Attachment E CAMS 3 Schedule.pdf

PDF 2 MB Posted

Attached to
SPECIAL INSPECTIONS AND TESTING
Solicitation number
S-15600-00007856
Issued by
Marion County, Oregon

About this file

This document is related to a state and local contract opportunity for construction inspection services in Marion County and the City of Salem, Oregon. The scope of work includes full-service construction inspection for the CAMS Phase 3 project, with inspectors required to be highly qualified in their areas of expertise. The contract involves field verification that construction is being performed according to plans, specifications, and applicable codes and standards. The contract term and any renewal options are not specified.

The contract does not provide details on pricing terms, set asides, incumbents, funding requirements, or other financial information. The document focuses on the technical requirements for the construction inspection services to be provided.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Original Duration

Start Finish Total Float

Predecessor Details

Preconstruction / Design / PermitsPreconstruction / Design / PermitsPreconstruction / Design / PermitsPreconstruction / Design / PermitsPreconstruction / Design / PermitsPreconstruction / Design / PermitsPreconstruction / Design / Permits

PRECON10180 Court Street Closure Permit 544 01-Nov-22 A 02-Dec-24 359

PRECON10440 Procure Long Lead / MEP Equipment 184 07-Dec-22 A 22-Aug-23 683

Construction MilestonesConstruction MilestonesConstruction MilestonesConstruction MilestonesConstruction MilestonesConstruction MilestonesConstruction Milestones

MS1130 2024 Legislative Session (Short) 26 29-Jan-24* 04-Mar-24 7

MS1140 2025 Legislative Session (Long) 109 21-Jan-25* 23-Jun-25 217

MS1150 Levels 1-4 Substantial Completion 0 12-Dec-24* -28

MS1160 Building '77 Substantial Completion 0 15-Jan-26 75

MS1170 Full Project Completion 0 30-Apr-26* 0

MS1180 G Level Substantial 0 01-Aug-25* 0

MS1190 Landscape & Civil Work 139 27-Jun-25 15-Jan-26 75

MS1200 Total Duration 974 16-Mar-22 A 15-Jan-26 75

ConstructionConstructionConstructionConstructionConstructionConstructionConstruction

New BuildoutNew BuildoutNew BuildoutNew BuildoutNew BuildoutNew BuildoutNew Buildout

G Level Zone 2G Level Zone 2G Level Zone 2G Level Zone 2G Level Zone 2G Level Zone 2G Level Zone 2

Zone 2 StructuralZone 2 StructuralZone 2 StructuralZone 2 StructuralZone 2 StructuralZone 2 StructuralZone 2 Structural

Exterior Wall Micro Piles at NE 1 & NE AExterior Wall Micro Piles at NE 1 & NE AExterior Wall Micro Piles at NE 1 & NE AExterior Wall Micro Piles at NE 1 & NE AExterior Wall Micro Piles at NE 1 & NE AExterior Wall Micro Piles at NE 1 & NE AExterior Wall Micro Piles at NE 1 & NE A

20800 Z2 SC - Install Shoring Towers Along NE1 20 30-May-23 A 28-Jul-23 0

20801 Z2 SC - Install PT strands in Beams 3 24-Jul-23 26-Jul-23 0

20802 Z2 SC - Cut column Rebar @N7, N5 line 5 24-Jul-23 28-Jul-23 0

20810 Z2 SC - Transfer Load Into Shoring Towers Along NE1 5 31-Jul-23 04-Aug-23 0

20820 Z2 SC - Core / Cut Wall At Needle Beam Locations Along NEA 10 05-Jun-23 A 19-Jul-23 0

20830 Z2 SC - Install Shoring Towers Along NEA 10 12-Jun-23 A 28-Jul-23 0

20831 Install PT strands in Beams 3 24-Jul-23 26-Jul-23 0

20832 Cut column and rebar as necessary 5 24-Jul-23 28-Jul-23 0

20840 Z2 SC - Transfer Load Into Shoring Towers Along NEA 5 31-Jul-23 04-Aug-23 0

InteriorInteriorInteriorInteriorInteriorInteriorInterior

20910 Z2 SC - Build Shoring Towers 20 01-Jun-23 A 28-Jul-23 0

20911 Z2 SC - Install PT strands in Beams 3 24-Jul-23 26-Jul-23 0

20912 Z2 SC - Cut Columns and rebar as necessary 5 24-Jul-23 28-Jul-23 0

20920 Z2 SC - Stress PT Transfer Beams 5 31-Jul-23 04-Aug-23 0

20930 Z2 SC - Transfer Load To Shoring Towers 5 31-Jul-23 04-Aug-23 0

20950 Z2 SC - Demo Columns / Walls / Footings 15 07-Aug-23 25-Aug-23 0

20960 Z2 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation20 21-Aug-23 18-Sep-23 0

20970 Z2 SC - Install cross bracing on Shoring towers 15 28-Aug-23 18-Sep-23 0

20980 Z2 SC - Excavate Utility Trench 5 19-Sep-23 25-Sep-23 0

20990 Z2 SC - Under Slab Drainage 5 19-Sep-23 25-Sep-23 0

21000 Z2 SC - Waterproof / Prepare For Mat Slab 5 26-Sep-23 02-Oct-23 0

21005 Z2 SC - FRP Utility Trench Pour #1 10 03-Oct-23 16-Oct-23 0

21010 Z2 SC - FRP Mat Slab Pour #2 20 10-Oct-23 06-Nov-23 0

21011 Z2 SC - FRP Base Isolator Pedestal North 5 07-Nov-23 13-Nov-23 163

21015 Z2 SC - FRP Mat Slab Pour #3 16 31-Oct-23 21-Nov-23 0

Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D

2023 2024 2025 2026

Court Street Closure Permit

Procure Long Lead / MEP Equipment

2024 Legislative Session (Short)

2025 Legislative Session (Long)

Levels 1-4 Substantial Completion

Building '77 Substantial Completion

Full Project Completion

G Level Substantial

Landscape & Civil Work

Total Duration

Z2 SC - Install Shoring Towers Along NE1

Z2 SC - Install PT strands in Beams

Z2 SC - Cut column Rebar @N7, N5 line

Z2 SC - Transfer Load Into Shoring Towers Along NE1

Z2 SC - Core / Cut Wall At Needle Beam Locations Along NEA

Z2 SC - Install Shoring Towers Along NEA

Install PT strands in Beams

Cut column and rebar as necessary

Z2 SC - Transfer Load Into Shoring Towers Along NEA

Z2 SC - Build Shoring Towers

Z2 SC - Install PT strands in Beams

Z2 SC - Cut Columns and rebar as necessary

Z2 SC - Stress PT Transfer Beams

Z2 SC - Transfer Load To Shoring Towers

Z2 SC - Demo Columns / Walls / Footings

Z2 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation

Z2 SC - Install cross bracing on Shoring towers

Z2 SC - Excavate Utility Trench

Z2 SC - Under Slab Drainage

Z2 SC - Waterproof / Prepare For Mat Slab

Z2 SC - FRP Utility Trench Pour #1

Z2 SC - FRP Mat Slab Pour #2

Z2 SC - FRP Base Isolator Pedestal North

Z2 SC - FRP Mat Slab Pour #3

PROJECT ID : CAMS III - 02 18-Jul-23

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

CAMS III 071423

TASK filter: InCOMPLETE.

Run Date: 18-Jul-23 07:33

Layout: CAMS III

Start Finish Total Float

Predecessor Details

21016 Z2 SC - FRP Base Isolator Pedestal South 5 22-Nov-23 30-Nov-23 154

21017 Z2 SC - Install Isolators 10 22-Nov-23 07-Dec-23 154

21020 FRP Concourse # 1 10 29-Nov-23 12-Dec-23 154

21025 FRP Concourse # 2 10 08-Dec-23 21-Dec-23 154

21040 FRP Concourse # 3 10 19-Dec-23 03-Jan-24 154

21050 Z2 FRP Interior walls/Columns 20 27-Dec-23 24-Jan-24 154

21060 Z2 SC - Wall and Column Cure 10 25-Jan-24 07-Feb-24 154

21120 Z2 SC - Pressure Inject / Dry Pack At Transfer / Column Connections 9 08-Feb-24 20-Feb-24 154

21130 Z2 SC - Coordinate Removal Of Remaining Shoring 2 15-Feb-24 16-Feb-24 154

21140 Z2 SC - Remove Remaining Shoring 10 19-Feb-24 01-Mar-24 154

Zone 2 Architectural / MEPZone 2 Architectural / MEPZone 2 Architectural / MEPZone 2 Architectural / MEPZone 2 Architectural / MEPZone 2 Architectural / MEPZone 2 Architectural / MEP

21150 Z2 AC - Layout Walls / Top Track 10 04-Mar-24 15-Mar-24 154

21160 Z2 AC - MEP Submittal, Investigation, Planning Out Of East Vault 223 04-Jan-23 A 27-Nov-23 203

21170 Z2 AC - Begin Home Run Pulls From Vault 23 28-Nov-23 29-Dec-23 203

21180 Z2 AC - Electrical OH Rough In 9 11-Mar-24 21-Mar-24 154

21190 Z2 AC - Fire Sprinkler OH Rough In 10 18-Mar-24 29-Mar-24 154

21200 Z2 AC - HVAC / Plumb OH Rough In 10 25-Mar-24 05-Apr-24 154

21210 Z2 AC - Door Frame Install 5 01-Apr-24 05-Apr-24 154

21220 Z2 AC - Wall Framing & Soffit Framing 15 08-Apr-24 26-Apr-24 154

21230 Z2 AC - HVAC Wall Rough In 10 15-Apr-24 26-Apr-24 154

21240 Z2 AC - HVAC Insulation 10 29-Apr-24 10-May-24 154

21250 Z2 AC - Fire Sprinkler Rough In 10 06-May-24 17-May-24 154

21260 Z2 AC - Plumbing Rough In 10 28-May-24 10-Jun-24 154

21270 Z2 AC - Plumbing Insulation 10 04-Jun-24 17-Jun-24 154

21280 Z2 AC - Electrical Rough In 10 11-Jun-24 24-Jun-24 154

21290 Z2 AC - Low Voltage & DDC Rough In 10 18-Jun-24 01-Jul-24 154

21300 Z2 AC - Cover Inspections 2 25-Jun-24 26-Jun-24 154

21310 Z2 AC - Plaster Work In Corridors Of Historic Preservation 15 27-Jun-24 18-Jul-24 154

21320 Z2 AC - Sheetrock 10 05-Jul-24 18-Jul-24 154

21330 Z2 AC - Tape & Finish 10 12-Jul-24 25-Jul-24 154

21340 Z2 AC - Terrazzo Flooring 15 19-Jul-24 08-Aug-24 154

21350 Z2 AC - Bathroom Tile Work 10 26-Jul-24 08-Aug-24 154

21360 Z2 AC - Paint, First Two Coats 10 02-Aug-24 15-Aug-24 154

21370 Z2 AC - ACT Grid 10 09-Aug-24 22-Aug-24 154

21380 Z2 AC - Light Fixtures 10 16-Aug-24 29-Aug-24 154

21390 Z2 AC - Casework 10 30-Aug-24 13-Sep-24 154

21400 Z2 AC - Electrical Trim 10 09-Sep-24 20-Sep-24 154

21410 Z2 AC - Plumbing Trim 10 16-Sep-24 27-Sep-24 154

21420 Z2 AC - HVAC Trim 10 30-Sep-24 11-Oct-24 154

21430 Z2 AC - Hang Doors 5 14-Oct-24 18-Oct-24 154

21440 Z2 AC - Fire Sprinkler Trim 5 21-Oct-24 25-Oct-24 154

21450 Z2 AC - Drop Ceiling Tile 5 28-Oct-24 01-Nov-24 154

21460 Z2 AC - All Bathroom Fixtures, PTH, TPH, Mirrors 5 04-Nov-24 08-Nov-24 154

Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D

2023 2024 2025 2026

Z2 SC - FRP Base Isolator Pedestal South

Z2 SC - Install Isolators

FRP Concourse # 1

FRP Concourse # 2

FRP Concourse # 3

Z2 FRP Interior walls/Columns

Z2 SC - Wall and Column Cure

Z2 SC - Pressure Inject / Dry Pack At Transfer / Column Connections

Z2 SC - Coordinate Removal Of Remaining Shoring

Z2 SC - Remove Remaining Shoring

Z2 AC - Layout Walls / Top Track

Z2 AC - MEP Submittal, Investigation, Planning Out Of East Vault

Z2 AC - Begin Home Run Pulls From Vault

Z2 AC - Electrical OH Rough In

Z2 AC - Fire Sprinkler OH Rough In

Z2 AC - HVAC / Plumb OH Rough In

Z2 AC - Door Frame Install

Z2 AC - Wall Framing & Soffit Framing

Z2 AC - HVAC Wall Rough In

Z2 AC - HVAC Insulation

Z2 AC - Fire Sprinkler Rough In

Z2 AC - Plumbing Rough In

Z2 AC - Plumbing Insulation

Z2 AC - Electrical Rough In

Z2 AC - Low Voltage & DDC Rough In

Z2 AC - Cover Inspections

Z2 AC - Plaster Work In Corridors Of Historic Preservation

Z2 AC - Sheetrock

Z2 AC - Tape & Finish

Z2 AC - Terrazzo Flooring

Z2 AC - Bathroom Tile Work

Z2 AC - Paint, First Two Coats

Z2 AC - ACT Grid

Z2 AC - Light Fixtures

Z2 AC - Casework

Z2 AC - Electrical Trim

Z2 AC - Plumbing Trim

Z2 AC - HVAC Trim

Z2 AC - Hang Doors

Z2 AC - Fire Sprinkler Trim

Z2 AC - Drop Ceiling Tile

Z2 AC - All Bathroom Fixtures, PTH, TPH, Mirrors

PROJECT ID : CAMS III - 02 18-Jul-23

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

CAMS III 071423

TASK filter: InCOMPLETE.

Start Finish Total Float

Predecessor Details

21470 Z2 AC - Carpet 10 11-Nov-24 22-Nov-24 154

21480 Z2 AC - Base 5 18-Nov-24 22-Nov-24 154

21490 Z2 AC - TAB / Commissioning 10 25-Nov-24 10-Dec-24 154

21500 Z2 AC - Punch / Substantial Completion 10 11-Dec-24 24-Dec-24 154

21510 Z2 AC - Grind and Polish Terrazzo 5 23-Aug-24 29-Aug-24 159

Zone 2 Elevator (007)Zone 2 Elevator (007)Zone 2 Elevator (007)Zone 2 Elevator (007)Zone 2 Elevator (007)Zone 2 Elevator (007)Zone 2 Elevator (007)

21525 Z2 Elev - Infill Level 1 Ledger & Decking 5 22-Nov-23 30-Nov-23 106

21530 Z2 Elev - FRP Level 1 Deck 10 01-Dec-23 14-Dec-23 106

21540 Z2 Elev - MEP Rough In For New Walls / Elevator Pit 10 15-Dec-23 29-Dec-23 106

21550 Z2 Elev - Elevator Shaft Buildout / Exterior Walls 14 02-Jan-24 19-Jan-24 106

21560 Z2 Elev - Install Rails Or Modify As Necessary 10 22-Jan-24 02-Feb-24 106

21570 Z2 Elev - Finish Exterior Shaft Walls & Install Elect 15 05-Feb-24 23-Feb-24 106

21580 Z2 Elev - Adjust Cars & Test 15 29-Jul-24 16-Aug-24 -2

21582 Z2 Elev - Refurbish Interiors 15 19-Aug-24 09-Sep-24 213

21590 Z2 Elev - Commission Elevator / State Inspections - Workman's 2 19-Aug-24 20-Aug-24 40

21600 Z2 Elev - Receive Elevator Workman's Permit 1 21-Aug-24 21-Aug-24 40

G Level Zone East Hearing Rooom Z2.1G Level Zone East Hearing Rooom Z2.1G Level Zone East Hearing Rooom Z2.1G Level Zone East Hearing Rooom Z2.1G Level Zone East Hearing Rooom Z2.1G Level Zone East Hearing Rooom Z2.1G Level Zone East Hearing Rooom Z2.1

Zone 2.1 StructuralZone 2.1 StructuralZone 2.1 StructuralZone 2.1 StructuralZone 2.1 StructuralZone 2.1 StructuralZone 2.1 Structural

22260 Z2.1 SC - Install Shotcrete, Soil Nail Wall At '77 Building 24 26-Jun-23 A 20-Jul-23 32

22270 Z2.1 SC - Excavate With Soil Nail Wall 20 14-Jul-23 10-Aug-23 32

22280 Z2.1 SC - Demobe All Equipment Out Of Zone 5 11-Aug-23 17-Aug-23 32

22290 Z2.1 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation20 28-Aug-23 25-Sep-23 26

22300 Z2.1 SC - Build / Strengthen Shoring Towers With Excavation 15 05-Sep-23 25-Sep-23 26

22310 Z2.1 SC - Install Under Slab Drainage 10 26-Sep-23 09-Oct-23 26

22320 Z2.1 SC - Waterproof / Prepare For Mat Slab 5 10-Oct-23 16-Oct-23 26

22325 FRP Mat Slab Pour #4 15 22-Nov-23 14-Dec-23 0

22330 FRP Base Isolator Pedestals 5 15-Dec-23 21-Dec-23 0

22332 Install Base Isolators 5 22-Dec-23 29-Dec-23 0

22335 FRP Concourse Pour #4 10 02-Jan-24 15-Jan-24 0

22340 FRP Concourse Pour #5 10 11-Jan-24 24-Jan-24 0

22342 Z2.1 SC - Concourse MEP Homerun 20 25-Jan-24 21-Feb-24 50

22345 FRP Interior Walls/Columns 15 25-Jan-24 14-Feb-24 0

22350 Column and Beam cure 20 15-Feb-24 13-Mar-24 25

22355 Stress PT 5 14-Mar-24 20-Mar-24 25

22360 Pressure inject/Dry Pack Base isolator/column 5 14-Mar-24 20-Mar-24 25

22365 Coordinate Removal of Shoring 2 21-Mar-24 22-Mar-24 25

22380 Z2.1 SC - Remove Shoring As Approved By Engineers 3 25-Mar-24 27-Mar-24 25

22420 Z2.1 SC - Install Structural Roof Steel 15 15-Feb-24 06-Mar-24 0

22430 Z2.1 SC - Install Metal Deck 7 07-Mar-24 15-Mar-24 0

22440 Z2.1 SC - MEP Install Hangers, Blockouts 5 18-Mar-24 22-Mar-24 0

22450 Z2.1 SC - FRP SOMD 10 25-Mar-24 05-Apr-24 0

2.1 First Floor Interior Hearing Room2.1 First Floor Interior Hearing Room2.1 First Floor Interior Hearing Room2.1 First Floor Interior Hearing Room2.1 First Floor Interior Hearing Room2.1 First Floor Interior Hearing Room2.1 First Floor Interior Hearing Room

Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D

2023 2024 2025 2026

Z2 AC - Carpet

Z2 AC - Base

Z2 AC - TAB / Commissioning

Z2 AC - Punch / Substantial Completion

Z2 AC - Grind and Polish Terrazzo

Z2 Elev - Infill Level 1 Ledger & Decking

Z2 Elev - FRP Level 1 Deck

Z2 Elev - MEP Rough In For New Walls / Elevator Pit

Z2 Elev - Elevator Shaft Buildout / Exterior Walls

Z2 Elev - Install Rails Or Modify As Necessary

Z2 Elev - Finish Exterior Shaft Walls & Install Elect

Z2 Elev - Adjust Cars & Test

Z2 Elev - Refurbish Interiors

Z2 Elev - Commission Elevator / State Inspections - Workman's

Z2 Elev - Receive Elevator Workman's Permit

Z2.1 SC - Install Shotcrete, Soil Nail Wall At '77 Building

Z2.1 SC - Excavate With Soil Nail Wall

Z2.1 SC - Demobe All Equipment Out Of Zone

Z2.1 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation

Z2.1 SC - Build / Strengthen Shoring Towers With Excavation

Z2.1 SC - Install Under Slab Drainage

Z2.1 SC - Waterproof / Prepare For Mat Slab

FRP Mat Slab Pour #4

FRP Base Isolator Pedestals

Install Base Isolators

FRP Concourse Pour #4

FRP Concourse Pour #5

Z2.1 SC - Concourse MEP Homerun

FRP Interior Walls/Columns

Column and Beam cure

Stress PT

Pressure inject/Dry Pack Base isolator/column

Coordinate Removal of Shoring

Z2.1 SC - Remove Shoring As Approved By Engineers

Z2.1 SC - Install Structural Roof Steel

Z2.1 SC - Install Metal Deck

Z2.1 SC - MEP Install Hangers, Blockouts

Z2.1 SC - FRP SOMD

PROJECT ID : CAMS III - 02 18-Jul-23

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

CAMS III 071423

TASK filter: InCOMPLETE.

Start Finish Total Float

Predecessor Details

22460 Z2.1 AC - Layout Walls / Top Track 10 02-May-24 15-May-24 0

22470 Z2.1 AC - Electrical OH Rough In 10 16-May-24 30-May-24 0

22480 Z2.1 AC - Fire Sprinkler OH Rough In 10 31-May-24 13-Jun-24 0

22490 Z2.1 AC - HVAC / Plumb OH Rough In 15 14-Jun-24 05-Jul-24 0

22500 Z2.1 AC - Door Frame Install 5 08-Jul-24 12-Jul-24 0

22510 Z2.1 AC - Wall Framing & Soffit Framing 15 15-Jul-24 02-Aug-24 0

22520 Z2.1 AC - HVAC Wall Rough In 10 05-Aug-24 16-Aug-24 0

22530 Z2.1 AC - HVAC Insulation 10 19-Aug-24 30-Aug-24 0

22540 Z2.1 AC - Fire Sprinkler Rough In 10 03-Sep-24 16-Sep-24 0

22550 Z2.1 AC - Plumbing Rough In 10 17-Sep-24 30-Sep-24 0

22560 Z2.1 AC - Plumbing Insulation 9 01-Oct-24 11-Oct-24 0

22570 Z2.1 AC - Electrical Rough In 10 14-Oct-24 25-Oct-24 0

22580 Z2.1 AC - Low Voltage & DDC Rough In 10 28-Oct-24 08-Nov-24 0

22590 Z2.1 AC - Cover Inspections 2 11-Nov-24 12-Nov-24 0

22600 Z2.1 AC - Plaster Work In Corridors Of Historic Preservation 15 13-Nov-24 05-Dec-24 0

22610 Z2.1 AC - Sheetrock 9 06-Dec-24 18-Dec-24 0

22620 Z2.1 AC - Tape & Finish 10 19-Dec-24 03-Jan-25 0

22630 Z2.1 AC - Terrazzo Flooring 15 06-Jan-25 24-Jan-25 0

22640 Z2.1 AC - Bathroom Tile Work 10 27-Jan-25 07-Feb-25 0

22650 Z2.1 AC - Paint, First Two Coats 10 10-Feb-25 21-Feb-25 0

22660 Z2.1 AC - ACT Grid 10 24-Feb-25 07-Mar-25 0

22670 Z2.1 AC - Light Fixtures 8 10-Mar-25 19-Mar-25 0

22680 Z2.1 AC - Casework 10 20-Mar-25 02-Apr-25 0

22690 Z2.1 AC - Electrical Trim 10 03-Apr-25 16-Apr-25 0

22700 Z2.1 AC - Plumbing Trim 10 17-Apr-25 30-Apr-25 0

22710 Z2.1 AC - HVAC Trim 10 01-May-25 14-May-25 0

22720 Z2.1 AC - Hang Doors 5 15-May-25 21-May-25 0

22730 Z2.1 AC - Fire Sprinkler Trim 5 22-May-25 29-May-25 0

22740 Z2.1 AC - Drop Ceiling Tile 5 30-May-25 05-Jun-25 0

22750 Z2.1 AC - All Bathroom Fixtures, PTH, TPH, Mirrors 5 06-Jun-25 12-Jun-25 0

22760 Z2.1 AC - Carpet 10 13-Jun-25 26-Jun-25 0

22770 Z2.1 AC - Base 5 27-Jun-25 03-Jul-25 0

22780 Z2.1 AC - TAB / Commissioning 10 07-Jul-25 18-Jul-25 0

22790 Z2.1 AC - Punch / Substantial Completion 10 21-Jul-25 01-Aug-25 0

Zone 2.1 Roof / CourtyardZone 2.1 Roof / CourtyardZone 2.1 Roof / CourtyardZone 2.1 Roof / CourtyardZone 2.1 Roof / CourtyardZone 2.1 Roof / CourtyardZone 2.1 Roof / Courtyard

22800 Z2.1 RC - Remove Windows & Install Doors For Access 15 28-Mar-24 17-Apr-24 0

22810 Z2.1 RC - Waterproof SOMD 10 18-Apr-24 01-May-24 0

22820 Z2.1 RC - Install Roof Insulation 10 02-May-24 15-May-24 203

22830 Z2.1 RC - Install Seismic Joints 20 16-May-24 13-Jun-24 203

22840 Z2.1 RC - Install Drains 10 14-Jun-24 27-Jun-24 203

22850 Z2.1 RC - Install Electrical 10 28-Jun-24 12-Jul-24 203

22860 Z2.1 RC - Install Irrigation 10 15-Jul-24 26-Jul-24 203

22870 Z2.1 RC - Install Organic Material 10 29-Jul-24 09-Aug-24 203

Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D

2023 2024 2025 2026

Z2.1 AC - Layout Walls / Top Track

Z2.1 AC - Electrical OH Rough In

Z2.1 AC - Fire Sprinkler OH Rough In

Z2.1 AC - HVAC / Plumb OH Rough In

Z2.1 AC - Door Frame Install

Z2.1 AC - Wall Framing & Soffit Framing

Z2.1 AC - HVAC Wall Rough In

Z2.1 AC - HVAC Insulation

Z2.1 AC - Fire Sprinkler Rough In

Z2.1 AC - Plumbing Rough In

Z2.1 AC - Plumbing Insulation

Z2.1 AC - Electrical Rough In

Z2.1 AC - Low Voltage & DDC Rough In

Z2.1 AC - Cover Inspections

Z2.1 AC - Plaster Work In Corridors Of Historic Preservation

Z2.1 AC - Sheetrock

Z2.1 AC - Tape & Finish

Z2.1 AC - Terrazzo Flooring

Z2.1 AC - Bathroom Tile Work

Z2.1 AC - Paint, First Two Coats

Z2.1 AC - ACT Grid

Z2.1 AC - Light Fixtures

Z2.1 AC - Casework

Z2.1 AC - Electrical Trim

Z2.1 AC - Plumbing Trim

Z2.1 AC - HVAC Trim

Z2.1 AC - Hang Doors

Z2.1 AC - Fire Sprinkler Trim

Z2.1 AC - Drop Ceiling Tile

Z2.1 AC - All Bathroom Fixtures, PTH, TPH, Mirrors

Z2.1 AC - Carpet

Z2.1 AC - Base

Z2.1 AC - TAB / Commissioning

Z2.1 AC - Punch / Substantial Completion

Z2.1 RC - Remove Windows & Install Doors For Access

Z2.1 RC - Waterproof SOMD

Z2.1 RC - Install Roof Insulation

Z2.1 RC - Install Seismic Joints

Z2.1 RC - Install Drains

Z2.1 RC - Install Electrical

Z2.1 RC - Install Irrigation

Z2.1 RC - Install Organic Material

PROJECT ID : CAMS III - 02 18-Jul-23

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

CAMS III 071423

TASK filter: InCOMPLETE.

Start Finish Total Float

Predecessor Details

22880 Z2.1 RC - Install Finish Products - Lights / Benches 10 12-Aug-24 23-Aug-24 203

22890 Z2.1 RC - Landscape 10 26-Aug-24 09-Sep-24 203

22900 Z2.1 RC - Finish Windows / Doors 10 10-Sep-24 23-Sep-24 203

22910 Z2.1 RC - Punchlist / Substantial Completion 10 24-Sep-24 07-Oct-24 203

22920 Z2.1 RC - Turnover 5 08-Oct-24 14-Oct-24 203

G Level Zone 1G Level Zone 1G Level Zone 1G Level Zone 1G Level Zone 1G Level Zone 1G Level Zone 1

Zone 1 Structural - Concourse LevelZone 1 Structural - Concourse LevelZone 1 Structural - Concourse LevelZone 1 Structural - Concourse LevelZone 1 Structural - Concourse LevelZone 1 Structural - Concourse LevelZone 1 Structural - Concourse Level

10270 Z1 SC - Build shoring towers 20 02-Aug-23 29-Aug-23 64

10310 Z1 SC - Transfer Load to shoring towers 5 30-Aug-23 06-Sep-23 94

10314 Z1 SC - Excavate To The Bottom Of (E) Footings 10 07-Sep-23 20-Sep-23 94

10315 Z1 SC - Demo Concrete Walls & Columns 15 21-Sep-23 11-Oct-23 94

10320 Z1 SC - Excavate To Bottom Of New Mat Slab with shoring wall 15 12-Oct-23 01-Nov-23 94

10325 Z1 SC - Install Shoring Wall South Of Sh Line 15 19-Oct-23 08-Nov-23 99

10360 Z1 SC - Add Bracing To Micro Piles While Excavating Down 15 19-Oct-23 08-Nov-23 99

10370 Z1 SC - Under Slab Drainage 10 09-Nov-23 22-Nov-23 99

10380 Z1 SC - Waterproof / Prepare For Mat Slab 5 27-Nov-23 01-Dec-23 99

10400 Z1 SC - FRP Mat Slab #8 15 04-Dec-23 22-Dec-23 99

10405 FRP Base Isolator Pedestals East 5 26-Dec-23 02-Jan-24 107

10406 Install base isolators East 5 03-Jan-24 09-Jan-24 107

10410 FRP Mat Slab #12 15 26-Dec-23 16-Jan-24 99

10415 FRP Base Isolator Pedestals West 5 17-Jan-24 23-Jan-24 99

10416 Install Base Isolators West 5 24-Jan-24 30-Jan-24 99

10420 FRP Concoures #7 10 10-Jan-24 23-Jan-24 107

10425 FRP Concoures #10 10 31-Jan-24 13-Feb-24 99

10427 Z1 SC - MEP Concourse Prep 20 24-Jan-24 20-Feb-24 157

10430 FRP Walls and Columns 25 14-Feb-24 19-Mar-24 99

10435 Wall and Column Cure 15 20-Mar-24 09-Apr-24 99

10440 Z1 SC - Pressure Inject / Dry Pack At Transfer / Column Connections 5 10-Apr-24 16-Apr-24 99

10445 Coordinate removal of Shoring 2 15-Apr-24 16-Apr-24 99

10450 Z1 SC - Remove Shoring towers 13 17-Apr-24 03-May-24 99

Zone 1 Architectural / MEP - Concourse LevelZone 1 Architectural / MEP - Concourse LevelZone 1 Architectural / MEP - Concourse LevelZone 1 Architectural / MEP - Concourse LevelZone 1 Architectural / MEP - Concourse LevelZone 1 Architectural / MEP - Concourse LevelZone 1 Architectural / MEP - Concourse Level

10520 Z1 AC - Layout Walls / Top Track 10 06-May-24 17-May-24 99

10530 Z1 AC - Electrical OH Rough In 15 13-May-24 03-Jun-24 99

10540 Z1 AC - Fire Sprinkler OH Rough In 15 20-May-24 10-Jun-24 99

10550 Z1 AC - HVAC / Plumb OH Rough In 15 28-May-24 17-Jun-24 99

10560 Z1 AC - Door Frame Install 5 04-Jun-24 10-Jun-24 99

10570 Z1 AC - Wall Framing & Soffit Framing 15 11-Jun-24 01-Jul-24 99

10580 Z1 AC - HVAC Wall Rough In 5 18-Jun-24 24-Jun-24 99

10590 Z1 AC - HVAC Insulation 10 25-Jun-24 09-Jul-24 99

10600 Z1 AC - Fire Sprinkler Rough In 10 02-Jul-24 16-Jul-24 99

10610 Z1 AC - Plumbing Rough In 10 24-Jul-24 06-Aug-24 99

10620 Z1 AC - Plumbing Insulation 10 31-Jul-24 13-Aug-24 99

Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D

2023 2024 2025 2026

Z2.1 RC - Install Finish Products - Lights / Benches

Z2.1 RC - Landscape

Z2.1 RC - Finish Windows / Doors

Z2.1 RC - Punchlist / Substantial Completion

Z2.1 RC - Turnover

Z1 SC - Build shoring towers

Z1 SC - Transfer Load to shoring towers

Z1 SC - Excavate To The Bottom Of (E) Footings

Z1 SC - Demo Concrete Walls & Columns

Z1 SC - Excavate To Bottom Of New Mat Slab with shoring wall

Z1 SC - Install Shoring Wall South Of Sh Line

Z1 SC - Add Bracing To Micro Piles While Excavating Down

Z1 SC - Under Slab Drainage

Z1 SC - Waterproof / Prepare For Mat Slab

Z1 SC - FRP Mat Slab #8

FRP Base Isolator Pedestals East

Install base isolators East

FRP Mat Slab #12

FRP Base Isolator Pedestals West

Install Base Isolators West

FRP Concoures #7

FRP Concoures #10

Z1 SC - MEP Concourse Prep

FRP Walls and Columns

Wall and Column Cure

Z1 SC - Pressure Inject / Dry Pack At Transfer / Column Connections

Coordinate removal of Shoring

Z1 SC - Remove Shoring towers

Z1 AC - Layout Walls / Top Track

Z1 AC - Electrical OH Rough In

Z1 AC - Fire Sprinkler OH Rough In

Z1 AC - HVAC / Plumb OH Rough In

Z1 AC - Door Frame Install

Z1 AC - Wall Framing & Soffit Framing

Z1 AC - HVAC Wall Rough In

Z1 AC - HVAC Insulation

Z1 AC - Fire Sprinkler Rough In

Z1 AC - Plumbing Rough In

Z1 AC - Plumbing Insulation

PROJECT ID : CAMS III - 02 18-Jul-23

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

CAMS III 071423

TASK filter: InCOMPLETE.

Start Finish Total Float

Predecessor Details

10630 Z1 AC - Electrical Rough In 10 07-Aug-24 20-Aug-24 99

10640 Z1 AC - Low Voltage & DDC Rough In 10 14-Aug-24 27-Aug-24 99

10650 Z1 AC - Cover Inspections 2 21-Aug-24 22-Aug-24 99

10660 Z1 AC - Plaster Work In Corridors Of Historic Preservation 15 23-Aug-24 13-Sep-24 99

10670 Z1 AC - Sheetrock 10 30-Aug-24 13-Sep-24 99

10680 Z1 AC - Tape & Finish 10 09-Sep-24 20-Sep-24 99

10690 Z1 AC - Terrazzo Flooring 20 16-Sep-24 11-Oct-24 99

10700 Z1 AC - Kitchen Build Out 10 23-Sep-24 04-Oct-24 99

10710 Z1 AC - Kitchen Appliances 10 30-Sep-24 11-Oct-24 99

10720 Z1 AC - Bathroom Tile Work 10 07-Oct-24 18-Oct-24 99

10730 Z1 AC - Paint, First Two Coats 10 14-Oct-24 25-Oct-24 99

10740 Z1 AC - ACT Grid 10 21-Oct-24 01-Nov-24 99

10750 Z1 AC - Light Fixtures 10 28-Oct-24 08-Nov-24 99

10760 Z1 AC - Casework 10 11-Nov-24 22-Nov-24 99

10770 Z1 AC - Electrical Trim 10 18-Nov-24 03-Dec-24 99

10780 Z1 AC - Plumbing Trim 5 25-Nov-24 03-Dec-24 99

10790 Z1 AC - HVAC Trim 5 04-Dec-24 10-Dec-24 99

10800 Z1 AC - Hang Doors 5 11-Dec-24 17-Dec-24 99

10810 Z1 AC - Fire Sprinkler Trim 5 18-Dec-24 24-Dec-24 99

10820 Z1 AC - Drop Ceiling Tile 10 26-Dec-24 09-Jan-25 99

10830 Z1 AC - All Bathroom Fixtures, PTH, TPH, Mirrors 5 03-Jan-25 09-Jan-25 99

10840 Z1 AC - Carpet 10 10-Jan-25 23-Jan-25 99

10850 Z1 AC - Base 10 17-Jan-25 30-Jan-25 99

10860 Z1 AC - TAB / Commissioning 20 24-Jan-25 20-Feb-25 99

10870 Z1 AC - Punch / Substantial Completion 15 21-Feb-25 13-Mar-25 99

10880 Z1 AC - Grind & Polish Terrazzo 5 04-Nov-24 08-Nov-24 99

G Level Zone 3G Level Zone 3G Level Zone 3G Level Zone 3G Level Zone 3G Level Zone 3G Level Zone 3

Zone 3 StructuralZone 3 StructuralZone 3 StructuralZone 3 StructuralZone 3 StructuralZone 3 StructuralZone 3 Structural

Exterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro Piles

30430 Z3 SC - Core / Cut Wall At Needle Beam Locations Along NEA 15 05-Jul-23 A 31-Jul-23 55

30435 Z3 SC - Install soil nails in lagging wall 5 25-Jul-23 31-Jul-23 55

30440 Z3 SC - Install Shoring Towers 15 01-Aug-23 21-Aug-23 100

30450 Z3 SC - Transfer Load Into Shoring Towers Along NE1 5 22-Aug-23 28-Aug-23 100

30460 Z3 SC - Excavate Down To Bottom Of Footings 10 29-Aug-23 12-Sep-23 100

30470 Z3 SC - Abatement Of Exterior Wall 5 13-Sep-23 19-Sep-23 100

30480 Z3 SC - Demo Exterior Wall 10 20-Sep-23 03-Oct-23 100

InteriorInteriorInteriorInteriorInteriorInteriorInterior

30530 Z3 SC - Drill Micro Piles 30 05-Jul-23 A 17-Aug-23 -20

30540 Z3 SC - Build Shoring Towers 20 26-Jul-23 22-Aug-23 64

30550 Z3 SC - Stress Transfer Beams 5 16-Aug-23 22-Aug-23 114

30560 Z3 SC - Transfer Load To Shoring Towers 5 23-Aug-23 29-Aug-23 114

30570 Z3 SC - Excavate To Bottom Of Footings 10 30-Aug-23 13-Sep-23 114

30580 Z3 SC - Demo Columns / Walls / Footings 15 04-Oct-23 24-Oct-23 100

Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D

2023 2024 2025 2026

Z1 AC - Electrical Rough In

Z1 AC - Low Voltage & DDC Rough In

Z1 AC - Cover Inspections

Z1 AC - Plaster Work In Corridors Of Historic Preservation

Z1 AC - Sheetrock

Z1 AC - Tape & Finish

Z1 AC - Terrazzo Flooring

Z1 AC - Kitchen Build Out

Z1 AC - Kitchen Appliances

Z1 AC - Bathroom Tile Work

Z1 AC - Paint, First Two Coats

Z1 AC - ACT Grid

Z1 AC - Light Fixtures

Z1 AC - Casework

Z1 AC - Electrical Trim

Z1 AC - Plumbing Trim

Z1 AC - HVAC Trim

Z1 AC - Hang Doors

Z1 AC - Fire Sprinkler Trim

Z1 AC - Drop Ceiling Tile

Z1 AC - All Bathroom Fixtures, PTH, TPH, Mirrors

Z1 AC - Carpet

Z1 AC - Base

Z1 AC - TAB / Commissioning

Z1 AC - Punch / Substantial Completion

Z1 AC - Grind & Polish Terrazzo

Z3 SC - Core / Cut Wall At Needle Beam Locations Along NEA

Z3 SC - Install soil nails in lagging wall

Z3 SC - Install Shoring Towers

Z3 SC - Transfer Load Into Shoring Towers Along NE1

Z3 SC - Excavate Down To Bottom Of Footings

Z3 SC - Abatement Of Exterior Wall

Z3 SC - Demo Exterior Wall

Z3 SC - Drill Micro Piles

Z3 SC - Build Shoring Towers

Z3 SC - Stress Transfer Beams

Z3 SC - Transfer Load To Shoring Towers

Z3 SC - Excavate To Bottom Of Footings

Z3 SC - Demo Columns / Walls / Footings

PROJECT ID : CAMS III - 02 18-Jul-23

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

CAMS III 071423

TASK filter: InCOMPLETE.

Start Finish Total Float

Predecessor Details

30590 Z3 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation20 25-Oct-23 21-Nov-23 100

30600 Z3 SC - Build / Strengthen Shoring Towers With Excavation 15 08-Nov-23 30-Nov-23 146

30610 Z3 SC - Excavate Utility Trench 5 22-Nov-23 30-Nov-23 100

30620 Z3 SC - Under Slab Drainage 5 01-Dec-23 07-Dec-23 146

30630 Z3 SC - Waterproof / Prepare For Mat Slab 5 08-Dec-23 14-Dec-23 146

30640 Z3 SC - FRP Utility Trench Pour #5 7 15-Dec-23 26-Dec-23 146

30645 FRP Mat Slab Pour #6 15 27-Dec-23 17-Jan-24 146

30646 FRP Base Isolator Pedestals North 5 18-Jan-24 24-Jan-24 156

30655 FRP Mat Slab Pour #7 15 18-Jan-24 07-Feb-24 146

30656 FRP Base Isolator Pedestals South 5 08-Feb-24 14-Feb-24 146

30657 FRP Concourse Pour #6 15 15-Feb-24 06-Mar-24 146

30670 Z3 SC - FRP Walls and columns 15 07-Mar-24 27-Mar-24 146

30680 Wall and Column Cure 10 28-Mar-24 10-Apr-24 146

30750 Z3 SC - Pressure Inject / Dry Pack At Transfer / Column Connections 10 11-Apr-24 24-Apr-24 146

30760 Z3 SC - Coordinate Removal Of Remaining Shoring 2 18-Apr-24 19-Apr-24 146

30770 Z3 SC - Remove Remaining Shoring 3 22-Apr-24 24-Apr-24 146

Zone 3 Architectural / MEPZone 3 Architectural / MEPZone 3 Architectural / MEPZone 3 Architectural / MEPZone 3 Architectural / MEPZone 3 Architectural / MEPZone 3 Architectural / MEP

30780 Z3 AC - Layout Walls / Top Track 10 25-Apr-24 08-May-24 146

30790 Z3 AC - Electrical OH Rough In 10 02-May-24 15-May-24 146

30800 Z3 AC - Fire Sprinkler OH Rough In 10 09-May-24 22-May-24 146

30810 Z3 AC - HVAC / Plumb OH Rough In 10 16-May-24 30-May-24 146

30820 Z3 AC - Door Frame Install 5 23-May-24 30-May-24 146

30830 Z3 AC - Wall Framing & Soffit Framing 15 31-May-24 20-Jun-24 146

30840 Z3 AC - HVAC Wall Rough In 10 07-Jun-24 20-Jun-24 146

30850 Z3 AC - HVAC Insulation 10 14-Jun-24 27-Jun-24 146

30860 Z3 AC - Fire Sprinkler Rough In 10 21-Jun-24 05-Jul-24 146

30870 Z3 AC - Plumbing Rough In 10 28-Jun-24 12-Jul-24 146

30880 Z3 AC - Plumbing Insulation 10 08-Jul-24 19-Jul-24 146

30890 Z3 AC - Electrical Rough In 10 15-Jul-24 26-Jul-24 146

30900 Z3 AC - Low Voltage & DDC Rough In 10 22-Jul-24 02-Aug-24 146

30910 Z3 AC - Cover Inspections 2 29-Jul-24 30-Jul-24 146

30920 Z3 AC - Plaster Work In Corridors Of Historic Preservation 15 31-Jul-24 20-Aug-24 146

30930 Z3 AC - Sheetrock 10 07-Aug-24 20-Aug-24 146

30940 Z3 AC - Tape & Finish 10 14-Aug-24 27-Aug-24 146

30950 Z3 AC - Terrazzo Flooring 15 21-Aug-24 11-Sep-24 146

30960 Z3 AC - Bathroom Tile Work 10 28-Aug-24 11-Sep-24 146

30970 Z3 AC - Paint, First Two Coats 10 05-Sep-24 18-Sep-24 146

30980 Z3 AC - ACT Grid 10 12-Sep-24 25-Sep-24 146

30990 Z3 AC - Light Fixtures 10 19-Sep-24 02-Oct-24 146

31000 Z3 AC - Casework 10 26-Sep-24 09-Oct-24 146

31010 Z3 AC - Electrical Trim 10 03-Oct-24 16-Oct-24 146

31020 Z3 AC - Plumbing Trim 10 10-Oct-24 23-Oct-24 146

31030 Z3 AC - HVAC Trim 10 17-Oct-24 30-Oct-24 146

Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D

2023 2024 2025 2026

Z3 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation

Z3 SC - Build / Strengthen Shoring Towers With Excavation

Z3 SC - Excavate Utility Trench

Z3 SC - Under Slab Drainage

Z3 SC - Waterproof / Prepare For Mat Slab

Z3 SC - FRP Utility Trench Pour #5

FRP Mat Slab Pour #6

FRP Base Isolator Pedestals North

FRP Mat Slab Pour #7

FRP Base Isolator Pedestals South

FRP Concourse Pour #6

Z3 SC - FRP Walls and columns

Wall and Column Cure

Z3 SC - Pressure Inject / Dry Pack At Transfer / Column Connections

Z3 SC - Coordinate Removal Of Remaining Shoring

Z3 SC - Remove Remaining Shoring

Z3 AC - Layout Walls / Top Track

Z3 AC - Electrical OH Rough In

Z3 AC - Fire Sprinkler OH Rough In

Z3 AC - HVAC / Plumb OH Rough In

Z3 AC - Door Frame Install

Z3 AC - Wall Framing & Soffit Framing

Z3 AC - HVAC Wall Rough In

Z3 AC - HVAC Insulation

Z3 AC - Fire Sprinkler Rough In

Z3 AC - Plumbing Rough In

Z3 AC - Plumbing Insulation

Z3 AC - Electrical Rough In

Z3 AC - Low Voltage & DDC Rough In

Z3 AC - Cover Inspections

Z3 AC - Plaster Work In Corridors Of Historic Preservation

Z3 AC - Sheetrock

Z3 AC - Tape & Finish

Z3 AC - Terrazzo Flooring

Z3 AC - Bathroom Tile Work

Z3 AC - Paint, First Two Coats

Z3 AC - ACT Grid

Z3 AC - Light Fixtures

Z3 AC - Casework

Z3 AC - Electrical Trim

Z3 AC - Plumbing Trim

Z3 AC - HVAC Trim

PROJECT ID : CAMS III - 02 18-Jul-23

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

CAMS III 071423

TASK filter: InCOMPLETE.

Start Finish Total Float

Predecessor Details

31040 Z3 AC - Hang Doors 5 24-Oct-24 30-Oct-24 146

31050 Z3 AC - Fire Sprinkler Trim 5 31-Oct-24 06-Nov-24 146

31060 Z3 AC - Drop Ceiling Tile 5 07-Nov-24 13-Nov-24 146

31070 Z3 AC - All Bathroom Fixtures, PTH, TPH, Mirrors 5 14-Nov-24 20-Nov-24 146

31080 Z3 AC - Carpet 10 21-Nov-24 06-Dec-24 146

31090 Z3 AC - Base 5 02-Dec-24 06-Dec-24 146

31100 Z3 AC - TAB / Commissioning 10 09-Dec-24 20-Dec-24 146

31110 Z3 AC - Punch / Substantial Completion 10 23-Dec-24 07-Jan-25 146

Zone 3 Elevator (001)Zone 3 Elevator (001)Zone 3 Elevator (001)Zone 3 Elevator (001)Zone 3 Elevator (001)Zone 3 Elevator (001)Zone 3 Elevator (001)

31130 Z3 Elev - Excavate New Pit 10 01-Dec-23 14-Dec-23 100

31140 Z3 Elev - Waterproof Pits 10 15-Dec-23 29-Dec-23 100

31150 Z3 Elev - FRP Pits 10 02-Jan-24 15-Jan-24 100

31160 Z3 Elev - MEP Rough In For New Walls / Elevator Pit 15 16-Jan-24 05-Feb-24 100

31170 Z3 Elev - Elevator Shaft Buildout / Exterior Walls 15 06-Feb-24 26-Feb-24 100

31180 Z3 Elev - Install Rails Or Modify As Necessary 10 27-Feb-24 11-Mar-24 100

31190 Z3 Elev - Finish Exterior Shaft Walls & Install Elect 10 12-Mar-24 25-Mar-24 100

31200 Z3 Elev - Adjust Cars & Test 15 19-Aug-24 09-Sep-24 -2

31210 Z3 Elev - Commission Elevator / State Inspections - Workman's 2 10-Sep-24 11-Sep-24 -2

31220 Z3 Elev - Receive Elevator Permit 1 12-Sep-24 12-Sep-24 20

Zone 3 NE Central StairZone 3 NE Central StairZone 3 NE Central StairZone 3 NE Central StairZone 3 NE Central StairZone 3 NE Central StairZone 3 NE Central Stair

31230 Z3 NE Str - Install Collector Steel Under 1st Floor 10 07-Mar-24 20-Mar-24 233

31240 Z3 NE Str - Shore Stairs As Necessary 5 21-Mar-24 27-Mar-24 233

31250 Z3 NE Str - Cut New Opening For Stair From G Level To Level 1 5 28-Mar-24 03-Apr-24 233

31260 Z3 NE Str - Install Steel At Opening 10 04-Apr-24 17-Apr-24 233

31270 Z3 NE Str - Install Stair From G To 1 15 18-Apr-24 08-May-24 233

31280 Z3 NE Str - Rebar & Pour Landing 10 09-May-24 22-May-24 233

31290 Z3 NE Str - Install Handrails 10 23-May-24 06-Jun-24 233

31300 Z3 NE Str - Frame Walls 10 07-Jun-24 20-Jun-24 233

31310 Z3 NE Str - MEP Rough In 10 21-Jun-24 05-Jul-24 233

31320 Z3 NE Str - Cover Walls & Ceilings 10 08-Jul-24 19-Jul-24 233

31330 Z3 NE Str - Terrazzo Flooring / Treads 15 22-Jul-24 09-Aug-24 233

31340 Z3 NE Str - Paint / Final Finishes 5 12-Aug-24 16-Aug-24 233

31350 Z3 NE Str - Punch / Substantial Completion 10 19-Aug-24 30-Aug-24 233

G Level Zone 4G Level Zone 4G Level Zone 4G Level Zone 4G Level Zone 4G Level Zone 4G Level Zone 4

Zone 4 StructuralZone 4 StructuralZone 4 StructuralZone 4 StructuralZone 4 StructuralZone 4 StructuralZone 4 Structural

Exterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro Piles

40370 Z4 SC - Drill Micro Piles 10 01-Aug-23 14-Aug-23 55

40380 Z4 SC - Core / Cut Wall At Needle Beam Locations 5 15-Aug-23 21-Aug-23 80

40390 Z4 SC - Install Shoring Towers 15 23-Aug-23 13-Sep-23 79

40400 Z4 SC - Transfer Load Into Shoring Towers 5 14-Sep-23 20-Sep-23 79

40430 Z4 SC - Excavate Down To Bottom Of Footings 10 21-Sep-23 04-Oct-23 79

40440 Z4 SC - Abatement Of Exterior Wall 5 05-Oct-23 11-Oct-23 79

Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D

2023 2024 2025 2026

Z3 AC - Hang Doors

Z3 AC - Fire Sprinkler Trim

Z3 AC - Drop Ceiling Tile

Z3 AC - All Bathroom Fixtures, PTH, TPH, Mirrors

Z3 AC - Carpet

Z3 AC - Base

Z3 AC - TAB / Commissioning

Z3 AC - Punch / Substantial Completion

Z3 Elev - Excavate New Pit

Z3 Elev - Waterproof Pits

Z3 Elev - FRP Pits

Z3 Elev - MEP Rough In For New Walls / Elevator Pit

Z3 Elev - Elevator Shaft Buildout / Exterior Walls

Z3 Elev - Install Rails Or Modify As Necessary

Z3 Elev - Finish Exterior Shaft Walls & Install Elect

Z3 Elev - Adjust Cars & Test

Z3 Elev - Commission Elevator / State Inspections - Workman's

Z3 Elev - Receive Elevator Permit

Z3 NE Str - Install Collector Steel Under 1st Floor

Z3 NE Str - Shore Stairs As Necessary

Z3 NE Str - Cut New Opening For Stair From G Level To Level 1

Z3 NE Str - Install Steel At Opening

Z3 NE Str - Install Stair From G To 1

Z3 NE Str - Rebar & Pour Landing

Z3 NE Str - Install Handrails

Z3 NE Str - Frame Walls

Z3 NE Str - MEP Rough In

Z3 NE Str - Cover Walls & Ceilings

Z3 NE Str - Terrazzo Flooring / Treads

Z3 NE Str - Paint / Final Finishes

Z3 NE Str - Punch / Substantial Completion

Z4 SC - Drill Micro Piles

Z4 SC - Core / Cut Wall At Needle Beam Locations

Z4 SC - Install Shoring Towers

Z4 SC - Transfer Load Into Shoring Towers

Z4 SC - Excavate Down To Bottom Of Footings

Z4 SC - Abatement Of Exterior Wall

PROJECT ID : CAMS III - 02 18-Jul-23

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

CAMS III 071423

TASK filter: InCOMPLETE.

Start Finish Total Float

Predecessor Details

40450 Z4 SC - Demo Exterior Wall 10 12-Oct-23 25-Oct-23 79

40460 Z4 SC - Excavation To Bottom Of Mat Slab 15 01-Dec-23 21-Dec-23 75

InteriorInteriorInteriorInteriorInteriorInteriorInterior

40510 Z4 SC - Micro Pile Mobilization 2 18-Aug-23* 21-Aug-23 -20

40520 Z4 SC - Drill Micro Piles 30 22-Aug-23 03-Oct-23 -20

40530 Z4 SC - Build Shoring Towers 20 13-Sep-23 10-Oct-23 70

40540 Z4 SC - Stress Transfer Beams 5 11-Oct-23 17-Oct-23 70

40550 Z4 SC - Transfer Load To Shoring Towers 5 18-Oct-23 24-Oct-23 70

40560 Z4 SC - Excavate To Bottom Of Footings 10 25-Oct-23 07-Nov-23 70

40570 Z4 SC - Demo Columns / Walls / Footings 15 08-Nov-23 30-Nov-23 70

40580 Z4 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation15 01-Dec-23 21-Dec-23 70

40590 Z4 SC - Build / Strengthen Shoring Towers With Excavation 15 08-Dec-23 29-Dec-23 70

40600 Z4 SC - Excavate Utility Trench 5 22-Dec-23 29-Dec-23 70

40610 Z4 SC - Under Slab Drainage 5 02-Jan-24 08-Jan-24 70

40620 Z4 SC - Waterproof / Prepare For Mat Slab 5 09-Jan-24 15-Jan-24 70

40630 Z4 SC - FRP Utility Trench Pour #9 10 06-Feb-24 19-Feb-24 70

40635 FRP Mat Slab Pour #10 15 20-Feb-24 11-Mar-24 70

40640 FRP Mat Slab Pour #11 15 12-Mar-24 01-Apr-24 70

40645 FRP Base Isolator Pedestals North 5 12-Mar-24 18-Mar-24 85

40650 Install Base Isolators North 5 19-Mar-24 25-Mar-24 85

40655 FRP Base Isolator Pedestals South 5 02-Apr-24 08-Apr-24 70

40660 Install Base Isolators South 5 09-Apr-24 15-Apr-24 70

40665 FRP Concourse Pour #9 10 16-Apr-24 29-Apr-24 70

40670 FRP Concourse pour #11 10 30-Apr-24 13-May-24 70

40675 FRP Columns and Walls 25 14-May-24 18-Jun-24 70

40680 Columns and Walls Cure 20 19-Jun-24 17-Jul-24 70

40740 Z4 SC - Pressure Inject / Dry Pack At Transfer / Column Connections 10 18-Jul-24 31-Jul-24 70

40750 Z4 SC - Coordinate Removal Of Remaining Shoring 2 30-Jul-24 31-Jul-24 70

40760 Z4 SC - Remove Remaining Shoring 8 01-Aug-24 12-Aug-24 70

Zone 4 Architectural / MEPZone 4 Architectural / MEPZone 4 Architectural / MEPZone 4 Architectural / MEPZone 4 Architectural / MEPZone 4 Architectural / MEPZone 4 Architectural / MEP

40770 Z4 AC - Layout Walls / Top Track 10 13-Aug-24 26-Aug-24 70

40780 Z4 AC - Electrical OH Rough In 10 20-Aug-24 03-Sep-24 70

40790 Z4 AC - Fire Sprinkler OH Rough In 10 27-Aug-24 10-Sep-24 70

40800 Z4 AC - HVAC / Plumb OH Rough In 10 04-Sep-24 17-Sep-24 70

40810 Z4 AC - Door Frame Install 5 11-Sep-24 17-Sep-24 70

40820 Z4 AC - Wall Framing & Soffit Framing 15 18-Sep-24 08-Oct-24 70

40830 Z4 AC - HVAC Wall Rough In 10 25-Sep-24 08-Oct-24 70

40840 Z4 AC - HVAC Insulation 10 02-Oct-24 15-Oct-24 70

40850 Z4 AC - Fire Sprinkler Rough In 10 09-Oct-24 22-Oct-24 70

40860 Z4 AC - Plumbing Rough In 10 16-Oct-24 29-Oct-24 70

40870 Z4 AC - Plumbing Insulation 10 23-Oct-24 05-Nov-24 70

40880 Z4 AC - Electrical Rough In 10 30-Oct-24 12-Nov-24 70

40890 Z4 AC - Low Voltage & DDC Rough In 10 06-Nov-24 19-Nov-24 70

Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D

2023 2024 2025 2026

Z4 SC - Demo Exterior Wall

Z4 SC - Excavation To Bottom Of Mat Slab

Z4 SC - Micro Pile Mobilization

Z4 SC - Drill Micro Piles

Z4 SC - Build Shoring Towers

Z4 SC - Stress Transfer Beams

Z4 SC - Transfer Load To Shoring Towers

Z4 SC - Excavate To Bottom Of Footings

Z4 SC - Demo Columns / Walls / Footings

Z4 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation

Z4 SC - Build / Strengthen Shoring Towers With Excavation

Z4 SC - Excavate Utility Trench

Z4 SC - Under Slab Drainage

Z4 SC - Waterproof / Prepare For Mat Slab

Z4 SC - FRP Utility Trench Pour #9

FRP Mat Slab Pour #10

FRP Mat Slab Pour #11

FRP Base Isolator Pedestals North

Install Base Isolators North

FRP Base Isolator Pedestals South

Install Base Isolators South

FRP Concourse Pour #9

FRP Concourse pour #11

FRP Columns and Walls

Columns and Walls Cure

Z4 SC - Pressure Inject / Dry Pack At Transfer / Column Connections

Z4 SC - Coordinate Removal Of Remaining Shoring

Z4 SC - Remove Remaining Shoring

Z4 AC - Layout Walls / Top Track

Z4 AC - Electrical OH Rough In

Z4 AC - Fire Sprinkler OH Rough In

Z4 AC - HVAC / Plumb OH Rough In

Z4 AC - Door Frame Install

Z4 AC - Wall Framing & Soffit Framing

Z4 AC - HVAC Wall Rough In

Z4 AC - HVAC Insulation

Z4 AC - Fire Sprinkler Rough In

Z4 AC - Plumbing Rough In

Z4 AC - Plumbing Insulation

Z4 AC - Electrical Rough In

Z4 AC - Low Voltage & DDC Rough In

PROJECT ID : CAMS III - 02 18-Jul-23

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

CAMS III 071423

TASK filter: InCOMPLETE.

Start Finish Total Float

Predecessor Details

40900 Z4 AC - Cover Inspections 2 13-Nov-24 14-Nov-24 70

40910 Z4 AC - Plaster Work In Corridors Of Historic Preservation 15 15-Nov-24 09-Dec-24 70

40920 Z4 AC - Sheetrock 10 22-Nov-24 09-Dec-24 70

40930 Z4 AC - Tape & Finish 10 03-Dec-24 16-Dec-24 70

40940 Z4 AC - Terrazzo Flooring 15 10-Dec-24 31-Dec-24 70

40950 Z4 AC - Bathroom Tile Work 10 17-Dec-24 31-Dec-24 70

40960 Z4 AC - Paint, First Two Coats 10 24-Dec-24 08-Jan-25 70

40970 Z4 AC - ACT Grid 10 02-Jan-25 15-Jan-25 70

40980 Z4 AC - Light Fixtures 10 09-Jan-25 22-Jan-25 70

40990 Z4 AC - Casework 10 16-Jan-25 29-Jan-25 70

41000 Z4 AC - Electrical Trim 10 23-Jan-25 05-Feb-25 70

41010 Z4 AC - Plumbing Trim 10 30-Jan-25 12-Feb-25 70

41020 Z4 AC - HVAC Trim 10 06-Feb-25 19-Feb-25 70

41030 Z4 AC - Hang Doors 5 13-Feb-25 19-Feb-25 70

41040 Z4 AC - Fire Sprinkler Trim 5 20-Feb-25 26-Feb-25 70

41050 Z4 AC - Drop Ceiling Tile 5 27-Feb-25 05-Mar-25 70

41060 Z4 AC - All Bathroom Fixtures, PTH, TPH, Mirrors 5 06-Mar-25 12-Mar-25 70

41070 Z4 AC - Carpet 10 13-Mar-25 26-Mar-25 70

41080 Z4 AC - Base 5 20-Mar-25 26-Mar-25 70

41090 Z4 AC - TAB / Commissioning 10 27-Mar-25 09-Apr-25 70

41100 Z4 AC - Punch / Substantial Completion 10 10-Apr-25 23-Apr-25 70

Zone 4 Elevator (002)Zone 4 Elevator (002)Zone 4 Elevator (002)Zone 4 Elevator (002)Zone 4 Elevator (002)Zone 4 Elevator (002)Zone 4 Elevator (002)

41110 Z4 Elev 2 - Elevator Shaft Demo As Required / Reshore 10 02-Jan-24 15-Jan-24 87

41120 Z4 Elev 2 - Excavate New Pit 10 16-Jan-24 29-Jan-24 87

41130 Z4 Elev 2 - Waterproof Pits 10 30-Jan-24 12-Feb-24 87

41140 Z4 Elev 2 - FRP Pits 10 13-Feb-24 26-Feb-24 87

41150 Z4 Elev 2 - MEP Rough In For New Walls / Elevator Pit 15 27-Feb-24 18-Mar-24 87

41160 Z4 Elev 2 - Elevator Shaft Buildout / Exterior Walls 15 19-Mar-24 08-Apr-24 87

41170 Z4 Elev 2 - Install Rails Or Modify As Necessary 10 09-Apr-24 22-Apr-24 87

41180 Z4 Elev 2 - Finish Exterior Shaft Walls & Install Elect 10 23-Apr-24 06-May-24 87

41190 Z4 Elev 2 - Adjust Cars & Test 10 12-Sep-24 25-Sep-24 -2

41200 Z4 Elev 2 - Commission Elevator / State Inspections 2 26-Sep-24 27-Sep-24 8

41210 Z4 Elev 2 - Receive Elevator Permit 1 30-Sep-24 30-Sep-24 8

Zone 4 Elevator (009)Zone 4 Elevator (009)Zone 4 Elevator (009)Zone 4 Elevator (009)Zone 4 Elevator (009)Zone 4 Elevator (009)Zone 4 Elevator (009)

41220 Z4 Elev 9 - Elevator Shaft Demo As Required / Reshore 10 02-Jan-24 15-Jan-24 97

41230 Z4 Elev 9 - Excavate New Pit 10 30-Jan-24 12-Feb-24 87

41240 Z4 Elev 9 - Waterproof Pits 10 13-Feb-24 26-Feb-24 87

41250 Z4 Elev 9 - FRP Pits 10 27-Feb-24 11-Mar-24 87

41260 Z4 Elev 9 - MEP Rough In For New Walls / Elevator Pit 15 12-Mar-24 01-Apr-24 87

41270 Z4 Elev 9 - Elevator Shaft Buildout / Exterior Walls 15 02-Apr-24 22-Apr-24 87

41280 Z4 Elev 9 - Install Rails Or Modify As Necessary 10 23-Apr-24 06-May-24 87

41290 Z4 Elev 9 - Finish Exterior Shaft Walls & Install Elect 10 07-May-24 20-May-24 87

41300 Z4 Elev 9 - Adjust Cars & Test 10 26-Sep-24 09-Oct-24 -2

Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D

2023 2024 2025 2026

Z4 AC - Cover Inspections

Z4 AC - Plaster Work In Corridors Of Historic Preservation

Z4 AC - Sheetrock

Z4 AC - Tape & Finish

Z4 AC - Terrazzo Flooring

Z4 AC - Bathroom Tile Work

Z4 AC - Paint, First Two Coats

Z4 AC - ACT Grid

Z4 AC - Light Fixtures

Z4 AC - Casework

Z4 AC - Electrical Trim

Z4 AC - Plumbing Trim

Z4 AC - HVAC Trim

Z4 AC - Hang Doors

Z4 AC - Fire Sprinkler Trim

Z4 AC - Drop Ceiling Tile

Z4 AC - All Bathroom Fixtures, PTH, TPH, Mirrors

Z4 AC - Carpet

Z4 AC - Base

Z4 AC - TAB / Commissioning

Z4 AC - Punch / Substantial Completion

Z4 Elev 2 - Elevator Shaft Demo As Required / Reshore

Z4 Elev 2 - Excavate New Pit

Z4 Elev 2 - Waterproof Pits

Z4 Elev 2 - FRP Pits

Z4 Elev 2 - MEP Rough In For New Walls / Elevator Pit

Z4 Elev 2 - Elevator Shaft Buildout / Exterior Walls

Z4 Elev 2 - Install Rails Or Modify As Necessary

Z4 Elev 2 - Finish Exterior Shaft Walls & Install Elect

Z4 Elev 2 - Adjust Cars & Test

Z4 Elev 2 - Commission Elevator / State Inspections

Z4 Elev 2 - Receive Elevator Permit

Z4 Elev 9 - Elevator Shaft Demo As Required / Reshore

Z4 Elev 9 - Excavate New Pit

Z4 Elev 9 - Waterproof Pits

Z4 Elev 9 - FRP Pits

Z4 Elev 9 - MEP Rough In For New Walls / Elevator Pit

Z4 Elev 9 - Elevator Shaft Buildout / Exterior Walls

Z4 Elev 9 - Install Rails Or Modify As Necessary

Z4 Elev 9 - Finish Exterior Shaft Walls & Install Elect

Z4 Elev 9 - Adjust Cars & Test

PROJECT ID : CAMS III - 02 18-Jul-23

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone

CAMS III 071423

TASK filter: InCOMPLETE.

Start Finish Total Float

Predecessor Details

41310 Z4 Elev 9 - Commission Elevator / State Inspections 2 10-Oct-24 11-Oct-24 -2

41320 Z4 Elev 9 - Receive Elevator Permit 1 14-Oct-24 14-Oct-24 -2

Zone 4 NW Central StairZone 4 NW Central StairZone 4 NW Central StairZone 4 NW Central StairZone 4 NW Central StairZone 4 NW Central StairZone 4 NW Central Stair

41330 Z4 Str C - Install Floor Steel Under First Floor 10 14-May-24 28-May-24 215

41340 Z4 Str C - Shore Stairs As Necessary 5 29-May-24 04-Jun-24 215

41350 Z4 Str C - Install Steel Deck At Opening 10 05-Jun-24 18-Jun-24 215

41360 Z4 Str C - Rebar & Pour Landing 10 19-Jun-24 02-Jul-24 215

41370 Z4 Str C - Install Handrails 10 03-Jul-24 17-Jul-24 215

41380 Z4 Str C - Frame Walls 10 18-Jul-24 31-Jul-24 215

41390 Z4 Str C - MEP Rough In 10 01-Aug-24 14-Aug-24 215

41400 Z4 Str C - Cover Walls & Ceilings 5 15-Aug-24 21-Aug-24 215

41410 Z4 Str C - Terrazzo Flooring / Treads 15 22-Aug-24 12-Sep-24 215

41420 Z4 Str C - Paint / Final Finishes 5 13-Sep-24 19-Sep-24 215

41430 Z4 Str C - Punch / Substantial Completion 5 20-Sep-24 26-Sep-24 215

G Level Zone 5.1G Level Zone 5.1G Level Zone 5.1G Level Zone 5.1G Level Zone 5.1G Level Zone 5.1G Level Zone 5.1

Zone 5.1 StructuralZone 5.1 StructuralZone 5.1 StructuralZone 5.1 StructuralZone 5.1 StructuralZone 5.1 StructuralZone 5.1 Structural

52210 Z5.1 SC - Install Shoring Towers 20 30-Aug-23 27-Sep-23 64

52220 Z5.1 SC - Transfer Building Loads To Shoring Towers 2 28-Sep-23 29-Sep-23 64

52230 Z5.1 SC - Install Shotcrete, Soil Nail Wall At '77 Building 20 02-Oct-23 27-Oct-23 121

52240 Z5.1 SC - Excavate With Soil Nail Wall 20 09-Oct-23 03-Nov-23 121

52260 Z5.1 SC - Cross brace towers wtih Excavation 20 16-Oct-23 10-Nov-23 121

52270 Z5.1 SC - Install Under Slab Drainage 10 13-Nov-23 28-Nov-23 121

52280 Z5.1 SC - Waterproof / Prepare For Mat Slab 5 29-Nov-23 05-Dec-23 121

52282 FRP Mat Slab Pour #16 15 06-Dec-23 27-Dec-23 121

52284 FRP Base Isolator Pedestals 5 28-Dec-23 04-Jan-24 121

52286 Install Base Isolators 5 05-Jan-24 11-Jan-24 121

52288 FRP Concourse Pour #13 10 12-Jan-24 25-Jan-24 121

52290 FRP Concourse Pour #14 10 23-Jan-24 05-Feb-24 121

52292 MEP Homerun 20 06-Feb-24 04-Mar-24 178

52302 FRP Columns and Walls 15 06-Feb-24 26-Feb-24 121

52308 Column/Beam Cure 20 27-Feb-24 25-Mar-24 148

52318 Stress PT Beams 5 26-Mar-24 01-Apr-24 148

52323 Pressure Inject/Pack Base isolators 5 02-Apr-24 08-Apr-24 148

52333 Coordinate Removal of shoring towers 2 09-Apr-24 10-Apr-24 148

52343 Remove shoring towers 3 11-Apr-24 15-Apr-24 148

52400 Z5.1 SC - Install Structural Roof Steel 15 27-Feb-24 18-Mar-24 121

52410 Z5.1 SC - Install Metal Deck 7 19-Mar-24 27-Mar-24 121

52415 MEP Install Hangers 5 28-Mar-24 03-Apr-24 121

52420 Z5.1 SC - FRP SOMD 10 04-Apr-24 17-Apr-24 121

5.1 Interiror Hearing room5.1 Interiror Hearing room5.1 Interiror Hearing room5.1 Interiror Hearing room5.1 Interiror Hearing room5.1 Interiror Hearing room5.1 Interiror Hearing room

52430 Z5.1 Hr - Layout Walls / Top Track 10 23-May-24 06-Jun-24 121

52440 Z5.1 Hr - Electrical OH Rough In 10 31-May-24 13-Jun-24 121

Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D

2023 2024 2025 2026

Z4 Elev 9 - Commission Elevator / State Inspections

Z4 Elev 9 - Receive Elevator Permit

Z4 Str C - Install Floor Steel Under First Floor

Z4 Str C - Shore Stairs As Necessary

Z4 Str C - Install Steel Deck At Opening

Z4 Str C - Rebar & Pour Landing

Z4 Str C - Install Handrails

Z4 Str C - Frame Walls

Z4 Str C - MEP Rough In

Z4 Str C - Cover Walls & Ceilings

Z4 Str C - Terrazzo Flooring / Treads

Z4 Str C - Paint / Final Finishes

Z4 Str C - Punch / Substantial Completion

Z5.1 SC - Install Shoring Towers

Z5.1 SC - Transfer Building Loads To Shoring Towers

Z5.1 SC - Install Shotcrete, Soil Nail Wall At '77 Building

Z5.1 SC - Excavate With Soil Nail Wall

Z5.1 SC - Cross brace towers wtih Excavation

Z5.1 SC - Install Under Slab Drainage

Z5.1 SC - Waterproof / Prepare For Mat Slab

FRP Mat Slab Pour #16

FRP Base Isolator Pedestals

Install Base Isolators

FRP Concourse Pour #13

FRP Concourse Pour #14

MEP Homerun

FRP Columns and Walls

Column/Beam…