About this file

This is a Performance and Payment Bond form issued by the District of Columbia Government, Department of General Services, Contracts and Procurement Division, for use on construction contracts. The document serves as a dual-purpose bonding instrument combining both performance and payment bond requirements into a single standardized form (Form No. DC 26-40-7 and DC 26-40-8). The bond is executed concurrently with contract execution and requires the Principal (contractor) and Surety(ies) to guarantee faithful performance of all contract obligations, including completion of work during the original term and any District-authorized extensions, compliance with all contract modifications, and protection of the District from claims arising from patent infringement, personal injury, or property damage resulting from the contractor's actions. The bond form accommodates multiple sureties with individually stated liability limits and requires execution by authorized corporate representatives with appropriate corporate seals and Powers of Attorney.

The bond's penal sum must be specified in millions, thousands, hundreds, and cents, with surety companies required to appear on the U.S. Treasury Department's list of approved sureties and maintain active licensure through the District's Insurance Administration, Department of Consumer and Regulatory Affairs. Signatories must provide typed names, titles, and appropriate attestations; corporate bonds require certified Board of Directors meeting minutes or bylaw extracts demonstrating signatory authority if the signer is not a President or Vice-President. The form includes provisions for bond premium calculation and identification of the agency or agent receiving commission. All instructions specify strict compliance with execution requirements, including the mandatory use of corporate seals, proper witness signatures with addresses for individual signatories, and adhesive seals in Maine and New Hampshire. This bond form is applicable to the District's design-build and construction task order proposals, including projects such as temporary classroom construction and HVAC upgrades at educational facilities, where contractors must provide bonding prior to commencing work.

View the file

Other files

File Type Posted
Attachment_Y_-_Campaign_Finance_Reform_Act_Self-Certification.pdf PDF
Attachment_X_-_DGS_Standard_Specifications_&_Owner's_Projects_Requirments.pdf PDF
Attachment_V_-_Building_Information_Modeling_(BIM)_Guide.pdf PDF
Attachment_U_-_DGS_Project_Turnover_Protocol.pdf PDF
Attachment_S_-_Certification_to_Furnish_Performance_and_Payment_Bond.pdf PDF
Attachment_R_-_Equal_Employment_Opportunity_Policy_Statement.pdf PDF
Attachment_Q_-_Release_of_Lien_Forms.pdf PDF
Attachment_P_-_Conflict_of_Interest_Disclosure_Statement.pdf PDF
Attachment_O_-_Bid_Guaranty_Certification.pdf PDF
Attachment_N_-_Form_of_Notice_to_Proceed_and_Letter_Contract.pdf PDF
Attachment_M_-_Form_of_Contract.pdf PDF
Attachment_L_-_Past_Performance_Evaluation_Form.pdf PDF
Attachment_K_-_Living_Wage_Act.pdf PDF
Attachment_J_-_First_Source_Employment_Agreement_and_Plan.pdf PDF
Attachment_I_-_SBE_Subcontracting_Plan.pdf PDF
Attachment_H2_-_Standard_Contract_Provision_Architectural_&_Engineering.pdf PDF
Attachment_H1_-_Standard_Contract_Provision_Construction_Contracts.pdf PDF
Attachment_F_-_Bid_Bond_Form.pdf PDF
Attachment_E2_-_Title_29_CFR_5.5_Davis_Bacon_Provision.pdf PDF
Attachment_E1_-_Davis-Bacon_Wage_Determination.pdf PDF
Attachment_D_-_Tax_Certification_Affidavit.pdf PDF
Attachment_C_-_Offeror's_Certification_Form.pdf PDF
Attachment_B_-_Form_of_Offer_Letter.pdf PDF
Attachment_A5_-_Transfere_of_Jurisdiction.pdf PDF
Attachment_A4_-_Existing_Drawings.pdf PDF
Attachment_A3_-_DPR_Lighting_Guideline_2024.pdf PDF
Attachment_A2_-_DPR_Tree_Design_and_Planting_Guidelines.pdf PDF
Attachment_A1_-_Specifications_For_Recreation_Centers_Facilities.pdf PDF
DCAM-26-CS-RFP-0005_Anacostia_Pool_Replacement.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE BOND

(CONSTRUCTION)

(See Instructions on Reverse)

Date Bond Executed (Must be same or later than date of Contract)

PRINCIPAL (Legal Name and Address) TYPE OF ORGANIZATION (“x”)

INDIVIDUAL PARTNERSHIP

JOINT VENTURE CORPORATION

STATE OF INCORPORATION

SURETY(IES) (Name(s) and Address(es) PENAL SUM OF BOND

MILLION(S) THOUSAND(S) HUNDRED(S) CENTS

CONTRACT DATE CONTRACT NUMBER

KNOW ALL MEN BY THESE PRESENTS. That we, the Principal and Surety(ies) hereto are firmly bounds to the

District of Columbia Government, a municipal corporation, hereinafter called the District, in the above penal sum for the payment of which we bind ourselves, our heirs, executors, and successors, bind ourselves in such sum “jointly” and

“severally” only for the purpose of allowing a joint action or actions against any or all of us, and for all other purposes each Surety binds itself, jointly and severally with the Principal, for the payment of such sum only as is set forth opposite the name of such Surety, but if no limit of liability is indicated, the limit of liability shall be the full amount of the penal sum.

THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Principal entered into the Contract identified above.

NOW THEREFORE, if the Principal shall well and truly perform and fulfill all undertakings, covenants, terms and condition, and agreements of the Contract during the original term of the Contract and any extension thereof that may be granted by the District with or without notice to the Surety, and during the life of guaranty required under the Contract, and shall also well and truly perform and fulfill all the undertakings, covenants, terms, conditions and agreements of any duly authorized modifications of the Contract that may hereafter be made, notice of which modifications to the Surety being hereby waived, and shall save harmless and indemnify the District from any and all claims, delays, suits, costs, charges, damages, counsel fees, judgments and decrees to which the District may be subjected at any time on account of any infringement by the Principal of letters, patents, or copyrights, unless otherwise specifically stipulated in the

Contract or on account of any injury to persons or damage to property or premises that occur as a result of any act or omission of Principal in connection with the prosecution of the work under the Contract and shall pay the same, then the above obligation shall be void; otherwise to remain in full force and virtue.

IN WITNESS WEHREOF, the Principal and Surety(ies) have executed this performance bond and have affixed their seals on the date set forth above.

PRINCIPAL

1. Signature

(Seal)

1. Attest

Corporate

Seal Name & Title (typed) Name & Title (typed)

2. Signature

(Seal)

2. Attest

Corporate

Seal Name & Title (typed)

Form No. DC 26-40-7 86-p4002-1 wd-206

SURETY (IES)

1. Name & Address (typed) State of Inc. Liability Limit

Corporate

Seal

Signature of Attorney-in-Fact Attest (Signature)

Name & Address (typed) Name & Address (typed)

1. Name & Address (typed) State of Inc. Liability Limit

Corporate

Seal

Signature of Attorney-in-Fact Attest (Signature)

Name & Address (typed) Name & Address (typed)

BOND PREMIUM

Rate Per Thousand Total Premium Name & Address of Agency or Agent Receiving Commission

INSTRUCTIONS

1. The full legal name and business address of the Principal shall be inserted in the space designated “Principal” on the face of this form. The bond shall be signed by the authorized person signing the Contract. When such person signing is other than the President or Vice-President of a corporation, evidence of authority shall be furnished. Such evidence shall be in the form of either an Extract of Minutes of a meeting of the Board of Directors, or Extract of

Bylaws, certified by the Corporate Secretary, or Assistant Secretary and with Corporate Seal affixed thereto.

2. Corporations executing the bond as sureties shall be among those appearing on the U.S. Treasury Department’s list of approved sureties and shall be acting within the limitations set forth therein, and shall also be licensed by the

Insurance Administration, Department of Consumer and Regulatory Affairs, to do business in the District of

Columbia. The surety shall (1) insert on the bond form the name and addresses of the agency receiving the commission; and (2) attach an adequate Power-of-Attorney for each representative signing the bond.

3. Corporations executing the bond shall affix their Corporate Seals. Individuals shall sign full first name, middle initial and last name opposite the word “seal”; two witnesses shall sign and include their addresses, under the word

“witness”. If executed in Maine or New Hampshire, an adhesive seal shall be affixed.

4. The name of each person signing this performance bond shall be typed in the space provided.

Rev. July 1986 86-p4002-2 wd-206

Form No. DC 26-40-8 86-p4003-1 wd-206

PAYMENT BOND

(CONSTRUCTION)

(See Instructions on Reverse)

Date Bond Executed (Must be same or later than date of Contract)

PRINCIPAL (Legal Name and Address) TYPE OF ORGANIZATION (“x”)

INDIVIDUAL PARTNERSHIP

JOINT VENTURE CORPORATION

STATE OF INCORPORATION

SURETY (IES) (Name(s) and Address(es) PENAL SUM OF BOND

THOUSAND(S) HUNDRED(S) CENTS

CONTRACT DATE CONTRACT NUMBER

KNOW ALL MEN BY THESE PRESENTS. That we, the Principal and Surety(ies) hereto are firmly bounds to the

District of Columbia Government, a municipal corporation, hereinafter called the District, in the above penal sum for the payment of which we bind ourselves, our heirs, executors, and successors, bind ourselves in such sum “jointly” and

“severally” only for the purpose of allowing a joint action or actions against any or all of us, and for all other purposes each Surety binds itself, jointly and severally with the Principal, for the payment of such sum only as is set forth opposite the name of such Surety, but if no limit of liability is indicated, the limit of liability shall be the full amount of the penal sum.

THE CONDITION OF THIS OBLIGATION IS SUCH that whereas the Principal entered into the Contract identified above.

NOW THEREFORE, if the Principal shall well and truly perform and fulfill all undertakings, covenants, terms and condition, and agreements of the Contract during the original term of the Contract and any extension thereof that may be granted by the District with or without notice to the Surety, and during the life of guaranty required under the Contract, and shall also well and truly perform and fulfill all the undertakings, covenants, terms, conditions and agreements of any duly authorized modifications of the Contract that may hereafter be made, notice of which modifications to the Surety being hereby waived, and shall save harmless and indemnify the District from any and all claims, delays, suits, costs, charges, damages, counsel fees, judgments and decrees to which the District may be subjected at any time on account of any infringement by the Principal of letters, patents, or copyrights, unless otherwise specifically stipulated in the

Contract or on account of any injury to persons or damage to property or premises that occur as a result of any act or omission of Principal in connection with the prosecution of the work under the Contract and shall pay the same, then the above obligation shall be void; otherwise to remain in full force and virtue.

IN WITNESS WEHREOF, the Principal and Surety (ies) have executed this payment bond and have affixed their seals on the date set forth above.

PRINCIPAL

1. Signature

(Seal)

1. Attest

Corporate

Seal Name & Title (typed) Name & Title (typed)

2. Signature

(Seal)

2. Attest

Corporate

Seal Name & Title (typed)

SURETY (IES)

1. Name & Address (typed) State of Inc. Liability Limit

Corporate

Seal

Signature of Attorney-in-Fact Attest (Signature)

Name & Address (typed) Name & Address (typed)

1. Name & Address (typed) State of Inc. Liability Limit

Corporate

Seal

Signature of Attorney-in-Fact Attest (Signature)

Name & Address (typed) Name & Address (typed)

BOND PREMIUM

Rate Per Thousand Total Premium Name & Address of Agency or Agent Receiving Commission

INSTRUCTIONS

1. The full legal name and business address of the Principal shall be inserted in the space designated “Principal” on the face of this form. The bond shall be signed by the authorized person signing the Contract. When such person signing is other than the President or Vice-President of a corporation, evidence of authority shall be furnished. Such evidence shall be in the form of either an Extract of Minutes of a meeting of the Board of

Directors, or Extract of Bylaws, certified by the Corporate Secretary, or Assistant Secretary and with Corporate

Seal affixed thereto.

2. Corporations executing the bond as sureties shall be among those appearing on the U.S. Treasury Department’s list of approved sureties and shall be acting within the limitations set forth therein, and shall also be licensed by the Insurance Administration, Department of Consumer and Regulatory Affairs, to do business in the District of

Columbia. The surety shall (1) insert on the bond form the name and addresses of the agency receiving the commission; and (2) attach an adequate Power-of-Attorney for each representative signing the bond.

3. Corporations executing the bond shall affix their Corporate Seals. Individuals shall sign full first name, middle initial and last name opposite the word “seal”; two witnesses shall sign and include their addresses, under the word “witness”. If executed in Maine or New Hampshire, an adhesive seal shall be affixed.

4. The name of each person signing this payment bond shall be typed in the space provided.

Attachment C through O.pdf
RFTOP - 0033 - SWW DRAFT.docx kh rev
REQUEST FOR TASK ORDER PROPOSAL
Issued by: Department of General Services
Contracts and Procurement Division
2000 14th Street, NW – 8th Floor
Washington, DC 20009
2. PROGRAM MANAGER (“PM” or “Project Manager”)
The Contractor is required to comply with the provisions set forth in Article 12 of the underlying IDIQ Contract.
7. DAVIS BACON wage determination
The Contractor agrees that the work performed under the proposed Task Order shall be subject to the Davis Bacon Wage Determination as set forth in (Attachment D) in effect at the time of the Task Order execution by the Department.
7.1. LIVING WAGE ACT
The Contractor agrees that the work performed under the proposed Task Order shall be subject to the living wage act in effect at the time of the Task Order execution by the Department. As such, the Contractor and its subcontractors shall comply with ...
7.2. SERVICE CONTRACT ACT
The Contractor agrees that the work performed under the proposed Task Order shall be subject to the Service Contract act in effect at the time of the Task Order execution by the Department. As such, the Contractor(s) and its subcontractors shall comp...
8. PERFORMANCE AND PAYMENT BONDS
The Contractor shall provide to the Department a payment and performance bond prior to commencing work on the Project, in accordance with Article 11.5 of the underlying IDIQ Contract.
9. LIQUIDATED DAMAGES
10. FIRST SOURCE AGREEMENT AND EMPLOYMENT PLAN
11. ADMINISTRATIVE MATTERS
12. TERMS AND CONDITIONS
13. TASK ORDER PROPOSAL REQUIREMENTS
A complete (Attachment B), Bid Form addressing all of the Scope of Work, including, but not limited to, furnish all supervision, labor, materials, and equipment necessary to design and build Temporary Classrooms at Francis-Stevens Education Campus (t...
The Proposal shall include the following price elements:
i. Preconstruction Fee – The Preconstruction Fee should cover all costs necessary to develop the Final Lump Sum Price, including, but not limited to, working with the Department as the design is finalized; and bidding the design documents with trade s...
ii. Design Fee – The Design Fee should cover all design and engineering costs necessary to complete design documents and/or performance specifications necessary for required permits and bidding.
iii. Design-Build Fee – The Design-Build Fee should cover all costs necessary to oversee and manage the construction of the work and should include the cost of overhead and profit.
iv. General Conditions Price.
The Design Fee should be a firm, fixed fee to develop design documents sufficient for permitting and soliciting trade bids. The Preconstruction Fee should be a firm, fixed fee to cover the selected Contractor’s efforts through the trade bidding proces...
i. A list of key personnel, to include the (i) the Field Superintendent, and (ii) the Project Manager as appropriate for the Scope of the Work, that would be assigned to this Project and details of the personnel experience, qualifications, certificat...
ii. Potential subcontractors and suppliers that Contractor intents to utilize in the performance of the proposed Task Order;
iii. A project management plan and preliminary schedule outlining how the Offeror intends to implement the Project, key subcontractors and vendors that will be utilized, means and methods that will be implemented to accomplish the Scope of Work and ac...
iv. Bid Bond, in the Form of (Attachment E);
v. Subcontracting Plan as set forth in (Attachment H);
14. ATTACHMENTS
The RFTOP contains the following Attachments:
15. METHOD OF AWARD
The District intends to award a single Task Order to the responsive and responsible Offeror with the lowest bid and who will be determined to be the most advantageous to the District. However, the Department reserves the right to consider non price fa...
For the purpose of evaluation, the lowest bid will be the lowest total amount as further described in the Bid Form (Attachment B)
__________________________________ ________________________
Ebti K. Hana Date:
Contracting Officer
SWWFS Swing SOW Draft (2) for IDIQ RFTOP draft (002)
EXHIBITS 1-3 - SWWFS Francis Stevens.pdf
EXHIBIT 1 - SWWFS Temporary Classroom Layout, Dated 02.14.2020 pdf
EXHIBIT 2 - SWWFS Francis Stevens Construction Set 05.27.15 Arch Elec Plumb
ALL-PLUMB
P0001 PLUMBING COVER SHEET
P0002 PLUMBING SPECIFICATIONS
P0101 PLUMBING BASEMENT PLAN
P0303 PLUMBING RISERS (CAFETERIA)
ALL-ELEC
Sheets
E0001 - ELECTRICAL COVER SHEET
E0121 - ELECTRICAL FIRST FLOOR POWER PLAN (AUDITORIUM)
E0130 - ELECTRICAL BASEMENT HVAC POWER PLAN (AUDITORIUM)
E0601 - ELECTRICAL ONE LINE RISER DIAGRAM
E0602 - ELECTRICAL RISER DIAGRAM
E0701 - ELECTRICAL SCHEDULES
E0702 - ELECTRICAL SCHEDULES
ARCHITECURE ALL .pdf
0001 - COVER SHEET
0002-CODE SHEET
0004-EMERGENCY EGRESS PLAN
D100-DEMOLITION BASEMENT FLOOR PLAN
A001-ARCHITECTURAL SITE PLAN
A101 - PROPOSED 1ST FLOOR PLAN
A300-BUILDING SECTION-AUDITORIUM
A620-DOOR & HARDWARE SCHEDULE
Sheets
A620 - DOOR & HARDWARE SCHEDULE
EXHIBIT 3 - 1927 Building Drawings - Property Line Dwg & Struc Lower levels + Subbasement Plumbing
Francis145 - 9 Elevation + Plan Showing Property Line
Francis154 - 18A Struc Foundation Elev
Francis155 - 18 Struc Subbasement
Francis156 - 19 Struc Basement Floor Framing
Attachment I- First Source Employment Agreementn -.pdf
Untitled
Untitled
Untitled
Untitled
Revised Employment Plan 51% Requirement Final (1).pdf
I. REVISED FIRST SOURCE EMPLOYMENT PLAN
GOVERNMENT‐ASSISTED PROJECT/CONTRACT INFORMATION
EMPLOYER INFORMATION
ALL EMPLOYERS:
Please indicate ALL new position(s) you will create as a result of the project. If you WILL NOT be creating any new employment opportunities, please complete the attached justification sheet with an explanation. Attach additional sheets as needed.
B. JUSTIFICATION SHEET: Please provide a detailed explanation of why the Employer will not have any new hires on the project.
I. Provide a timetable outlining the 51% Hiring of District Resident over the life of the project or contract and an associated hiring schedule.
III. Provide a strategy to fill the 51% hiring of District residents requirement, including a component on communicating these requirements to contractors and subcontractors and a component on potential community outreach partnerships with the Univers...
VIII. Provide a strategy to hire graduates of District of Columbia Public Schools, District of Columbia Public Charter Schools, community‐based job training providers, and hard‐to‐ employ residents.
Attachment L - Tax Affidavit Certification Form n.pdf
GOVERNMENT OF THE DISTRICT OF COLUMBIA
Office of the Chief Financial Officer
TAX CERTIFICATION AFFIDAVIT
THIS AFFIDAVIT IS TO BE COMPLETED ONLY BY THOSE WHO ARE REGISTERED TO CONDUCT BUSINESS IN THE DISTRICT OF COLUMBIA.
RFTOP LANGDON EC HVAC UPGRADE.pdf
REQUEST FOR TASK ORDER PROPOSAL
Issued by: Department of General Services
Contracts and Procurement Division
2000 14th Street, NW – 8th Floor
Washington, DC 20009
2. PROGRAM MANAGER (“PM” or “Project Manager”)
The Contractor is required to comply with the provisions set forth in Article 12 of the underlying IDIQ Contract.
7. DAVIS BACON wage determination
The Contractor agrees that the work performed under the proposed Task Order shall be subject to the Davis Bacon Wage Determination as set forth in (Attachment D) in effect at the time of the Task Order execution by the Department.
7.1 LIVING WAGE ACT
The Contractor agrees that the work performed under the proposed Task Order shall be subject to the living wage act in effect at the time of the Task Order execution by the Department. As such, The Contractor and its subcontractors shall comply with ...
8. PERFORMANCE AND PAYMENT BONDS
The Contractor shall provide to the Department a payment and performance bond prior to commencing work on the Project, in accordance with Article 11.5 of the underlying IDIQ Contract.
9. FIRST SOURCE AGREEMENT AND EMPLOYMENT PLAN
10. LIQUIDATED DAMAGES
11. ADMINISTRATIVE MATTERS
12. SERVICE CONTRACT ACT
The Contractor agrees that the work performed under the proposed Task Order shall be subject to the Service Contract act in effect at the time of the Task Order execution by the Department. As such, the Contractor(s) and its subcontractors shall compl...
13. TERMS AND CONDITIONS
14. TASK ORDER PROPOSAL REQUIREMENTS
A complete (Attachment B), Bid Form addressing all of the Scope of Work, including, but not limited to, furnish all supervision, labor, materials, and equipment necessary to Upgrade HVAC to Multi-Purpose Room and Remove Boiler at Langdon Education ...
The RFTOP contains the following Attachments:
16. METHOD OF AWARD
The District intends to award a single Task Order to the responsive and responsible Offeror with the lowest bid and who will be determined to be the most advantageous to the District. However, the Department reserves the right to consider non price fa...
For the purpose of evaluation, the lowest bid will be the lowest total amount considering only the Lump sum price and the allowances as further described in the Bid Form (Attachment B)
__________________________________ ________________________
Ebti K. Hana Date:
Contracting Office
SOW EXHIBITS BID FORM.pdf
REQUEST FOR TASK ORDER PROPOSAL
Issued by: Department of General Services
Contracts and Procurement Division
2000 14PthP Street, NW – 8PthP Floor
Washington, DC 20009
2. PROGRAM MANAGER (“PM” or “Project Manager”)
The Contractor is required to comply with the provisions set forth in Article 12 of the underlying IDIQ Contract.
7. DAVIS BACON wage determination
The Contractor agrees that the work performed under the proposed Task Order shall be subject to the Davis Bacon Wage Determination as set forth in (Attachment D) in effect at the time of the Task Order execution by the Department.
7.1 LIVING WAGE ACT
The Contractor agrees that the work performed under the proposed Task Order shall be subject to the living wage act in effect at the time of the Task Order execution by the Department. As such, The Contractor and its subcontractors shall comply with ...
8. PERFORMANCE AND PAYMENT BONDS
The Contractor shall provide to the Department a payment and performance bond prior to commencing work on the Project, in accordance with Article 11.5 of the underlying IDIQ Contract.
9. FIRST SOURCE AGREEMENT AND EMPLOYMENT PLAN
10. LIQUIDATED DAMAGES
11. FIRST SOURCE AGREEMENT AND EMPLOYMENT PLAN
12. ADMINISTRATIVE MATTERS
13. SERVICE CONTRACT ACT
The Contractor agrees that the work performed under the proposed Task Order shall be subject to the Service Contract act in effect at the time of the Task Order execution by the Department. As such, the Contractor(s) and its subcontractors shall compl...
14. TERMS AND CONDITIONS
15. TASK ORDER PROPOSAL REQUIREMENTS
A complete (Attachment B), Bid Form addressing all of the Scope of Work, including, but not limited to, furnish all supervision, labor, materials, and equipment necessary to Upgrade HVAC to Multi-Purpose Room and Remove Boiler at Langdon Education ...
The RFTOP contains the following Attachments:
Attachment A –Scope of Work.
Attachment B – Bid Form.
Attachment C – The District of Columbia Department of General Services Standard Contract Provisions for Construction Contracts.
Attachment D – Davis Bacon Wage Determination.
Attachment E – Bid Bond Form.
Attachment F – Bid Guaranty Certification.
Attachment G – Certification to Furnish Performance and Payment Bond.
Attachment H – SBE Subcontracting Plan.
Attachment I – First Source Employment Agreement and Employment Plan.
17. METHOD OF AWARD
The District intends to award a single Task Order to the responsive and responsible Offeror with the lowest bid and who will be determined to be the most advantageous to the District. However, the Department reserves the right to consider non price fa...
For the purpose of evaluation, the lowest bid will be the lowest total amount considering only the Lump sum price and the allowances as further described in the Bid Form (Attachment B)
__________________________________ ________________________
Ebti K. Hana Date:
Contracting Office
Attachment I - First Source Employment Agreement and Plan-Construction.pdf
First Source Revised Employment Plan for Non Construction and Construction under 5 million.pdf
I. REVISED FIRST SOURCE EMPLOYMENT PLAN
GOVERNMENT‐ASSISTED PROJECT/CONTRACT INFORMATION
EMPLOYER INFORMATION
ALL EMPLOYERS:
Please indicate ALL new position(s) you will create as a result of the project. If you WILL NOT be creating any new employment opportunities, please complete the attached justification sheet with an explanation. Attach additional sheets as needed.
B. JUSTIFICATION SHEET: Please provide a detailed explanation of why the Employer will not have any new hires on the project.
I. Provide a timetable outlining the 51% Hiring of District Resident over the life of the project or contract and an associated hiring schedule.
III. Provide a strategy to fill the 51% hiring of District residents requirement, including a component on communicating these requirements to contractors and subcontractors and a component on potential community outreach partnerships with the Univers...
VIII. Provide a strategy to hire graduates of District of Columbia Public Schools, District of Columbia Public Charter Schools, community‐based job training providers, and hard‐to‐ employ residents.
RFTOP LANGDON EC HVAC UPGRADE.pdf
REQUEST FOR TASK ORDER PROPOSAL
Issued by: Department of General Services
Contracts and Procurement Division
2000 14PthP Street, NW – 8PthP Floor
Washington, DC 20009
2. PROGRAM MANAGER (“PM” or “Project Manager”)
The Contractor is required to comply with the provisions set forth in Article 12 of the underlying IDIQ Contract.
7. DAVIS BACON wage determination
The Contractor agrees that the work performed under the proposed Task Order shall be subject to the Davis Bacon Wage Determination as set forth in (Attachment D) in effect at the time of the Task Order execution by the Department.
7.1 LIVING WAGE ACT
The Contractor agrees that the work performed under the proposed Task Order shall be subject to the living wage act in effect at the time of the Task Order execution by the Department. As such, The Contractor and its subcontractors shall comply with ...
8. PERFORMANCE AND PAYMENT BONDS
The Contractor shall provide to the Department a payment and performance bond prior to commencing work on the Project, in accordance with Article 11.5 of the underlying IDIQ Contract.
9. FIRST SOURCE AGREEMENT AND EMPLOYMENT PLAN
10. LIQUIDATED DAMAGES
11. ADMINISTRATIVE MATTERS
12. SERVICE CONTRACT ACT
The Contractor agrees that the work performed under the proposed Task Order shall be subject to the Service Contract act in effect at the time of the Task Order execution by the Department. As such, the Contractor(s) and its subcontractors shall compl...
13. TERMS AND CONDITIONS
14. TASK ORDER PROPOSAL REQUIREMENTS
A complete (Attachment B), Bid Form addressing all of the Scope of Work, including, but not limited to, furnish all supervision, labor, materials, and equipment necessary to Upgrade HVAC to Multi-Purpose Room and Remove Boiler at Langdon Education ...
The RFTOP contains the following Attachments:
Attachment A –Scope of Work.
Attachment B – Bid Form.
Attachment C – The District of Columbia Department of General Services Standard Contract Provisions for Construction Contracts.
Attachment D – Davis Bacon Wage Determination.
Attachment E – Bid Bond Form.
Attachment F – Bid Guaranty Certification.
Attachment G – Certification to Furnish Performance and Payment Bond.
Attachment H – SBE Subcontracting Plan.
Attachment I – First Source Employment Agreement and Employment Plan.
16. METHOD OF AWARD
The District intends to award a single Task Order to the responsive and responsible Offeror with the lowest bid and who will be determined to be the most advantageous to the District. However, the Department reserves the right to consider non price fa...
For the purpose of evaluation, the lowest bid will be the lowest total amount considering only the Lump sum price and the allowances as further described in the Bid Form (Attachment B)
__________________________________ ________________________
Ebti K. Hana Date:
Contracting Office
Bidder Offeror Certification Form.xls.pdf
Sheet1

File details come from the government source that posted it. Updated .