This is a Quality Assurance Surveillance Plan (QASP) for Special Boat Training Command Logistics and Training Support services. The QASP establishes the Government's systematic method to verify that the contractor performs all services required by the Performance Work Statement in a timely, accurate, and complete manner.

The plan identifies three critical performance standards: Schedule (assessed against original due dates and milestones), Deliverables (assessed against specifications in the contract/task order and Quality Control Plan for content, quality, timeliness, and accuracy), and Past Performance (evaluated per FAR 42.15 regarding conformance to contract requirements, workmanship standards, schedule adherence, cooperative behavior, and customer satisfaction commitment). Surveillance methods include random or planned sampling, periodic inspection, and validated customer complaints. The performance measurement table specifies four key elements: Contractor Quality Control Plan (100% compliance, quarterly inspection), Contract Deliverables (100% inspection of all deliverables with >95% acceptable quality level for timely submission without rework), Overall Contract Performance (annual COR assessment requiring Satisfactory or higher rating), and Invoicing (100% accuracy, monthly review). Performance within acceptable levels is considered satisfactory; failure to meet standards may result in Contract Discrepancy Reports, termination of the contract/task order, loss of future Government contracts, or non-exercise of available options. The contractor must respond in writing within 5 days to any discrepancy report, and the Government may require replacement or correction of deficient work at no additional cost.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY ASSURANCE SURVEILLANCE PLAN

Purpose: To ensure that the Government has an effective and systematic method of surveillance for the services in the PWS. The QASP will be used primarily as a tool to verify that the contractor is performing all services required by the PWS in a timely, accurate and complete fashion.

1. Critical performance processes and requirements. Critical to the performance of the Special Boat Training

Command Logistics and Training Support described in the PWS is the timely, accurate and thorough completion of all contract/task order requirements.

2. Performance Standards

a. Schedule - The due dates for deliverables and the actual accomplishment of the schedule will be assessed against original due dates and milestones established for the contract or task order(s).

b. Deliverables – The deliverables required to be submitted will be assessed against the specifications for the deliverables detailed in the contract/task order(s) and the Quality Control Plan (QCP), if required by the contract, for the required content, quality, timeliness, and accuracy.

c. Past Performance - In addition to any schedule, deliverables, and cost aspects of performance discussed above, pursuant to FAR 42.15, the Government will assess the contractor’s record of conforming to contract requirements and to standards of good workmanship, the contractor’s adherence to contract schedules including the administrative aspects of performance, the contractor’s history of reasonable and cooperative behavior and commitment to customer satisfaction, and the contractor’s business-like concern for the interest of the customer.

3. Surveillance methods: The primary methods of surveillance used to monitor performance of this contract will include, but not be limited to, random or planned sampling, periodic or inspection, and validated customer complaints.

4. Performance Measurement: Performance will be measured in accordance with the following table:

Performance

Element

Performance

Requirement

Surveillance Method Frequency Acceptable

Quality Level

Contractor Quality

Control Plan

QC activities, inspections, and corrective actions completed as required by the plan.

Inspection by the COR Quarterly for overall

QC activities;

100% Compliance with the contractor plan.

As Required for corrective actions.

(If required by the contract)

Contract

Deliverables

Contract deliverables furnished as prescribed in the PWS, attachments, CDRLs, Task Orders, etc., as applicable.

Inspection by the COR 100% inspection of all contract deliverables.

>95% of deliverables submitted timely and without rework required.

Overall Contract Performance

Overall contract performance of sufficient quality to earn a

Satisfactory (or higher) rating in the COR’s annual report on Contractor

Performance

Assessment by the COR Annual All performance elements rated

Satisfactory (or higher)

Invoicing Monthly invoices per contract procedures are timely and accurate.

Review & acceptance of the invoice

Monthly 100% accuracy

If performance is within acceptable levels, it will be considered to be satisfactory. If not, overall performance may be considered unsatisfactory.

Incentives/Disincentives:

The COR’s makes an annual report on Contractor Performance (CPARS or other annual report). The contractor’s failure to achieve satisfactory performance under the contract/task order, reflected in the COR’s annual report, may result in termination of the contract/task order and may also result in the loss of future Government contracts/task orders. The contractor’s failure to achieve satisfactory performance under the contract/task order may result in the non-exercise of available options

For each item that does not meet acceptable levels, the Government may issue a Contract Discrepancy Report

(CDR). CDRs will be forwarded to the Contracting Officer with a copy sent to the contractor. The contractor must reply in writing within 5 days of receipt identifying how future occurrences of the problem will be prevented. Based upon the contractor’s past performance and plan to solve the problem, the Contracting Officer will determine if any further action will be taken.

In accordance with the inspection of services provisions of the contract, the contractor will be incentivized to provide quality products in a timely manner since the Government can require the Contractor, at no additional cost, to replace or correct work that fails to meet contract requirements.