Attachment 2 - Performance Work Statement (PWS).pdf
PDF 172 KB Posted
- Attached to
- API Fuel Tank Inspection - Moody AFB, GA Federal contract opportunity
- Solicitation number
- W9128F25QA016
About this file
This Performance Work Statement (PWS) outlines requirements for aboveground storage tank (AST) external inspection services at Moody Air Force Base, GA. The contractor must perform inspections on Department of Defense fuel tanks listed in Attachment B, following applicable industry standards including API 653, API RP 575, NFPA 30, NFPA 326, and UFGS 33 01 50.65.
The contractor is responsible for providing all personnel, equipment, supplies, facilities, transportation, tools, materials, and supervision. Key deliverables include a Project Inspection Management Plan/Work Plan due 15 days after award, Health and Safety Plan, and inspection reports. The inspection work must be conducted between 0730-1630 Monday through Friday, excluding federal holidays. Required inspection activities include UT scanning with 5 points per shell plate on the first shell course, visual inspection of secondary containment areas, and testing of alarms and tank appurtenances. Draft inspection reports are due 28 days after field inspection, with final reports due 7 days after receipt of comments. Key personnel requirements include a Certified API 653 Inspector and Project Manager.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment J2 - Previous Inspection Report 5017-Tank 2.pdf | ||
| Attachment I - API External Template.docx | DOCX document | |
| Attachment B - Fuel Storage Tank LIst.xlsx | XLSX spreadsheet | |
| Combined Synopsis-Solicitation Moody AFB.pdf | ||
| Wage Determination.pdf | ||
| Attachment E - Inspection Telecon Briefing Template.docx | DOCX document | |
| Attachment D - MCP and MS Report.xlsx | XLSX spreadsheet | |
| Attachment C - Fuel Storage Tank Data Sheet.xlsx | XLSX spreadsheet | |
| Attachment A - General Installation Security Requirements.pdf | ||
| Attachment 1 - CLIN Schedule.pdf | ||
| Attachment J4 - Previous Inspection Report 5019-Tank 4.pdf | ||
| Attachment J3 - Previous Inspection Report 5018-Tank 3.pdf | ||
| Attachment J1 - Previous Inspection Report 5016-Tank 1.pdf | ||
| Attachment 4-Addendum to 52.212-1.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SP-POL-CMP-INSPECT-FY25-MDY (PO 30) PWS
Moody AFB, GA
Part 1 General Information
1. GENERAL:
1.1. Scope: This is a non-personnel services contract to perform inspections on
Department of Defense fuel tanks. This service entails providing an aboveground storage tank AST External Inspection on tank(s) listed in Attachment B.
1.2. Background: See Attachment J for previous inspection report(s).
1.3. Objectives: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items. The contractor shall also provide non-personnel services necessary to perform an AST External inspection on the tank(s), as applicable, at the location and for the tanks specified in Attachment B, as defined in this Performance Work Statement (PWS), except for those items specified as government furnished property and services.
1.4. General Information
1.4.1. Recognized Holidays:
New Year’s Day Martin Luther King Birthday President’s Day Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veteran’s Day Thanksgiving Christmas
1.4.2. Hours of Operation: The contractor is responsible for conducting business, between the hours of 0730-1630 Monday through Friday, except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Other than normal duty hours must be coordinated with the KO or his/her designated representative. The Contractor must always maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall maintain stability and continuity of the workforce.
1.4.3. Place of Performance: The work to be performed under this contract will be performed at the installation and facilities identified in Attachment B.
1.4.4. Type of Contract: The government will award a Firm Fixed Price Contract
1.4.5. Security Requirements: Reference Attachment A – General Installation Security Requirements
1.4.6. Site Access: Contractor shall coordinate with Installation personnel for access to the site. Points of contact for the installation will be provided upon award.
1.4.7. Meetings/Kick-Off Meetings: The Contractor shall coordinate with the USACE PM and conduct a kickoff meeting prior to field activities. This can be accomplished either prior to mobilization and inspection activities or on site prior to commencement of inspection activities. The Work Plan shall be discussed, and further coordination and scheduling shall be accomplished at this meeting. These meetings shall be at no additional cost to the government.
1.4.8. Key Personnel: Certified API 653 Inspector and Project Manager.
1.4.9. Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications, or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI.
The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as they deem necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.4.10. Suitability For Service: Evaluate inspection data to determine suitability for continued use. Identify conditions which pose a risk to integrity. Determine a metal loss threshold for mandatory repairs. In the determination of mandatory repairs:
• Use a "first, do no harm" approach to classifying tank repairs.
• Use Desired Service Interval as the time to next inspection unless notified otherwise by the Contracting Officer.
• Use minimum remaining thickness (MRT) no less than 100 mils at the next inspection.
• Do not classify as mandatory repair of conditions which are noncompliant with current standards but are un-related to structural or hydraulic integrity (e.g., gouge, improper weld spacing, weld profile).
• Apply repair determination to individual indications. Do not average across an entire plate or course.
PART 2
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND
SERVICES
2. GOVERNMENT FURNISHED ITEMS AND SERVICES:
2.1. Services: No Government furnished items or services are required.
PART 3
CONTRACTOR FURNISHED ITEMS AND SERVICES
3. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
3.1. General: The Contractor shall furnish all supplies, equipment, facilities, and services required to perform work under this contract that are not listed under Section 3 of this PWS.
3.2. Equipment: The Contractor shall provide all tools and inspection equipment needed to perform the inspection and other services to be performed under the PWS.
3.2.1. Precision Equipment: Contractor is responsible to ensure all equipment to be used is certified and calibrated to the parameters and tolerances of the required equipment.
3.3. Project Inspection Management Plan (PMP): As part of the initial PMP, the
Contractor shall prepare and include a brief (< 10 pages) Work Plan, as an attachment, which will include proposed schedule, inspection activities, personnel performing inspection, required training certificates, and additional data or support requests.
3.4. Health and Safety Plan (HSP) and Accident Prevention Plan (APP): The
Contractor will prepare a Health and Safety Plan (HSP) to comply with 29 Code of Federal Regulations (CFR) 1910 and 1926 as well as applicable Military Service (Army, Air Force, or Navy), OSHA, state, host nation, and local and installation health and safety regulations regarding the proposed work effort. Qualifications for individuals who will be on site for safety shall be submitted in the HSP.
3.4.1. The Accident Prevention Plan (APP) is required by FAR clause 52.236-13.
The APP describes the methods by which the contractor or USACE personnel will meet the safety and health requirements listed in EM 385-1-1. Entry into Confined Spaces shall comply with the requirements of 29 CFR 1910.146.
Provide additional monitoring for toxic (petroleum) vapors in addition to normal air monitoring requirements.
3.4.2. Abbreviated Accident Prevention Plans may be developed and submitted per
Form A-01 Abbreviated Accident Prevention Plan Checklist Page A-13 of the EM 385-1-1. This may be submitted to develop a plan more specific to the work performed under this PWS but shall still comply as indicated above.
PART 4
SPECIFIC TASKS
4. Specific Tasks: Per each tank as identified in attachment B
4.1. Basic Services.
4.1.1. Perform a Teleconference kick-off meeting either prior to mobilization or the morning of the commencement of work on site.
4.1.2. Perform an external AST inspection to include visual inspection of the containment area. The tank Inspection shall be in conformance with applicable industry standards API 653, API RP 575, NFPA 30, NFPA 326, and UFGS 33 01 50.65, and in compliance with 40 CFR 112, UFC 3-460-01, UFC 3-460-03 and any other applicable federal, state, local and service regulations. Complete the API Std 653 checklist and provide them with the DRAFT and FINAL reports. Utilize UFC 3-460-01 Table 8-1 and indicate appurtenances that are not present. Alarms, Automatic Tank Gauge equipment, and all tank appurtenances shall be tested and verified. The attached Inspection Report template must be utilized in submitting both the DRAFT and FINAL inspection reports. Contractor shall leave a clean and orderly site upon the completion of the inspection.
4.1.3. The contractor shall visually inspect the secondary containment area for the ability to contain the entire contents of the tank in the event of catastrophic failure, assessing for cracks, settlement, and deterioration. Record dimensions of cracks and provide photographic evidence of each deficiency.
Visually assess the liner integrity and impermeability where applicable.
Provide calculations demonstrating the containment area has sufficient capacity in accordance with 40 CFR 112.
4.1.4. Coverage of the UT scan shall include 5 points per shell plate on the first shell course. Spot UT scans shall be made once every foot along the circumference of the tank shell within the critical zone and along the tank chime as accessible. Five points per shell plate should also be taken along the spiral staircase for each shell course as accessible. Provide UT scans of tank shell nozzles on the first shell course and their respective reinforcements plates as applicable. Include all findings in the inspection report.
4.1.5. Provide DRAFT and FINAL inspection reports per the attached templates.
The report(s) must include a record of NDE findings with drawings depicting plate layout and thickness measurement locations, if applicable. Incorporate engineering analysis, suitability for service analysis, corrosion rate determinations, and remaining service life calculations. Provide separate report for each tank inspected. Specify the due date for the next inspection.
Include the API Std 653 inspector of record certificate number and signature.
PART 5
APPLICABLE PUBLICATIONS
5. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
5.1. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.
American Petroleum Institute (API) 653 Standard for the Tank Inspection, Repair, Alteration, and
Reconstruction 650 Welded Tanks for Oil Storage RP 575 Inspection Practices for Atmospheric and Low-pressure Storage
Tanks Std 2015 Requirements for Safe Entry and Cleaning of Petroleum Storage
Tanks
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 30 Flammable and Combustible Liquids Code NFPA 70 National Electrical Code (NEC) NFPA 326 Standard for Safeguarding of Tanks and Containers for Entry, Cleaning, or Repairs
UNIFIED FACILITIES CRITERIA (UFC)
UFC 3-460-01 Design: Petroleum Fuel Facilities UFC 3-460-03 Petroleum Fuel Systems Maintenance
UNIFIED FACILITIES GUIDE SPECIFICATIONS (UFGS)
UFGS 09 97 13.27 High Performance Coating for Steel Structures UFGS 33 01 50.65 Inspection of Field Fabricated Fuel Storage Tanks UFGS 33 56 21.17 Single Wall Aboveground Fixed Roof Steel POL Storage Tank
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 112 EPA: Oil Pollution Prevention
PART 6
ATTACHMENT
7. Attachment/Technical Exhibit List:
7.1. Attachment A – General Installation Security Requirements
7.2. Attachment B – Fuel Storage Tank List
7.3. Attachment C – Fuel Storage Tank Data Sheet
7.4. Attachment D – Monthly Contractors Progress, Management and Status Report
7.5. Attachment E – Inspection Telecon Briefing Template
7.6. Attachment F – Not Applicable
7.7. Attachment G – Not Applicable
7.8. Attachment H – Not Applicable
7.9. Attachment I – API External Template
7.10. Attachment J1 – Previous Inspection Report
7.11. Attachment J2 – Previous Inspection Report
7.12. Attachment J3 – Previous Inspection Report
7.13. Attachment J4 – Previous Inspection Report
TECHNICAL EXHIBIT 1
Performance Requirements Summary
The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
DELIVERABLES SCHEDULE
Performance Objective
Standard Performance Threshold
Method of Surveillance
PRS # 1.
Kick-Off Meeting with USACE and Stakeholders
Para. 1.4.7.
State, local, and federal requirements regulating fuel storage tanks
100% The contractor will schedule this Meeting either on site prior to commencement of work or via tel-con prior to being on site. Submit agenda and meeting minutes to stakeholders.
PRS # 2.
On site Inspection
Para. 4.1.2.
State, local, and federal requirements regulating fuel storage tanks.
100% Random Inspection.
PRS # 3.
Provide a UT and Roundness Inspection.
Para. 4.1.4.
State, local, and federal requirements regulating fuel storage tanks
100% Random Inspection.
DELIVERABLE SCOPE OF
WORK
PARAGRAPH
DUE DATE
Project Inspection Management Plan/Work Plan, Accident Prevention Plan & Health and Safety Plan (Draft)
3.3 & 3.4 15 days after award
Project Inspection Management Plan/Work Plan, Accident Prevention Plan & Health and Safety Plan (Final)
3.3 & 3.4 5 days after receipt of comments
Inspection and Evaluation Report – (Draft) 4.1.5. 28 days after Field Inspection
Inspection and Evaluation Report – to include populated Attachment C Excel Sheet for each base (Final)
4.1.5. 7 days after receipt of comments
TECHNICAL EXHIBIT 1