Attachment J.8 Incentive and Monitoring Framework.docx

DOCX document 22 KB Posted

Attached to
Adapting and Modifying Optimized Sample Transport Routes for Achieving Impact (AMOSTRA) Federal contract opportunity
Solicitation number
72065621R00001
Issued by
US Agency for International Development Mozambique

About this file

This document contains an incentive and monitoring framework for the Adapting and Modifying Optimized Sample Transport Routes for Achieving Impact (AMOSTRA) federal contract opportunity. The framework establishes two key performance indicators for on-time delivery and full delivery of laboratory specimens, with contractors incentivized through quarterly fee payments of up to 8% based on performance against the targets. Contractors are to propose a minimum 2% fee, with costs reimbursed and performance monitored monthly by the USAID Integrated Health Office and Mozambique's Department of Central Laboratories, aimed at gradually transitioning the specimen transportation system to government management over three years while expanding access to viral load, early infant diagnosis, and tuberculosis testing across Mozambique.

View the file

Other files for this federal contract opportunity

Other files attached to Adapting and Modifying Optimized Sample Transport Routes for Achieving Impact (AMOSTRA), newest first.
File Type Posted
SOL-72065621R00001 - AMOSTRA Amendment 01.pdf PDF
Attachment J.9 Samples per HF.pdf PDF
Revised Attachment J.8 Incentive and Monitoring Framework .pdf PDF
Attachment J.6 Employee Biodata sheet.doc DOC document
Attachment J.3 Specimen Transport Guidelines.pdf PDF
Attachment J.2 Inherently governmental functions Unsigned.pdf PDF
Attachment J.5 Budget Template.xlsx XLSX spreadsheet
72065621R00001 RFP.pdf PDF
Attachment J.7 Past Performance.docx DOCX document
Attachment J.4 Work Plan Template.xlsx XLSX spreadsheet
Attachment J.1 AMOSTRA List of Acronyms.docx DOCX document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USAID AMOSTRA Incentive and Monitoring Framework

I. Performance Incentive Plan

Under USAID AMOSTRA, offerors will provide a detailed cost and a minimum fee that does not exceed 2% of the target cost. Once awarded, the contractor will be reimbursed for all reasonable, allowable and allocable costs, in accordance with the Limitations of Funds Clause—FAR 52-232-22. An incentive payment, up to 8% of the target cost will be calculated based on the measure below and be paid on a quarterly basis.

USAID intends to provide performance incentives (PI) based on the performance against two key performance indicators. These performance incentive payments will be based on the value of deliveries that are approved for reimbursement on a semi-annual basis (for a total of 6 payments over the lifespan of the three-year contract). Contractors should propose a reasonable base fee not exceeding 2% in accordance with the quantity and risks. The maximum fee for this procurement will be 8% of the target cost. Indicators are defined so that they are within the manageable control of the contractor. The contractor is invited to suggest additional industry-specific indicators that will improve performance monitoring and maximizing efficiency. Performance will be tracked on a monthly basis; however, the incentive calculations will be made on a quarterly basis.

Key Performance Metric
Target
Fee Structure
Fee Application

On time delivery

This key performance metric measures the timeliness to which health facilities receive specimens in accordance with the pre-established distribution plan agreed with the contractor.

91-100%

81-90%

71-80% Tier 3 (91-100%): 4%

Tier 2 (81-90%): 3%

Tier 1 (71-80%): 1%

Applied to the expected target cost for the quarter

In full delivery

This key performance metric measures the completeness of deliveries in accordance with the pre-established distribution plan agreed with the contractor.

96-100%
Tier 3 (>96-100%): 4%

Tier 2 (90-95%): 3%

Tier 1 (85-89%): 1%

Applied to the expected target cost for the quarter

II. Illustrative Performance Monitoring Plan

USAID intends to track performance on a monthly basis; however, the incentive calculations will be made on a quarterly basis.

Key Performance Metric
Data Acquisition Plan
Data Quality Considerations
Data Analysis

On time delivery

Data collection method: Submitted & approved in AMOSTRA reporting to be reviewed by DCL

Data Source: Agreed upon plan signed by DPS and signed proof of delivery (POD)

Frequency: Monthly Data Quality Assessment: DQA performed quarterly for a randomly selected province, and on an as needed basis when performance problems or complaints are raised

Potential Limitations: Districts may not have distribution plans Mitigation Plan: Make clear the distribution plan requirement before starting distributions in each geographic area.

Reported monthly with quarterly and semi-annual and annual review of trends by USAID IHO, and DCL serve as the basis for the semi-annual incentive payment

In full delivery

Data collection method: Submitted in AMOSTRA reporting

Data Source: Delivery notes

Frequency: Monthly Data Quality Assessment: DQA performed quarterly for a randomly selected province, and on an as needed basis when performance problems or complaints are raised Potential Limitations: Delivery notes without signature and/or date Mitigation Plan: Training at the start of implementation on how to fill out delivery notes and conduct quality assurance during data review meetings Reported monthly with quarterly and semi-annual and annual review of trends by USAID IHO, and DCL serve as the basis for the quarterly incentive payment

Performance Monitoring Roles:

USAID Integrated Health Office (IHO), and Departamento Central de Laboratorios (DCL) will monitor the performance of the AMOSTRA contractor. Under this award, there will be a strong collaboration USG and the DCL. Other direct stakeholders include Mozambican Government officials at the national and sub-national level, health facilities and PEPFAR and other service delivery partners that support health facilities. Over the three years of the contract, the contractor and USAID will play a prominent role in monitoring performance and after the third year the responsibility for delivery of laboratory specimens and diagnosis will be gradually transitioned to the DCL The monitoring roles for the two main institutions validating AMOSTRA performance, are detailed in the table below:

Monitoring Activity
USAID IHO
DCL

Start of Award

Desk review, progress versus agreed deliverables and milestones
Monthly
Monthly
Central review performance data reported by AMOSTRA contractor
Quarterly
Quarterly
Conduct site monitoring visits with data validation checks
Quarterly
Monthly
Participate in in-person provincial level performance reviews with provinces/DPSs
Ad hoc
Quarterly
Conduct data quality assessment
Ad hoc
Quarterly
Review corrective action plans and completion of agreed actions
As needed
As needed