This document summarizes a request for proposal for the Landing Craft, Air Cushion Extended Service Life Extension Program. The Naval Sea Systems Command is seeking proposals to extend the service life of up to 18 LCAC craft through repair and installation of hull structures, machinery, electrical systems, electronics, and piping systems. Offerors must integrate government furnished property, such as unique cables and command/control systems, using the provided technical data package. Delivery of the first reworked craft is required within 16-20 months of contract award, and performance will occur at Assault Craft Unit Five. Responsible offerors from any company may respond by the specified due date. While the procurement is unrestricted, it includes provisions for a small business set-aside if two responsible small business bids meet requirements. The technical data package will be provided electronically via an Integrated Data Environment website requiring DoD PKI authentication.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N00024-20-R-2427 Amend 0003.docx | DOCX document | |
| N00024-20-R-2427 Amend 0002.docx | DOCX document | |
| N00024-20-R-2427 Amend 0001.docx | DOCX document | |
| Attachment J-2e CDRLs Exhibit B 27MAY20 - SIGNED.docx | DOCX document | |
| Attachment J-4b GFP Performance_13-24 11MAR20.pdf | ||
| Attachment J-2a CDRL Information 26MAY20.docx | DOCX document | |
| Attachment J-2d Exhibit B Index 27MAY20.doc | DOC document | |
| N00024-20-R-2427.docx | DOCX document | |
| Attachment J-4c GFP Performance_25-28 11MAR20.pdf | ||
| Attachment J-2b Exhibit A Index 27MAY20.doc | DOC document | |
| Attachment J-4a GFP Performance_1-12 11MAR20.pdf | ||
| Attachment J-3 Perf Miles Pay Sch 26 May 2020.xlsx | XLSX spreadsheet | |
| Attachment J-1 TDP 26MAY20.DOCX | DOCX document | |
| J-12 Designation of Key Personnel.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LCAC E-SLEP
N00024-20-R-2427
ATTACHMENT J-2c
CONTRACT DATA REQUIREMENTS LIST,
DD FORM 1423
EXHIBIT A
27 MAY 2020
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item) Form Approved
OMB NO. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
CLIN 0200
B. EXHIBIT
A
C. CATEGORY:
TDP _____ TM _____ OTHER __X__
D. SYSTEM/ITEM
LCAC/E-SLEP
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-01: GENERAL CRITERIA (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80711A
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
SUPERVISOR (SWRMC)
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
(SEE BLOCK 16)
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
N/A
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT.
DATA SUBMISSIONS AS LISTED IN SI 009-01 WITH THE FOLLOWING EXCEPTIONS:
(A) PARAGRAPH 3.2.5 DRY DOCK INSPECTION REPORTS NOT APPLICABLE.
(B) SUBMIT SECURITY REQUIREMENTS DATA OF PARAGRAPHS 3.10 DIRECTLY TO THE SUPERVISOR (SWRMC). DO NOT POST IN LCAC IDE.
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE, SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP. 2401 ET. SEQ.).
VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES.
DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25. DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 12 – DATA SUBMISSIONS AS LISTED IN SI 009-01 AS MODIFIED BY ATTACHMENT TO CDRL A001.
BLOCK 13 – AS SPECIFIED SI 009-01.
BLOCK 14 – ALL CDRL DATA SUBMISSION REQUIREMENTS SHALL BE PROVIDED TO
SUPERVISOR (SWRMC) AND ACU 5. CDRL A001-B SHALL ALSO BE PROVIDED TO PMS377 BY POSTING TO THE PMS377 IDE:
| CDRL | DATA | STANDARD ITEM 009-01 REFERENCE* | |
| A001-A | CONDITION FOUND REPORT | PARAGRAPHS 3.2.1**, 3.2.2, 3.2.6***, 3.2.6.3*** |
BLK10 – FREQUENCY – AS DEFINED IN 009-001 PARAGRAPH 3.2.1, AND 3.2.2 WITH THE EXCEPTION THAT THE 20% REFERENCE IS NOT APPLICABLE FOR LCAC AVAILABILITIES
A001-B REQUEST FOR DEVIATION PARAGRAPH 3.8
BLK10 – FREQUENCY – WITHIN ONE DAY OF IDENTIFYING THE DEVIATION
A001-C MATERIAL SAFETY DATA SHEET PARAGRAPH 3.12
BLK10 – FREQUENCY – AS REQUESTED BY THE SUPERVISOR AS DEFINED ON 009-001 PARAGRAPH 3.12
*INCLUDES ASSOCIATED SUBPARAGRAPHS
**CFRs SHALL BE SUBMITTED TO NMD PER SECTION C.
***LIST OF MATERIAL SHALL INCLUDE NATIONAL STOCK NUMBERS (NSN) WHERE APPLICABLE.
SUBMIT WORK ITEM INSPECTION REPORTS, SI 009-01 PARAGRAPH 3.2.2, THAT INCLUDE
REPAIR RECOMMENDATIONS WITHIN 45 DAYS OF START OF A CRAFT’S E-SLEP AVAILABILITY,
EXCEPT FOR WORK ITEMS 120-11-001 AND 150-11-001. FOR THOSE WORK ITEMS, INSPECTION REPORTS WITH REPAIR RECOMMENDATIONS SHALL BE SUBMITTED WITHIN 7 DAYS AFTER ENGINE MODULE REMOVAL FROM CRAFT.
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| PMS377 IDE |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 3 |
| 0 |
G. PREPARED BY
PIERCE SCHREIBER
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A002
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-04: QUALITY MANAGEMENT SYSTEM (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
A (SEE BLOCK 16)
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – SUBMIT INITIAL QUALITY MANAGEMENT SYSTEM AND UPDATES PER SI 009-04. OTHER DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT. DATA SUBMISSIONS AS LISTED IN SI 009-04.
BLOCK 08 – APPROVAL FOR CONTENT. APPROVAL AUTHORITY – SUPERVISOR (SWRMC).
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF
PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE, SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP .2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25. DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 10, 11, 13 – AS SPECIFIED IN SI 009-04.
BLOCK 12 – SUBMIT QUALITY ASSURANCE PROGRAM NO LATER THAN 10 CALENDAR DAYS AFTER CONTRACT AWARD.
BLOCK 14 – ALL CDRL DATA SUBMISSION REQUIREMENTS SHALL BE PROVIDED TO SUPERVISOR (SWRMC) AND ACU 5. CDRL A002-A AND A002-B SHALL ALSO BE PROVIDED TO PMS377 BY POSTING TO THE IDE:
| CDRL | DATA | STANDARD ITEM 009-04 REFERENCE* |
| A002-A | QUALITY MANAGEMENT SYSTEM MANUAL | |
| AND PROCEDURES | PARAGRAPH 3.1 | |
| A002-B CORRECTIVE ACTION RESPONSES | PARAGRAPH 3.5 |
*INCLUDES ASSOCIATED SUBPARAGRAPHS
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| PMS377 IDE |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 3 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A003
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-09: PROCESS CONTROL PROCEDURE (PCP) – DOCUMENTATION (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT. DATA SUBMISSIONS AS LISTED IN SI 009-09.
BLOCK 08 – APPROVAL FOR CONTENT. THE CONTRACTOR SHALL ALLOW SEVEN (7) WORKING DAYS FOR REVIEW AND COMMENT BY THE GOVERNMENT. APPROVAL AUTHORITY – SUPERVISOR (SWRMC).
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF
PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE., SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP .2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 10, 11, 12, 13 – AS SPECIFIED IN SI 009-09.
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| PMS377 IDE |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 3 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A004
2. TITLE OF DATA ITEM
CERTIFICATION/DATA REPORT
3. SUBTITLE
SI 009-12: WELDING, FABRICATION, AND INSPECTION
REQUIREMENTS – PERSONNEL QUALIFICATIONS (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80678
5. CONTRACT REFERENCE
C.1.2.11
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT. DATA SUBMISSIONS AS LISTED IN SI 009-12.
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF
PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE, SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP .2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 10, 11, 12, 13 – AS SPECIFIED IN SI 009-12.
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 2 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A005
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-23: INTERFERENCES (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT. DATA SUBMISSIONS AS LISTED IN SI 009-23.
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF
PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE, SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP .2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 10, 11, 12, 13 – AS SPECIFIED IN SI 009-23.
| CDRL | DATA | STANDARD ITEM 009-23 REFERENCE* |
| A005-A | REPORT OF ADDITIONAL INTERFERENCES | |
| TO BE REMOVED | PARAGRAPH 3.2 | |
| A005-B | REPORT OF PREVIOUSLY DAMAGED OR | |
| DETERIORATED INTERFERENCES | PARAGRAPH 3.3 |
*INCLUDES ASSOCIATED SUBPARAGRAPHS
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 2 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A006
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-40: REQUIREMENTS FOR CONTRACTOR
CRANES, MULTI-PURPOSE MACHINES AND MATERIAL HANDLING EQUIPMENT AT NAVAL FACILITIES – ACCIDENT REPORT (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSIONS AS LISTED IN SI 009-40.
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE., SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP. 2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 10, 11, 12, 13 – AS SPECIFIED IN SI 009-40.
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 2 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A007
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-60: SCHEDULE AND ASSOCIATED REPORTS FOR AVAILABILITIES OVER 9 WEEKS IN DURATION (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.2.7
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT. DATA SUBMISSIONS AS LISTED IN SI 009-60 AND AS MODIFIED BY SECTION C REQUIREMENTS.
BLOCK 03, 10, 11, 12, 13 – SEE BELOW.
CDRL DATA SI 009-60 PARAGRAPH*
A007-A
| BLK03 SUBTITLE | PRODUCTION SCHEDULE | 3.2** |
| BLK10 FREQUENCY | BI-WEEKLY AFTER START OF WEEKLY PRODUCTION MEETINGS | |
| BLK11 AS OF DATE | 0 | |
| BLK12 DATE OF 1ST SUBM | 15 DAYS PRIOR TO THE INDUCTION OF THE FIRST CRAFT | |
| BLK13 DATE OF SUBS SUBM | BI-WEEKLY |
A007-B
| BLK03 SUBTITLE | CRITICAL PATH AND CONTROLLING WORK ITEMS 3.2** |
| BLK10 FREQUENCY | BI-WEEKLY AFTER START OF WEEKLY PRODUCTION MEETINGS |
| BLK11 AS OF DATE | NA |
| BLK12 DATE OF 1ST SUBM | AT START OF CRAFT'S E-SLEP AVAILABILITY |
| BLK13 DATE OF SUBS SUBM | BI-WEEKLY |
A007-C
| BLK03 SUBTITLE | MILESTONE AND KEY EVENT LISTING | 3.4 |
| BLK10 FREQUENCY | BI-WEEKLY AFTER START OF WEEKLY PRODUCTION MEETINGS | |
| BLK11 AS OF DATE | NA | |
| BLK12 DATE OF 1ST SUBM | 15 DAYS PRIOR TO A CRAFT'S E-SLEP INDUCTION DATE | |
| BLK13 DATE OF SUBS SUBM | BI-WEEKLY |
A007-D
| BLK03 SUBTITLE | MANPOWER MANAGEMENT INFORMATION 3.5** |
| BLK10 FREQUENCY | BI-WEEKLY AFTER START OF WEEKLY PRODUCTION MEETINGS |
| BLK11 AS OF DATE | NA |
| BLK12 DATE OF 1ST SUBM | AT FIRST WEEKLY PRODUCTION MEETING |
| BLK13 DATE OF SUBS SUBM | BI-WEEKLY |
A007-E
| BLK03 SUBTITLE | MANPOWER UTILIZATION REPORT | 3.5.4** |
| BLK10 FREQUENCY | BI-WEEKLY AFTER START OF WEEKLY PRODUCTION MEETINGS | |
| BLK11 AS OF DATE | NA | |
| BLK12 DATE OF 1ST SUBM | AT FIRST WEEKLY PRODUCTION MEETING | |
| BLK13 DATE OF SUBS SUBM | BI-WEEKLY |
A007-F
| BLK03 SUBTITLE | LIST OF SUBCONTRACTORS BY WORK ITEMS |
| BLK10 FREQUENCY | ONE/R |
| BLK11 AS OF DATE | NA |
| BLK12 DATE OF 1ST SUBM | 15 DAYS PRIOR TO THE INDUCTION OF THE FIRST CRAFT |
| BLK13 DATE OF SUBS SUBM | AS REQUESTED BY SUPERVISOR AND WHEN MAJOR CHANGES |
IN SUBCONTRACTORS OR SUBCONTRACTOR WORK OCCURS
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| PMS377 IDE |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 3 |
| 0 |
| 15. TOTAL |
| 0 |
| 3 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
A. CONTRACT LINE ITEM NO.
CLIN 0200
B. EXHIBIT
A
C. CATEGORY:
TDP _____ TM _____ OTHER __X__
D. SYSTEM/ITEM
LCAC/E-SLEP
E. CONTRACT/PR NO.
F. CONTRACTOR
16. REMARKS (Continued)
A007-G
| BLK03 SUBTITLE | LIST OF PLANNED WORK DAYS AND | |
| HOLIDAYS | ** | |
| BLK10 FREQUENCY | ANNUALLY | |
| BLK11 AS OF DATE | NA | |
| BLK12 DATE OF 1ST SUBM | 45 DAYS AFTER CONTRACT AWARD | |
| BLK13 DATE OF SUBS SUBM | 10TH WORK DAY OF DECEMBER FOR FOLLOWING CALENDAR |
YEAR DATA
A007-H
| BLK03 SUBTITLE | PRODUCTION SCHEDULE CHANGE | |
| DOCUMENT | ** | |
| BLK10 FREQUENCY | BI-WEEKLY AFTER START OF WEEKLY PRODUCTION MEETINGS | |
| BLK11 AS OF DATE | NA | |
| BLK12 DATE OF 1ST SUBM | ONE DAY PRIOR TO FIRST WEEKLY PRODUCTION MEETING | |
| BLK13 DATE OF SUBS SUBM | BI-WEEKLY |
*INCLUDES ASSOCIATED SUBPARAGRAPHS
**ALSO SEE SECTION C, SUPPLEMENTAL PRODUCTION SCHEDULE REQUIREMENTS
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE., SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP. 2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A008
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-63: LUBRICATING OILS AND HYDRAULIC
FLUIDS – ANALYSIS REPORT (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT. DATA SUBMISSIONS AS LISTED IN SI 009-63.
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF
PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE, SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP .2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 10, 11, 12, 13 – AS SPECIFIED IN SI 009-63.
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 2 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A009
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-67: INTEGRATED TOTAL SHIP TESTING (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT. DATA SUBMISSIONS AS LISTED IN SI 009-67.
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF
PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE., SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP .2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 10, 11, 12, 13 – AS SPECIFIED IN SI 009-67.
| CDRL | DATA | SI 009-67 REFERENCE* | |
| A009-A | COMPREHENSIVE TEST PLAN | PARAGRAPH 3.1 | |
| A009-B | INTEGRATED TOTAL SHIP TEST PLAN | PARAGRAPH 3.1 |
*INCLUDES ASSOCIATED SUBPARAGRAPHS
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| PMS377 IDE |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 3 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A010
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-69: HEAVY WEATHER PLAN (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSIONS AS LISTED IN SI 009-69.
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF
PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE, SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP. 2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 10, 11, 12, 13 – AS SPECIFIED IN SI 009-69.
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 2 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A011
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-73: SHIPBOARD ELECTRICAL/ELECTRONIC CABLE PROCEDURE (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT. DATA SUBMISSIONS AS LISTED IN SI 009-73.
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF
PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE, SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP .2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25. DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 10, 11, 12, 13 – AS SPECIFIED IN SI 009-73.
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 2 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A012
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-74: OCCUPATIONAL, SAFETY AND HEALTH
REQUIREMENTS – SAFETY PLAN (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT. DATA SUBMISSIONS AS LISTED IN SI 009-74.
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF
PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE, SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP .2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 10, 11, 12, 13 – AS SPECIFIED IN SI 009-74.
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 2 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A013
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-81: COMPARTMENT CLOSEOUT SCHEDULE - COMPARTMENT CLOSEOUT INSPECTION REPORT (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT. DATA SUBMISSIONS AS LISTED IN SI 009-81.
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF
PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE, SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP .2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 10, 11, 13 – AS SPECIFIED IN SI 009-81.
BLOCK 12 – PRIOR TO 50% AVAILABILITY COMPLETE.
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| PMS377 IDE |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 3 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A014
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-82: DATA REQUIREMENTS WHEN INSTALLING
AN EQUAL COMPONENT VICE SPECIFIED COMPONENT – COMPONENT REPLACEMENT REPORT DATA (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT. DATA SUBMISSIONS AS LISTED IN SI 009-82.
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF
PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE, SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP .2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 10, 12, 13 – AS SPECIFIED IN SI 009-82 PARAGRAPH 3.1 – EACH INSTANCE WHEN THE WORK ITEM ALLOWS, AND THE CONTRACTOR CHOOSES, TO INSTALL "AN EQUAL COMPONENT" VICE A “SPECIFIED COMPONENT” LISTED IN THE WORK ITEM.
| ACU 5 |
| 0 |
| 1 |
| 0 |
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| PMS377 IDE |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 3 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A015
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
SI 009-99: SHIP DEPARTURE REPORT (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.1.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
ONE TIME PER CRAFT
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
(SEE BLOCK 16)
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 03 – DATA SUBMISSION REQUIREMENTS ARE APPLICABLE TO EACH E-SLEP CRAFT. ONE REPORT IN MS EXCEL AND PDF FORMAT FOR EACH E-SLEP CRAFT. DATA FORMAT AND CONTENT AS LISTED BELOW AND IN ATTACHMENT.
A. THE SHIP DEPARTURE REPORT SHALL CONTAIN INFORMATION IN GENERAL ACCORDANCE
WITH ATTACHMENT B OF NAVSEA STANDARD ITEM 009-99, SHIP DEPARTURE REPORT, AS MODIFIED HEREIN AND SHOWN IN THE ATTACHED “SAMPLE SHIP DEPARTURE REPORT.”
B. SHIP DEPARTURE REPORT GENERAL REQUIREMENTS:
(1) EACH WORK ITEM SHALL BE LISTED AS A SEPARATE LINE ITEM.
(2) THE DATA PRESENTED IN THE REPORT SHALL BE BID PRICE AND ACTUAL EXPENSES INCURRED.
(3) THE MULTI-COLUMN HEADING “CLASS “C” ESTIMATES” OF ATTACHMENT B OF NAVSEA
STANDARD ITEM 009-99 SHALL BE REPLACED WITH “BID PRICE.” BID PRICE TOTAL $ SHALL BE THE SUM OF CONTRACTOR AND, IF APPLICABLE, SUBCONTRACTOR DATA UNDER THE COLUMN HEADINGS LABOR $ AND CFM $’S.
(4) THE MULTI-COLUMN HEADING “ACTUAL EXPENSES” OF ATTACHMENT B OF NAVSEA
STANDARD ITEM 009-99 SHALL BE REPLACED WITH “ACTUAL EXPENSES (INCLUDING GROWTH
WORK) INCURRED.” BREAKOUTS OF SUBCONTRACTOR LABOR COSTS AND MATERIAL COSTS
ARE REQUIRED. SEPARATE CONTRACTOR AND SUBCONTRACTOR DATA SHALL BE PROVIDED
UNDER THE APPROPRIATE COLUMN HEADINGS HOURS, M/D, LABOR COST $, CFM COST $, AND TOTAL $. DATA ENTRIES UNDER THE COLUMN HEADING “PRIME + SUB TOTAL $” SHALL BE THE SUM OF THE “TOTAL $” OF THE CONTRACTOR AND THE SUBCONTRACTOR.
(5) ACTUAL EXPENSES (INCLUDING GROWTH WORK) INCURRED FOR EACH WORK ITEM SHALL INCLUDE THAT OF THE ORIGINAL WORK ITEM AND, IF APPLICABLE, SEPARATE ENTRIES FOR EACH GROWTH ITEM APPROVED AS A CONTRACT CHANGE TO THE WORK ITEM. GROWTH ITEMS SHALL BE IDENTIFIED WITH SPECIFIC CONTRACT MODIFICATION NUMBER AND RCC DESIGNATION.
(6) DATA UNDER THE COLUMN HEADING “% TO BID PRICE” SHALL BE THE RATIO OF THE “PRIME + SUB TOTAL $” UNDER ACTUAL EXPENSES (INCLUDING GROWTH WORK) INCURRED DIVIDED BY THE “TOTAL $” OF THE BID PRICE EXPRESSED IN PERCENT.
(7) SUBCONTRACTOR DATA SHALL INDICATE THE TOTAL OF ALL SUBCONTRACTOR DATA UNDER THE APPROPRIATE COLUMN HEADING IF MORE THAN ONE SUBCONTRACTOR SUPPORTS A WORK ITEM, AND IF APPLICABLE, A GROWTH WORK ITEM.
(8) THE SHIP DEPARTURE REPORT SHALL ALSO INCLUDE DATA DEFINED IN SUBPARAGRAPHS B. (1) THROUGH B. (7) ABOVE FOR ANY NEW WORK ITEMS ADDED TO A CRAFT’S SPECIFICATION FOR WORK TO BE ACCOMPLISHED.
C. THE FORMAT OF THE SHIP DEPARTURE REPORT IS SHOWN IN THE ATTACHED “SAMPLE SHIP DEPARTURE REPORT.”
BLOCK 08 – APPROVAL FOR CONTENT. APPROVAL AUTHORITY – PMS377.
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE, SE, WASHINGTON, DC 20376-2101.
| SUPERVISOR (SWRMC) |
| 0 |
| 1 |
| 0 |
| PMS377 IDE |
| 0 |
| 1 |
| 0 |
| 15. TOTAL |
| 0 |
| 2 |
| 0 |
G. PREPARED BY
H. DATE
03 MAR 2020
I. APPROVED BY
FORREST SMITH
J. DATE
A. CONTRACT LINE ITEM NO.
CLIN 0200
B. EXHIBIT
A
C. CATEGORY:
TDP _____ TM _____ OTHER __X__
D. SYSTEM/ITEM
LCAC/E-SLEP
E. CONTRACT/PR NO.
F. CONTRACTOR
16. REMARKS (Continued)
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY
THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT
ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP. 2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLOCK 11 – THE CUTOFF DATE FOR REPORT DATA SHALL BE NO EARLIER THAN NINETY (90) DAYS AFTER THE DATE THE E-SLEP CRAFT IS DELIVERED.
BLOCK 12 – NINETY-FIVE (95) DAYS AFTER THE DATE THE FIRST E-SLEP CRAFT IS DELIVERED.
BLOCK 13 – NINETY-FIVE (95) DAYS AFTER THE DATE EACH SUBSEQUENT E-SLEP CRAFT IS DELIVERED.
ATTACHMENT TO CDRL A015 “SAMPLE SHIP DEPARTURE REPORT”
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
C. CATEGORY:
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A016
2. TITLE OF DATA ITEM
SCIENTIFIC AND TECHNICAL REPORTS
3. SUBTITLE
PRE-INDUCTION SURVEY REPORT (SEE BLOCK 16)
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
C.1.2.1.4
6. REQUIRING OFFICE
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
9. DIST STMT RQD
D (SEE BLOCK 16)
10. FREQUENCY
(SEE BLOCK 16)
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
| a. ADDRESSEE |
| b. COPIES |
8. APP CODE
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT SUBMISSION
(SEE BLOCK 16)
| Draft |
| Final |
| Reg |
| Repro |
16. REMARKS
BLOCK 09 – DISTRIBUTION STATEMENT D: DISTRIBUTION AUTHORIZED TO DEPARTMENT OF
DEFENSE (DOD) AND U.S. DOD CONTRACTORS ONLY; (CRITICAL TECHNOLOGY), (DATE OF
PUBLICATION). OTHER REQUESTS SHALL BE REFERRED TO PEO SHIPS (PMS377), WASHINGTON NAVY YARD, 1333 ISAAC HULL AVE, SE, WASHINGTON, DC 20376-2101.
WARNING: THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC. 2751, ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED, (TITLE 50, U.S.C., APP. 2401 ET. SEQ.). VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTROY THIS DOCUMENT BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .