Attachment J-3 - Deliverables Schedule.docx

DOCX document 15 KB Posted

Attached to
Master Synch
Solicitation number
030ADV26Q0068
Issued by

About this file

This is a Deliverables Schedule that outlines the timeline and milestones for a Master Sync system replacement project at the Library of Congress's National Audio-Visual Conservation Center (NAVCC) in Culpeper, Virginia. The project requires the contractor to provide hardware, installation, and documentation for a replacement Evertz Master Sync Generator system that will serve as a crucial reference signal provider for the video digitization lab. The schedule establishes sequential deliverables beginning with a Project Kickoff Meeting within one week of the performance start date, followed by a Project Schedule, Cutover and Testing Plan due within five days after the kickoff. The System Design Review and Hardware Procurement invoice are due no later than three weeks after the introductory meeting, with all hardware delivery required on-site no later than six weeks after System Design Acceptance.

Installation, Integration Testing, System Commissioning, and removal of obsolete cabling must be completed no later than two weeks after all hardware arrives on-site. The final deliverables include resolution of issues identified on the punch list and Final Sign-Off documentation, along with System As Built Documentation, due no later than 15 days after installation completion. The contractor will invoice separately for the hardware portion of the project and submit an invoice for the final balance upon written acceptance of system completion by the Contracting Officer's Representative (COR). The Project Kickoff Meeting is marked as Not Separately Priced (NSP), indicating this service is included in the overall contract pricing.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F.1 DELIVERABLES

SCHEDULE OF DELIVERABLES

Requirements Paragraph
Description of Events/Deliverable
Due Date
Amount
3.1
Project Kickoff Meeting/Introductory Planning Meeting
Within one (1) week of period of performance start date.
Not Separately Price (NSP)
3.1, 3.3
Project Schedule, Cutover and Testing Plan
No Later than (NLT) five (5) days after Introductory Planning Meeting.
3.2, 3.4
System Design Review,

Hardware Procurement NLT – 3 weeks after introductory meeting Invoice for Hardware portion of the Project

3.5, 3.6 Site Preparation and Delivery: All hardware must be delivered on site before installation

NLT – 6 weeks after System Design Acceptance.

3.7, 3.8
Installation, Integration Testing, System Commissioning, Removal of Obsolete Cabling System

NLT -2 weeks after all Hardware on site.

3.9, 3.10
Resolve Issues Identified on the Final Punch List and Final Sign-Off documentations

System As Built Documentation NLT 15 days after completion of Installation Invoice for final balance on written acceptance of system completion by COR