ATTACHMENT J01 STATMENT OF OWRK.docx
DOCX document 91 KB Posted
- Attached to
- La Mina Trail Repairs/Construction
- Solicitation number
- 12445225R0030
- Issued by
-
Department of Agriculture Forest Service
About this file
This Statement of Work (SOW) details the La Mina Trail Reconstruction Design-Build (DB) Project for the El Yunque National Forest in Puerto Rico. The project requires a single contractor to provide both engineering design and construction services for reconstructing the La Mina Trail, which currently has an average width of 2-3 feet and includes damaged historic Civilian Conservation Corps (CCC) stairways with trail grades exceeding -50%. Reconstruction activities include temporary traffic control, construction surveying, retaining wall reconstruction, trail bridge construction, trail guardrails, passing lanes, culverts, drainage improvements, erosion control, and vegetation restoration.
Key technical requirements include design deliverables at 35%, 85%, and 100% completion stages, with specific requirements for a 78'-0" trail bridge designed to AASHTO LRFD standards. The project is located approximately 11.9 miles south of Palmer, Puerto Rico, at an elevation of 2,097 feet, in an area receiving over 240 inches of annual rainfall. The contract requires all design work to be performed and stamped by a professional engineer licensed in Puerto Rico, with construction to commence immediately upon 100% design approval. Normal operational hours are 6:30 AM to 5:30 PM Monday through Friday, with potential weekend work requiring prior written approval from the Contracting Officer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 01 12445225R0030.pdf | ||
| J02 FS Supplemental Specifications.pdf | ||
| J04 Attachment Construction Experience Form.docx | DOCX document | |
| J05 Attachment Architect- Engineering Experience Form.docx | DOCX document | |
| J07 Attachment Key Personnel Resume.docx | DOCX document | |
| 12445225R0030.pdf | ||
| J03 La Mina Trail Rehab - Supporting Drawings.pdf | ||
| J06 Attachment Past Performance.docx | DOCX document | |
| J08 SOI LaMina.xlsx | XLSX spreadsheet | |
| J09 WD PR.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LA MINA TRAIL RECONSTRUCTION DB PROJECT
Statement of Work (SOW)
El Yunque National Forest
TABLE OF CONTENTS FOR SOW
| Section 1 - general | 3 | |
| 1.01 | GENERAL SCOPE OF THE PROJECT | 3 |
| 1.02 | PROJECT TRAFFIC CONTROL | 5 |
| 1.03 | project background | 5 |
| 1.04 | available information | 6 |
| 2. | Section 2 – design summary | 6 |
| 2.01 | Design: General administration | 6 |
| 2.02 | design tasks | 6 |
| 2.03 | project management (task 1) | 6 |
| 2.04 | design deliverables (tasks 2-5) | 7 |
| 3. | section 3 – construction summary | 9 |
| 3.01 | general administration | 9 |
| 3.02 | construction: inspection & acceptance | 10 |
| 3.03 | construction: bid & Payment | 10 |
| 3.04 | BASE construction tasks (Tasks 6-9) | 10 |
Section 1 - general
GENERAL SCOPE OF THE PROJECT
The USFS El Yunque National Forest (EYNF) proposes to reconstruct La Mina Trail as specified in this Statement of Work, Schedule of Items, and supporting sketches.
Reconstruction of the La Mina Trail will require the contractor to provide construction services through design-build (DB) method. The DB method would require the same contractor to provide both, the P.E. Engineering design and construction activities. The contractor shall be required to provide all labor, materials, supplies, equipment, transportation, supervision, tools, safety incidentals, ancillary services, and all other necessary items to complete the work in accordance with the Schedule of Items, Forest Service Supplemental Specification (FSSS), Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects per FP-14 Specifications and supporting attached Conceptual & Preliminary Drawings.
The design requirements and other engineering related services required for this project must be performed and stamped/seal by professional engineer(s) licensed in Puerto Rico. The design services may include but are not limited to site visit(s), site investigation, topographic services, geotechnical services, and providing 85% and 100% design deliverables for CO approval before construction of the approved 100% design deliverables can commence. Only the new proposed trail bridge will require a 35%, 85%, and 100% design deliverable. All other design deliverables shall require an 85%, and 100% design deliverable.
The DB contractor’s designs and construction shall be done simultaneously, meaning that as the government approves the DB contractor’s 100% design deliverable, the DB contractor shall immediately start construction on the respective 100% design deliverable.
Reconstruction activities include but not limited to temporary traffic control measures, construction surveying and staking, construction and reconstruction of retaining walls, trail bridges, damaged trail sections, trail guardrails, trail passing lanes, culverts, reinforced concrete low water crossing drainages, riprap placement, aggregate placement with compaction, finish concrete surfacing work, masonry work, protection of historic structures, erosion control measures, turf establishment, and tree planting.
At all times during the performance of this contract and until the work is completed and accepted, the Contractor shall directly supervise the work or assign and have on the work site a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor. The superintendent shall be designated in writing to the Contracting Officer prior to the commencement of work. This individual shall be able to read, speak, and understand English.
During the duration of construction project, the Contractor shall preserve and protect all historic structure(s) and vegetation (such as historic ccc walls, trees, shrubs, and grass) adjacent to the work site within the clearing limits of the contractor’s approved DB Drawings, which are not to be removed and which do not unreasonably interfere with the work required under this solicitation. Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc).
Prior to beginning work, the Contractor is responsible for identifying all appropriate commercial sources of material and equipment.
The existing La Mina Trail system has an average existing trail width of 2’ – 3’ wide with multiple existing damaged and historic CCC stairways and trail grades exceeding -50%.
The specified work is generally confined within the limits of the existing trail traveled way, adjacent ditches, shoulders, cut/fill slopes, and trail embankment.
The El Yunque National Forest can receive rainfall of over 240 inches (6.1 m) per year. The contractor shall be responsible for monitoring the local weather conditions at project site. An unexpected or unanticipated rain shower can develop anytime without warning.
All contractor’s movement or transportation of equipment to or from project site required to pursue the work in this solicitation, to repair or replace equipment, or for the Contractor's convenience shall be at the Contractor's expense and considered incidental to their proposal.
Normal operational hours are approximately from 06:30 am to 5:30 PM Atlantic Standard Time, Monday through Friday (Federal Holidays excluded). Weekend work may be permitted with written approval from the Contracting Officer (COR) prior.
Federal Holidays
1. New Year’s Day – January 1st
2. Martin Luther King Junior’s Birthday – Third Monday in January
3. President’s Day – Third Monday in February
4. Memorial Day – Last Monday in May
5. Juneteenth Day – Third (3rd) Monday in June
6. Independence Day – July 4th
7. Labor Day – First Monday in September
8. Columbus Day – Second Monday in October
9. Veteran’s Day – November 11th
10. Thanksgiving Day – Fourth Thursday in November
11. Christmas Day – December 25th
PROJECT TRAFFIC CONTROL
The La Mina Trail project site will be closed for construction. Contractor’s temporary traffic control plan shall be submitted to the Contracting Officer for approval in the construction phase.
· The contractor’s temporary traffic control plan, and signs installations, and barricades shall be covered and incidental to the contractor’s design and construction pay items.
· The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the PR-191 Highway, Palo Colorado Recreation Area, and La Mina Trail. Warning signs and temp traffic control signs shall be erected at all intermediate points, where the new work crosses or coincides with an existing road or trail, trail head, parking lot, and during contractor’s hauling activities. The Contractor shall post warning signs on before the section of road being worked (Ex. 1500 ft ahead, 1000 feet ahead, 500 feet, and type 3 barricade). Signs are to be of the size, quantity, and colors as required in the current edition of the "Manual on Uniform Traffic Control Devises", (MUTCD). All slow-moving equipment is to have a reflectorized "slow moving" vehicle emblem properly attached. A copy of MUTCD can be downloaded at the link below.
https://mutcd.fhwa.dot.gov/pdfs/2009/mutcd2009edition.pdf project background Project Locations: The “La Mina Trail Reconstruction DB Project” is located approximately 19.15 KM (11.9 miles) south of Palmer, Puerto Rico. It lies at an approximate elevation of 2,097 feet above mean sea level.
Approximate geodetic coordinates for the “La Mina Trail Reconstruction” Site are 18.301255, -65.784940 available information Government furnished Autocad Civil 3D Templates (.dwg format).
Pictures of site (.jpg) Section 2 – design summary Design: General administration The Contractor shall furnish all materials, supplies, equipment, transportation, and personnel to provide the described architectural and engineering services.
Final construction documents shall be stamped and sealed by a Professional Engineer licensed in Puerto Rico.
The design and construction documents shall document all relevant design criteria, governing codes and standards, FP-14 Specification, AASHTO LRFD 2017, Construction Specifications Institute (CSI), or Latest Specification as reflected below.
The Design-Build Team shall keep data and drawings in a confidential manner and shall not release this information to people outside the C.O. and the Design-Build Team who are working on this project without the Forest Service’s written approval.
design tasks See Prospectus for detailed information regarding design tasks.
Task 1: Project Management Task 2: Field Investigations Task 3: 85% Design Package Task 4: 100% Design Package Task 5: Final/Construction Design Package project management (task 1) The Design-Build Team shall designate a point of contact for coordination of this project. This individual shall have overall responsibility for the performance of the work to ensure the work is progressing on schedule and within budget.
The Design-Build Team shall maintain communication records, project budget summary sheet, all project related conversations, meeting notes, critical decision log, and quality assurance audits and make these available to the C.O. as requested.
The Design-Build Team shall prepare a project schedule noting the submittal points for each task and other critical phases in the design process. The proposed design schedule will incorporate a timeline beginning after issuance of the Notice to Proceed and ending with the completion of the Construction Documents. The schedule will incorporate a submittal review by the C.O. for the durations described in this section.
The Design-Build Team shall schedule meetings as required by the project. At a minimum the Design-Build Team shall anticipate and conduct the following:
Kick-Off Meeting. The meeting shall be held within 10 calendar days after the issuance of the Notice to Proceed. The purpose of the meeting is to schedule and organize field visits, review existing data, establish goals, objectives, review provided attachments, and organize design criteria as necessary.
Field Investigation Meeting: The meeting shall be held within 10 calendar days after the Forest Service has concluded the review of the field investigation summary, described in the Prospectus, and to discuss findings and design considerations.
Design Submittal Review Meetings. Each submittal review meeting will be held within 10 calendar days after the Forest Service review has concluded. The purpose of the meeting is to review submitted materials, address concerning concepts or features, discuss design and construction estimates, and determine the scope of remaining work with respective schedule.
design deliverables (tasks 2-5) Design submittals and reviews shall be accomplished when 85%, and Final 100% of the work is completed, unless otherwise noted below (trail bridge design). The Design-Build Team shall present required accomplished work and the proposed direction of work in the formats according to the information and schedule detailed in the Prospectus.
All 100% Design Deliverables Shall Be Construction Surveyed and Staked for Construction which shall be the responsibility of the contractor. C.O. Approval is Required of All Construction Surveying and Staking Items Before DB Contractor Can Commence On Construction. All Construction Survey and Staking Shall be Incidental to Contractor’s Proposal.
35%, 85%, and 100% Design Requirements
· Design of a 78’-0” Span x 6’-0” Clear Width Trail Bridge as reflected in the Schedule of Items Pay Item # 50
· DB contractor shall submit a trail bridge designed by P.E. Engineer licensed in PR.
· Trail bridge shall be designed to the requirements of AASHTO LRFD which shall include but not limited to: dynamic load allowance, resistance factors, Strength I, Strength II, Service I AASHTO LRFD Limit states, 75 years structure life, trail bridge guardrails, and designed for a minimum live load of 158 pounds square foot (psf).
· Design deliverable shall include DB contractor submitting to the CO a 35%, 85%, and 100% design deliverable.
· 35% design deliverable shall reflect a 100% Licensed Surveyor Stamped/Sealed topographic survey, 100% H&H Analysis Report, and proposed trail bridge conceptual plan and profile reflecting the 100-Yr flood event elevation with 3-feet of freeboard.
· 85% design deliverable shall reflect a 100% Stamped/Sealed Geotechnical Exploration, and 85% trail trail bridge design effort.
· 100% design deliverable shall reflect 100% P.E. Stamped/Sealed structural calculations, and 100% design drawings deliverable ready for construction with P.E. Stamp/Seal
· DB contractor shall allow a minimum of 10 business days (Mon.-Friday) for government review of each trail bridge’s deliverables (35%, 85% and 100%). The contractor shall not proceed on the trail bridge’s construction until the CO officially approves the DB Contractor’s 100% design deliverable in writing.
85% and 100% Design Requirements
· Design of multiple retaining wall fill slope and cut slope failure repairs for the respective stationing as reflected in the Schedule of Items
· DB contractor shall submit P.E. stamp/sealed structural calculations that supports each respective retaining wall structure(s).
· All retaining wall structures structural calculations shall reflect AASHTO LRFD Strength 1 and Service 1 Limit State checks for sliding stability, overturning stability, eccentricity, and bearing resistance checks conforming to AASHTO LRFD Specification requirements.
· All geotechnical services and requirements for successful design and construction shall be the responsibility of the DB contractor.
· Design of trail re-construction repairs for the respective stationing as reflected in the Schedule of Items
· Design of trail widening for the respective stationing as reflected in the Schedule of Items
· Design of passing lanes for the respective stationing as reflected in the Schedule of Items
· Design of drainage crossing for the respective stationing as reflected in the Schedule of Items
· Design of stairway widening for the respective stationing as reflected in the Schedule of Items
· Re-design of Trail Bridge # 5 and Trail Bridge #6 to reflect a proposed 6’-0” out-to-out width widening
· All 85% and 100% design deliverables shall reflect all respective detail drawings, cross sections, reinforcement layout, footing and base layouts and stem walls etc, bottom and top of structure elevations, construction stakeout coordinates, finished grade elevations, and culvert and drainage crossing inlet and outlet inverts for a successful construction.
The Government will review the Contractor’s submittals for conformance with the terms of this Statement of Work and Prospectus. Expect the Government to return comments on submittals within timelines noted in this Section. Submittals must be received as a complete package reflecting respective percentage progress; incomplete submittals will be returned without review.
If the submittal conforms with the contract requirements, the Forest Service will provide the following statement: “The Government concurs the __ percent submittals conform to the terms of the contract. Government concurrence in this design review does not relieve the Contractor from correction of errors or omissions.”
If the submittals do not conform to the terms of the contract, the Design-Build Team will be advised of deficiencies.
Forest Service review or approval of submittals only indicate that the design, general method of construction, materials, detailing, and other information appear to meet the Project Criteria.
Forest Service review or approval will not relieve the Design-Build Team of the responsibility for any error which may exist, as the Design-Build Team is responsible for the satisfactory and quality control of their design and construction work.
The Government reserves the right to reject the final submittal and request revisions to the final based on significant comments of the design and upon necessary changes needed to establish accurate and precise construction.
section 3 – construction summary general administration Project Control & Management The DB Team shall account for all Temporary Traffic Control during the performance period of this contract for the life of the contract. Refer to Section 1.02 Per Subsection “A” of the SOW for temporary traffic control requirements.
Weather conditions typical for this area are the tornado and hurricane seasons.
Design-Build Team is responsible for protecting workers from injury (refer to FAR 52.236-13, Accident Prevention, for full text).
The Government is not responsible for loss of or damage to materials or supplies stored on-site during performance of this awarded contract. Staging areas on government lands shall be authorized and approved by the C.O..
The Design-Build Team shall conduct activities so that interference with the public shall be kept at a minimum.
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the Specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.
Designation of Contracting Officer’s Representative The CO will designate a Contracting Officer's Representative (COR) at the time of contract award.
The CO and COR should be informed as soon as possible of any actions or inactions by the Design-Build Team or the Government which will change the required delivery or completion times stated in the contract, and the contract.
On all matters that pertain to the contract terms the Design-Build Team shall communicate with the CO and COR.
Notification of Subcontracting. The Design-Build Team shall promptly notify the CO upon entering into any subcontract arrangement. The subcontractor shall have the experience and be equipped for such work. The Design-Build Team and subcontractor shall fill out the SF 1413, Statement and Acknowledgement and submit to the CO. Subcontracting any portion of the task order shall not relieve the Prime Contractor of any responsibility under this task order. Any subcontract agreement shall contain all terms and conditions of the prime task order. Other written notification shall include the minimum:
A copy of the Statement of Acknowledgement form (SF-1413) must be provided to the to the CO prior to any subcontractor work beginning.
Wage Determination Decision. The general wage determination applicable to this contract will be incorporated into the solicitation by the C.O..
construction: inspection & acceptance The contractor is 100% responsible for their own quality control.
· The government may perform random sampling, testing and inspection of the contractor’s work in progress. This does not relieve the contractor of their quality control.
Following final inspection, if work is determined substantially complete, Contracting Officer will prepare list of deficiencies for the contractor’s corrections before government’s final acceptance of project.
The contractor shall notify the C.O. a minimum of 2-weeks in advance of the government’s Final Inspection. The Design-Build Team shall allow themselves enough time to complete work described on the government’s list of deficiencies (Punch List) within the awarded contract days.
If Design-Build Team fails to complete the work within this time frame, Contracting Officer may either replace or correct the work with an appropriate reduction in contract price or charge for re-inspection costs according to the contract’s Inspection of Construction clause.
If deficiencies are corrected, the CO will issue a Letter of Final Acceptance.
construction: bid & Payment Invoicing Processing Platform (IPP). Contractors shall submit all invoices electronically via IPP at www.ipp.gov. Paper copies of invoices shall be provided to the C.O. in advance for approval prior to submitting invoice into the IPP system. The Design-Build Team shall also attach a detailed invoice in IPP.
Payment for Incidental Items. The intent of the contract is to provide for the complete construction of the project described. The Design-Build Team shall furnish all labor, materials, equipment, tools, transportation and supplies and perform all work required to complete the project in accordance with drawings, specifications and provisions of the contract. Payment for contract work will be made only for and under the Design and Construction pay items included in the Bid Schedule. All other work and materials will be considered incidental or indirect to and shall be included in the contractor’s proposal.
BASE construction tasks (Tasks 6-9) See Prospectus for detailed information regarding construction tasks.
Task 6: Construction of Government Approved Design Task 7: Debris Disposal Task 8: Final Cleanup Task 9: As-Built Drawings (Shall be Submitted to the Government Prior to Final Payment) image1.png