This document contains the technical specifications for the Replacement of Computer Room Air Conditioner (CRAC) and Clean Agent Fire Suppression System at the Maryland Motor Vehicle Administration (MVA) Cumberland Branch Office. The project includes the removal and replacement of the existing CRAC units and all associated equipment located in Cumberland, Maryland. This is a single prime contract based on a Stipulated Price. The Owner, MVA, intends to occupy the project upon Substantial Completion, and the Contractor is required to coordinate construction activities accordingly.
The contract opportunity is open to all qualified bidders. Pricing will be based on a Stipulated Price, and the contract will include allowances, unit prices, and alternates as defined in the specifications. No specific set-asides or incumbents are mentioned. Funding requirements and sources are not provided, but the specifications indicate the Owner will be responsible for certain utilities during construction.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT No.1.pdf | ||
| Attachment P_Prevailing Wage Determination Document.pdf | ||
| Q & A _ VCUM24008C_Cumberland MVA.pdf | ||
| Attachment B-1_BID FORM.xlsx | XLSX spreadsheet | |
| AMENDMENT No.2.pdf | ||
| Attachment S_VCUM24008C_Drawings.pdf | ||
| AMENDMENT No. 3.pdf | ||
| GeneralConditionsforConstruction2018.pdf.pdf | ||
| IFB_VCUM24008C.pdf | ||
| Addendum No. 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MVA Replacement of Computer Room Air Conditioner (CRAC) and Clean Agent Fire Suppression System for
Cumberland Branch Office
Contract No: V-CUM-24008-C
ATTACHMENT R
TECHNICAL SPECIFICATIONS
MOTOR VEHICLE ADMINISTRATION (MVA)
TABLE OF CONTENTS
Cumberland Branch CRAC Replacement Table of Contents
067196-11 06/21/2023 TOC-1
MOTOR VEHICLE ADMINISTRATION (MVA)
Replacement of Computer Room Air Conditioner and Clean Agent Fire Suppression System for
Cumberland Branch Office
DIVISION 01
01 10 00
01 20 00
01 21 00
01 22 00
01 23 00
01 25 00
01 30 00
01 32 16
01 35 53
01 40 00
01 50 00
01 51 00
01 52 13
01 55 00
01 60 00
01 61 16
01 70 00
01 74 19
01 78 00
01 91 13
01 91 14
DIVISION 02
02 41 00
DIVISION 21
21 12 05
DIVISION 23
23 05 00
23 05 13
23 05 29
23 05 48
23 05 53
23 05 93
23 23 00
23 81 23
GENERAL REQUIREMENTS
Summary
Price and Payment Procedures
Allowances
Unit Prices
Alternates
Substitution Procedures
Administrative Requirements
Construction Progress Schedule
Security Procedures
Quality Requirements
Temporary Facilities and Controls
Temporary Utilities
Field Offices and Sheds
Vehicular Access and Parking
Product Requirements
Volatile Organic Compound (VOC) Content Restrictions
Execution and Closeout Requirements
Construction Waste Management and Disposal
Closeout Submittals
General Commissioning Requirements
Commissioning Authority Responsibilities
EXISTING CONDITIONS
Demolition
FIRE SUPPRESSION
Fire Protection and Suppression
HEATING, VENTILATIING, AND AIR-CONDITIONING (HVAC)
Common Work Results for HVAC
Common Motor Requirements for HVAC Equipment
Hangers and Supports for HVAC Piping and Equipment
Vibration Controls for HVAC
Identification for HVAC Piping and Equipment
Testing, Adjusting, and Balancing for HVAC
Refrigerant Piping
Computer-Room Air-Conditioner
Cumberland Branch CRAC Replacement Table of Contents
067196-11 06/21/2023 TOC-2
DIVIDION 26 ELECTRICAL
26 00 10 Electrical General Provisions
26 00 51 Common Work Results for Electrical
26 05 19 Conductors and Cables
26 05 26 Grounding and Bonding
26 05 29 Hangers and Supports for Electrical Systems
26 05 33 Raceways and Boxes
26 28 16 Enclosed Switches and Circuit Breakers
Cumberland Branch CRAC Replacement 067196-11 06/21/2023
01 10 00 - 1 Summary
SECTION 01 10 00
SUMMARY
PART 1 GENERAL
1.01 PROJECT
A. Project Name: 067196.11 MVA Cumberland Branch CRAC Replacement
B. Owner's Name: Maryland Motor Vehicle Administration (MVA) .
C. Architect's Name: Gannett Fleming.
D. The Project consists of the removal and replacement of the CRAC units and all associated equipment located in Cumberland, Maryland.
1.02 CONTRACT DESCRIPTION
A. Contract Type: A single prime contract based on a Stipulated Price.
1.03 DESCRIPTION OF ALTERATIONS WORK
A. Scope of alterations work is indicated on drawings.
1.04 OWNER OCCUPANCY
A. Owner intends to occupy the Project upon Substantial Completion.
B. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.
C. Schedule the Work to accommodate Owner occupancy.
1.05 CONTRACTOR USE OF SITE AND PREMISES
A. Provide access to and from site as required by law and by Owner:
1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.
2. Do not obstruct roadways, sidewalks, or other public ways without permit.
1.06 WORK SEQUENCE
A. Coordinate construction schedule and operations with Owner.
1.07 SPECIFICATION SECTIONS APPLICABLE TO EVERY CONTRACT
A. Unless otherwise noted, provisions of the sections listed below apply to every contract.
Specific items of work listed under individual contract descriptions constitute exceptions.
B. Section 01 20 00 - Price and Payment Procedures.
C. Section 01 21 00 - Allowances.
D. Section 01 22 00 - Unit Prices.
E. Section 01 23 00 - Alternates.
F. Section 01 25 00 - Substitution Procedures.
G. Section 01 30 00 - Administrative Requirements.
H. Section 01 31 14 - Facility Services Coordination.
I. Section 01 32 16 - Construction Progress Schedule.
J. Section 01 35 53 - Security Procedures.
K. Section 01 40 00 - Quality Requirements.
L. Section 01 42 16 - Definitions.
M. Section 01 42 19 - Reference Standards.
N. Section 01 50 00 - Temporary Facilities and Controls.
O. Section 01 51 00 - Temporary Utilities.
P. Section 01 52 13 - Field Offices and Sheds.
01 10 00 - 2 Summary
Q. Section 01 55 00 - Vehicular Access and Parking.
R. Section 01 58 13 - Temporary Project Signage.
S. Section 01 60 00 - Product Requirements.
T. Section 01 61 16 - Volatile Organic Compound (VOC) Content Restrictions.
U. Section 01 70 00 - Execution and Closeout Requirements.
V. Section 01 78 00 - Closeout Submittals.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
END OF SECTION
01 20 00 - 1 Price and Payment Procedures
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Procedures for preparation and submittal of applications for progress payments.
B. Change procedures.
C. Procedures for preparation and submittal of application for final payment.
1.02 SCHEDULE OF VALUES
A. Use Schedule of Values Form: AIA G703, edition stipulated in the Agreement.
B. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit draft to Architect for approval.
C. Forms filled out by hand will not be accepted.
D. Submit Schedule of Values in duplicate within 15 calendar days after date of Owner-Contractor Agreement.
1.03 APPLICATIONS FOR PROGRESS PAYMENTS
A. Payment Period: Submit at intervals stipulated in the Agreement.
B. Use Form AIA G702 and Form AIA G703, edition stipulated in the Agreement.
C. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to Architect for approval.
D. Forms filled out by hand will not be accepted.
E. For each item, provide a column for listing each of the following:
1. Item Number.
2. Description of work.
3. Scheduled Values.
4. Previous Applications.
5. Work in Place and Stored Materials under this Application.
6. Authorized Change Orders.
7. Total Completed and Stored to Date of Application.
8. Percentage of Completion.
9. Balance to Finish.
10. Retainage.
F. Execute certification by signature of authorized officer.
G. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of work.
H. Submit one electronic and zero hard-copies of each Application for Payment.
I. Include the following with the application:
1. Transmittal letter as specified for submittals in Section 01 30 00.
2. Construction progress schedule, revised and current as specified in Section 01 30 00.
1.04 MODIFICATION PROCEDURES
A. For minor changes not involving an adjustment to the Contract Sum or Contract Time, Architect will issue instructions directly to Contractor.
B. For other required changes, Architect will issue a document signed by Owner instructing Contractor to proceed with the change, for subsequent inclusion in a Change Order.
1. The document will describe the required changes and will designate method of determining any change in Contract Sum or Contract Time.
2. Promptly execute the change.
01 20 00 - 2 Price and Payment Procedures
C. For changes for which advance pricing is desired, Architect will issue a document that includes a detailed description of a proposed change with supplementary or revised drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required and the period of time during which the requested price will be considered valid . Contractor shall prepare and submit a fixed price quotation within 7 days.
D. Computation of Change in Contract Amount: As specified in the Agreement and Conditions of the Contract.
E. Execution of Change Orders: Architect will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.
1.05 APPLICATION FOR FINAL PAYMENT
A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Sum, previous payments, and sum remaining due.
B. Application for Final Payment will not be considered until the following have been accomplished:
1. All closeout procedures specified in Section 01 70 00.
PART 2 PRODUCTS - NOT USED
01 21 00 - 1 Allowances
SECTION 01 21 00
ALLOWANCES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Inspecting and testing allowances.
B. Payment and modification procedures relating to allowances.
1.02 INSPECTING AND TESTING ALLOWANCES
A. Costs Not Included in the Inspecting and Testing Allowances:
1. Costs of incidental labor and facilities required to assist inspecting or testing agency.
2. Costs of testing services used by Contractor separate from Contract Document requirements.
3. Costs of retesting upon failure of previous tests as determined by Architect.
B. Payment Procedures:
1. Submit one copy of the inspecting or testing firm's invoice with next application for payment.
PART 2 PRODUCTS - NOT USED
01 22 00 - 1 Unit Prices
SECTION 01 22 00
UNIT PRICES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. List of unit prices, for use in preparing Bids.
B. Measurement and payment criteria applicable to Work performed under a unit price payment method.
1.02 COSTS INCLUDED
A. Unit Prices included on the Bid Form shall include full compensation for all required labor, products, tools, equipment, plant, transportation, services and incidentals; erection, application or installation of an item of the Work; overhead and profit.
1.03 UNIT QUANTITIES SPECIFIED
A. Quantities indicated in the Bid Form are for bidding and contract purposes only. Quantities and measurements of actual Work will determine the payment amount.
1.04 MEASUREMENT OF QUANTITIES
A. Measurement methods delineated in the individual specification sections complement the criteria of this section. In the event of conflict, the requirements of the individual specification section govern.
B. Take all measurements and compute quantities. Measurements and quantities will be verified by Architect.
C. Assist by providing necessary equipment, workers, and survey personnel as required.
D. Measurement by Weight: Concrete reinforcing steel, rolled or formed steel or other metal shapes will be measured by handbook weights. Welded assemblies will be measured by handbook or scale weight.
E. Measurement by Volume: Measured by cubic dimension using mean length, width and height or thickness.
F. Measurement by Area: Measured by square dimension using mean length and width or radius.
G. Linear Measurement: Measured by linear dimension, at the item centerline or mean chord.
H. Stipulated Price Measurement: Items measured by weight, volume, area, or linear means or combination, as appropriate, as a completed item or unit of the Work.
1.05 PAYMENT
A. Payment for Work governed by unit prices will be made on the basis of the actual measurements and quantities of Work that is incorporated in or made necessary by the Work and accepted by the Architect, multiplied by the unit price.
B. Payment will not be made for any of the following:
1. Products wasted or disposed of in a manner that is not acceptable.
2. Products determined as unacceptable before or after placement.
3. Products not completely unloaded from the transporting vehicle.
4. Products placed beyond the lines and levels of the required Work.
5. Products remaining on hand after completion of the Work.
6. Loading, hauling, and disposing of rejected Products.
1.06 DEFECT ASSESSMENT
A. Replace Work, or portions of the Work, not complying with specified requirements.
B. If, in the opinion of Architect, it is not practical to remove and replace the Work, Architect will direct one of the following remedies:
1. The defective Work will be partially repaired to the instructions of the Architect, and the unit price will be adjusted to a new unit price at the discretion of Architect.
01 22 00 - 2 Unit Prices
C. If, in the opinion of Owner, it is not practical to remove and replace the Work, Owner will direct one of the following remedies:
1. The defective Work will be partially repaired to the instructions of the Owner, and the unit price will be adjusted to a new unit price at the discretion of Owner.
D. The individual specification sections may modify these options or may identify a specific formula or percentage price reduction.
E. The authority of Owner to assess the defect and identify payment adjustment is final.
PART 2 PRODUCTS - NOT USED
01 23 00 - 1 Alternates
SECTION 01 23 00
ALTERNATES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Description of Alternates.
B. Procedures for pricing Alternates.
C. Documentation of changes to Contract Price and Contract Time.
1.02 ACCEPTANCE OF ALTERNATES
A. Alternates quoted on Bid Forms will be reviewed and accepted or rejected at Owner's option.
Accepted Alternates will be identified in the Owner-Contractor Agreement.
B. Coordinate related work and modify surrounding work to integrate the Work of each Alternate.
PART 2 PRODUCTS - NOT USED
01 25 00 - 1 Substitution Procedures
SECTION 01 25 00
SUBSTITUTION PROCEDURES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Procedural requirements for proposed substitutions.
1.02 DEFINITIONS
A. Substitutions: Changes from Contract Documents requirements proposed by Contractor to materials, products, assemblies, and equipment.
1. Substitutions for Cause: Proposed due to changed Project circumstances beyond
Contractor's control.
a. Unavailability.
b. Regulatory changes.
2. Substitutions for Convenience: Proposed due to possibility of offering substantial advantage to the Project.
1.03 REFERENCE STANDARDS
A. CSI/CSC Form 1.5C - Substitution Request (During the Bidding/Negotiating Stage).
B. CSI/CSC Form 13.1A - Substitution Request (After the Bidding/Negotiating Phase).
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 GENERAL REQUIREMENTS
A. A Substitution Request for products, assemblies, materials, and equipment constitutes a representation that the submitter:
1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product, equipment, assembly, or system.
2. Agrees to provide the same warranty for the substitution as for the specified product.
3. Agrees to coordinate installation and make changes to other work that may be required for the work to be complete, with no additional cost to Owner.
4. Waives claims for additional costs or time extension that may subsequently become apparent.
B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents. Burden of proof is on proposer.
C. Content: Include information necessary for tracking the status of each Substitution Request, and information necessary to provide an actionable response.
1. No specific form is required. Contractor's Substitution Request documentation must include the following:
a. Project Information:
1) Official project name and number, and any additional required identifiers established in Contract Documents.
b. Substitution Request Information:
1) Discrete and consecutive Substitution Request number, and descriptive subject/title.
2) Issue date.
3) Reference to particular Contract Document(s) specification section number, title, and article/paragraph(s).
4) Description of Substitution.
5) Reason why the specified item cannot be provided.
6) Differences between proposed substitution and specified item.
7) Description of how proposed substitution affects other parts of work.
c. Attached Comparative Data: Provide point-by-point, side-by-side comparison addressing essential attributes specified, as appropriate and relevant for the item:
01 25 00 - 2 Substitution Procedures
1) Physical characteristics.
2) In-service performance.
3) Expected durability.
4) Warranties.
5) Other salient features and requirements.
6) Include, as appropriate or requested, the following types of documentation:
(a) Product Data:
(b) Samples.
(c) Certificates, test, reports or similar qualification data.
(d) Drawings, when required to show impact on adjacent construction elements.
d. Impact of Substitution:
1) Savings to Owner for accepting substitution.
2) Change to Contract Time due to accepting substitution.
D. Limit each request to a single proposed substitution item.
1. Submit an electronic document, combining the request form with supporting data into single document.
3.02 SUBSTITUTION PROCEDURES DURING PROCUREMENT
A. Submittal Time Restrictions:
1. Instructions to Bidders specifies time restrictions and the documents required for submitting substitution requests during the bidding period.
2. Owner will consider requests for substitutions only if submitted at least 10 days prior to the date for receipt of bids.
B. Submittal Form (before award of contract):
1. Submit substitution requests by completing CSI/CSC Form 1.5C - Substitution Request.
See this form for additional information and instructions. Use only this form; other forms of submission are unacceptable.
3.03 SUBSTITUTION PROCEDURES DURING CONSTRUCTION
A. Submittal Form (after award of contract):
1. Submit substitution requests by completing CSI/CSC Form 13.1A - Substitution Request
(After Bidding/Negotiating). See this form for additional information and instructions. Use only this form; other forms of submission are unacceptable.
B. Submit request for Substitution for Cause within 14 days of discovery of need for substitution, but not later than 14 days prior to time required for review and approval by Architect, in order to stay on approved project schedule.
C. Submit request for Substitution for Convenience within 14 days of discovery of its potential advantage to the project, but not later than 14 days prior to time required for review and approval by Architect, in order to stay on approved project schedule.
1. In addition to meeting general documentation requirements, document how the requested substitution benefits the Owner through cost savings, time savings, greater energy conservation, or in other specific ways.
2. Document means of coordinating of substitution item with other portions of the work, including work by affected subcontractors.
3. Bear the costs engendered by proposed substitution of:
a. Owner's compensation to the Architect for any required redesign, time spent processing and evaluating the request.
D. Substitutions will not be considered under one or more of the following circumstances:
1. When they are indicated or implied on shop drawing or product data submittals, without having received prior approval.
2. Without a separate written request.
01 25 00 - 3 Substitution Procedures
3.04 RESOLUTION
A. Architect may request additional information and documentation prior to rendering a decision.
Provide this data in an expeditious manner.
B. Architect will notify Contractor in writing of decision to accept or reject request.
1. Architect's decision following review of proposed substitution will be noted on the submitted form.
3.05 ACCEPTANCE
A. Accepted substitutions change the work of the Project. They will be documented and incorporated into work of the project by Change Order, Construction Change Directive, Architectural Supplementary Instructions, or similar instruments provided for in the Conditions of the Contract.
3.06 CLOSEOUT ACTIVITIES
A. See Section 01 78 00 - Closeout Submittals, for closeout submittals.
B. Include completed Substitution Request Forms as part of the Project record. Include both approved and rejected Requests.
01 30 00 - 1 Administrative Requirements
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. General administrative requirements.
B. Electronic document submittal service.
C. Preconstruction meeting.
D. Site mobilization meeting.
E. Progress meetings.
F. Construction progress schedule.
G. Contractor's daily reports.
H. Progress photographs.
I. Coordination drawings.
J. Submittals for review, information, and project closeout.
K. Number of copies of submittals.
L. Requests for Interpretation (RFI) procedures.
M. Submittal procedures.
1.02 REFERENCE STANDARDS
A. AIA G716 - Request for Information.
B. AIA G810 - Transmittal Letter.
1.03 GENERAL ADMINISTRATIVE REQUIREMENTS
A. Comply with requirements of Section 01 70 00 - Execution and Closeout Requirements for coordination of execution of administrative tasks with timing of construction activities.
B. Make the following types of submittals to Architect:
1. Requests for Interpretation (RFI).
2. Requests for substitution.
3. Shop drawings, product data, and samples.
4. Test and inspection reports.
5. Design data.
6. Manufacturer's instructions and field reports.
7. Applications for payment and change order requests.
8. Progress schedules.
9. Coordination drawings.
10. Correction Punch List and Final Correction Punch List for Substantial Completion.
11. Closeout submittals.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 ELECTRONIC DOCUMENT SUBMITTAL SERVICE
A. All documents transmitted for purposes of administration of the contract are to be in electronic (PDF, MS Word, or MS Excel) format, as appropriate to the document, and transmitted via an Internet-based submittal service that receives, logs and stores documents, provides electronic stamping and signatures, and notifies addressees via email.
1. Besides submittals for review, information, and closeout, this procedure applies to
Requests for Interpretation (RFIs), progress documentation, contract modification documents (e.g. supplementary instructions, change proposals, change orders), applications for payment, field reports and meeting minutes, Contractor's correction punchlist, and any other document any participant wishes to make part of the project
01 30 00 - 2 Administrative Requirements record.
2. Contractor and Architect are required to use this service.
3. It is Contractor's responsibility to submit documents in allowable format.
4. Subcontractors, suppliers, and Architect's consultants are to be permitted to use the service at no extra charge.
5. Users of the service need an email address, internet access, and PDF review software that includes ability to mark up and apply electronic stamps (such as Adobe Acrobat, www.adobe.com, or Bluebeam PDF Revu, www.bluebeam.com), unless such software capability is provided by the service provider.
6. Paper document transmittals will not be reviewed; emailed electronic documents will not be reviewed.
7. All other specified submittal and document transmission procedures apply, except that electronic document requirements do not apply to samples or color selection charts.
B. Submittal Service: The selected service is:
C. Training: One, one-hour, web-based training session will be arranged for all participants, with representatives of Architect and Contractor participating; further training is the responsibility of the user of the service.
D. Project Closeout: Architect will determine when to terminate the service for the project and is responsible for obtaining archive copies of files for Owner.
3.02 PRECONSTRUCTION MEETING
A. Architect will schedule a meeting after Notice of Award.
B. Attendance Required:
1. Owner.
2. Architect.
3. Contractor.
C. Agenda:
1. Execution of Owner-Contractor Agreement.
2. Submission of executed bonds and insurance certificates.
3. Distribution of Contract Documents.
4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.
5. Submission of initial Submittal schedule.
6. Designation of personnel representing the parties to Contract and Architect .
7. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.
8. Scheduling.
D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.
3.03 SITE MOBILIZATION MEETING
A. Owner will schedule meeting at the Project site prior to Contractor occupancy.
B. Attendance Required:
1. Contractor.
2. Owner.
3. Architect.
4. Contractor's superintendent.
5. Major subcontractors.
C. Agenda:
1. Use of premises by Owner and Contractor.
2. Owner's requirements.
3. Construction facilities and controls provided by Owner.
4. Temporary utilities provided by Owner.
01 30 00 - 3 Administrative Requirements
5. Survey and building layout.
6. Security and housekeeping procedures.
7. Schedules.
8. Application for payment procedures.
9. Procedures for testing.
10. Procedures for maintaining record documents.
11. Requirements for start-up of equipment.
12. Inspection and acceptance of equipment put into service during construction period.
D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.
3.04 PROGRESS MEETINGS
A. Schedule and administer meetings throughout progress of the work at maximum bi-monthly intervals.
B. Attendance Required:
1. Contractor.
2. Owner.
3. Architect.
4. Contractor's superintendent.
5. Major subcontractors.
C. Agenda:
1. Review minutes of previous meetings.
2. Review of work progress.
3. Field observations, problems, and decisions.
4. Identification of problems that impede, or will impede, planned progress.
5. Review of submittals schedule and status of submittals.
6. Review of RFIs log and status of responses.
7. Review of off-site fabrication and delivery schedules.
8. Maintenance of progress schedule.
9. Corrective measures to regain projected schedules.
10. Planned progress during succeeding work period.
11. Maintenance of quality and work standards.
12. Effect of proposed changes on progress schedule and coordination.
13. Other business relating to work.
D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.
3.05 CONSTRUCTION PROGRESS SCHEDULE - SEE SECTION 01 32 16
A. Within 10 business days after date of the Agreement, submit preliminary schedule defining planned operations for the first 60 days of work, with a general outline for remainder of work.
B. If preliminary schedule requires revision after review, submit revised schedule within 10 business days.
C. Within 20 business days after review of preliminary schedule, submit draft of proposed complete schedule for review.
1. Include written certification that major contractors have reviewed and accepted proposed schedule.
D. Within 10 working days after joint review, submit complete schedule.
E. Submit updated schedule with each Application for Payment.
3.06 DAILY CONSTRUCTION REPORTS
A. Include only factual information. Do not include personal remarks or opinions regarding operations and/or personnel.
01 30 00 - 4 Administrative Requirements
B. In addition to transmitting electronically a copy to Owner and Architect, submit two printed copies at weekly intervals.
1. Submit in format acceptable to Owner.
C. Prepare a daily construction report recording the following information concerning events at Project site and project progress:
1. Date.
2. High and low temperatures, and general weather conditions.
3. List of subcontractors at Project site.
4. List of separate contractors at Project site.
5. Approximate count of personnel at Project site.
a. Include a breakdown for supervisors, laborers, journeymen, equipment operators, and helpers.
6. Major equipment at Project site.
7. Material deliveries.
8. Safety, environmental, or industrial relations incidents.
9. Meetings and significant decisions.
10. Unusual events (submit a separate special report).
11. Stoppages, delays, shortages, and losses. Include comparison between scheduled work activities (in Contractor's most recently updated and published schedule) and actual activities. Explain differences, if any. Note days or periods when no work was in progress and explain the reasons why.
12. Testing and/or inspections performed.
13. Signature of Contractor's authorized representative.
3.07 PROGRESS PHOTOGRAPHS
A. Submit new photographs at least once a month, within 3 days after being taken.
B. Maintain one set of all photographs at project site for reference; same copies as submitted, identified as such.
C. Photography Type: Digital; electronic files.
D. Provide photographs of site and construction throughout progress of work produced by an experienced photographer, acceptable to Architect.
E. In addition to periodic, recurring views, take photographs of each of the following events:
1. Final completion, minimum of ten (10) photos.
F. Views:
1. Provide non-aerial photographs from four cardinal views at each specified time, until date of Substantial Completion.
2. Consult with Architect for instructions on views required.
3. Provide factual presentation.
4. Provide correct exposure and focus, high resolution and sharpness, maximum depth of field, and minimum distortion.
G. Digital Photographs: 24 bit color, minimum resolution of 1024 by 768, in JPG format; provide files unaltered by photo editing software.
1. Delivery Medium: Via email.
2. File Naming: Include project identification, date and time of view, and view identification.
3. PDF File: Assemble all photos into printable pages in PDF format, with 2 to 3 photos per page, each photo labeled with file name; one PDF file per submittal.
3.08 COORDINATION DRAWINGS
A. Review drawings prior to submission to Architect.
3.09 REQUESTS FOR INFORMATION (RFI)
A. Definition: A request seeking one of the following:
1. An interpretation, amplification, or clarification of some requirement of Contract
Documents arising from inability to determine from them the exact material, process, or
01 30 00 - 5 Administrative Requirements system to be installed; or when the elements of construction are required to occupy the same space (interference); or when an item of work is described differently at more than one place in Contract Documents.
2. A resolution to an issue which has arisen due to field conditions and affects design intent.
B. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of Contract Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.
1. Prepare a separate RFI for each specific item.
a. Review, coordinate, and comment on requests originating with subcontractors and/or materials suppliers.
b. Do not forward requests which solely require internal coordination between subcontractors.
2. Prepare in a format and with content acceptable to Owner.
a. Use AIA G716 - Request for Information .
3. Prepare using software provided by the Electronic Document Submittal Service.
C. Reason for the RFI: Prior to initiation of an RFI, carefully study all Contract Documents to confirm that information sufficient for their interpretation is definitely not included.
1. Unacceptable Uses for RFIs: Do not use RFIs to request the following::
a. Approval of submittals (use procedures specified elsewhere in this section).
b. Approval of substitutions (see Section - 01 60 00 - Product Requirements)
c. Changes that entail change in Contract Time and Contract Sum (comply with provisions of the Conditions of the Contract).
d. Different methods of performing work than those indicated in the Contract Drawings and Specifications (comply with provisions of the Conditions of the Contract).
2. Improper RFIs: Requests not prepared in compliance with requirements of this section, and/or missing key information required to render an actionable response. They will be returned without a response, with an explanatory notation.
3. Frivolous RFIs: Requests regarding information that is clearly indicated on, or reasonably inferable from, Contract Documents, with no additional input required to clarify the question. They will be returned without a response, with an explanatory notation.
D. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.
1. Official Project name and number, and any additional required identifiers established in
Contract Documents.
2. Issue date, and requested reply date.
3. Reference to particular Contract Document(s) requiring additional information/interpretation. Identify pertinent drawing and detail number and/or specification section number, title, and paragraph(s).
4. Annotations: Field dimensions and/or description of conditions which have engendered the request.
5. Contractor's suggested resolution: A written and/or a graphic solution, to scale, is required in cases where clarification of coordination issues is involved, for example;
routing, clearances, and/or specific locations of work shown diagrammatically in Contract Documents. If applicable, state the likely impact of the suggested resolution on Contract Time or the Contract Sum.
E. RFI Log: Prepare and maintain a tabular log of RFIs for the duration of the project.
1. Indicate current status of every RFI. Update log promptly and on a regular basis.
2. Note dates of when each request is made, and when a response is received.
3. Highlight items requiring priority or expedited response.
4. Highlight items for which a timely response has not been received to date.
F. Review Time: Architect will respond and return RFIs to Contractor within seven calendar days of receipt. For the purpose of establishing the start of the mandated response period, RFIs received after 12:00 noon will be considered as having been received on the following regular working day.
01 30 00 - 6 Administrative Requirements
1. Response period may be shortened or lengthened for specific items, subject to mutual agreement, and recorded in a timely manner in progress meeting minutes.
G. Responses: Content of answered RFIs will not constitute in any manner a directive or authorization to perform extra work or delay the project. If in Contractor's belief it is likely to lead to a change to Contract Sum or Contract Time, promptly issue a notice to this effect, and follow up with an appropriate Change Order request to Owner.
1. Response may include a request for additional information, in which case the original RFI will be deemed as having been answered, and an amended one is to be issued forthwith.
Identify the amended RFI with an R suffix to the original number.
2. Do not extend applicability of a response to specific item to encompass other similar conditions, unless specifically so noted in the response.
3. Upon receipt of a response, promptly review and distribute it to all affected parties, and update the RFI Log.
4. Notify Architect within seven calendar days if an additional or corrected response is required by submitting an amended version of the original RFI, identified as specified above.
3.10 SUBMITTAL SCHEDULE
A. Submit to Architect for review a schedule for submittals in tabular format.
1. Submit at the same time as the preliminary schedule specified in Section - 01 32 16 -
Construction Progress Schedule.
2. Coordinate with Contractor's construction schedule and schedule of values.
3. Format schedule to allow tracking of status of submittals throughout duration of construction.
4. Arrange information to include scheduled date for initial submittal, specification number and title, submittal category (for review or for information), description of item of work covered, and role and name of subcontractor.
5. Account for time required for preparation, review, manufacturing, fabrication and delivery when establishing submittal delivery and review deadline dates.
a. For assemblies, equipment, systems comprised of multiple components and/or requiring detailed coordination with other work, allow for additional time to make corrections or revisions to initial submittals, and time for their review.
3.11 SUBMITTALS FOR REVIEW
A. When the following are specified in individual sections, submit them for review:
1. Product data.
2. Shop drawings.
3. Samples for selection.
4. Samples for verification.
B. Submit to Architect for review for the limited purpose of checking for compliance with information given and the design concept expressed in Contract Documents.
C. Samples will be reviewed for aesthetic, color, or finish selection.
D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 78 00 - Closeout Submittals.
3.12 SUBMITTALS FOR INFORMATION
A. When the following are specified in individual sections, submit them for information:
1. Design data.
2. Certificates.
3. Test reports.
4. Inspection reports.
5. Manufacturer's instructions.
6. Manufacturer's field reports.
7. Other types indicated.
01 30 00 - 7 Administrative Requirements
B. Submit for Architect's knowledge as contract administrator or for Owner.
3.13 SUBMITTALS FOR PROJECT CLOSEOUT
A. Submit Correction Punch List for Substantial Completion.
B. Submit Final Correction Punch List for Substantial Completion.
C. When the following are specified in individual sections, submit them at project closeout in compliance with requirements of Section 01 78 00 - Closeout Submittals:
1. Project record documents.
2. Operation and maintenance data.
3. Warranties.
4. Bonds.
5. Other types as indicated.
D. Submit for Owner's benefit during and after project completion.
3.14 NUMBER OF COPIES OF SUBMITTALS
A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.
B. Samples: Submit the number specified in individual specification sections; one of which will be retained by Architect.
1. After review, produce duplicates.
2. Retained samples will not be returned to Contractor unless specifically so stated.
3.15 SUBMITTAL PROCEDURES
A. General Requirements:
1. Submit separate packages of submittals for review and submittals for information, when included in the same specification section.
2. Transmit using approved form.
a. Use Contractor's form, subject to prior approval by Architect.
3. Identify: Project; Contractor; subcontractor or supplier; pertinent drawing and detail number; and specification section number and article/paragraph, as appropriate on each copy.
4. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.
5. Schedule submittals to expedite the Project, and coordinate submission of related items.
a. For each submittal for review, allow 10 business days excluding delivery time to and from the Contractor .
b. For sequential reviews involving Architect's consultants, Owner, or another affected party, allow an additional 7 calendar days.
c. For sequential reviews involving approval from authorities having jurisdiction (AHJ), in addition to Architect's approval, allow an additional 30 calendar days.
6. Identify variations from Contract Documents and product or system limitations that may be detrimental to successful performance of the completed work.
7. Provide space for Contractor and Architect review stamps.
8. When revised for resubmission, identify all changes made since previous submission.
B. Product Data Procedures:
1. Submit only information required by individual specification sections.
2. Collect required information into a single submittal.
3. Do not submit (Material) Safety Data Sheets for materials or products.
C. Shop Drawing Procedures:
1. Prepare accurate, drawn-to-scale, original shop drawing documentation by interpreting
Contract Documents and coordinating related work.
2. Do not reproduce Contract Documents to create shop drawings.
01 30 00 - 8 Administrative Requirements
3. Generic, non-project-specific information submitted as shop drawings do not meet the requirements for shop drawings.
D. Samples Procedures:
1. Transmit related items together as single package.
2. Identify each item to allow review for applicability in relation to shop drawings showing installation locations.
3.16 SUBMITTAL REVIEW
A. Submittals for Review: Architect will review each submittal, and approve, or take other appropriate action.
B. Submittals for Information: Architect will acknowledge receipt and review. See below for actions to be taken.
C. Architect's actions will be reflected by marking each returned submittal using virtual stamp on electronic submittals.
D. Architect's and consultants' actions on items submitted for review:
1. Authorizing purchasing, fabrication, delivery, and installation:
a. "Approved", or language with same legal meaning.
b. "Approved as Noted, Resubmission not required", or language with same legal meaning.
1) At Contractor's option, submit corrected item, with review notations acknowledged and incorporated.
2. Not Authorizing fabrication, delivery, and installation:
E. Architect's and consultants' actions on items submitted for information:
1. Items for which no action was taken:
a. "Received" - to notify the Contractor that the submittal has been received for record only.
2. Items for which action was taken:
a. "Reviewed" - no further action is required from Contractor.
01 32 16 - 1 Construction Progress Schedule
SECTION 01 32 16
CONSTRUCTION PROGRESS SCHEDULE
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Preliminary schedule.
B. Construction progress schedule, bar chart type.
1.02 SUBMITTALS
A. Within 10 business days after date of Agreement, submit preliminary schedule.
B. If preliminary schedule requires revision after review, submit revised schedule within 10 businedays.
C. Within 20 business days after review of preliminary schedule, submit draft of proposed complete schedule for review.
1. Include written certification that major contractors have reviewed and accepted proposed schedule.
D. Within 10 business days after joint review, submit complete schedule.
E. Submit updated schedule with each Application for Payment.
F. Submit in PDF format.
1.03 SCHEDULE FORMAT
A. Listings: In chronological order according to the start date for each activity. Identify each activity with the applicable specification section number.
B. Diagram Sheet Size: Maximum 22 x 17 inches.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 PRELIMINARY SCHEDULE
A. Prepare preliminary schedule in the form of a horizontal bar chart.
3.02 CONTENT
A. Show complete sequence of construction by activity, with dates for beginning and completion of each element of construction.
B. Identify each item by specification section number.
C. Identify work of separate stages and other logically grouped activities.
D. Provide sub-schedules for each stage of Work identified in Section 01 10 00 - Summary.
E. Provide sub-schedules to define critical portions of the entire schedule.
F. Show accumulated percentage of completion of each item, and total percentage of Work completed, as of the first day of each month.
G. Coordinate content with schedule of values specified in Section 01 20 00 - Price and Payment Procedures.
H. Provide legend for symbols and abbreviations used.
3.03 BAR CHARTS
A. Include a separate bar for each major portion of Work or operation.
B. Identify the first work day of each week.
3.04 REVIEW AND EVALUATION OF SCHEDULE
A. Participate in joint review and evaluation of schedule with Architect at each submittal.
B. Evaluate project status to determine work behind schedule and work ahead of schedule.
C. After review, revise as necessary as result of review, and resubmit within10 business days.
01 32 16 - 2 Construction Progress Schedule
3.05 UPDATING SCHEDULE
A. Maintain schedules to record actual start and finish dates of completed activities.
B. Indicate progress of each activity to date of revision, with projected completion date of each activity.
C. Annotate diagrams to graphically depict current status of Work.
D. Identify activities modified since previous submittal, major changes in Work, and other identifiable changes.
E. Indicate changes required to maintain Date of Substantial Completion.
F. Submit reports required to support recommended changes.
3.06 DISTRIBUTION OF SCHEDULE
A. Distribute copies of updated schedules to Contractor's project site file, to subcontractors, suppliers, Architect, Owner, and other concerned parties.
B. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules.
01 35 53 - 1 Security Procedures
SECTION 01 35 53
SECURITY PROCEDURES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Security measures including entry control, personnel identification, and miscellaneous restrictions .
1.02 SECURITY PROGRAM
A. Protect Work , existing premises and Owner's operations from theft, vandalism, and unauthorized entry.
B. Initiate program in coordination with Owner's existing security system at project mobilization.
C. Maintain program throughout construction period until Owner occupancy.
1.03 ENTRY CONTROL
A. Restrict entrance of persons and vehicles into Project site and existing facilities.
B. Allow entrance only to authorized persons with proper identification.
C. Maintain log of workers and visitors, make available to Owner on request.
1.04 PERSONNEL IDENTIFICATION
A. Provide identification badge to each person authorized to enter premises.
B. Badge To Include: Personal photograph, name, assigned number , expiration date and employer.
C. Require return of badges at expiration of their employment on the Work.
1.05 RESTRICTIONS
PART 2 PRODUCTS - NOT USED
01 40 00 - 1 Quality Requirements
SECTION 01 40 00
QUALITY REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Submittals.
B. Quality assurance.
C. References and standards.
D. Testing and inspection agencies and services.
E. Control of installation.
F. Tolerances.
G. Defect Assessment.
1.02 REFERENCE STANDARDS
A. IAS AC89 - Accreditation Criteria for Testing Laboratories.
1.03 DEFINITIONS
A. Contractor's Quality Control Plan: Contractor's management plan for executing the Contract for Construction.
1.04 SUBMITTALS
A. See Section 01 30 00 - Administrative Requirements, for submittal procedures.
B. Designer's Qualification Statement: Submit for Architect's knowledge as contract administrator, or for Owner's information.
1. Include information for each individual professional responsible for producing, or supervising production of, design-related professional services provided by Contractor.
a. Full name.
b. Professional licensure information.
c. Statement addressing extent and depth of experience specifically relevant to design of items assigned to Contractor.
C. Design Data: Submit for Architect's knowledge as contract administrator for the limited purpose of assessing compliance with information given and the design concept expressed in the Contract Documents, or for Owner's information.
1. Include calculations that have been used to demonstrate compliance to performance and regulatory criteria provided, and to determine design solutions.
2. Include required product data and shop drawings.
3. Include a statement or certification attesting that design data complies with criteria indicated, such as building codes, loads, functional, and similar engineering requirements.
4. Include signature and seal of design professional responsible for allocated design services on calculations and drawings.
D. Test Reports: After each test/inspection, promptly submit two copies of report to Architect and to Contractor.
1. Include:
a. Date issued.
b. Project title and number.
c. Name of inspector.
d. Date and time of sampling or inspection.
e. Identification of product and specifications section.
f. Location in the Project.
g. Type of test/inspection.
h. Date of test/inspection.
i. Results of test/inspection.
j. Compliance with Contract Documents.
01 40 00 - 2 Quality Requirements
k. When requested by Architect, provide interpretation of results.
2. Test report submittals are for Architect's knowledge as contract administrator for the limited purpose of assessing compliance with information given and the design concept expressed in the Contract Documents, or for Owner's information.
E. Manufacturer's Instructions: When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, for the Owner's information. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.
1.05 QUALITY ASSURANCE
A. Testing Agency Qualifications:
1. Prior to start of work, submit agency name, address, and telephone number, and names of full time registered Engineer and responsible officer.
2. Submit copy of report of laboratory facilities inspection made by NIST Construction
Materials Reference Laboratory during most recent inspection, with memorandum of remedies of any deficiencies reported by the inspection.
3. Qualification Statement: Provide documentation showing testing laboratory is accredited under IAS AC89.
B. Designer Qualifications: Where professional engineering design services and design data submittals are specifically required of Contractor by Contract Documents, provide services of a Professional Engineer experienced in design of this type of work and licensed in the State in which the Project is located.
C. Contractor's Quality Control (CQC) Plan:
1. Prior to start of work, submit a comprehensive plan describing how contract deliverables will be produced. Tailor CQC plan to specific requirements of the project. Include the following information:
a. Management Structure: Identify personnel responsible for quality. Include a chart showing lines of authority.
1) Include qualifications (in resume form), duties, responsibilities of each person assigned to CQC function.
b. Owner will not make a separate payment for providing and maintaining a Quality
Control Plan. Include associated costs in Bid price.
c. Acceptance of the plan is required prior to start of construction activities not including mobilization work. Owner's acceptance of the plan will be conditional and predicated on continuing satisfactory adherence to the plan. Owner reserves the right to require Contractor to make changes to the plan and operations, including removal of personnel, as necessary, to obtain specified quality of work results.
D. Quality-Control Personnel Qualifications.