Attachment J1 - Previous Inspection Report 5016-Tank 1.pdf
PDF 7 MB Posted
- Attached to
- API Fuel Tank Inspection - Moody AFB, GA Federal contract opportunity
- Solicitation number
- W9128F25QA016
About this file
This is an API 653 Out-of-Service Inspection Report for Tank 1 (Facility 5016) at Moody Air Force Base in Georgia, conducted by the US Army Corps of Engineers (USACE) Omaha District on June 3-4, 2020. The inspection was performed on a 45-foot diameter, 34.5-foot high welded carbon steel vertical aboveground Jet-A (F-24) storage tank with a 10,000 barrel (420,000 gallon) capacity, constructed in 1953 and repaired in 2007.
The report identified several mandatory repairs needed, including replacement of damaged internal floating roof (IFR) wiper seals and vapor seals, and repair of the flexible membrane liner in the secondary containment. Multiple short-term and long-term recommended repairs were also identified, such as coating repairs, replacement of receipt valves, installation of proper pipe supports, and various structural/safety upgrades to meet current standards. The tank's cathodic protection system was functioning properly, and based on thickness measurements and corrosion rates, the next internal inspection is recommended for June 2040, with external inspections recommended for June 2025 (visual) and June 2035 (ultrasonic testing), contingent upon completion of mandatory repairs.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment J4 - Previous Inspection Report 5019-Tank 4.pdf | ||
| Attachment J3 - Previous Inspection Report 5018-Tank 3.pdf | ||
| Attachment 4-Addendum to 52.212-1.pdf | ||
| Wage Determination.pdf | ||
| Attachment E - Inspection Telecon Briefing Template.docx | DOCX document | |
| Attachment D - MCP and MS Report.xlsx | XLSX spreadsheet | |
| Attachment C - Fuel Storage Tank Data Sheet.xlsx | XLSX spreadsheet | |
| Attachment A - General Installation Security Requirements.pdf | ||
| Attachment 2 - Performance Work Statement (PWS).pdf | ||
| Attachment 1 - CLIN Schedule.pdf | ||
| Attachment J2 - Previous Inspection Report 5017-Tank 2.pdf | ||
| Attachment I - API External Template.docx | DOCX document | |
| Attachment B - Fuel Storage Tank LIst.xlsx | XLSX spreadsheet | |
| Combined Synopsis-Solicitation Moody AFB.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers Omaha District
API 653 Out-of-Service Inspection Report
Moody Air Force Base Facility 5016
Tank 1
US Army Corps of Engineers Center of Expertise for Petroleum, Oils and Lubricants
(USACE POL-MCX)
06/04/2020
API 653 Out-of-Service Inspection Report Moody AFB, Georgia
TABLE OF CONTENTS
ACRONYMS AND ABBREVIATIONS
GENERAL SUMMARY
INSPECTION DATE
STATE REGULATIONS
PREVIOUS INSPECTION DATES
RECOMMENDED FUTURE INSPECTION DATES
GENERAL TANK INFORMATION
A. GENERAL PROJECT INFORMATION
1. API 653 OOS (INTERNAL) INSPECTION
2. SITE INFORMATION
B. TANK INSPECTION COMMENTS
1. TANK CONSTRUCTION
2. TANK FOUNDATION
3. TANK BOTTOM
4. TANK SHELL
5. FIXED ROOF
6. TANK APPURTENANCES
7. TANK AND PIPING COATING
8. TANK PIPING SYSTEM
9. FIRE PROTECTION SYSTEM
10. SECONDARY CONTAINMENT
11. CATHODIC PROTECTION
C. FINDINGS AND RECOMMENDATIONS
1. MANDATORY REPAIRS PER API 650/653, UFC 3-460-01/3-460-03, OR DoD AW 78-24-27
2. SHORT-TERM RECOMMENDED REPAIRS
3. LONG-TERM RECOMMENDED REPAIRS
APPENDIX A: ENGINEERING CALCULATIONS AND DRAWINGS
NEXT INSPECTION
API/OSHA ACCESS STRUCTURE REPORT
APPENDIX B: API 653 CHECKLISTS FOR TANK INSPECTIONS
APPENDIX C: PHOTOGRAPHS
ACRONYMS AND ABBREVIATIONS
AFB Air Force Base
AFFF Aqueous Film Forming Foam
API American Petroleum Institute
ATG Automatic Tank Gauge
BBL Barrel
BMP Best Management Practices
CP Cathodic Protection
DB&B Double Block and Bleed
DFT Dry Film Thickness
DoD Department of Defense
FML Flexible Membrane Liner
HHLA High-High Level Alarm
HLA High Level Alarm
HLCV High Level Control Valve
IAW In Accordance With
ICCP Impressed Current Cathodic Protection
IFR Internal Floating Roof
LLA Low Level Alarm
LLLA Low-Low Level Alarm
MFL Magnetic Flux Leakage
MT Magnetic Particle Testing
NACE NACE International
NDT Non-Destructive Testing
NFPA National Fire Protection Association
OSHA Occupational Health and Safety Administration
OOR Out-of-Roundness
OOS Out-of-Service
PST Product Saver Tank
PT Dye Penetrant Testing
RMMR Recurring Maintenance and Minor Repair
SS Soil-Side
TLG Tape Level Gauge
TRV Thermal Relief Valve
TS Top-Side
UFC Unified Facilities Criteria
USACE United States Army Corps of Engineers
UTT Ultrasonic Thickness Testing
VT Visual Testing
GENERAL SUMMARY
Pond was retained by the United States Army Corps of Engineers (USACE) Omaha District to provide an out-of-service (OOS) tank inspection for Tank 1 (Facility 5016) at Moody Air Force Base (AFB) in Valdosta, Georgia.
The OOS inspection was performed 3-4 June 2020. Results of this inspection identified mandatory and recommended repairs/upgrades to fully comply with applicable sections of American Petroleum Institute (API) 650/653, Unified
Facilities Criteria (UFC) 3-460-01/3-460-03, Department of Defense (DoD) standard AW 78-24-27, Occupational
Safety and Health Administration (OSHA) guidelines, industry standards, and best management practices (BMP).
Tank 1 is a welded, carbon steel, vertical, aboveground Jet-A (F-24) storage tank. The tank is assumed to be constructed to API 12C standards by an unknown manufacturer in 1953 and was repaired by Toltest in April 2007 to API 653, 3rd Edition, Addendum 1. The tank is 45’-0” in diameter and 34’-6” high with a nominal capacity of 10,000
Barrels (BBL) (420,000 gallons).
Testing and inspection activities were performed in accordance with (IAW) applicable sections of API 653, 5th
Edition. This report contains a detailed account of the tank inspection, non-destructive testing (NDT) methods, and conclusions derived from the inspection and testing activities. Findings from this inspection are further detailed in
Section B – Tank Inspection Comments. Mandatory and recommended repairs/upgrades identified in Section B are further classified and listed in Section C – Findings and Recommendations.
INSPECTION DATE
API Out-of-Service (Internal) Inspection Date: 3-4 June 2020 Equipment Used:
Manufacturer: MFE Enterprises Tank Floor Scanner Model Number: MFE 2412 Mark III Calibration Method: Manufacturer Calibrated
Manufacturer: GE Krautkramer Ultrasonic Thickness Gauge Model Number: DMS GO+ Calibration Method: One-Point Calibration with Topcoat Function
Manufacturer: Fischer Technologies Dry Film Thickness (DFT) Gauge Model Number: Dual Scope MPOR
Manufacturer: Technidea Corporation Model Number: Zip Level Pro-200
Manufacturer: Fluke Model Number: True RMS Multimeter
Inspectors:
Darrell A. Walters James F. Hancock II
STATE REGULATIONS
State Regulation for API In-Service Tank Inspections: N/A State Regulation for API Out-of-Service Tank Inspections: N/A
PREVIOUS INSPECTION DATES
API Out-of-Service (Internal) Inspection Date: February 2018 API In-Service (External) Inspection Date: February 2018
RECOMMENDED FUTURE INSPECTION DATES
API Out-of-Service (Internal) Inspection Date: June 2040* API In-Service (External) Inspection Date: June 2025* *Inspection intervals are only valid upon completion of all mandatory repairs.
Darrell A. Walters James F. Hancock II
Integrity Engineer Sr. Technician
API 653 Inspector #93640 ST Certified Inspector # AST-6409
ASNT NDT Level I/II ASNT NDT Level I/II
GENERAL TANK INFORMATION
ITEM DESCRIPTION
Owner United States Air Force
Location Moody AFB
Facility Number 5016
Tank Number 1
State / Country Georgia / USA
City Valdosta
Inspection Date 3-4 June 2020
Tank Manufacturer Original: Unknown Repaired By: Toltest, Inc.
Design Standard Original: API 12C (Assumed) Repaired: API 653, 3rd Edition, Addendum 1
Date of Construction 1953
Tank Contents Jet-A (F-24)
Tank Serial Number N/A
Tank Diameter 45’-0”
Shell Height 34’-6”
Product Height Unknown
Tank Capacity 10,000 BBL (420,000 Gallons)
Foundation Concrete Ringwall
Construction
Bottom (Annular): Lap-Welded (Butt-Welded)
Shell: Butt-Welded W/ Six (6) Shell Courses
Fixed Roof: Lap-Welded W/ Center Support Column
Floating Roof: Honeycomb Pan
Material
Bottom: Carbon Steel
Shell: Carbon Steel
Fixed Roof: Carbon Steel
Floating Roof: Aluminum
Cathodic Protection (CP) Impressed Current Cathodic Protection (ICCP)
Interior Coating System* Epoxy
Exterior Coating System* Epoxy with Polyurethane Topcoat
Level Gauging Enraf Automatic Tank Gauge (ATG) and Varec Tape Level Gauge (TLG)
Overfill Protection High Level Alarm (HLA) / High-High Level Alarm (HHLA) / High-Level Control Valve (HLCV) Float Pilot
Piping
Receipt: 8-inch Carbon Steel
Main Suction: 16-inch Carbon Steel
Low Suction: 4-inch Carbon Steel
Water Draw-Off: 1 ½-inch Carbon Steel
Level Alarms HLA/HHLA and Low-Level Alarm (LLA)/Low-Low Level Alarm (LLLA)
Notes:
*Repair drawings and the previous OOS inspection reports dated July 2012 and March 2018 were available for review and comparison.
A. GENERAL PROJECT INFORMATION
1. API 653 OOS (INTERNAL) INSPECTION
The OOS inspection was performed 3-4 June 2020. Results of this inspection identified recommended repairs/upgrades to fully comply with applicable sections of API 650/653, UFC 3-460-01/3-460-03, DoD standard AW 78-24-27, National Fire Protection Association (NFPA) 407, OSHA guidelines, and industry standards.
2. SITE INFORMATION
The Major Command at Moody AFB is the Air Combat Command. The 23rd wing is the home of the world famous “Flying Tigers”, combat search and rescue, and security forces warriors. The 23rd wing consists of “first in” combat search and rescue, close air support, forward air control, interdiction and force protection airmen who conduct worldwide operations in support of United States national security interests and the global war on terror. Additionally, under the wing’s command is the 563rd rescue group at Davis-Monthan AFB with an operating location at Nellis AFB.
B. TANK INSPECTION COMMENTS
1. TANK CONSTRUCTION
Tank 1 is a welded, carbon steel, vertical, aboveground Jet A (F-24) storage tank. The tank is assumed to be constructed to API 12C standards by an unknown manufacturer in 1953 and was repaired by
Toltest in April 2007 to API 653, 3rd Edition, Addendum 1. The tank is 45’-0” in diameter and 34’-6” high with a nominal capacity of 10,000 Barrels (BBL) (420,000 gallons).
2. TANK FOUNDATION
Tank 1 is provided a concrete ringwall foundation, which is in good overall condition with no signs of spalling or cracking. Four (4) leak detection ports are provided between the new and original bottom.
No fluid was expelled from the leak detection ports during inspection.
A settlement evaluation was performed during the inspection. The settlement evaluation satisfied API
653 Appendix B requirements. See Appendix A for settlement results.
3. TANK BOTTOM
The tank is provided a double bottom. The new tank bottom is cone-down with a 29-inch diameter and
10-inch deep center sump and constructed of lap-welded carbon steel plates with butt-welded annular carbon steel plates. The tank bottom was examined using magnetic flux leakage (MFL), ultrasonic thickness testing (UTT), and visual testing (VT) methods. Five (5) UTT measurements were taken on each bottom and annular plate. UTT readings were also taken circumferentially every 2-feet within 3-inches of the shell-to-bottom weld on the annular plates. UTT measurements indicated no significant signs of metal loss on bottom or annular plates. VT was performed at bottom plate lap-welds, annular plate butt-welds, and the shell-to-bottom weld. No significant findings were observed. VT was limited due to internal coating.
An MFL bottom scan was performed on accessible areas of the tank bottom to detect top-side (TS) and soil-side (SS) metal loss. During the internal MFL scan of the tank bottom and annular plates, no TS or
SS indications were identified.
Internal piping for the water draw-off is provided with u-bolt pipe supports. Three (3) water draw-off u-bolt pipe supports are not provided isolation between the support and pipe. Contact point corrosion was observed at the time of inspection. The receipt diffuser is misaligned at the flange connection and is in direct contact with the inner most pipe support leg. Contact point corrosion was observed at this area. The receipt diffuser is also configured such that the flow of fuel into the tank encounters appurtenances within 180°.
Refer to Drawing A-1, “Bottom Layout”, in Appendix A for bottom plate locations, Table 1, “Bottom UTT
Measurements”, in Appendix A for tank bottom plate UTT measurements, and Table 2, “Bottom
Circumferential UTT Measurements”, in Appendix A for tank bottom circumferential UTT measurements.
4. TANK SHELL
The tank shell is equipped with six (6) fully coated, butt-welded, carbon steel shell courses. Shell plates were examined using UTT and VT methods. Nine (9) UTT measurements were taken on each plate of the 1st shell course, three (3) UTT measurements on each insert plate, and ten (10) UTT measurements on each of the 2nd through 6th shell courses using the spiral staircase for access. UTT measurements indicated no significant signs of metal loss on shell plates.
Numerous weld projections on the internal tank shell exhibit porosity, under-cut, and voids. Crevice corrosion was observed at these locations.
Tank shell plates adjacent to the main suction line exhibit inward deformations. The largest deformation measures approximately 10-feet wide with a maximum depth of ½-inch. According to the previous OOS report dated March 2018, shell deformations were found to be acceptable with no repair required. Five (5) conduit supports are welded within 1-inch of the horizontal weld seam between the
1st and 2nd shell course. API mandates tank shell attachments be provided a minimum 3-inches of spacing between welds.
An out-of-roundness (OOR) survey was conducted on the internal tank shell. The largest deviation from the tank nominal diameter was 1 5/8 -inches at the shell-to-bottom weld. The maximum allowable deviation at the shell-to-bottom weld per API 653 Table 10.2 is 1 ½-inches. While the OOR survey conducted does not meet API tolerances, no significant signs of damage were observed on the tank shell.
Refer to Drawing A-2, “Shell Layout”, in Appendix A for shell plate locations, Table 3, “Shell UTT
Measurements”, in Appendix A for shell plate UTT measurements, and Table 8, “Shell Out-of-Roundness
Measurements” in Appendix A for OOR results.
5. FIXED ROOF
The tank fixed roof was examined using UTT and VT methods. Five (5) UTT measurements were taken on each fixed roof plate. UTT measurements indicated no significant signs of metal loss on fixed roof plates.
The fixed roof is provided a center column to support of the fixed roof. The fixed roof center column is stitch welded, creating a crevice for fluid to collect, potentially accelerating coating failure and surface corrosion. Crevice corrosion and corrosion staining were observed during inspection.
Three (3) conduit supports provided for the Vito temperature/water probe are not sealed to the fixed roof. Surface corrosion was observed at the time of inspection.
Refer to Drawing A-3, “Fixed Roof Layout”, in Appendix A for fixed roof plate locations and Table 4, “Fixed Roof UTT Measurements”, in Appendix A for fixed roof plate UTT measurements.
6. TANK APPURTENANCES
6.1 TANK SHELL
Nozzles and appurtenances associated with the shell were inspected using UTT and VT methods. Four (4) UTT measurements were taken on each nozzle with a welded connection greater than 1-inch at four (4) quadrants (0°, 90°, 180°, and 270°). One (1) UTT measurement was taken on each associated reinforcement pad or thickened insert plate. UTT measurements indicated no significant signs of metal loss on the nozzles, reinforcing pads, or thickened insert plates.
Tank 1 is equipped with thirteen (13) shell nozzle penetrations: two (2) 36-inch manways, one (1) 8-inch receipt, two (2) 1 ½” HLA/HHLA nozzle penetrations, two (2) 1 ½-inch
LLA/LLLA penetrations, two (2) 1 ½-inch HLCV float pilot penetrations, one (1) 16-inch main suction, one (1) 4-inch low suction, one (1) aqueous film forming foam (AFFF), and one (1) 1
½-inch water draw-off.
The davit arms for each of the two (2) manways are not provided with grease fittings.
Refer to Drawing A-2, “Shell Layout”, in Appendix A for shell nozzle locations and Table 6, “Nozzle/Repad UTT Measurement”, in Appendix A for nozzle and associated reinforcement pad/thickened insert plate UTT measurements.
6.2 INTERNAL FLOATING ROOF
Tank 1 is provided with an aluminum honeycomb floating pan with a double wiper seal for fire protection. The primary wiper seal provided for the internal floating roof (IFR) is brittle, damaged, and no longer attached to the IFR. Vapor seals for the IFR access ladder and stilling well penetrations for the Enraf ATG, Vito temperature/water probe, and manual gauging hatch are damaged or no longer attached. Damaged wiper seals and IFR penetration seals allow for fuel to evaporate into the environment.
6.3 FIXED ROOF
Nozzles and appurtenances associated with the fixed roof were inspected using UTT and VT methods. Four (4) UTT measurements were taken on each nozzle with a welded connection greater than 1-inch at four (4) quadrants (0°, 90°, 180°, and 270°). One (1) UTT measurement was taken on each associated reinforcement pad. UTT measurements indicated no significant signs of metal loss on nozzles or reinforcing pads.
The fixed roof is provided thirteen (13) nozzle penetrations: one (1) 72-inch by 24-inch IFR installation hatch, one (1) 6-inch blind flange, four (4) 2-inch threaded plugs, one (1) 6-inch
Vito temperature/water probe, one (1) 36-inch by 36-inch IFR inspection hatch with manual gauge hatch, one (1) 10-inch Enraf ATG, one (1) 1-inch Varec TLG, two (2) 1-inch threaded caps, and one (1) ¾-inch threaded plug.
The manual gauge hatch on the IFR inspection hatch is not provided with a latch to secure the hatch cover while not in use.
Refer to Drawing A-3, “Fixed Roof Layout”, in Appendix A for fixed roof nozzle locations and
Table 6, “Nozzle/Repad UTT Measurement”, in Appendix A for nozzle and associated reinforcement pad UTT measurements.
6.4 GAUGING
The tank is provided a manual gauge hatch for manual gauging operations. An Enraf ATG and
Vito temperature/water probe are provided for automatic tank gauging and sampling. The
Enraf ATG and Vito temperature/water probe display is attached to the bottom of the spiral staircase for checking product level from the ground. A mechanical Varec TLG is provided for monitoring product level from the ground and is attached to the IFR. The Varec TLG failed the field operability test and the product level reads incorrectly compared to the Enraf ATG.
6.5 LEVEL ALARMS
The tank is provided with independent, shell mounted alarms in the low, low-low, high, and high-high positions as well as a HLCV float pilot for overfill protection. According to facility personnel, all level alarms and the HLCV float pilot are functioning properly. Piping and nozzle connections for the HLA, HHLA, and HLCV float pilot are provided with threaded connections.
The tank is not provided with a standard product saver tank (PST) with means of testing the level alarms and HLCV system. The PST system should include tubing to the HLA, HHLA, and
HLCV float pilot to facilitate wet testing of the chambers.
6.6 STAIRS AND PLATFORMS
The tank is provided a spiral staircase with one (1) upper platform for fixed roof access. The
HLCV float pilot extends into the path of the spiral staircase, allowing 20-inches of clearance between the appurtenance and staircase railing. OSHA mandates a minimum 26-inches of clearance between appurtenances and staircase railings. The handrail provided for the spiral staircase is 41-inches in height. OSHA mandates that handrail heights are between 30 to 38-inches above the walking surface.
External coating for handrails and balusters provided for the dike access, pipe crossover, and spiral stairs exhibits failure with flaking, base metal exposure, and surface corrosion.
Crossover stair platforms provided at the main suction piping is less than ¼-inch of the main suction flange connection. No contact point corrosion was observed during inspection.
6.7 GROUNDING AND BONDING
The tank shell is equipped with four (4) grounding cables, which are in good overall condition with no signs of deterioration or fraying.
7. TANK AND PIPING COATING
The external tank shell, fixed roof, and piping are provided with an epoxy polyurethane coating system.
External coating for the tank shell and chime exhibits chalking, flaking, and base metal exposure with surface corrosion. External coating for the fixed roof and associated nozzles and appurtenances exhibits chalking, flaking, and base metal exposure with surface corrosion. External coating for the receipt, LLA/LLLA, and PST piping exhibits flaking, cracking, and base metal exposure with surface corrosion.
The internal tank shell, fixed roof, bottom, and piping are provided with a two-coat epoxy coating system. Internal coating for the tank shell exhibits base metal exposure, surface corrosion, and corrosion staining. Internal coating for the tank bottom, appurtenances, and piping exhibits base metal exposure, surface corrosion, and corrosion staining.
DFT measurements were taken on the external shell, fixed roof, internal shell, and bottom. Refer to
Table 5, “Tank DFT Measurements”, in Appendix A for complete DFT data.
8. TANK PIPING SYSTEM
Piping within the containment dike is constructed of carbon steel. The low suction nozzle is not provided with a main suction branch connection, limiting the tank low suction system to aid in fuel removal during maintenance and inspection activities.
Two (2) 8-inch ball valves are located upstream of the HLCV. UFC mandates that double block and bleed
(DB&B) valves are used for positive isolation of the HLCV for maintenance activities. The receipt is provided with u-bolt pipe supports with integrated uni-strut supports. Four (4) u-bolt attachments at the receipt with integrated uni-strut supports for the PST piping are not provided isolation, allowing direct metal-to-metal contact. Four (4) uni-strut supports are missing brackets, enabling the PST piping to freely move laterally. Contact point corrosion was observed during inspection. One (1) pipe support for the receipt TRV piping is not provided isolation.
PST piping is provided threaded connections, one (1) sight flow indicator, and not provided isolation between piping and supports at six (6) u-bolts. Threaded connections and sight flow indicators are no longer used in this application as they are potential leak paths. Contact point corrosion was observed at the pipe-to-support interfaces. One (1) non-standard pipe support was observed supporting the PST piping. Contact point corrosion was observed at the pipe-to-wire interface.
9. FIRE PROTECTION SYSTEM
For internal fire protection, an aluminum honeycomb IFR is provided. Prior to the installation of the
IFR, an AFFF system was provided. The AFFF system is still integrated with the tank, however it is not necessary due to the presence of the IFR. Based on discussions with facility personnel, approval to remove the AFFF discharge chamber and piping has been granted by the Fire Chief.
10. SECONDARY CONTAINMENT
Tank 1 is located within a concrete containment dike partially covered with a flexible membrane liner
(FML). The containment dike is capable of holding approximately 510,000 gallons of liquid, satisfying the 1-foot UFC secondary containment freeboard height requirement. The FML exhibits damage, deterioration, and tears adjacent to the dike drain. After heavy rains water collects underneath the FML as the tank is situated at a low point on the base. Water was observed seeping through small holes in the FML from the underside, potentially creating a leak path in the event of a spill.
The drain provided for the secondary containment is equipped with a manually operated valve and was tested during inspection. The drain was filled with water and maintained for 24-hours to test for leaks. After 24-hours of testing, the valve did not leak, resulting in a sealed draining system.
11. CATHODIC PROTECTION
Tank 1 is equipped with an ICCP system to protect the tank bottom from SS corrosion. The rectifier for
Tank 1 was operating at 23.31 volts and 0.24 amps. Three (3) potential readings were taken for Tank
1. All readings met the -850 millivolt National International (NACE) CP acceptance criteria.
C. FINDINGS AND RECOMMENDATIONS
Based on the OOS API 653 inspection of Tank 1 located at Moody AFB in Valdosta, Georgia mandatory and recommended repair/upgrades have been identified. The following recommendations outline observations from this inspection. All repair recommendations are based on applicable sections of API 650/653, UFC 3-
460-01/3-460-03, DoD Standard AW 78-24-27, NFPA 407, and industry standards.
1. MANDATORY REPAIRS PER API 650/653, UFC 3-460-01/3-460-03, OR DoD AW 78-24-27
Mandatory repairs represent items that require immediate attention, in order to prevent imminent risk to system operators, equipment integrity, or the adjacent environment. The tank should remain out of service until these repairs are completed.
1.1 IFR Double Wiper Seal
OBSERVATION: The primary wiper seal provided for the IFR is damaged and no longer attached to the IFR.
REFERENCE: UFC 3-460-03, Section 8-9.1.1 (F)
RECOMMENDATION: Provide the IFR with a new primary wiper seal. No signs of damage or shell gapping were observed on the secondary wiper seal. To be completed via an emergency service order.
1.2 IFR Penetration Seals
OBSERVATION: IFR vapor seals provided at four (4) penetrations for the IFR access ladder and stilling well, the Enraf ATG, Vito temperature/water probe, and manual gauging hatch are damaged or no longer attached.
REFERENCE: UFC 3-460-03, Section 8-9.1.1 (E)
RECOMMENDATION: Provide IFR vapor seals at the IFR access ladder and stilling well penetrations for the Enraf ATG, Vito temperature/water probe, and manual gauging hatch.
To be completed via an emergency service order.
1.3 Secondary Containment Liner
OBSERVATION: The secondary containment FML exhibits damage, deterioration, and tears adjacent to the dike drain due to the collection of rainwater underneath the
FML. This situation results in excess stress at the FML seems and creates a leak path for fluid.
REFERENCE: UFC 3-460-03, Section 8-10.2.1
RECOMMENDATION: Provide 50 linear feet of FML repair adjacent to the dike drain. Remediation to the site drainage should be considered to prevent further damage to the FML.
Repair of the FML to be completed via an emergency service order by the facility.
2. SHORT-TERM RECOMMENDED REPAIRS
Short-term repairs relate to the long-term preservation of the asset. Short-term repairs represent items that should be addressed in a timely manner in order to prevent future potential risks to system operators, equipment integrity, or the adjacent environment. These items may be required by federal, state, and local codes or by military criteria.
2.1 Internal Shell Weld Projections
OBSERVATION: Ten (10) weld projections on the internal tank shell exhibit porosity, under-cut, and voids. Crevice corrosion on the tank shell was observed at these locations.
REFERENCE: API 653, Section 9.4
RECOMMENDATION: Remove ten (10) internal weld projections on shell course 2, between the main suction and Manway 1.
2.2 Fixed Roof Center Support
OBSERVATION: The fixed roof center support is stitch welded. Crevice corrosion and corrosion staining were observed during inspection.
REFERENCE: UFC 3-460-01, Section 8-11
RECOMMENDATION: Provide sealant at the fixed roof center support crevice, approximately 140 linear feet.
2.3 Tank Shell Internal Coating
OBSERVATION: Internal coating for the tank shell exhibits spot failure with base metal exposure, surface corrosion, and corrosion staining.
REFERENCE: UFC 3-460-01, Section 8-3.9 (a)
RECOMMENDATION: Provide approximately 100 ft2 of spot coating repair to the internal tank shell.
2.4 Tank Internal Piping and Appurtenances Coating
OBSERVATION: Coating for the ATG datum plate, manual gauge hatch datum plate, tank receipt diffuser, main suction, low suction, and water draw-off, including pipe supports, exhibits failure with base metal exposure, surface corrosion, and corrosion staining.
REFERENCE: UFC 3-460-01, Section 8-3.9 (c)
RECOMMENDATION: Provide approximately 50 ft2 of external coating repair to the tank internal piping.
2.5 Tank Bottom Internal Coating
OBSERVATION: Internal coating for the tank bottom plates and appurtenances exhibits failure with base metal exposure, surface corrosion, and corrosion staining.
REFERENCE: UFC 3-460-01, Section 8-3.9 (a)
RECOMMENDATION: Provide approximately 900 ft2 (50%) of coating repair to the internal tank bottom and appurtenances.
2.6 Tank Shell External Coating
OBSERVATION: External coating for the tank shell exhibits widespread chalking. Chalking indicates the coating system is near the end of its life cycle. Minor instances of coating failure with flaking, base metal exposure, and surface corrosion were observed on the tank shell.
REFERENCE: UFC 3-460-01, Section 8-3.10 (a)
RECOMMENDATION: Provide a full recoat of the tank shell, approximately 5,900 ft2 (100%). Prior to recoat, perform a coating condition survey, including an adhesion test, to determine if a full recoat is required or if a topcoat reapplication is sufficient.
2.7 Tank Chime External Coating
OBSERVATION: External coating on the tank chime exhibits flaking and base metal exposure with surface corrosion.
REFERENCE: UFC 3-460-01, Section 8-3.10
RECOMMENDATION: Provide approximately 20 ft2 of spot coating repair on the tank chime.
2.8 Tank Fixed Roof External Coating
OBSERVATION: External coating for the tank fixed roof exhibits widespread chalking with minor surface corrosion. Chalking indicates the coating system is near the end of its life cycle. Minor instances of coating failure with flaking, base metal exposure, and surface corrosion were observed on the tank fixed roof.
REFERENCE: UFC 3-460-01, Section 8-3.10 (a)
RECOMMENDATION: Provide a full recoat of the tank fixed roof, approximately 2,000 ft2 (100%).
Prior to recoat, perform a coating condition survey, including an adhesion test, to determine if a full recoat is required or if a topcoat reapplication is sufficient.
2.9 Tank Fixed Roof Nozzle External Coating
OBSERVATION: External coating on the Enraf ATG, Vito temperature/water probe, blind flange, three (3) threaded plugs, two (2) threaded caps, and the fixed roof perimeter handrail exhibit flaking and base metal exposure with surface corrosion.
REFERENCE: UFC 3-460-01, Section 8-3.10 (a)
RECOMMENDATION: Provide approximately 30 ft2 of spot coating repair on the LLAs, Enraf ATG, Vito temperature/water probe, blind flange, three (3) threaded plugs, two
(2) threaded caps, and the fixed roof perimeter handrail.
2.10 Receipt Valves
OBSERVATION: The tank is equipped with two (2) 8-inch ball valves upstream of the HLCV at the receipt line.
REFERENCE: UFC 3-460-01, Section 3-3.1.2
RECOMMENDATION: Replace the two (2) 8-inch ball valves upstream of the HLCV with two (2) 8-inch DB&B valves for manual isolation.
2.11 Tank Shell and PST Piping External Coating
OBSERVATION: External coating at the LLAs, receipt, receipt thermal relief valve (TRV) crossover piping, and PST drain piping exhibits flaking, cracking, and base metal exposure with surface corrosion.
REFERENCE: UFC 3-460-01, Section 9-10
RECOMMENDATION: Provide approximately 1,600 ft2 of external coating repair on the LLA, receipt, receipt TRV, PST, and drain piping.
2.12 Access, Crossover, and Spiral Stairs External Coating
OBSERVATION: External coating for handrails and balusters provided for the dike access, pipe crossover, and spiral stairs exhibits failure with flaking, base metal exposure, and surface corrosion.
REFERENCE: UFC 3-460-03, Appendix F, Item 6
RECOMMENDATION: Provide approximately 90 ft2 of external coating repair for the access, crossover, and spiral stairs.
2.13 PST Piping
OBSERVATION: PST piping is provided one (1) sight flow indicator.
REFERENCE: AW 78-24-27, Sheet D.13, Detail 5
RECOMMENDATION: Remove one (1) sight flow indicator on PST piping. Sight flow indicators are no longer used as they are a potential leak path. To be completed via the recurring maintenance and minor repair (RMMR) program service order.
2.14 PST Piping
OBSERVATION: PST piping is provided threaded connections.
REFERENCE: UFC 3-460-01, Section 9-8
RECOMMENDATION: Provide flanged or socket welded connections for PST piping. Threaded connections should be avoided as they are a potential leak path. To be completed via RMMR service order.
2.15 PST and TRV Piping
OBSERVATION: One (1) receipt TRV crossover pipe support and six (6) PST pipe supports are not provided with Teflon isolation, or equivalent. A wire was observed supporting the PST piping. Contact point corrosion was observed at interface.
REFERENCE: UFC 3-460-03, Section 6-1.5 C, AW 78-24-33, Sheet CD.11
RECOMMENDATION: Provide one (1) receipt TRV crossover pipe support and six (6) PST pipe supports with Teflon isolation, or equivalent. Remove one (1) wire pipe support and provide pipe supports IAW AW DoD Design Standard requirements.
2.16 Receipt Piping
OBSERVATION: Four (4) u-bolt attachments at the receipt with integrated uni-strut supports for the PST piping are not provided isolation, allowing direct metal-to-metal contact. Four (4) uni-strut supports are missing brackets, enabling the PST piping to freely move laterally. Contact point corrosion was observed during inspection.
REFERENCE: UFC 3-460-03, Section 6-1.5 C
RECOMMENDATION: Provide isolation at four (4) u-bolt attachments at the receipt line and four
(4) brackets for the PST piping at the uni-strut supports.
3. LONG-TERM RECOMMENDED REPAIRS
Long-term repairs that relate to repair/upgrade of an asset to bring it up to the current standard from the standard at time of construction. Long-term repairs represent items that should be addressed in a timely manner in order to prevent future potential risks to system operators, equipment integrity, or the adjacent environment.
3.1 Low Suction Nozzle
OBSERVATION: The low suction nozzle is not provided with a main suction branch connection.
REFERENCE: UFC 3-460-01, Table 8-1 (Z), AW 78-24-27, Sheet D.01. Detail 2.
RECOMMENDATION: Provide a branch connection between the low suction nozzle and main suction pipeline IAW AW DoD Design Standard.
3.2 Main Suction Pipe Support
OBSERVATION: One (1) main suction u-bolt pipe support is not anchored to the secondary containment dike floor.
REFERENCE: UFC 3-460-03, Section 6-1.5 (D), AW 78-24-33, Sheet CD.11
RECOMMENDATION: Anchor one (1) main suction pipe support to the secondary containment dike floor.
3.3 Weld Spacing
OBSERVATION: Weld spacing for two (2) stair treads are welded within 1-inch of the shell-to-bottom weld, two (2) upper stair treads and five (5) conduit supports are welded within 1-inch of the horizontal weld seam separating the 2nd and 1st shell courses.
REFERENCE: API 653, Section 4.3.9.1
RECOMMENDATION: Perform magnetic particle (MT) or dye penetrant (PT) testing IAW API 650 at four (4) stair treads and five (5) conduit supports welded within 1-inch of shell welds.
3.4 Main Suction Crossover Stair Clearance
OBSERVATION: The crossover stair platform provided at the main suction piping are within
¼-inch of contacting the flanged connection, potentially inducing unintentional stress to the main suction piping system during thermal expansion of the stairway and normal pipe movement. No contact point corrosion was observed during inspection.
REFERENCE: UFC 3-460-03, Section 6-1.5
RECOMMENDATION: Rework the main suction crossover stairs to allow clearance between the piping and the concrete structure.
3.5 Manual Gauging Hatch
OBSERVATION: The cover for the manual gauging hatch is not provided a latch.
REFERENCE: BMP
RECOMMENDATION: Provide a latch for the manual gauging hatch to secure the cover while not in use.
3.6 Fixed Roof Conduit Support
OBSERVATION: Three (3) conduit supports for the Vito temperature/water probe are not sealed to the fixed roof.
REFERENCE: UFC 3-460-01, Section 8-11
RECOMMENDATION: Fully seal four (4) conduit supports for the Vito temperature/water probe to the fixed roof. Coating failure with surface corrosion was observed at the time of inspection.
3.7 AFFF
OBSERVATION: The tank is provided an AFFF and an IFR for fire protection.
REFERENCE: UFC 3-460-01, Section 2-13.4.2
RECOMMENDATION: Remove the AFFF piping and discharge chamber, as it is no longer in use.
Based on discussions with facility personnel, approval to remove the AFFF discharge chamber and piping has been granted by the Fire Chief.
3.8 HLA, HHLA, and HLCV Float Pilot Piping
OBSERVATION: Piping and nozzle connections for the HLA, HHLA, and HLCV float pilot are provided threaded connections.
REFERENCE: UFC 3-460-01, Section 8-11 and 9-8 (E)
RECOMMENDATION: Provide the HLA, HHLA, and HLCV float pilot with flanged or socket welded connections. Threaded connections should be avoided as they are a potential leak path. To be completed via RMMR service order.
3.9 PST System
OBSERVATION: The tank is not provided a standard PST with means of testing the level alarms and HLCV.
REFERENCE: AW 78-24-27, Sheet D.13 Detail 5
RECOMMENDATION: Provide the tank with a PST IAW AW DoD Design Standard. The PST system should include tubing to the HLA, HHLA, and HLCV float pilot to facilitate wet testing of the chambers.
3.10 Varec TLG System
OBSERVATION: The Varec TLG failed the field operability test and does not match the Enraf
ATG tank level readings.
REFERENCE: BMP
RECOMMENDATION: Remove the Varec TLG system from Tank 1 per the facility’s request.
3.11 Manway 1 and Manway 2 Davit Arms
OBSERVATION: Davit arms for Manway 1 and Manway 2 are not equipped with grease fittings.
REFERENCE: API 650, Section 5.8.3.5
RECOMMENDATION: Provide Manway 1 and Manway 2 davit arms with grease fittings to allow ease of use.
3.12 Receipt Piping Flow Arrows
OBSERVATION: Flow arrows and product designation labeling for the receipt piping exhibit fading and peeling.
REFERENCE: UFC 3-460-01, Section 2-17
RECOMMENDATION: Replace flow arrows and product designation labeling for receipt piping. To be completed via RMMR.
3.13 Spiral Staircase
OBSERVATION: The spiral staircase handrail height is 41-inches, which is greater than the
38-inch maximum allowable height per OSHA requirements.
REFERENCE: OSHA 1926.1051(c)(6)
RECOMMENDATION: Rework the spiral staircase at the tank shell, so the handrail is positioned at a height between 30 to 38-inches, meeting OSHA requirements.
3.14 HLCV Float Pilot Clearance
OBSERVATION: The clearance between the HLCV float pilot and spiral staircase handrail is approximately 20-inches, less than the OSHA required 26-inch clearance.
REFERENCE: OSHA 1910.25 (d)(1)
RECOMMENDATION: Extend the stair treads or provide a work platform at the HLCV float pilot to allow for a minimum 26-inches of clear space between the spiral staircase handrail and appurtenance.
3.15 Internal Pipe Supports
OBSERVATION: The internal pipe supports for three (3) water draw-off supports are not provided isolation.
REFERENCE: AW 78-24-27, Sheet D.08 Detail 6
RECOMMENDATION: Provide Teflon-coated u-bolts at three (3) water draw-off supports.
3.16 Internal Receipt Diffuser
OBSERVATION: The receipt diffuser is misaligned at the flange connection and is in direct contact with the inner most pipe support leg, potentially adding additional unintended stresses to the support. Contact point corrosion was observed during inspection. Additionally, the receipt diffuser orientation is such that the flow of fuel into the tank encounters appurtenances within 180°.
REFERENCE: UFC 3-460-03, Section 6-1.5 (A); AW 78-24-27, Sheet D-08, Detail 1, Note 2
RECOMMENDATION: Rework the receipt diffuser and associated pipe support to allow for proper diffuser movement and provide adequate support. Additionally, rework the receipt diffuser such that the flow of fuel into the tank does not encounter appurtenances for at least 180°.
APPENDIX A: ENGINEERING CALCULATIONS AND DRAWINGS
NOZZLE
SCHEDULE
NOZZLE SIZE SHELL LAYOUT
MW1 36" MANWAY
N1 8" RECEIPT
N2 1
" HLA/HHLA
N3 1
" HLA/HHLA
N4 1
" LLA/LLLA
N5 1
" LLA/LLLA
N6 1
" HLCV FLOAT PILOT
N7 1
" HLCV FLOAT PILOT
MW2 36" MANWAY 2
N8 16" MAIN SUCTION
N9 4" LOW SUCTION
N10 -
AFFF DISCHARGE
CHAMBER
N11 1
" WATER DRAW OFF
MW1
CONDUIT SUPPORT
(TYP. 11)
N1
N2
N3
N6
N8
N9
ROOF PERIMETER
HANDRAIL
SPIRAL STAIRCASE
UPPER PLATFORM
GROUNDING
CABLE (TYP. 4)
1-21-1 1-51-41-3
MW2
N10
N11
N7
VAREC
TLG
TANK
NAMEPLATE
AFFF
SUPPORT
(TYP. 2)
LEAK DETECTION
PORT (TYP. 4)
N4
N5
NEW
TANK BOTTOM
2-12-52-4 2-2 2-3
3-1 3-2 3-33-53-4
4-44-3 4-1 4-2
5-1 5-25-55-45-3
6-3 6-4 6-5 6-1 6-2
OVERFLOW
VENT (TYP. 2)
LLA/LLLA CHAMBER
SUPPORT (TYP. 2)
TLG
SUPPORT
(TYP. 3)
4'-6"
ORIGINAL
TANK BOTTOM
6'-0"
6'-0"
6'-0"
6'-0"
6'-0"
1'-6"
C O
N T
R A
C T
N
O
F I L E
A M
E
D W
N
B
Y
C K
D
B
Y
D E
S I G
N E
D
B
Y
D E
S C
R I P
T I O
N
D
2 3
C
A
B
M A
R K
A P
P R
D A
T E
F I
U M
B E
R
S I Z
E
S U
B M
I T
T E
D
B
Y
P L O
T
S
C A
L E
P
L O
T
D
A T
E
D A
T E
M A
R K
D E
S C
R I P
T I O
N
D E
L I V
E R
Y
O
R D
R
SHEET
IDENTIFICATION
D A
T E
A P
P R
SHEET OF
U S
A
R M
Y
C
O R
P S
F
E
N G
I N
E E
R S
O M
A H
A
N
E
O M
A H
A
D
I S
T R
I C
T
V A
L D
O S
T A
G
A
M O
O D
Y
A
F B
T A
K
Y
O U
T
N T
S
N A
W
F
D
W
F
F
A N
S I
B
P a r k w a y
L a n e
S u i t e
P e a c h t r e e
C o r n e r s
G
A
P h o n e
F a x
J O
B
N
O
C A
W
A E
C
C R
P
N A
TANK INFORMATION
TANK NO.: TANK 1 (FACILITY 5016)
MANUFACTURER: UNKNOWN
YEAR BUILT: 1953
TANK DIAMETER: 45'-0"
TANK HEIGHT: 34'-6"
NOMINAL CAPACITY: 10,000
PRODUCT: JET-A (F-24)
PRODUCT SPECIFIC GRAVITY: 0.84
GPS COORDINATES: 30.97005°, -83.21005°
N A
S H
E L
L
L
A Y
O U
T
A-2
NOTES:
1. REFER TO TABLE 3, "SHELL UTT MEASUREMENTS", IN
APPENDIX A FOR INDIVIDUAL SHELL PLATE UTT
READINGS.
2. REFER TO TABLE 6, " NOZZLE / REPAD UTT
MEASUREMENTS", IN APPENDIX A FOR NOZZLE
MEASUREMENTS.
SPIRAL
STAIRCASE
NOZZLE
SCHEDULE
NOZZLE SIZE FIXED ROOF LAYOUT
N12 ¾"
THREADED PLUG
N13 1" THREADED CAP
N14 1" VAREC TLG
N15 1" THREADED CAP
N16 6" BLIND FLANGE
N17 6"
VITO TEMPERATURE AND
WATER PROBE
N18 2" THREADED PLUG
N19 2" THREADED PLUG
N20 2" THREADED PLUG
N21 10" ENRAF ATG
N22 2" THREADED PLUG
N23 72" X 24" IFR INSTALLATION HATCH
N24 36" X 36"
IFR INSPECTION HATCH
WITH MANUAL GAUGING
HATCH
N24
N23
N16
N17
N21
N18
N12
N20
23 24
25 26
N14
N15
N13
N19
N22
CONDUIT
SUPPORT
(TYP. 3)
C O
N T
R A
F I
M
E
D W
N
B
Y
C K
D
B
Y
D E
S I G
N E
D
B
Y
D E
S C
R I P
T I O
N
D
2 3
C
A
B
M A
R K
A P
P R
D A
T E
F I
M
B E
R
S I Z
E
S U
B M
I T
T E
D
B
Y
P L O
T
S
C A
L E
P
L O
T
D
A T
E
D A
T E
M A
R K
D E
S C
R I P
T I O
N
D E
L I V
E R
Y
O
R D
SHEET
IDENTIFICATION
D A
T E
A P
P R
SHEET OF
U S
A
R M
Y
C
O R
E
N G
I N
E E
R S
O M
A H
A
N
E
O M
A H
A
D
I S
T R
I C
T
V A
L D
O S
T A
G
A
M O
O D
Y
A
F B
T A
Y
O U
T
N T
S
N A
W
F
D
W
F
F
A N
S I
B
P a r k w a y
L a n e
S u i t e
P e a c h t r e e
C o r n e r s
G
A
P h o n e
F a x
J O
B
N
O
C A
W
A E
C
C R
P
N A
TANK INFORMATION
TANK NO.: TANK 1 (FACILITY 5016)
MANUFACTURER: UNKNOWN
YEAR BUILT: 1953
TANK DIAMETER: 45'-0"
TANK HEIGHT: 34'-6"
NOMINAL CAPACITY: 10,000
PRODUCT: JET-A (F-24)
PRODUCT SPECIFIC GRAVITY: 0.84
GPS COORDINATES: 30.97005°, -83.21005°
N A
F I X
D
O
F
L
A Y
O U
T
A-3
C O
N T
R A
F I
M
E
D W
N
B
Y
C K
D
B
Y
D E
S I G
N E
D
B
Y
D E
S C
R I P
T I O
N
D
2 3
C
A
B
M A
R K
A P
P R
D A
T E
F I
M
B E
R
S I Z
E
S U
B M
I T
T E
D
B
Y
P L O
T
S
C A
L E
P
L O
T
D
A T
E
D A
T E
M A
R K
D E
S C
R I P
T I O
N
D E
L I V
E R
Y
O
R D
SHEET
IDENTIFICATION
D A
T E
A P
P R
SHEET OF
U S
A
R M
Y
C
O R
E
N G
I N
E E
R S
O M
A H
A
N
E
O M
A H
A
D
I S
T R
I C
T
V A
L D
O S
T A
G
A
M O
O D
Y
A
F B
T A
Y
O U
T
N T
S
N A
W
F
D
W
F
F
A N
S I
B
P a r k w a y
L a n e
S u i t e
P e a c h t r e e
C o r n e r s
G
A
P h o n e
F a x
J O
B
N
O
C A
W
A E
C
C R
P
N A
TANK INFORMATION
TANK NO.: TANK 1 (FACILITY 5016)
MANUFACTURER: UNKNOWN
YEAR BUILT: 1953
TANK DIAMETER: 45'-0"
TANK HEIGHT: 34'-6"
NOMINAL CAPACITY: 10,000
PRODUCT: JET-A (F-24)
PRODUCT SPECIFIC GRAVITY: 0.84
GPS COORDINATES: 30.97005°, -83.21005°
N A
LEGEND:
TANK DEPRESSION WITH WATER STAINING
NOTES:
1. REFER TO TABLE 4, "FIXED ROOF ULTRASONIC
THICKNESS READINGS", IN APPENDIX A FOR INDIVIDUAL
ROOF PLATE UTT READINGS.
2. REFER TO TABLE 6, " NOZZLE / REPAD UTT
MEASUREMENTS", IN APPENDIX A FOR NOZZLE
MEASUREMENTS.
30 31
MW2
MW1
WATER DRAW-OFF
SUPPORT (TYP. 3)
FIXED ROOF
SUPPORT (TYP.4)
RECEIPT, MAIN SUCTION,
LOW SUCTION SUPPORT
(TYP. 7)
ENRAF ATG
IFR ACCESS
LADDER/MANUAL GAUGE
HATCH
ANTI-ROTATION CABLE
(TYP. 2)
IFR LEG SUPPORT
(TYP. 10)
VITO PROBE
SUPPORT (TYP. 2)
SUMP
LAP PATCH
(TYP. 5)
32 33
1714 16
SUMP DETAIL
.523"
.528"
.529"
.521"
.486"
.483"
.482"
.483" .476"
2'-5"
0'-10"
C O
N T
R A
F I
M
E
D W
N
B
Y
C K
D
B
Y
D E
S I G
N E
D
B
Y
D E
S C
R I P
T I O
N
D
2 3
C
A
B
M A
R K
A P
P R
D A
T E
F I
M
B E
R
S I Z
E
S U
B M
I T
T E
D
B
Y
P L O
T
S
C A
L E
P
L O
T
D
A T
E
D A
T E
M A
R K
D E
S C
R I P
T I O
N
D E
L I V
E R
Y
O
R D
SHEET
IDENTIFICATION
D A
T E
A P
P R
SHEET OF
U S
A
R M
Y
C
O R
E
N G
I N
E E
R S
O M
A H
A
N
E
O M
A H
A
D
I S
T R
I C
T
V A
L D
O S
T A
G
A
M O
O D
Y
A
F B
T A
Y
O U
T
N T
S
N A
W
F
D
W
F
F
A N
S I
B
P a r k w a y
L a n e
S u i t e
P e a c h t r e e
C o r n e r s
G
A
P h o n e
F a x
J O
B
N
O
C A
W
A E
C
C R
P
N A
TANK INFORMATION
TANK NO.: TANK 1 (FACILITY 5016)
MANUFACTURER: UNKNOWN
YEAR BUILT: 1953
TANK DIAMETER: 45'-0"
TANK HEIGHT: 34'-6"
NOMINAL CAPACITY: 10,000
PRODUCT: JET-A (F-24)
PRODUCT SPECIFIC GRAVITY: 0.84
GPS COORDINATES: 30.97005°, -83.21005°
N A
F I X
D
O
F
L
A Y
O U
T
A-1
C O
N T
R A
F I
M
E
D W
N
B
Y
C K
D
B
Y
D E
S I G
N E
D
B
Y
D E
S C
R I P
T I O
N
D
2 3
C
A
B
M A
R K
A P
P R
D A
T E
F I
M
B E
R
S I Z
E
S U
B M
I T
T E
D
B
Y
P L O
T
S
C A
L E
P
L O
T
D
A T
E
D A
T E
M A
R K
D E
S C
R I P
T I O
N
D E
L I V
E R
Y
O
R D
SHEET
IDENTIFICATION
D A
T E
A P
P R
SHEET OF
U S
A
R M
Y
C
O R
E
N G
I N
E E
R S
O M
A H
A
N
E
O M
A H
A
D
I S
T R
I C
T
V A
L D
O S
T A
G
A
M O
O D
Y
A
F B
T A
Y
O U
T
N T
S
N A
W
F
D
W
F
F
A N
S I
B
P a r k w a y
L a n e
S u i t e
P e a c h t r e e
C o r n e r s
G
A
P h o n e
F a x
J O
B
N
O
C A
W
A E
C
C R
P
N A
TANK INFORMATION
TANK NO.: TANK 1 (FACILITY 5016)
MANUFACTURER: UNKNOWN
YEAR BUILT: 1953
TANK DIAMETER: 45'-0"
TANK HEIGHT: 34'-6"
NOMINAL CAPACITY: 10,000
PRODUCT: JET-A (F-24)
PRODUCT SPECIFIC GRAVITY: 0.84
GPS COORDINATES: 30.97005°, -83.21005°
N A
LEGEND:
- UTT READING (INCHES)
NOTES:
1. REFER TO TABLE 1, "BOTTOM UTT MEASURMENTS", IN
APPENDIX A FOR INDIVIDUAL BOTTOM PLATE UTT
READINGS.
2. REFER TO TO TABLE 2, " BOTTOM CIRCUMFERENTIAL UTT
MEASUREMENTS", IN APPENDIX A FOR
CIRCUMFERENTIAL MEASUREMENTS.
.XXX"
TABLE 1 – BOTTOM UTT MEASUREMENTS
Plate 1 Plate 2 Plate 3 Plate 4 Plate 5 .305 .305 .307 .307 .308 .307 .308 .306 .309 .306 .307 .305 .308 .304 .307 .304 .300 .307 .306 .308 .308 .306 .306 .308 .307 Avg. .304 .306 .308 .306 .307 Plate 6 Plate 7 Plate 8 Plate 9 Plate 10 .304 .306 .307 .307 .305 .307 .306 .305 .308 .306 .306 .305 .308 .303 .306 .306 .305 .307 .307 .307 .304 .305 .306 .308 .308 Avg. .305 .307 .306 .305 .307 Plate 11 Plate 12 Plate 13 Plate 14 Plate 15 .305 .307 .307 .302 .312 .310 .312 .311 .309 .311 .306 .308 .312 .313 .311 .306 .306 .306 .309 .312 .311 .312 .311 .310 .310 Avg. .306 .306 .311 .312 .310 Plate 16 Plate 17 Plate 18 Plate 19 Plate 20 .310 .314 .307 .309 .314 .314 .313 .311 .315 .312 .313 .309 .315 .312 .315 .313 .313 .309 .309 .313 .314 .310 .311 .315 .314 Avg. .313 .309 .314 .311 .314 Plate 21 Plate 22 Plate 23 Plate 24 Plate 25 .308 .307 .315 .316 .314 .313 .310 .311 .308 .314 .307 .316 .315 .310 .313 .308 .309 .315 .312 .313 .312 .311 .310 .315 .314 Avg. .308 .315 .313 .310 .313 Plate 26 Plate 27 Plate 28 Plate 29 Plate 30 .312 .311 .310 .311 .310 .310 .314 .281 .309 .118 .312 .310 .311 .315 .311 .312 .313 .310 .311 .311 .309 .315 .314 .310 .120 Avg. .312 .310 .310 .308 .234 Plate 31 Plate 32 Plate 33 .312 .314 .309 .311 .311 .312 .316 .312 .313 .313 .316 .309 .311 .312 .313 Avg. .314 .310 .312
Thickness represented in inches.
Average bottom (general) plate thickness: .308”
Average bottom (annular) plate thickness: .306”
TABLE 2 – BOTTOM CIRCUMFERENTIAL UTT MEASUREMENTS
Ultrasonic Thickness Survey of Tank Floor 0' 3' 6' 9' 12' 15' 18' 21' 24' 27' 30' 33' 36' 39' 42' 45' 48'
.310 .312 .307 .307 .306 .303 .308 .311 .308 .311 .306 .310 .310 .308 .308 .310 .309 51' 54’ 57’ 60’ 63’ 66’ 69’ 72’ 75’ 78’ 81’ 84’ 87’ 90’ 93’ 96’ 99’
.307 .310 .308 .307 .308 .305 .306 .305 .305 .306 .306 .307 .309 .307 .307 .307 .309 102’ 105’ 108’ 111’ 114’ 117’ 120’ 123’ 126’ 129’ 132’ 135’ 138’ 141’ .306 .309 .303 .305 .303 .304 .306 .308 .307 .307 .306 .306 .308 .308 0’ = Manway 1 Locations are within 3-inches of the shell-to-bottom weld. Thickness measurements are taken at 2 feet increments around the circumference of the tank.
Thickness measurements are in inches.
Average Bottom Circumferential Readings: .307”
TABLE 3 - SHELL UTT MEASUREMENTS
Roof
Shell Course
Plate 6-1 Plate 6-2 Plate 6-3 Plate 6-4 Plate 6-5 .193 .193 .195 .192 .193 .192 .193 .194 .191
.185 Avg. .193
Circumferential Weld C6
Shell Course
Plate 5-1 Plate 5-2 Plate 5-3 Plate 5-4 Plate 5-5 .186 .187 .191 .187 .188 .192 .185 .190 .192
.191 Avg. .189
Circumferential Weld C5
Shell Course
Plate 4-1 Plate 4-2 Plate 4-3 Plate 4-4 Plate 4-5 .192 .195 .194 .193 .195 .194 .201 .194 .194
.191 Avg. .195
Circumferential Weld C4
Shell Course
Plate 3-1 Plate 3-2 Plate 3-3 Plate 3-4 Plate 3-5 .184 .196 .190 .186 .195 .191 .189 .193 .190
.186 Avg. .190
Circumferential Weld C3
Shell Course
Plate 2-1 Plate 2-2 Plate 2-3 Plate 2-4 Plate 2-5 .261 .265 .261 .263 .266 .258 .264 .264 .257
.256 Avg. .262
Circumferential Weld C2
Shell Course
Plate 1-1 Plate 1-2 Plate 1-3 Plate 1-4 Plate 1-5 .263 .268 .268 .248 .252 .257 .249 .265 .260 .254 .259 .256 .266 .255 .247 .264 .269 .270 .249 .257 .256 .250 .253 .259 .251 .258 .261 .264 .253 .248 .260 .263 .265 .249 .259 .257 .243 .246 .255 .246 .254 .256 .258 .247 .243
Avg. .266 .254 .253 .255 .253 Circumferential Weld C1
Thickness represented in inches.
Average shell course 1: .256” Average shell course 5: .189”
Average shell course 2: .262” Average shell course 6: .193”
Average shell course 3: .190”
Average shell course 4: .195”
TABLE 4 – FIXED ROOF UTT MEASUREMENTS
Plate 1 Plate 2 Plate 3 Plate 4 Plate 5
.205 .191 .195 .198 .194 .195 .192 .193 .199 .195
.199 .200 .199 .198 .196
.201 .191 .201 .192 .197 .195 .193 .193 .193 .192
Avg. .197 .197 .196 .194 .195
Plate 6 Plate 7 Plate 8 Plate 9 Plate 10
.191 .192 .189 .190 .193 .189 .195 .196 .202 .199
.195 .195 .197 .203 .202
.190 .193 .192 .189 .194 .192 .199 .202 .199 .195
Avg. .192 .191 .193 .199 .199
Plate 11 Plate 12 Plate 13 Plate 14 Plate 15
.193 .196 .192 .193 .190 .194 .197 .196 .194 .199
.187 .198 .200 .204 .201
.189 .189 .192 .194 .195 .195 .197 .198 .199 .195
Avg. .191 .194 .195 .198 .198
Plate 16 Plate 17 Plate 18 Plate 19 Plate 20
.192 .187 .191 .193 .190 .192 .196 .200 .192 .197
.196 .196 .198 .204 .203
.196 .190 .192 .191 .192 .192 .188 .201 .190 .195
Avg. .192 .193 .193 .198 .195
Plate 21 Plate 22 Plate 23 Plate 24 Plate 25
.194 .194 .198 .198 .198 .197 .190 .196 .198 .195
.198 .203 .203 .191 .201
.192 .192 .186 .202 .194 .196 .193 .196 .196 .194
Avg. .194 .197 .198 .193 .197
Plate 26 Plate 27 Plate 28 .189 .195 .193 .203 .196 .195 .199 .204 .193 .194 .197 .202 .199 .189 .192 Avg. .195 .200 .193
Thickness represented in inches.
Average fixed roof: .195”
TABLE 5 – TANK DFT MEASUREMENTS
External Shell Coating Thickness
Average Standard Deviation Number of Readings Minimum Maximum
12.90 2.66 20 9.43 21.25
Fixed Roof Coating Thickness
14.28 1.95 15 10.46 18.35
Internal Shell Coating Thickness
13.45 2.92 20 9.54 22.09
Bottom Coating Thickness
14.65 1.73 15 12.02 18.12
Thicknesses are represented in mils.
TABLE 6 - NOZZLE / REPAD UTT MEASUREMENTS
Nozzle Nozzle Size
(Diameter or Width/Height)
Repad Shape
Repad Size
(W X H)
Repad Thickness
Nozzle Thickness H1 H2
Nozzle Location (Measured circumferentially from Manway 1)
Notes
0⁰ 90⁰ 180⁰ 270⁰
MW1 36" B 72" .254 .248 .248 .245 .244 3'-6" 0'-6" 0'-0" Manway 1
N1 8'' D 24" x 26" .249 .498 .492 .494 .503 1'-3" - 29'-0'' Receipt
N2 1 ½" - - - TH TH TH TH 4'-8 1/2" 4'-8" 55'-0'' HLA/HHLA
N3 1 ½" - - - TH TH TH TH 2'-3 ½" 2'-3" 55'-0'' HLA/HHLA
N4 1 ½" - - - TH TH TH TH 3'-9 ½" 3'-9" 57'-0'' LLA/LLLA
N5 1 ½" - - - TH TH TH TH 2'-7 ½" 2'-7" 57'-0'' LLA/LLLA
N6 1 ½" - - - TH TH TH TH 5'-11" 5'-10 ½" 58'-6'' HLCV Float Pilot
N7 1 ½" - - - TH TH TH TH 1'-9 ½" 1'-9" 58'-6'' HLCV Float Pilot
MW2 36'' B 72" .251 .247 .246 .246 .248 3'-6" 0'-6" 65'-0'' Manway 2
N8 16'' D 31'' x 33'' .494 .520 .519 .525 .529 1'-7" - 101'-0'' Main Suction
N9 4'' B 12" .250 .292 .295 .299 .289 0'-10" 0'-3 ½" 106'-0'' Low Suction
N10 - - - - Obst. Obst. Obst. Obst. Obst. Obst. 135'-0'' AFFF Discharge Chamber
N11 1 ½" - - - .184 .173 .166 .180 0'-10" 0'-9 1/2" 136'-8'' Water Draw Off
N12 ¾" - - - TH TH TH TH Fixed Roof Threaded Plug
N13 1" - - - TH TH TH TH Fixed Roof Threaded Cap
N14 1" - - - TH TH TH TH Fixed Roof Varec TLG
N15 1" - - - TH TH TH TH Fixed Roof Threaded Cap
N16 6" B 14" .251 .253 .282 .272 .276 Fixed Roof Blind Flange
N17 6" B 16" .252 .258 .248 .243 .249 Fixed Roof Vito Temperature/Water Probe
N18 2" - - - TH TH TH TH Fixed Roof Threaded Plug
N19 2'' - - - TH TH TH TH Fixed Roof Threaded Plug
N20 2'' - - - TH TH TH TH Fixed Roof Threaded Plug
N21 10" F 24" x 24" .196 .358 .356 .352 .356 Fixed Roof Enraf ATG
N22 2" - - - TH TH TH TH Fixed Roof…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .