D. Contractor’s Schedule shall incorporate sufficient time at the end for final closeout and completion of punchlist, as part of the base duration within the specified overall duration of the project.

E. Summary of types and schedule submittals required:

1. Preliminary Construction Schedule: Submit within 10 days after date of Notice of Award, a detailed breakdown of Proposed Construction Schedule for review;

2. Initial Construction Schedule: Submit within 14 days of date of Notice to Proceed (See Submittals Section for more details) a Revised version of the Preliminary Schedule, incorporating all of the Project Manager’s comments. Upon Project Manager approval, this will become the Initial “Baseline” Construction Schedule for the project until a revised schedule is required to be submitted; and,

3. Revised Construction Schedules: Updated revisions of the Initial

Construction Schedules as required by the Project Manager shall be submitted with each progress payment.

1.02 QUALIFICATIONS

A. The Contractor shall ensure that their organization has in-house capability qualified to prepare and use the CPM scheduling technique, or the Contractor will employ a CPM consultant who is so qualified.

1.03 SUBMITTAL PROCEDURES

A. Time of submittals: Within 10 days after the Notice of Award, the Contractor shall submit for acceptance by the Project Manager a Preliminary Construction Schedule, a detailed schedule which shall consist of a network diagram and CPM Schedule describing the work activities and procurement to be accomplished in the project, their dependency relationships and schedule reports (as defined following). The schedule produced shall indicate a project completion date on or before the contract completion date. The Project Manager shall meet with the Contractor to review the proposed plan and schedule within 14 days after receipt of the Preliminary Construction Schedule.

B. Within 14 days after the conclusion of the Project Manager’s review of the

Preliminary Construction Schedule, the Contractor shall revise the network diagram as required and re-submit the network diagram and the schedule reports produced therefrom. The revised network diagram and schedule reports shall be revised and approved or rejected by the Project Manager within 14 days after receipt. The network diagram and schedule reports, when accepted by the Project Manager, shall constitute the Initial Construction Schedule until a Revised Construction Schedule is required to be submitted.

C. Acceptance: When the Initial Construction Schedule network diagram and schedule reports have been accepted by the Project Manager, the Contractor shall submit to the Project Manager the time-scaled network diagram in native electronic Microsoft Project 2010 or later format, as well as PDF, with the activities sorted by Early Starting Date and showing free float and total float.

D. Additional Network Diagrams: If requested by the Project Manager, Contractor shall provide revised network diagrams if, at any time, the Project Manager considers the completion date to be in jeopardy because of "activities behind schedule." The Additional Network Diagrams shall include a new arrow or precedence diagram and schedule reports conforming to the requirements of Paragraph entitled "CPM Standards," herein, designed to show how the Contractor intends to accomplish the Work to meet the completion date. The form and method employed by the Contractor shall be the same as that required for the original Initial Construction Schedule.

E. Schedule Revisions: The Contractor shall modify any portions of the construction schedule that become unfeasible because of "activities or procurement behind schedule" or for any other valid reason. An activity that cannot be completed by its original latest completion date shall be deemed to be behind schedule.

1.04 CHANGE ORDERS

Upon issuance of a Change Order or Work Directive Change, the approved change shall be reflected in the next submittal of the Revised Construction Schedule by the Contractor.

1.05 CPM STANDARDS

A. Definition: CPM scheduling, as required by this Section, shall be interpreted to be generally as outlined in the Associated General Contractors publication, "The Use of CPM in Construction," except that either arrow diagramming or activity-on-node precedence diagramming format is acceptable.

B. Construction Schedules: Construction schedules shall include a computer-generated graphic network and computerized, construction schedule reports, as described below.

C. Networks: The CPM scheduling network shall be in the form of a time-scaled arrow or precedence diagram, shall be of the customary activity-on-arrow or activity-on-node type, and may be divided into a number of separate pages with suitable notation relating the interface points among the pages. Notation on each activity arrow shall include a brief work description and a duration estimate (see below). Precedence diagrams in box-node format are not acceptable.

D. All construction activities and procurement shall be indicated in a time-scaled format and a calendar scale shall be shown on all sheets along the entire sheet length. Each activity arrow or node shall be plotted so that the beginning and completion dates and free float time of said activity can be determined graphically by comparison with the calendar scale.

All activities shall be shown using the symbols that clearly distinguish between critical path activities, non-critical activities, and free float for each non-critical activity. All non-critical path activities shall show estimated performances time and free float time in scaled form.

E. Duration Estimates: The duration estimate indicated for each activity shall be computed in working days, converted to calendar days, and shown on the construction schedule in calendar days, and shall represent the single best estimate considering the scope of the Work and resources planned for the activity. Except for certain non-labor activities, such as curing concrete, paint drying, procurement, or delivering of materials, activity durations shall not exceed 10 working days (14 calendar days) or be shown in increments of less than 1 working day, unless otherwise accepted by the Project Manager.

F. The requirement for activity durations not in excess of 10 days shall apply to all schedule submittals except the Proposed Construction Schedule required to be submitted prior to the Notice to Proceed.

G. Schedule Reports: Schedule Reports shall be prepared from the Initial

Construction Schedule and from all subsequent Revised Construction Schedules, and shall include the following minimum data for each activity:

1. Activity Numbers or i-j Numbers.

2. Estimated Activity Duration.

3. Activity Description (including procurement items).

4. Early Start Date (Calendar Dated).

5. Early Finish Date (Calendar Dated).

6. Late Start Date (Calendar Dated).

7. Late Finish Date (Calendar Dated).

8. Status (Whether Critical).

9. Total Float for Each Activity.

10. Free Float for Each Activity.

H. Digital Format: The Contractor shall provide a copy of the Schedule Reports, sorted by activity number, including not less than Item Nos. 1 through 10, inclusive, of Paragraph F, above, on PDF as well as Native MS Project 2013 or later File Format.

I. Project Information: Each Schedule Report shall be prefaced with the following summary data:

1. Project Name.

2. Contractor Name.

3. Type of Tabulation (Initial or Revised; if revised, show a revision number or date).

4. Project Duration.

5. Project Scheduled Completion Date.

6. The date of commencement of Work as stated in the Notice to Proceed.

7. If an updated (revised) schedule, cite the new project completion date and current project status.

1.06 SCHEDULE REQUIREMENTS

The Contractor shall ensure that the following items are included and accommodated in the Initial Schedule, and subsequent schedule updates. The Initial Schedule shall not be approved as the Baseline Schedule until the all the items listed below as satisfactorily included in the schedule.

a. Ensure the submitted schedule incorporates all of the requirements of the specifications.

b. Ensures all the contract milestones, access restraints, shutdowns, permit dates and contract completion dates are consistent with the contract requirements.

c. Verify that the scope of work is completely reflected (all bid items are shown/included).

d. Verify activity durations are reasonable. Any activities longer than 14 calendar days in duration should be broken down into more detail, by location, etc.

e. Verify the overall sequencing, logic and approach makes sense. Physical constraints (i.e. foundations after excavation) and crew-based constraints need to be considered.

f. Include the required number of inclement weather days. These should be shown at the end of the schedule as a single task on the critical path, before the completion date.

g. Include procurement & submittal activities

h. Properly account for times of reduced productivity (i.e. holidays, CTO Alternate Fridays off)

i. Clearly define the critical path and ensure that it makes sense.

j. Verify that all activities are linked, and that there are no missing predecessors/successors. Forced end dates or activities without successors will not be allowed.

k. Verify activity durations are not inflated/excessively long.

l. Show sufficient detail to monitor complex/long duration items.

m. Include sufficient time for submittals, review, and procurement of the materials listed. Include adequate time for delivery of Owner-supplied materials and equipment or tie-ins.

n. Include listed activities for events performed by others, such as utilities or permit reviews.

o. Include sufficient time for punch list, cleanup, start-up, testing, final inspection and closeout as defined under specification 01 77 00 Project Closeout at the end of the schedule. Include them within the base duration.

p. Include adequate and reasonable resource loading with reasonable productivity.

q. Verify the resource loading is reasonable, and that crew sizes and resources are adequate to complete the project, with reasonable productivity.

1.07 CONSTRUCTION SCHEDULE MONITORING

A. At not less than monthly intervals, and when specifically requested by the Project Manager, the Contractor shall submit to the Project Manager a computer printout of a Revised Schedule Report for those activities that remain to be completed. At a minimum, revised Construction Schedules shall be submitted with each progress payment. Progress payments may be withheld if Contractor fails to provide schedule updates as noted above.

B. Each Revised Construction Schedule, including an updated network diagram, if required, shall be submitted in the form, sequence, and in the number of copies requested for the Initial Construction Schedule.

C. A final As-Built Schedule recording the completion of work activities shall be provided by the Contractor upon completion of Contract work along with the final billing. Final billing may be withheld if Contractor fails to provide the As-Built Schedule as noted above.

1.08 COST VALUE FOR ACTIVITIES

A. The Contractor shall establish a cost value for each activity in its CPM network so that monthly partial payments to the Contractor can be calculated on the basis of CPM-reported work in place. All cost value items shall be correlated with the line items of the required Schedule of Values.

B. Subject to the provisions of Article 41 of the General Conditions, all cost value reports for network activities shall be based upon the close of books as of the last day of the each month, and the computer printout report of such cost value for activities shall be submitted to the Project Manager for review and approval not later than the 10th day of the following month.

C. Where it is elsewhere provided in these Specifications that payments will be allowed for materials delivered to the site but not yet incorporated in the Work, separate pay items shall be established for such materials and for the furnishing and the installation of such items. Costs of such materials delivered to the site, but not yet incorporated into the Work, shall not be included in the cost value of the installation of such materials but shall be covered under a separate cost value report.

City of Thousand Oaks ABBREVIATION CI 5702 – Power Backup at Lang Ranch Pump Station 01 42 13

SECTION 01 42 13

ABBREVIATIONS

Wherever in these Specifications references are made to the standards, specifications, or other published data of the various national, regional, or local organizations, such organizations may be referred to by their acronym or abbreviation only. As a guide to the user, the following acronyms or abbreviations which may appear in these specifications shall have the meanings indicated herein.

1.02 ABBREVIATIONS AND ACRONYMS

AASHTO

ACI

AGC

AIA

AISC

AISI

ANSI

APWA

ASCE

ASME

ASQC

ASSE

ASTM

AWS

AWWA

BBC

BHMA

CLFMI

CMA

CRSI

EIA

ETL

ICBO

IEEE

IPCEA

ISA

ISO

MBMA

MPTA

NAAM

American Association of State Highway and Transportation Officials American Concrete Institute Associated General Contractors American Institute of Architects American Institute of Steel Construction American Iron and Steel Institute American National Standards Institute, Inc.

American Public Works Association American Society of Civil Engineers American Society of Mechanical Engineers American Society for Quality Control American Society of Sanitary Engineers American Society for Testing and Materials American Welding Society American Water Works Association Basic Building Code, Building Officials and Code Administrators International Builders Hardware Manufacturer’s Association Chain Link Fence Manufacturer's Institute Concrete Masonry Association Concrete Reinforcing Steel Institute Electronic Industries Association Electrical Test Laboratories International Conference of Building Officials Institute of Electrical and Electronics Engineers Insulated Power Cable Engineers Association Instrument Society of America International Organization for Standardization Metal Building Manufacturer's Association Mechanical Power Transmission of Association National Assn of Architectural Metal Manufacturer's

City of Thousand Oaks ABBREVIATION CI 5702 – Power Backup at Lang Ranch Pump Station 01 42 13

NACE

NBS

NEC

NEMA

NFPA

NGLI

OSHA

PCA

RWMA

SAMA

SI

SPR

SSBC

SSPC

SSPWC

UBC

UL

WCRSI

WRI

National Association of Corrosion Engineers National Bureau of Standards National Electrical Code National Electrical Manufacturer's Association National Fire Protection Association National Lubricating Grease Institute Occupational Safety and Health Administration Portland Cement Association Resistance Welder Manufacturer's Association Scientific Apparatus Maker Association International System of Units (Metric) (Système International d'Unités) Simplified Practice Recommendation Southern Standard Building Code, Southern Building Code Congress Steel Structures Painting Council Standard Specifications for Public Works Construction Uniform Building Code Underwriters Laboratories, Inc.

Western Concrete Reinforcing Steel Institute Wire Reinforcement Institute, Inc.

City of Thousand Oaks REFERENCE STANDARDS CI 5702 – Power Backup at Lang Ranch Pump Station 01 42 19

SECTION 01 42 19

REFERENCE STANDARDS

A. Titles of Sections and Paragraphs: Captions accompanying specification sections and paragraphs are for convenience of reference only, and do not form a part of the Specifications.

B. Applicable Publications: Whenever in these specifications references are made to published specifications, codes, standards, or other requirements, it shall be understood that wherever no date is specified, only the latest specifications, standards, or requirements of the respective issuing agencies which have been published as of the date that the Work is advertised for bids, shall apply; except to the extent that said standards or requirements may be in conflict with applicable laws, ordinances, or governing codes. No requirements set forth herein or shown on the drawings shall be waived because of any provision of, or omission from, said standards or requirements.

C. Specialists, Assignments: In certain instances, specifications test requires (or implies) that specific work is to be assigned to specialists or expert entities, who must be engaged for the performance of that work. Such assignments shall be recognized as special requirements over which the Contractor has no choice or option. These requirements shall not be interpreted so as to conflict with the enforcement of building codes and similar regulations governing the Work; also they are not intended to interfere with local union jurisdiction settlements and similar conventions. Such assignments are intended to establish which party or entity involved in a specific unit of work is recognized as "expert" for the indicated construction processes or operations.

Nevertheless, the final responsibility for fulfillment of the entire set of contract requirements remains with the Contractor.

1.02 REFERENCE SPECIFICATIONS, CODES, AND STANDARDS

A. The latest edition of the following standards shall be incorporated into the Contract Documents by Reference, and callouts the Contract Drawings:

1. City of Thousand Oaks Road Standards, latest edition

2. City of Thousand Oaks Water and Wastewater Standards, latest edition

3. Greenbook Standard Plans and Specifications for Public Works

Construction, latest edition (excluding all of Sections 1 through 8 inclusive)

4. Caltrans Standard Plans and Specifications, latest edition (excluding all of

Sections 1 through 9 inclusive)

5. MUTCD – Manual on Uniform Traffic Control Devices, latest edition

6. References herein to building codes shall mean the most current of the following listed codes, including all addenda, modifications, amendments, or other lawful changes thereto:

i. International Building Code, as published by the International Code

Council, Inc. (ICC)

ii. Uniform Plumbing Code, as published by the International Association of Plumbing and Mechanical Officials (IAPMO)

iii. Uniform Mechanical Code, as Published by the International

Association of Plumbing and Mechanical Officials (IAPMO)

iv. National Electric Code, as Published by the National Fire Protection Association (NFPA)

v. International Fire Code, as published by the International Code

Council, Inc. (ICC)

vi. California Administrative Code, Title 19 Public Safety, and Title 24

Building Standards

B. Without limiting the general provisions of other portions of the specifications, all work specified herein shall conform to or exceed the requirements of all applicable codes and the applicable requirements of the following documents to the extent that the provisions of such documents are not in conflict with the requirements of these Specifications nor the applicable codes.

C. In case of conflict between codes, reference standards, drawings and the other Contract Documents, the most stringent requirements shall govern. All conflicts shall be brought to the attention of the City for clarification and directions prior to ordering or providing any materials or labor. The Contractor shall bid the most stringent requirements.

D. Applicable Standard Specifications: The contractor shall construct the Work specified herein in accordance with the requirements of the Contract Documents and the referenced portions of those referenced codes, standards, and specifications listed herein; except, that whenever references to "Standard Specifications" are made, the provisions therein for measurement and payment shall not apply.

E. References in the Contract Documents to "Standard Specifications" shall mean the GREENBOOK Standard Specifications.

F. Applicable Standard Drawings: References herein to "Standard Drawings" shall mean the Standard Plans of the GREENBOOK Standard Specifications, which drawings are hereby incorporated in and made a part of these Contract Documents, and copies of which are included in Appendix A herein.

G. Applicable Safety Standards: References herein to "Cal-OSHA" shall mean

State of California, Department of Industrial Relations, Construction Safety Orders, as amended to Date, and all changes and amendments thereto which are effective as of the date of construction. References herein to "OSHA Standards" shall mean Title 29, Part 1910, Occupational Safety and Health Standards, Code of Federal Regulations (OSHA), including all changes and amendments thereto.

City of Thousand Oaks QUALITY CONTROL CI 5702 – Power Backup at Lang Ranch Pump Station 01 45 00

SECTION 01 45 00

QUALITY CONTROL

1.01 SITE INVESTIGATION AND CONTROL

A. The Contractor shall verify all dimensions in the field and shall check all field conditions continuously during construction. The Contractor shall be solely responsible for any inaccuracies built into the Work.

B. The Contractor shall inspect related and appurtenant work and shall report in writing to the Engineer any conditions that will prevent proper completion of the Work. Any required removal, repair, or replacement caused by unsuitable conditions shall be done by the Contractor at its sole cost and expense.

1.02 INSPECTION OF THE WORK

A. General: The Work shall be conducted under the general observation of the Engineer and shall be subject to inspection by representatives of the City to assure strict compliance with the requirements of the Contract Documents.

B. The authorized representative of the Engineer on the project site shall be the Resident Project Representative acting directly and through various inspectors at the site. The presence of the Inspectors, however, shall not relieve the Contractor of the responsibility for the proper execution of the Work in accordance with all requirements of the Contract Documents. Compliance is distinctly a duty of the Contractor, and said duty shall not be avoided by any act or omission on the part of the inspector(s).

C. All materials and articles furnished by the Contractor shall be subject to rigid inspection, and no material or articles shall be used in the Work until it has been inspected and accepted by the Engineer or the City.

D. Inspection at Place of Manufacture: Unless otherwise specified, all products, materials, and equipment shall be subject to inspection by the Engineer at the place of manufacture.

E. The presence of the Engineer at the place of manufacture, however, shall not relieve the Contractor of the responsibility for furnishing products, materials, and equipment that comply with all requirements of the Contract Documents.

1.03 SAMPLING AND TESTING

A. Unless otherwise specified, all sampling and testing shall be in accordance with the methods prescribed in the current standards of the ASTM or other specified published standards, as applicable to the class and nature of the article or materials considered; however, the City reserves the right to use any generally accepted system of sampling and testing which, in the opinion of the Engineer, will assure the City that the quality of the workmanship is in full accord with the Contract Documents.

B. Any waiver by the City of any specific testing or other quality assurance measures, whether or not such waiver is accompanied by a guarantee of substantial performance as a relief from the specified testing or other quality assurance requirements as originally specified, and whether or not such guarantee is accompanied by a performance bond to assure execution of any necessary corrective or remedial Work, shall not be construed as a waiver of any prescriptive or performance requirements of the Contract Documents.

C. Notwithstanding the existence of such waiver, and in addition to any testing and inspection performed by any other inspector on behalf of the City or any other public agency having jurisdiction, the Engineer shall have the right to make independent investigations and tests, and failure of any portion of the Work to meet any of the requirements of the Contract Documents, shall be reasonable cause for the Engineer to require the removal or correction and reconstruction of any such work in accordance with the General Conditions.

1.04 TIME OF INSPECTIONS AND TESTS

A. Samples and test specimens required under the Contract Documents shall be furnished by the Contractor and prepared for testing in ample time for the completion of the necessary tests and analyses before the subject materials or articles are to be used. The Contractor shall furnish all required test specimens that are selected or required by the City or the City’s testing lab.Except as otherwise provided in the Contract Documents, performance of the required tests will be by the City, and all costs therefor will be borne by the City, except the cost of any test which shows unsatisfactory results shall be borne by the Contractor.

B. Whenever the Contractor is ready to backfill, bury, cast in concrete, hide, or otherwise cover or make inaccessible any work under the Contract, the Contractor shall notify the Engineer not less than 48 hours in advance of beginning any such work of backfilling, burying, casting in concrete, hiding, covering, or making inaccessible any portion of the Work to be inspected, so that the required inspections can be scheduled and performed. Failure of the Contractor to notify the Engineer at least 48 hours in advance of any such inspections shall be reasonable cause for the Engineer to require sufficient delay in the Contractor's schedule to allow time for such inspections and any remedial or corrective work required, and all costs of such delays, including its impact or effect upon other portions of the Work, shall be borne by the Contractor.

City of Thousand Oaks TEMPORARY UTILITIES CI 5702 – Power Backup at Lang Ranch Pump Station 01 51 00

SECTION 01 51 00

TEMPORARY UTILITIES

It shall be the Contractor's responsibility to provide plant and equipment that is adequate for the performance of the Work under this Contract within the time specified. All plant and equipment shall be kept in satisfactory operating condition, shall be capable of safely and efficiently performing the required Work, and shall be subject to inspection and approval by the City's representative at any time within the duration of the Contract. All work hereunder shall conform to the applicable requirements of Cal-OSHA Construction Safety Orders.

1.02 POWER AND LIGHTING

A. Power: The Contractor shall provide all necessary temporary power required for its operations under the Contract, and shall provide and maintain all temporary power lines required to perform the Work in a safe and satisfactory manner.

B. Construction Lighting: All Work conducted at night or under conditions of deficient daylight shall be suitably lighted to ensure proper Work and to afford adequate facilities for inspection and safe working conditions.

C. Approval of Electrical Connections: All temporary connections for electricity shall be subject to approval of the Engineer and the power company representative, and shall be removed in like manner at the Contractor's expense prior to the City’s issuance of Notice of Completion of the Work.

D. Separation of Circuits: Unless otherwise permitted by the Engineer, circuits separate from lighting circuits shall be used for all power purposes.

E. Construction Wiring: All wiring for temporary electric light and power shall be properly installed and maintained and shall be securely fastened in place. All electrical facilities shall conform to the requirements of Title 8, Industrial Relations, Subchapter 5, Electrical Safety Orders, California Administrative Code; and Subpart K of the OSHA Safety and Health Standards for Construction.

1.03 WATER SUPPLY

A. General: Contractor shall be responsible for providing construction water. If the Contractor intends to use water from the Water Provider's fire hydrants, the Contractor will be required to apply for a water construction meter and pay for all charges required by the Water Provider. The Contractor shall provide all facilities necessary to convey the water from the water source to the points of use in accordance with the requirements of the Contract Documents.

B. The Contractor will be responsible for all water charges from the Water Provider's fire hydrants during construction.

C. The Contractor shall not make connection to, or draw water from, any fire hydrant or pipeline without first obtaining permission of the Water Provider for the use of said fire hydrant or pipeline. For each such connection made, the Contractor shall first attach to the fire hydrant or pipeline a valve and a meter of a size and type acceptable to the Water Provider. The Contractor shall contact the Water Provider for specific requirements for water usage and charges.

D. Contractor shall be solely responsible for the adequate functioning of its water supply system and shall be solely liable for any claims arising from the use of same, including discharge or waste of water therefrom.

E. Potable Water: All drinking water on the site during construction shall be furnished by the Contractor and shall be bottled water or water furnished in approved metal dispensers. Notices shall be posted conspicuously throughout the site warning the Contractor's personnel that piped water may be contaminated.

F. Water Connections: The Contractor shall not make connection to, or draw water from, any fire hydrant or pipeline without first obtaining permission of the City or other authority having jurisdiction over the use of said fire hydrant or pipeline, and from the agency owning the affected water system. For each such connection made, the Contractor shall first attach to the fire hydrant or pipeline a valve and a meter, if required by the City or other authority, of a size and type acceptable to the City or said other authority and agency.

G. Removal of Water Connections: Before Final Completion of the Work on the project, all temporary connections and piping installed by the Contractor shall be entirely removed, and all affected improvements shall be restored to their original condition, or better, to the satisfaction of Engineer, the City, and/or other agency owning the affected utility.

H. Fire Protection: The construction plant and all other parts of the Work shall be connected with the Contractor's water supply system and shall be adequately protected against damage by fire. Hose connections and hose, water casks, chemical equipment, or other sufficient means shall be provided for fighting fires in the temporary structures and other portions of the Work, and responsible persons shall be designated and instructed in the operation of such fire apparatus so as to prevent or minimize the hazard of fire. The Contractor's fire protection program shall conform to the requirements of Article 36 of Cal-OSHA

I. The Contractor shall provide and operate all pumping facilities, pipelines, valves, hydrants, storage tanks, and all other equipment necessary for the adequate development and operation of its water supply system. Water used for domestic purposes shall be free of contamination and shall conform to the requirements of the State and local authorities for potable water. The Contractor shall be solely responsible for the adequate functioning of its water supply system and shall be solely liable for any claims arising from the use of same, including discharge or waste of water therefrom.

1.04 SANITATION

A. Toilet Facilities: The Contractor shall provide sanitary temporary toilet buildings for the use of all workers. All toilets shall comply with local codes and ordinances. Toilets shall be kept supplied with toilet paper and shall have workable door fasteners. Toilets shall be serviced no less than once weekly and shall be present in a quantity of not less than 1 per 20 workers or as required by CAL-OSHA regulation. The toilets shall be maintained in a sanitary condition at all times. Use of toilet facilities in the Work under construction shall not be permitted. Any other Sanitary Facilities required by CAL-OSHA shall be the responsibility of the Contractor.

B. Sanitary and Other Organic Wastes: The Contractor shall establish a regular daily collection of all sanitary and organic wastes. All wastes and refuse from sanitary facilities provided by the Contractor or organic material wastes from any other source related to the Contractor's operations shall be disposed of away from the site in a manner satisfactory to the Engineer and in accordance with all laws and regulations pertaining thereto.

City of Thousand Oaks SITE ACCESS AND PARKING CI 5702 – Power Backup at Lang Ranch Pump Station 01 55 00

SECTION 01 55 00

SITE ACCESS AND PARKING

The Contractor shall take all necessary precautions for the protection of the Work and the safety of the public. All barricades and obstructions shall be illuminated at night, and all lights shall be kept burning from sunset until sunrise.

The Contractor shall station such guards or flaggers and shall conform to such special safety regulations relating to traffic control as may be required by the public authorities within their respective jurisdictions. All signs, signals, and barricades shall conform to the requirements of Article 11 of Cal-OSHA

1.02 HIGHWAY LIMITATIONS

The Contractor shall make its own investigation of the condition of available public and private roads and of clearances, restrictions, bridge load limits, and other limitations affecting transportation and ingress and egress to and from the site of the Work. It shall be the Contractor's responsibility to construct and maintain any access or haul roads required for its construction operations.

1.03 TEMPORARY STREET USE

A. Street Use: Nothing herein shall be construed to entitle the Contractor to the exclusive use of any public street, alley, way, or parking area during the performance of the Work hereunder, and it shall so conduct its operations so as not to interfere unnecessarily with the authorized work of the City, utility companies, or other agencies in such streets, alleys, ways, or parking areas.

City of Thousand Oaks TEMPORARY ENVIRONMENTAL CONTROLS CI 5702 – Power Backup at Lang Ranch Pump Station 01 56 00

SECTION 01 56 00

TEMPORARY ENVIRONMENTAL CONTROLS

1.01 EXPLOSIVES AND BLASTING

The use of explosives on the Work will NOT be permitted.

1.02 DUST ABATEMENT

The Contractor shall furnish all labor, equipment, and means required and shall carry out effective measures wherever and as often as necessary to prevent its operation from producing dust in amounts damaging to property, cultivated vegetation, or domestic animals, or causing a nuisance to persons living in or occupying buildings in the vicinity. The Contractor shall be responsible for any damage resulting from any dust originating from its operations. The dust abatement measures shall be continued until the Contractor is relieved of further responsibility by the City’s Project Manager or Inspector.

1.03 RUBBISH CONTROL

During the progress of the Work, the Contractor shall keep the site of the Work and other areas used by it in a neat and clean condition, and free from any accumulation of rubbish. The Contractor shall dispose of all rubbish and waste materials of any nature occurring at the Work site, and shall establish regular intervals of collection and disposal of such materials and waste. The Contractor shall also keep its haul roads free from dirt, rubbish, and unnecessary obstructions resulting from its operations. Disposal of all rubbish and surplus materials shall be off the site of construction in accordance with local codes and ordinances governing locations and methods of disposal, and in conformance with all applicable safety laws, and to the particular requirements of Article 3 of Cal-OSHA Construction Safety Orders. Contractor shall use only the City’s authorized haulers.

1.04 SANITATION

A. Toilet Facilities: Fixed or portable chemical toilets shall be provided wherever needed for the use of employees. Toilets at construction job sites shall conform to the requirements of Article 3 of Cal-OSHA Construction Safety Orders.

B. Sanitary and Other Organic Wastes: The Contractor shall establish a regular daily collection of all sanitary and organic wastes. All wastes and refuse from sanitary facilities provided by the Contractor or organic material wastes from any other source related to the Contractor's operations shall be disposed of away from the site in a manner satisfactory to the Engineer and in accordance with all laws and regulations pertaining thereto.

1.05 CHEMICALS

All chemicals used during project construction or furnished for project operation, whether defoliant, soil sterilant, herbicide, pesticide, disinfectant, polymer, reactant or of other classification, shall show approval of either the U.S. Environmental Protection Agency or the U.S. Department of Agriculture.

Use of all such chemicals and disposal of residues shall be in strict accordance with the printed instructions of the manufacturer.

1.06 EROSION AND SEDIMENT CONTROLS FOR GRADING

A. Contractor shall comply with the City of Thousand Oaks Grading Ordinance (Title 7, Chapter 3 of the City of Thousand Oaks Municipal Code).

B. Contractor shall submit plans for erosion control to the Project Representative and obtain design approval before the work starts. Said plans shall show adequate anti-erosion and drainage devices, i.e., check dams, retention and desilting basins, berms, or other devices necessary to protect public streets and property of others from damage of water run-off and erosive forces.

Contractor shall have all drainage devices shown on plans in place at the end of each working day when the forecast of rain probability is 40% or greater.

C. The contractor shall maintain drainage within and through the work areas.

Earth dams will not be permitted in paved areas. Temporary dams of sandbags, asphaltic concrete or other acceptable material will be permitted when necessary to protect…