This is a Cost Proposal Template (Attachment J.1) for a Time & Materials contract related to NHTSA's Low Cost Pedestrian Safety Zones Demonstrations project. The template is structured to capture costs across 17 different tasks (C.6.1 through C.6.17) and includes sections for direct labor, fringe benefits, travel, subcontractors, and other direct costs.
The template breaks down the contract into a base period (Year 1) and two option years, with specified labor categories and hours. Key labor categories include Senior Project Manager (KEY), Senior Software Engineer, Software Engineer, Solutions Architect, Senior Data Architect, Senior Business Analyst, and Quality Assurance Specialist. The base year requires 12,240 total labor hours, Option Year 2 requires 7,230 hours, and Option Year 3 requires 5,290 hours. The template provides space for fixed loaded hourly rates, indirect cost rates, and travel/ODC costs, though no actual costs are populated in the template.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Question and Answer Response.pdf | ||
| SFLLL_2_0-V2.0.pdf | ||
| Attachment J.4 Past Performance Questionnaire.doc | DOC document | |
| Attachment J.1 Cost Proposal Template.xlsx | XLSX spreadsheet | |
| RFP 693JJ925R000019.pdf | ||
| GG_LobbyingForm-V1.1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Task Breakout
| COST ELEMENTS | Total FTEs | TASK C.6.1 | TASK C.6.2 | TASK C.6.3 | TASK C.6.4 | TASK C.6.5 | TASK C.6.6 | TASK C.6.7 | TASK C.6.8 | TASK C.6.9 | TASK C.6.10 | TASK C.6.11 | TASK C.6.12 | TASK C.6.13 | TASK C.6.14 | TASK C.6.15 | TASK C.6.16 | ||||||||||||||||||||||||||||||||
| Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | Hours | Rates | Total | ||
| COST ELEMENTS |
| Labor Categories | ||||||||||||||||||||||||||||||||||||||||||||||||
| $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | 0 | $0.00 | $0 | ||||||||||||
| $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | 0 | $0.00 | $0 | ||||||||||||
| $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | 0 | $0.00 | $0 | ||||||||||||
| $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | 0 | $0.00 | $0 | ||||||||||||
| $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | 0 | $0.00 | $0 | ||||||||||||
| $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | 0 | $0.00 | $0 | ||||||||||||
| $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | 0 | $0.00 | $0 | ||||||||||||
| $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | 0 | $0.00 | $0 | ||||||||||||
| $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | 0 | $0.00 | $0 | ||||||||||||
| $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | 0 | $0.00 | $0 | ||||||||||||
| $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | 0 | $0.00 | $0 | ||||||||||||
| $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | $0.00 | $0 | 0 | $0.00 | $0 | ||||||||||||
| Subtotal Direct Labor | 0 | $0 | 0 | $0 | $0 | 0 | $0 | 0 | $0 | $0 | 0 | $0 | 0 | $0 | $0 | 0 | $0 | 0 | $0 | $0 | 0 | $0 | 0 | $0 | $0 | 0 | $0 | $0 | 0 | $0 |
Fringe Benefits (NA)
Total Direct Labor $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
| Travel (See separate schedule) | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||||||||||||||||||
| SUBCONTRACTORS | ||||||||||||||||||||||||||||||||||||
| Subcontractor Name | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||||||||||||||||||
| Subcontractor Name | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||||||||||||||||||
| Subcontractor Name | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||||||||||||||||||
| Subcontractor Name | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||||||||||||||||||
| Subcontractor Name | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||||||||||||||||||
| Subcontractor Name | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||||||||||||||||||
| Subcontractor Name | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||||||||||||||||||
| Total Subcontractor | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 | 0 | $0 |
Other Direct Costs (See separate schedule) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
SUBTOTAL ALL DIRECT COSTS $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Indirect Costs Rate (at ______ %) (Only on ODC's) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
SUBTOTAL COSTS $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Total Cost $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Offerors can add more columns as necessary to incorpotate all tasks.
&"-,Bold"NHTSA RFP 693JJ919R000090 TITLE: Low Cost Pedestrian Safety Zones Demonstrations
COST PROPOSAL TEMPLATE (T&M)
Attachment J.1&"-,Regular"&10
Price Schedule Base Period Yr 1
B.4.1 BASE PERIOD (YEAR 1) - TASK ORDER PERIOD OF PERFORMANCE:
Prices shall cover the performance period from the effective date of task order award through twelve (12) months thereafter.
| Labor Category | Level Of Effort (Hours) | Fixed Loaded Hourly Rate | Total Price |
| Senior Project Manager (KEY) | 1,000 | ||
| Senior Software Engineer | 1,880 | ||
| Software Engineer | 1,880 | ||
| Solutions Architect | 900 | ||
| Senior Data Architect | 1,880 | ||
| Senior Business Analyst | 1,880 | ||
| Quality Assurance Specialist | 2,820 | ||
| TOTAL LABOR COST | 12,240 | ||
| OTHER DIRECT COSTS CATEGORIES | ESTIMATED COST | INDIRECT RATE | TOTAL COST |
| Travel |
Subtotal ODCs
| Total ODCs |
| Total Labor Cost |
TOTAL TASK ORDER TERM NTE AMOUNT
Price Schedule Option Year 2
| B.4.2 OPTION PERIOD 1 (YEAR 2) - TASK ORDER PERIOD OF PERFORMANCE: |
| Prices shall cover the performance period from end of base period through twelve (12) months thereafter. |
| Labor Category | Level Of Effort (Hours) | Fixed Loaded Hourly Rate | Total Price |
| Senior Project Manager (KEY) | 100 | ||
| Senior Software Engineer | 1,400 | ||
| Software Engineer | 900 | ||
| Solutions Architect | 400 | ||
| Senior Data Architect | 500 | ||
| Senior Business Analyst | 1,150 | ||
| Quality Assurance Specialist | 1,880 | ||
| TOTAL LABOR COST | 7,230 | ||
| OTHER DIRECT COSTS CATEGORIES | ESTIMATED COST | INDIRECT RATE | TOTAL COST |
| Travel |
Subtotal ODCs
| Total ODCs |
| Total Labor Cost |
TOTAL TASK ORDER TERM NTE AMOUNT
Price Schedule Option Year 3
| B.4.3 OPTION PERIOD 1 (YEAR 3) - TASK ORDER PERIOD OF PERFORMANCE: |
| Prices shall cover the performance period from end of option period 1 through twelve (12) months thereafter. |
| Labor Category | Level Of Effort (Hours) | Fixed Loaded Hourly Rate | Total Price |
| Senior Project Manager (KEY) | 700 | ||
| Senior Software Engineer | 900 | ||
| Software Engineer | 800 | ||
| Solutions Architect | 350 | ||
| Senior Data Architect | 450 | ||
| Senior Business Analyst | 950 | ||
| Quality Assurance Specialist | 1,140 | ||
| TOTAL LABOR COST | 5,290 | ||
| OTHER DIRECT COSTS CATEGORIES | ESTIMATED COST | INDIRECT RATE | TOTAL COST |
| Travel |
Subtotal ODCs
| Total ODCs |
| Total Labor Cost |
TOTAL TASK ORDER TERM NTE AMOUNT