Attachment SOW 02-11-2026.pdf

PDF 2 MB Posted

Attached to
Z2DA--Install Sinks Outpatient Surgery Project No. 593-26-305 VAMC Las Vegas, NV
Solicitation number
36C26126R0020_2
Issued by

About this file

This is a Statement of Work (SOW) for construction services at VA Southern Nevada Healthcare System's Outpatient Surgery Department located at 6900 North Pecos Road, N. Las Vegas, Nevada 89086, Building 1 (Project 593-26-305).

The contractor must install six (6) new lavatories, relocate two (2) existing lavatories, mount seven (7) exam lights across seven rooms, and reconfigure one large exam room into two smaller exam rooms. Work includes ICRA barrier installation, wall demolition and rough-in cutting, plumbing installation (hot water and soft cold water piping, waste/vent lines, P-traps, shut-off valves), ground penetrating radar scanning of floor slabs, core drilling for drain connections, electrical conduit and GFCI receptacle installation, drywall patching and painting with water-resistant materials, plumbing fixture installation, exam light assembly and hard-wiring (Burton Outpatient LED OPLEDW model provided by VA), nurse call station installation, dividing wall construction with fire ratings and sound travel mitigation, new doorway creation with Medeco locking hardware, fire alarm speaker installation, return-air register installation with testing and balancing, and lighting fixture replacement. The project is staged into four phases with Phases 1-3 requiring completion within one week each to comply with VA ICRA Level 2 requirements, while Phase 4 requires ICRA Level IV compliance. Work must be performed between 6:00 PM and 2:00 AM and on weekends to minimize impact to clinic operations (Outpatient Surgery hours 8:00 AM–4:00 PM; Second Floor Clinics 7:00 AM–5:30 PM).

The contractor must submit a Construction QA/QC Plan within 5 business days of Notice to Proceed, a Specification Submittal Register and Phasing Plan before construction begins, and a CPM Estimated Construction Schedule within 10 business days of NTP. All submittals require PDF files with searchable text and bookmarked tables of contents, uploaded to Procore or similar construction management platform, with hard copies provided. The contractor must produce electrical, mechanical HVAC, plumbing, and fire alarm record drawings stamped by licensed engineers verifying compliance with VA Technical Information Library (TIL) guidelines. A pre-construction site investigation (minimum one day, after 4:30 PM) and kickoff meeting within 10 business days of NTP are required, followed by bi-weekly construction meetings via teleconference with 3-week lookahead schedules submitted two business days prior. The overall Period of Performance is ninety (90) calendar days from NTP issuance, with all contractor personnel requiring Non-PIV Card security clearance (30-45 day processing) per VA Directive 0735 and HSPD-12, including fingerprinting, background investigation, and submission of Declaration for Federal Employment (OF306) and other required forms. Government review and response to submittals and RFIs requires five (5) business days. As-built drawings in ARCH E1 format (42"x30") and half-size are due after construction completion. The contractor must comply with VA BIM & CAD Standards (PG-18-13 TIL) and all referenced VA construction specifications and design guidelines.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Project 593-26-305 Install Sinks Outpatient Surgery VA Southern Nevada Healthcare System

6900 North Pecos Road, N. Las Vegas, NV 89086

Building 1

PROJECT SUMMARY

The VA Southern Nevada Healthcare System (VASNHS) Outpatient Surgery Department provides podiatry, orthopedic, vascular, ear, nose and throat (ENT), and other outpatient surgery services for veteran patients. These services are rapidly approaching their maximum exam space capacity for patient care and require existing administrative spaces to be converted into examination rooms to meet the growing demands. Currently, these existing administrative spaces are not equipped with the proper plumbing fixtures or exam lights needed for clinicians to provide care to veteran patients. Additionally, certain spaces are large and underutilized and would be best divided into two separate exam spaces. To facilitate proper care to the growing veteran population, the VA requires construction services to reconfigure these existing spaces into standardized general-purpose exam rooms.

SCOPE

VASNHS solicits the services of a licensed contractor for the installation of six (6) new lavatories, relocation of two (2) existing lavatories, mounting of seven (7) exam lights throughout seven (7) rooms, and the reconfiguration of one large exam room into two smaller exam rooms within the outpatient surgery department’s clinical space. This will be inclusive of: installation of required ICRA barriers; cutting a rough-in for the lavatory out of the existing wall; piping, valving, and terminating the appropriate Hot Water (HW) and Cold Water (CW) pipes to each new lavatory; ground penetrating radar (GPR) of existing floor slab and subsequent core drilling for lavatory waste line; installation of new waste and vent pipes and connection to existing lines;

pulling and installing the electrical connections for new lavatory fixtures; final mounting and connection of the lavatory; mounting and energizing a wall-mounted exam light in each new exam room; erecting, mudding, and painting a new dividing wall; Installation two duplex receptacles on the new dividing wall; installing a new door for exam room access; installing a new ceiling-mounted fire alarm speaker; installing a new return-air (RA) register and tying its associated ductwork into an existing RA trunk; reconfiguring and rearranging lighting in existing exam room as necessary; and patching, repair, and painting of entire wall in which the new lavatory was installed.

The construction efforts will occur within an active outpatient surgery clinic and above other active outpatient ambulatory clinics. To mitigate the impact that construction will have on the clinics, the construction project will be staged. Each phase will be conducted as such that work is consolidated to a specific location within the outpatient surgery department. To abide by VA

ICRA level 2 requirements, the construction efforts for phases 1-3 shall conclude within 1 week of start.

HOURS OF OPERATION & HOLIDAYS

Normal duty hours are 8:00 AM – 4:30 PM, Monday thru Friday not including standard Federal

Holidays. Federal Holidays can be obtained on OPM’s website (www.opm.gov). All work performed shall be coordinated and scheduled through the COR. Any off-duty work must be coordinated with the COR at least 2 weeks (14 calendar days) prior to the work taking place.

Outpatient Surgery operation hours are 8:00 AM – 4:00PM and the Second Floor Clinics are open 7:00 AM-5:30 PM; Work shall be performed between the hours of 6:00 PM – 2:00AM and on weekends as necessary to minimize shutdown impact.

DESCRIPTION OF SUPPLIES OR SERVICE OBJECTIVES

The lavatories to be installed are to match the existing fixtures found throughout the facility and are described in detail in specification 22 40 00. Furnish all supervision, labor, and hardware/software equipment to facilitate the new installation of six (6) lavatories, relocation of two (2) lavatories, mounting and connection of seven (7) exam lights, erection of a new dividing wall, a new exam-room doorway, and all other work described within this SOW in the locations shown within the figures provided below as follows:

A. CONSTRUCTION PHASES AND REQUIREMENTS

Site Investigation, Engineering, and Inspections

1. Perform Ground Penetrating Radar (GPR) scanning to identify existing structure within the existing concrete floor slab.

a. GPR scanning shall be done outside of Outpatient Surgery operating hours.

b. Use the findings of the scanning to finalize coring pattern for new lavatory drain lines.

http://www.opm.gov/

2. Produce electrical record drawings and documents to justify and document electrical installations. Verify electrical work conforms to VA Technical Information Library (TIL) guidelines and is permittable. Retain a licensed Electrical Engineer (sub-consultant if necessary) to produce said electrical record drawings and documents including, but not limited to, load calculations, updated panel schedules, and conductor sizes.

3. Produce mechanical HVAC record drawings and documents to justify and document

HVAC installations. Verify HVAC work conforms to VA TIL guidelines and is permittable.

Retain a licensed Mechanical Engineer to produce said HVAC record drawings and documents, including, but not limited to, duct sizes, connection points, and register sizes.

4. Produce plumbing record drawings and documents to justify and document electrical installations. Verify plumbing work conforms to VA TIL guidelines and is permittable.

Retain a licensed Mechanical Engineer to produce said Plumbing record drawings and documents including, but not limited to, pipe sizes, connection points and material identification.

5. Produce Fire Alarm record drawings and documents to justify and document fire alarm installations. Verify fire alarm work conforms to VA TIL guidelines and is permittable.

Retain a licensed fire protection engineer to produce said fire alarm record drawings and documents including, but not limited to, conduit routing, connection points, and alarm information.

Installation

Contractor to establish final phasing plan via discussion with VA Engineering/COR. Should a better phasing plan be identified than the plan provided, it shall be brought to the attention of the

COR for review and approval. Please see Figure 1 for details.

Phase 1, 2 and 3

1. Construction of ICRA barrier and all other ICRA provisions, to protect construction work sites on both the 3rd and 2nd floor as necessary. Conform to ALL requirements described within VA ICRA document as described by the ICRA rating determined by VA

Engineering and VA Infection Control. Please reference Figure 3: ICRA Plan Phase 1-3 for further details.

a. Each phase will be assigned its own separate ICRA level.

2. Cut and demolish existing gypsum wall for required lavatory profile. Exact Lavatory location to be determined by contractor and approved by VA COR.

3. GPR floor to determine location of existing rebar in concrete slab.

a. GPR scanning is only required where core drilling is to be performed for drain line connections.

4. Core Drill for drain connections to 2nd floor above ceiling where connection to drain on third floor is not feasible.

a. Contractor is responsible for determining points of connections into waste/vent lines for lavatories that require coring PRIOR to core drilling. This information will be provided to VA COR a minimum of five (5) business days prior to work for review and approval.

b. Phases 2 and 3 will require coring.

5. Rough-in all required utilities for the installation of the new lavatory’s (Hot Water (HW) and Soft Cold Water (SCW) connections, Waste/Vent installation, P-traps, shut-off/line isolation valves, and all other components as described in the specifications.

6. Run new conduits, install GFCI-equipped receptacles where necessary, and terminate new conductors for the connection of motion-sensor-equipped plumbing fixtures.

a. In phase 3, Contractor shall install one (1) additional duplex receptacle in room

3B176. See figure for details.

7. Install wall-mounted lavatory carrier into designated space as detailed within specification 22 40 00.

8. Patch, mud, and paint to close space created within demolition. Patch and paint to match existing surrounding walls.

a. New drywall surrounding sink MUST be water-resistant. See specifications for details.

9. Install and connect all new plumbing fixtures.

a. This is inclusive of all lavatory components as stated within the specifications, including the solid waste interceptor for P-507 lavatory.

10. Run new electrical for energization of the new exam light. Assemble and mount exam light according to manufacturer instructions.

a. The exam lights will be provided by the VA for contractor Installation. The exam-light model is the Burton Outpatient LED OPLEDW. The exam lights shall be electrically hard-wired.

b. VA will designate the desired location of the exam light to the contractor. The contractor is responsible for all efforts relating to the assembly, mounting

(including any necessary structural backing), and energization of the exam lights within each room. See Attachment Exam Light Specification Sheet for more information.

11. Install new Nurse Call stations and associated doorway indicator lights for rooms 3B192, 3B118 and 3B146. Match and Integrate these new stations with the existing VASNHS nurse call system.

Phase 4

12. Abide by and install ALL necessary ICRA level IV requirements as described VA ICRA document. Refer to Figure 5: ICRA Plan Phase 4 for more details. Contractor is responsible for providing and implementing all necessary equipment and materials for compliance with VA ICRA Level IV control measures. Final ICRA plan to be submitted by contractor and approved by VA COR and VA Infection Control.

13. Steps 2 – 10 as described above are applicable to Phase 4.

14. Deconstruct existing patient lift system within 3B174.

15. Install new ceiling-mounted fire alarm speaker in northern half of 3B174. See figure for details.

16. Install a new Nurse Call pull station within the northern half of 3B174. See figure for details.

a. Nurse call station shall match existing and shall be integrated into VAMC’s nurse call system.

b. Install nurse call indicator light above new southern doorframe and connect to southern exam rooms nurse call station.

c. Reconfigure existing northern nurse call indicator light to indicate when new northern nurse call station is activated.

17. Install a new return-air register and tie new ductwork into existing nearest above-ceiling return-air trunk. This register will service the southern half of 3B174. See figure below for details.

a. Contractor will perform all necessary testing and balancing (TAB) as required for compliance of new rooms with the TIL, including ACH, room pressures and other

HVAC requirements.

18. Remove two (2) 2x4 lighting fixtures and replace them with two (2) 2x2 lighting fixtures to accommodate the construction of the dividing wall. See figures below for details.

a. New 2x2 fixtures will match existing 2x2 fixtures within other adjacent exam rooms. Adjust ceiling t-grid accordingly to accommodate installation.

b. Reconfigure existing lighting within exam room 3B174, such that southern fixtures are on a separate switch than the northern fixtures.

19. Install new dividing wall in existing room 3B174. See figures below for details.

a. New Wall shall have two (2) new electrical duplex receptacles, one on the northern face and the other on the southern face. These will be fed from existing electrical.

b. New wall shall NOT interfere or otherwise obstruct existing medical gas receptacles located on the eastern wall of 3B174.

c. New wall shall extend to the deck above. New wall shall match existing adjacent wall composition, including STC and fire ratings.

20. Create new exam-room doorway and install new door for southern access into 3B174.

The new Door shall match existing doors within the space. See figures below for details.

a. Contractor shall furnish all material for doorway construction including a new door, door frame, and associated door hardware.

b. Contractor to procure and install all necessary Medeco locking hardware as described in the specification 08 71 00 for the new door.

c. The Contractor shall refinish and reinstall all components removed for demolition after doorway construction is complete, including walls, handrails, wall-guards, and cove base.

PERIOD OF PERFORMANCE

The Period of Performance (PoP) for this project is ninety (90) calendar days from the issuance of the Notice the Proceed (NTP) letter from the VA Contracting Office. All tasks associated with this contract and project shall be completed within ninety (90) calendar days. Each construction phase, apart from phase IV, shall be completed within one (1) week. See Figure 1 for details.

Figures

All figures are diagrammatical and are for reference purposes only. Contractor will field-verify final positions of installation for all components of construction.

Figure 1: 3rd Floor Outpatient Surgery Clinics Floor Plan

Figure 2: 2nd Floor Ambulatory Clinic ICRA Impacts Floor Plan

Figure 3: ICRA Plan Phase 1-3

Figure 4: Electrical Plan Phase 3

Figure 5: ICRA Plan Phase 4

Figure 6: Architectural Plan Phase 4

Figure 7: Electrical Power Plan Phase 4

Figure 8: Mechanical HVAC Plan Phase 4

Figure 9: Lighting Plan Phase 4

Figure 10: Verco W2 Design Tables

SUBMISSION REQUIREMENTS FOR DELIVERABLES

1. The Contractor shall furnish the required documents in accordance with the Submittal

Table below.

2. All deliverables submitted as PDF files shall be searchable and contain a bookmarked

Table of Contents linked to respective sections, title pages, etc.

Drawings in PDF shall have bookmarks for each drawing page within a table of contents to allow quick navigation to individual drawing sheets.

3. All digital files shall be submitted electronically. Contractor to upload Submittals, RFIs, and other relevant documentation to an online construction management website such as Procore. Contractor will provide VA representatives proper access to the construction management website. Submittal title pages shall contain at minimum the following;

Project Name, Client Name (VA Southern Nevada Health Care System), Contract

Number, Project Number, Submittal phase, Name of Contractor/Designer, Submittal

Date.

4. Provide hard copies of all submittals per the Submittal Table below.

5. All files, layers, naming conventions and standards should follow the VA BIM & CAD

Standards described on PG-18-13 of the TIL.

6. The Construction Contractor or their assigned Architect-Engineer (A-E) shall develop As-built drawings based on record drawings from construction.

SUBMITTAL TABLE

Submission

Phase

Submittals Hard

Copies

Qt.

Paper Size for

Hard Copies

Digital File

Formats

NTP + 5

business days

Construction

QA/QC Plan

1 8 ½ x 11 inch PDF

Before

Construction

Specification

Submittal

Register

2 8 ½ x 11 inch PDF, Excel

Phasing Plan 2 8 ½ x 11 inch PDF

CPM Estimated

Construction

Schedule

2 11 x 17 inch PDF

After

Construction As-Builts

2 ARCH E1 – 42

inches by 30 inches and

Half Size

PDF, DWG

STAMPING OF CONTRACT DELIVERABLES

The Construction Contractor shall stamp/seal and date construction document drawings and specification as follows:

1. Each deliverable (drawings and specifications) shall have a certified cover document showing for each discipline the name and stamp or seal of the professional who supervised the work, and the date each stamp or seal was affixed; or

2. An electronic equivalent that indicates for each discipline the name, stamp or seal of the professional who supervised the work, and the date each stamp or seal was affixed.

CONSTRUCTION SCHEDULE REQUIREMENTS

1. Contractor shall develop and submit an estimated construction schedule within 10 business days of NTP and before start of construction on site.

2. The schedule shall be developed based on the critical path Method (CPM) showing at a minimum the milestones and durations, broken down by discipline applicable to the project (i.e. Mechanical, Electrical, Plumbing, Structural, etc.). This schedule and its durations will be submitted to VA for approval.

3. Contractor shall maintain the schedule to reflect any changes made throughout the construction period. Contractor shall re-submit the schedule if changes are made.

4. Complete construction schedule must fall within the period of performance as defined in the SOW.

5. The schedule, as a minimum, shall show the milestones within the construction phasing plan, proposed phasing notes, and inclusive of major divisions of work.

a. Contractor will identify all 2nd floor clinical room impacts associated with the work to be done and provide this information to VA COR within the project schedule no later than 30 days prior to work start.

REFERENCES

The references below provide essential, but not all-inclusive, references. Refer to individual technical documents in the Technical Information Library for all VA Design and Construction

Criteria. The Construction Contractor will be responsible for reviewing the guidelines in the TIL and incorporating the applicable criteria into the design and construction documents.

Comprehensive VA design guidelines and specifications can be found at the Technical

Information Library (TIL) at http://www.cfm.va.gov/TIL.

Conflicting criteria shall be brought to the attention of the VA Contracting Officer for resolution.

VA Standard Title/Section

DESIGN AND CONSTRUCTION PROCEDURES PG-18-3 Topics: 01 Codes, Standards and Executive Orders; 02 Drawings

Manual for Preparation for Cost Estimates and Related Documents for VA Facilities

Program Guide PG-18-1 Master Construction Specifications

Program Guide PG-18-3 Design and Construction Procedures

Program Guide PG-18-4 Standard Details and CAD Standards

Program Guide PG-18-10 Design Manuals – Electrical, Fire Protection, Plumbing, Structural

Program Guide PG-18-12 Design Guides – Pharmacy Service

Program Guide PG-18-13 Barrier Free Design Standard

Program Guide PG-18-14 Room Finishes, Door, and Hardware Schedule

Program Guide PG-18-15 A/E Submission Requirements – Volume C Minor and NRM

Projects http://www.cfm.va.gov/TIL

Program Guide PG-18-17 Environmental Compliance Manual

TIL SPECIFICATIONS PROVIDED:

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21

01 33 23 Shop Drawings, Product Data, and Samples 06-25

01 35 26 Safety Requirements for Major Projects 05-24

01 42 19 Reference Standards 11-20

01 45 00 Quality Control 02-21

01 57 19 Temporary Environmental Controls 01-21

01 74 19 Construction Waste Management 04-22

01 81 13 Sustainable Construction Requirements 10-17

01 91 00 General Commissioning Requirements 04-22

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 05 – METALS

05 50 00 Metal Fabrications 08-18

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 01-21

07 84 00 Firestopping 01-21

07 92 00 Joint Sealants 04-22

DIVISION 08 - OPENINGS

08 14 00 Interior Wood Doors 01-21

08 71 00 Door Hardware 03-24

DIVISION 09 – FINISHES

09 06 00 Schedule for Finishes 01-21

09 29 00 Gypsum Board 04-20

09 91 00 Painting 01-21

DIVISION 10 - SPECIALTIES

10 26 00 Wall and Door Protection 01-21

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural Components 01-21

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 01-23

22 05 23 General-Duty Valves for Plumbing Piping 09-20

22 07 11 Plumbing Insulation 09-19

22 08 00 Commissioning of Plumbing Systems 11-16

22 11 00 Facility Water Distribution 05-21

22 13 00 Facility Sanitary and Vent Piping 09-20

22 13 23 Sanitary Waste Interceptors 09-20

22 40 00 Plumbing Fixtures 05-24

DIVISION 23 – Heating, Ventilating, and Air Conditioning (HVAC)

23 05 11 Common Work Results for HVAC 03-23

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 03-23

23 05 93 Testing, Adjusting, and Balancing for HVAC 03 -23

23 08 00 Commissioning of HVAC Systems 03-23

23 31 00 HVAC Ducts and Casings 03-23

23 37 00 Air Outlets and Inlets 03-23

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22

26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22

26 05 26 Grounding and Bonding for Electrical Systems 11-22

26 05 33 Raceway and Boxes for Electrical Systems 11-22

26 08 00 Commissioning of Electrical Systems 11-22

26 27 26 Wiring Devices 11-22

26 51 00 Interior Lighting 03-24

DIVISION 27 - Communications

27 05 11 Requirements for Communications Installations 09-19

27 05 26 Grounding and Bonding for Communications Systems 06-15

27 05 33 Raceways and Boxes for Communications Systems 10-18

27 08 00 Commissioning of Communications Systems 11-16

27 10 00 Control, Communication and Signal Wiring 06-15

27 11 00 Telecommunications Room Fittings 06-15

27 15 00 Communications Structured Cabling 01-16

27 52 23 Nurse Call and Code Blue Systems 12-20

DIVISION 28 – Electronic Safety and Security

28 05 00 Common work results for Electronic Safety and Security 04-18

28 05 13 Conductors and Cables for Electronic Safety and Security 10-18

28 05 26 Grounding and Bonding for Electronic Safety and Security 09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and Security 09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16

28 31 00 Fire Detection and Alarm 10-11

QUALITY CONTROL

1. To reduce design errors and omissions, the Contractor shall develop and execute a

QA/QC plan that demonstrates the project plans and specifications have gone through a rigorous, thorough review and coordination effort.

2. Within 5 business days after receipt of Notice to Proceed, the Contractor shall submit a

QA/QC plan describing each task that will be taken during development of the various submittals of the project; name of Contractor member responsible for QA/QC for

Contracting Officer approval. Each task shall be initialed and dated by the responsible

Contractor member.

3. The QA/QC shall also cover the construction phase of the project and accompany the

100% final design document submittal package.

4. Submit and Maintain a Construction Quality Control (CQC) Plan: As an effective quality control program, the CQC Plan will assure that all services required by this contract are performed and provided in a manner that meets professional construction quality standards in accordance with VA Construction Specifications.

a. As a minimum, all construction activities must be technically reviewed by a competent reviewer identified in the CQC Plan.

i. The Contractor shall submit the resume of the proposed individual who will oversee Quality Control.

b. The same person that performs the construction work which is submitted for quality control may not perform the independent technical review (ITR).

c. Correct errors and deficiencies in construction activities before proceeding to subsequent stages or submitting them for Government review.

5. Include the Construction Schedule in the Master Project Schedule: Show the sequence of events involved in carrying out the construction tasks within the specific Contract period.

a. This should be at a detailed level of scheduling sufficient to identify all major construction tasks, including those that control the flow of work.

b. Include review and correction periods associated with each item to serve as both a forward planning and a project monitoring tool.

c. Include in the CQC Plan the discipline-specific checklists to be used during the construction phases and quality control of each submittal.

d. Submit at each construction phase or discipline-specific milestone as part of the project documentation these completed discipline-specific checklists.

e. If the schedule is changed, submit a revised schedule reflecting the change within 5 business days.

6. Field Construction Quality Control: The CQC Plan must capture the Contractor's intentions to keep field construction work to the utmost quality, ensuring adherence to VA

Construction Specifications.

a. The Contractor shall develop and follow specific procedures for conducting inspections, tests, and verifications at different construction stages, with scheduled VA inspections before moving on to other major divisions of labor or closing out major divisions of labor

b. Maintain thorough documentation of all inspections, materials testing, and verifications, including corrective actions taken to address any deficiencies found.

c. Ensure that all construction work, including subcontracted work, is performed in accordance with approved plans, specifications, and quality standards.

7. Implement the CQC Plan by a Construction Quality Control Manager: This individual will have the responsibility of being cognizant of and assuring that all construction activities on the project are coordinated and quality is maintained.

a. This individual must be a person who has verifiable construction experience and is a certified quality control manager or holds an equivalent qualification.

b. Notify the Contracting Officer, in writing, of the name of the individual, and the name of an alternate person assigned to the position.

8. Quality Assurance Liaison: The Contractor shall ensure ongoing communication and verification of quality standards.

a. Facilitate regular quality assurance meetings to review progress, discuss upcoming activities, and address any quality-related issues. This topic can be implemented in bi-weekly meetings.

b. Provide the COR with access to all quality control records and documentation for review and verification.

PRE-CONSTRUCTION SITE INVESTIGATION

1. The Contractor and/or their assigned A-E(s) shall conduct a site investigation to verify existing conditions of the project areas.

2. The site investigation shall be scheduled for a minimum of one day and be coordinated with the VA COR.

a. The site investigation may take place on the same day as the kickoff meeting.

3. Contractor shall plan to conduct all site investigation activities after hours (after 4:30 pm) to minimize impact to patient care.

4. Contractor shall at a minimum visually verify locations of floor mounted equipment to be moved prior to flooring install, locations of utilities and shut-down valves, telecommunications, and electrical that will need to be addressed.

CONSTRUCTION MEETINGS

1. The Contractor shall coordinate with the COR to hold a mini charrette within 10 business days of NTP.

a. The goal of the mini charrette will be to bring the Contractor, affected Services, and Engineering together to discuss typical operations of each area and phasing limitations from the perspective of the Service.

b. The overall intent for this meeting will be to better inform the Contractor’s phasing plan early on to minimize changes to the plan after construction start.

c. The Contractor should allow a minimum of 4 hours for the charrette.

d. Microsoft Teams is an acceptable method to carry out Mini Charrette

e. Mini Charrette Deliverables:

i. The Contractor shall prepare a document that summarizes Strengths, Weaknesses, Opportunities, and Threats (SWOT), phasing, etc. of the items discussed within the mini charette, due 5 VA business days after the mini charrette.

2. The Contractor shall attend the following meetings at the VASNHS Campus:

a. Kick-off meeting (Kick-off meeting shall be held within 10 business days of NTP)

3. The Contractor shall schedule bi-weekly construction meetings. Bi-weekly meetings in this context shall mean “to occur every two (2) weeks”.

a. Bi-weekly meetings shall be held via teleconference.

b. The Contractor shall record minutes for all conferences and meetings.

c. The minutes shall be sent to all attendees within 3 business days of meeting for review and comment.

d. A 3-week lookahead of the current construction schedule should be reviewed at this meeting.

i. Contractor to submit 3-week lookahead no later than 2 business days prior to the scheduled bi-weekly meeting.

e. The Contractor shall incorporate comments, finalize meeting minutes, and send final minutes to all attendees within 5 business days of respective meeting or conference.

REFERENCE MATERIALS

The government will provide the following materials to the contractor for reference during the pre-construction phase:

Item Description Provided Format

Hospital As-Built Drawings As requested by Contractor AutoCAD Files &

PDFs

GOVERNMENT REVIEWS

The government requires 5 business days to review and respond to submittals and RFIs unless otherwise modified by this SOW.

VA SECURITY REQUIREMENTS FOR CONTRACTORS

All contractor’s and subcontractor’s personnel shall be subject to VA Directive 0735, Homeland

Security Presidential Directive 12 (HSPD-12) Program, Federal laws, regulations, standards, and VA Handbooks regulating VA personnel regarding information and information system security.

a. Non-Personal Identity Verification (PIV) Card requests shall be submitted to

VA COR (Contracting Officer Representative) by the contractor. Request submission is the contractor’s responsibility to properly fill out the documents identified below. These documents will become a package for submission of

Non-PIV Card application:

1. VA Fingerprinting form

2. Declaration for Federal Employment (OF306), if there are any questions that were answered “yes” on item 9-13 on this form, fill out the appropriate addendum and include in the package.

3. Authorization For Release of Information (VA Form 0710)

4. Self-Certification of Continuous Service

5. Contractor Background Investigation Request

b. Non-PIV Card process may take 30-45 days, depending on the contractor’s personnel background check, Special Agreement Check (SAC). SAC is an automated records check conducted by the Federal Bureau of Investigation in collaboration with the Office of Personnel Management (OPM).

c. Non-PIV Card Applicant is subject to National Agency Check with written

Inquiries (NACI) conducted by OPM. This investigation covers a period of 5 years and a review of current records in the OPM Security Investigation Index (SII), DOD Defense Central Investigations Index (DCII), FBI name check, and FBI fingerprint check as well as written inquiries from previous employers and references on the application for employment. It is used for Non-sensitive or Low

Risk positions in VA.

d. Once all documents are completely and properly filled out, hand carry and submit to VA COR. Do not send completed forms through email due to Personal

Identifiable Information.

e. VA COR will then provide all documents to Engineering Service’s VA PIV

Sponsor/Manager to initiate the Non-PIV process.

f. PIV Sponsor/Manager will notify each applicant when to proceed for fingerprinting appointment.

g. Each applicant shall be fingerprinted at VA Southern Nevada Healthcare

System’s PIV Office, located first floor in Building 6 (Administration Building), 6900 N. Pecos Road, N. Las Vegas, NV 89086. Each applicant shall sign in at the Security Desk.

h. VA COR or PIV Sponsor/Manager will provide status of each applicant’s Non-PIV

Card.

i. Non-PIV Card is critical for the construction start date, as the contractor’s personnel without Non-PIV Card may result with a restricted, limited, or no access to the job site. See attached blank forms/documents that is required for submission of Non-PIV Card application for each of contractors/sub-contractors

Contractor shall not require access to the VA internal trusted network for this scope. The certification and accreditation (C&A) requirements do not apply and a Security Accreditation

Package is not required.

– END OF STATEMENT OF WORK –