Attachment E - Schedule B Price Proposal Form.pdf

PDF 192 KB Posted

Attached to
P903 Joint Mobility Processing Center at NSA Souda Bay, Greece
Solicitation number
N6247023R0005
Issued by

View the file

Other files

File Type Posted
N6247023R0005 Amend 0004.pdf PDF
N6247023R0005 Amend 0003.pdf PDF
N6247023R0005 Amend 0002.pdf PDF
Attachment K - Pre-proposal Conference Attendee Log.pdf PDF
N6247023R0005 Amend 0001.pdf PDF
Attachment H - dwg20of24.pdf PDF
Attachment F - LRA Commercial Vehicle Inspection Procedures.pdf PDF
Attachment H - dwg10of24.pdf PDF
Attachment H - dwg4of24.pdf PDF
Attachment B - SEC-NAV_5512_1_11787 Form.pdf PDF
Attachment A - Pre-Proposal Inquiry Form.xls XLS spreadsheet
Attachment H - dwg23of24.pdf PDF
Attachment H - dwg6of24.pdf PDF
Attachment H - dwg18of24.pdf PDF
Attachment C - Construction Experience Project Data Sheet.pdf PDF
Attachment I - DWG INDEX.pdf PDF
Attachment G - Specifications 1of3.pdf PDF
Attachment H - dwg1of24.pdf PDF
Attachment H - dwg2of24.pdf PDF
Attachment H - dwg9of24.pdf PDF
Attachment H - dwg16of24.pdf PDF
Attachment H - dwg3of24.pdf PDF
Attachment D - Past Performance Questionnaire (PPQ).pdf PDF
Attachment H - dwg11of24.pdf PDF
Attachment H - dwg15of24.pdf PDF
Attachment H - dwg8of24.pdf PDF
Attachment H - dwg21of24.pdf PDF
Attachment J - Base Access Form.pdf PDF
Attachment H - dwg5of24.pdf PDF
Attachment H - dwg7of24.pdf PDF
Attachment H - dwg17of24.pdf PDF
Attachment H - dwg12of24.pdf PDF
Attachment H - dwg19of24.pdf PDF
Attachment G - Specifications 2of3.pdf PDF
Attachment G - Specifications 3of3.pdf PDF
Attachment H - dwg24of24.pdf PDF
Attachment H - dwg14of24.pdf PDF
Attachment H - dwg13of24.pdf PDF
Attachment H - dwg22of24.pdf PDF
N6247023R0005.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT E

SCHEDULE B

DOCUMENT 00 22 13.00 20

DESIGN BUILD CONTRACT N62470-23-R-0005

JOINT MOBILITY PROCESSING CENTER P-903

NAVAL SUPPORT ACTIVITY SOUDA BAY, CRETE

PART 1 GENERAL

1.1 CONTRACT LINE ITEMS

The terms Offeror and Bidder and versions thereof (offer/bid) have the same definition as used within this contract.

Provide the Contract Line Item (CLIN) lump sum price for the following items:

CLIN 0001 - BASE PRICE.

Price includes the entire work (labor and materials), including all site and facility work, for P903-Joint Mobility Processing Facility in accordance with the drawings and specifications, but excluding work described in Contract Line Item (CLIN) 0002, 0003, 0004, 0005, 0006, 0007, 0008, 0009, 0010 and 0011.

CLIN DESCRIPTION TOTAL PRICE FOR

CLIN 0001

0001 P903 - Joint Mobility Processing Facility, Souda Bay, Crete

CLIN 0002 – Option No. 1

Unit price for all work in connection with the demolition, removal, and final disposal of unforeseen debris larger than 0.375 cubic meters (i.e. abandoned foundations, tanks, utility structures, etc.) encountered within planned excavations (i.e. utilities, foundations). Unit cost will include demolition, removal, transportation and final disposal. The volume of material removed will be determined based on field measurements (length x width x depth) of the completed excavation to remove the unsuitable materials as approved by the Contracting Officer.

CLIN ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE FOR

CLIN 0002 (UNIT

PRICE X NO. UNITS)

0002 Demolition, removal, and final disposal of unforeseen debris.

CM

CLIN 0003 – Option No.2

Unit price for all work in connection with the removal, transportation and final disposal of geotechnically unsuitable subgrade soil and placement of clean imported, compacted, select granular backfill. Unsuitable subgrade soil determinations will be made by the Contracting Officer. The price will include the removal of geotechnically unsuitable soils encountered within planned excavations (i.e. footings, utility trenches) or identified during proofrolling of planned subgrades, final disposal and backfilling the excavation with compacted clean imported select granular backfill. In addition, for P903 only, provide stabilization geotextile at the bottom of excavation prior to placement of select granular backfill. Stabilization geotextile physical requirements and placement procedures will conform to project specification requirements (Section 31 05 19). Clean imported, compacted select granular backfill will conform to project specification requirements for Select Material (Section 31 23 00.00, Paragraph 2.1.8. Soil disturbed by the Contractor's construction activities, or that are excessively wet and soft due to lack of proper site drainage or excavation dewatering will not be considered unsuitable. Unit price will include handling and transportation. The volume of material removed and imported backfill required will be determined based on field measurements (length x width x depth) of the completed excavation to remove the unsuitable soil as approved by the Contracting Officer.

CLIN ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE

FOR CLIN 0003

(UNIT PRICE X

NO. UNITS)

0003 Removal, final disposal and replacement of unsuitable soil.

CM

CLIN 0004 – Option No. 3

Unit price for all work in connection with the removal of hard materials or rock in planned excavations (i.e. foundations, utility trenches, etc.). Hard materials and rock are defined by Specification Section 31 23 00.00 20 Excavation and Fill, Parts 1.2.3 and 1.2.4, which require the use of heavy excavation equipment (i.e. ripper teeth, jack hammers, pneumatic hole punchers, etc.) for removal. Do not remove hard materials or rock beyond the limits of planned excavation without approval of the Contracting Officer. Unit cost will include all equipment and labor required for removal, transportation and final disposal. The volume of material removed and imported, compacted backfill placed will be determined based on field measurements (length x width x depth) of the completed excavation to remove the unsuitable materials as approved by the Contracting Officer.

CLIN ITEM UNIT UNIT PRICE NO. UNITS TOTAL PRICE

FOR CLIN 0004

(UNIT PRICE X

NO. UNITS)

0004 Removal of hard materials or rock.

CM

CLIN 0005 Option No. 4 - Price includes the following:

Price for providing all labor and materials in connection with landscape irrigation, complete in accordance with the drawings and specifications.

CLIN DESCRIPTION TOTAL PRICE

FOR CLIN

0005 Landscape Irrigation

CLIN 0006 Option No. 5 - Price includes the following:

Price for providing all labor and materials in connection with the installation of aluminum-framed sliding glass doors for the gate areas (Gate 1, Gate 2 and Gate 3), complete in accordance with the drawings and specifications.

FOR CLIN 0006

0006 Aluminum-Framed Sliding Glass Doors

CLIN 0007 Option No. 6 - Price includes the following:

Price for providing all work (labor and materials) in connection with the installation of ceramic wall tile in restrooms, complete in accordance with the drawings and specifications.

FOR CLIN 0007

0007 Provide all labor and materials associated with the installation of ceramic wall tile in restrooms.

CLIN 0008 Option No. 7 - Price includes the following:

Price for providing all work (labor and materials) in connection with the installation of wall finishes, other than paint, and corner guards, complete in accordance with the drawings and specifications.

FOR CLIN 0008

0008 Provide all labor and materials associated with the installation of wall finishes, other than paint, and corner guards.

CLIN 0009 Option No. 8 - Price includes the following:

Price for provision, design, installation, testing, and associated training for the Electronic Security System (ESS) equipment necessary for this facility. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Closed Circuit Television (CCTV) complete in accordance with the drawings and specifications. Equipment includes items such as Premise Control Units (PCU), central processing units, field panels, sensors, card readers, keypads, cameras, switches, video recorders, workstations, and the communication cabling connecting these devices together.

Include the price for supporting, permanent infrastructure under CLIN 0001AA - BASE PRICE.

Interior supporting infrastructure includes items such as conduit, junction boxes, electronic door strikes, door hardware, mounting hardware, and power connections. Exterior supporting infrastructure includes items such as exterior ductbanks, manholes, utility poles, utility connections, and power connections.

FOR CLIN 0009

Electronic Security System (ESS) equipment.

CLIN 0010 Option No. 9 - Price includes the following:

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in accordance with the plans and specifications and in accordance with the following schedule:

CLIN ITEM GOVERNMENT

FF&E

ESTIMATE

HAR

NTE

5%)

HAR

AMOUNT

(GOVT

FF&E

ESTIMATE

x HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0010 (GOVT FF&E

ESTIMATE + HAR

AMOUNT)

FF&E

$1,600,082.96

CLIN 0011 Option No. 10 - Price includes the following:

Price to procure and supervise installation of the Conveyor System (Inbound Baggage Conveyor, Outbound Baggage Conveyor, Gravity Roller Conveyor, Ball Transfer Conveyor and Pallet Lifts) complete in accordance with the plans and specifications and in accordance with the following schedule:

FOR CLIN 0011

Conveyor Equipment

1.2 GENERAL BID NOTES

a. Award will be made on the total sum of Contract Line Item(s) CLIN 0001 – CLIN 0011.

b. For CLINs 0002, 0003, and 0004, enter unit prices and extended totals in spaces provided. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price. The Government reserves the unilateral right to award CLIN 0002, 0003, and 0004 to the Contractor at the proposed price within 365 calendar days after the contract award. A firm fixed proposed price is required for all CLINs.

No provision is made for economic price adjustment.

c. The Government reserves the unilateral right to award CLIN 0005, 0006, 0007, 0008, and 0009 to the

Contractor at the proposed price within 365 calendar days after the contract award. A firm fixed proposed price is required for all CLINs. No provision is made for economic price adjustment.

d. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206(b)

Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for the Option(s) to the total price for CLIN 0001. In accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).

e. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices, which are significantly overstated for other work.

e. If CLIN 0005, 0006, 0007, 0008, 0009, 0010 and/or 0011 are exercised, additional bonding and consent of surety is required. Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all Items.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.