Attachment E CAMS 3 Schedule.pdf
PDF 2 MB Posted
- Attached to
- SPECIAL INSPECTIONS AND TESTING
- Solicitation number
- S-15600-00007856
- Issued by
- Marion County, Oregon
About this file
This document is related to a state and local contract opportunity for construction inspection services in Marion County and the City of Salem, Oregon. The scope of work includes full-service construction inspection for the CAMS Phase 3 project, with inspectors required to be highly qualified in their areas of expertise. The contract involves field verification that construction is being performed according to plans, specifications, and applicable codes and standards. The contract term and any renewal options are not specified.
The contract does not provide details on pricing terms, set asides, incumbents, funding requirements, or other financial information. The document focuses on the technical requirements for the construction inspection services to be provided.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Original Duration
Start Finish Total Float
Predecessor Details
Preconstruction / Design / PermitsPreconstruction / Design / PermitsPreconstruction / Design / PermitsPreconstruction / Design / PermitsPreconstruction / Design / PermitsPreconstruction / Design / PermitsPreconstruction / Design / Permits
PRECON10180 Court Street Closure Permit 544 01-Nov-22 A 02-Dec-24 359
PRECON10440 Procure Long Lead / MEP Equipment 184 07-Dec-22 A 22-Aug-23 683
Construction MilestonesConstruction MilestonesConstruction MilestonesConstruction MilestonesConstruction MilestonesConstruction MilestonesConstruction Milestones
MS1130 2024 Legislative Session (Short) 26 29-Jan-24* 04-Mar-24 7
MS1140 2025 Legislative Session (Long) 109 21-Jan-25* 23-Jun-25 217
MS1150 Levels 1-4 Substantial Completion 0 12-Dec-24* -28
MS1160 Building '77 Substantial Completion 0 15-Jan-26 75
MS1170 Full Project Completion 0 30-Apr-26* 0
MS1180 G Level Substantial 0 01-Aug-25* 0
MS1190 Landscape & Civil Work 139 27-Jun-25 15-Jan-26 75
MS1200 Total Duration 974 16-Mar-22 A 15-Jan-26 75
ConstructionConstructionConstructionConstructionConstructionConstructionConstruction
New BuildoutNew BuildoutNew BuildoutNew BuildoutNew BuildoutNew BuildoutNew Buildout
G Level Zone 2G Level Zone 2G Level Zone 2G Level Zone 2G Level Zone 2G Level Zone 2G Level Zone 2
Zone 2 StructuralZone 2 StructuralZone 2 StructuralZone 2 StructuralZone 2 StructuralZone 2 StructuralZone 2 Structural
Exterior Wall Micro Piles at NE 1 & NE AExterior Wall Micro Piles at NE 1 & NE AExterior Wall Micro Piles at NE 1 & NE AExterior Wall Micro Piles at NE 1 & NE AExterior Wall Micro Piles at NE 1 & NE AExterior Wall Micro Piles at NE 1 & NE AExterior Wall Micro Piles at NE 1 & NE A
20800 Z2 SC - Install Shoring Towers Along NE1 20 30-May-23 A 28-Jul-23 0
20801 Z2 SC - Install PT strands in Beams 3 24-Jul-23 26-Jul-23 0
20802 Z2 SC - Cut column Rebar @N7, N5 line 5 24-Jul-23 28-Jul-23 0
20810 Z2 SC - Transfer Load Into Shoring Towers Along NE1 5 31-Jul-23 04-Aug-23 0
20820 Z2 SC - Core / Cut Wall At Needle Beam Locations Along NEA 10 05-Jun-23 A 19-Jul-23 0
20830 Z2 SC - Install Shoring Towers Along NEA 10 12-Jun-23 A 28-Jul-23 0
20831 Install PT strands in Beams 3 24-Jul-23 26-Jul-23 0
20832 Cut column and rebar as necessary 5 24-Jul-23 28-Jul-23 0
20840 Z2 SC - Transfer Load Into Shoring Towers Along NEA 5 31-Jul-23 04-Aug-23 0
InteriorInteriorInteriorInteriorInteriorInteriorInterior
20910 Z2 SC - Build Shoring Towers 20 01-Jun-23 A 28-Jul-23 0
20911 Z2 SC - Install PT strands in Beams 3 24-Jul-23 26-Jul-23 0
20912 Z2 SC - Cut Columns and rebar as necessary 5 24-Jul-23 28-Jul-23 0
20920 Z2 SC - Stress PT Transfer Beams 5 31-Jul-23 04-Aug-23 0
20930 Z2 SC - Transfer Load To Shoring Towers 5 31-Jul-23 04-Aug-23 0
20950 Z2 SC - Demo Columns / Walls / Footings 15 07-Aug-23 25-Aug-23 0
20960 Z2 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation20 21-Aug-23 18-Sep-23 0
20970 Z2 SC - Install cross bracing on Shoring towers 15 28-Aug-23 18-Sep-23 0
20980 Z2 SC - Excavate Utility Trench 5 19-Sep-23 25-Sep-23 0
20990 Z2 SC - Under Slab Drainage 5 19-Sep-23 25-Sep-23 0
21000 Z2 SC - Waterproof / Prepare For Mat Slab 5 26-Sep-23 02-Oct-23 0
21005 Z2 SC - FRP Utility Trench Pour #1 10 03-Oct-23 16-Oct-23 0
21010 Z2 SC - FRP Mat Slab Pour #2 20 10-Oct-23 06-Nov-23 0
21011 Z2 SC - FRP Base Isolator Pedestal North 5 07-Nov-23 13-Nov-23 163
21015 Z2 SC - FRP Mat Slab Pour #3 16 31-Oct-23 21-Nov-23 0
Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D
2023 2024 2025 2026
Court Street Closure Permit
Procure Long Lead / MEP Equipment
2024 Legislative Session (Short)
2025 Legislative Session (Long)
Levels 1-4 Substantial Completion
Building '77 Substantial Completion
Full Project Completion
G Level Substantial
Landscape & Civil Work
Total Duration
Z2 SC - Install Shoring Towers Along NE1
Z2 SC - Install PT strands in Beams
Z2 SC - Cut column Rebar @N7, N5 line
Z2 SC - Transfer Load Into Shoring Towers Along NE1
Z2 SC - Core / Cut Wall At Needle Beam Locations Along NEA
Z2 SC - Install Shoring Towers Along NEA
Install PT strands in Beams
Cut column and rebar as necessary
Z2 SC - Transfer Load Into Shoring Towers Along NEA
Z2 SC - Build Shoring Towers
Z2 SC - Install PT strands in Beams
Z2 SC - Cut Columns and rebar as necessary
Z2 SC - Stress PT Transfer Beams
Z2 SC - Transfer Load To Shoring Towers
Z2 SC - Demo Columns / Walls / Footings
Z2 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation
Z2 SC - Install cross bracing on Shoring towers
Z2 SC - Excavate Utility Trench
Z2 SC - Under Slab Drainage
Z2 SC - Waterproof / Prepare For Mat Slab
Z2 SC - FRP Utility Trench Pour #1
Z2 SC - FRP Mat Slab Pour #2
Z2 SC - FRP Base Isolator Pedestal North
Z2 SC - FRP Mat Slab Pour #3
PROJECT ID : CAMS III - 02 18-Jul-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
CAMS III 071423
TASK filter: InCOMPLETE.
Run Date: 18-Jul-23 07:33
Layout: CAMS III
Start Finish Total Float
Predecessor Details
21016 Z2 SC - FRP Base Isolator Pedestal South 5 22-Nov-23 30-Nov-23 154
21017 Z2 SC - Install Isolators 10 22-Nov-23 07-Dec-23 154
21020 FRP Concourse # 1 10 29-Nov-23 12-Dec-23 154
21025 FRP Concourse # 2 10 08-Dec-23 21-Dec-23 154
21040 FRP Concourse # 3 10 19-Dec-23 03-Jan-24 154
21050 Z2 FRP Interior walls/Columns 20 27-Dec-23 24-Jan-24 154
21060 Z2 SC - Wall and Column Cure 10 25-Jan-24 07-Feb-24 154
21120 Z2 SC - Pressure Inject / Dry Pack At Transfer / Column Connections 9 08-Feb-24 20-Feb-24 154
21130 Z2 SC - Coordinate Removal Of Remaining Shoring 2 15-Feb-24 16-Feb-24 154
21140 Z2 SC - Remove Remaining Shoring 10 19-Feb-24 01-Mar-24 154
Zone 2 Architectural / MEPZone 2 Architectural / MEPZone 2 Architectural / MEPZone 2 Architectural / MEPZone 2 Architectural / MEPZone 2 Architectural / MEPZone 2 Architectural / MEP
21150 Z2 AC - Layout Walls / Top Track 10 04-Mar-24 15-Mar-24 154
21160 Z2 AC - MEP Submittal, Investigation, Planning Out Of East Vault 223 04-Jan-23 A 27-Nov-23 203
21170 Z2 AC - Begin Home Run Pulls From Vault 23 28-Nov-23 29-Dec-23 203
21180 Z2 AC - Electrical OH Rough In 9 11-Mar-24 21-Mar-24 154
21190 Z2 AC - Fire Sprinkler OH Rough In 10 18-Mar-24 29-Mar-24 154
21200 Z2 AC - HVAC / Plumb OH Rough In 10 25-Mar-24 05-Apr-24 154
21210 Z2 AC - Door Frame Install 5 01-Apr-24 05-Apr-24 154
21220 Z2 AC - Wall Framing & Soffit Framing 15 08-Apr-24 26-Apr-24 154
21230 Z2 AC - HVAC Wall Rough In 10 15-Apr-24 26-Apr-24 154
21240 Z2 AC - HVAC Insulation 10 29-Apr-24 10-May-24 154
21250 Z2 AC - Fire Sprinkler Rough In 10 06-May-24 17-May-24 154
21260 Z2 AC - Plumbing Rough In 10 28-May-24 10-Jun-24 154
21270 Z2 AC - Plumbing Insulation 10 04-Jun-24 17-Jun-24 154
21280 Z2 AC - Electrical Rough In 10 11-Jun-24 24-Jun-24 154
21290 Z2 AC - Low Voltage & DDC Rough In 10 18-Jun-24 01-Jul-24 154
21300 Z2 AC - Cover Inspections 2 25-Jun-24 26-Jun-24 154
21310 Z2 AC - Plaster Work In Corridors Of Historic Preservation 15 27-Jun-24 18-Jul-24 154
21320 Z2 AC - Sheetrock 10 05-Jul-24 18-Jul-24 154
21330 Z2 AC - Tape & Finish 10 12-Jul-24 25-Jul-24 154
21340 Z2 AC - Terrazzo Flooring 15 19-Jul-24 08-Aug-24 154
21350 Z2 AC - Bathroom Tile Work 10 26-Jul-24 08-Aug-24 154
21360 Z2 AC - Paint, First Two Coats 10 02-Aug-24 15-Aug-24 154
21370 Z2 AC - ACT Grid 10 09-Aug-24 22-Aug-24 154
21380 Z2 AC - Light Fixtures 10 16-Aug-24 29-Aug-24 154
21390 Z2 AC - Casework 10 30-Aug-24 13-Sep-24 154
21400 Z2 AC - Electrical Trim 10 09-Sep-24 20-Sep-24 154
21410 Z2 AC - Plumbing Trim 10 16-Sep-24 27-Sep-24 154
21420 Z2 AC - HVAC Trim 10 30-Sep-24 11-Oct-24 154
21430 Z2 AC - Hang Doors 5 14-Oct-24 18-Oct-24 154
21440 Z2 AC - Fire Sprinkler Trim 5 21-Oct-24 25-Oct-24 154
21450 Z2 AC - Drop Ceiling Tile 5 28-Oct-24 01-Nov-24 154
21460 Z2 AC - All Bathroom Fixtures, PTH, TPH, Mirrors 5 04-Nov-24 08-Nov-24 154
Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D
2023 2024 2025 2026
Z2 SC - FRP Base Isolator Pedestal South
Z2 SC - Install Isolators
FRP Concourse # 1
FRP Concourse # 2
FRP Concourse # 3
Z2 FRP Interior walls/Columns
Z2 SC - Wall and Column Cure
Z2 SC - Pressure Inject / Dry Pack At Transfer / Column Connections
Z2 SC - Coordinate Removal Of Remaining Shoring
Z2 SC - Remove Remaining Shoring
Z2 AC - Layout Walls / Top Track
Z2 AC - MEP Submittal, Investigation, Planning Out Of East Vault
Z2 AC - Begin Home Run Pulls From Vault
Z2 AC - Electrical OH Rough In
Z2 AC - Fire Sprinkler OH Rough In
Z2 AC - HVAC / Plumb OH Rough In
Z2 AC - Door Frame Install
Z2 AC - Wall Framing & Soffit Framing
Z2 AC - HVAC Wall Rough In
Z2 AC - HVAC Insulation
Z2 AC - Fire Sprinkler Rough In
Z2 AC - Plumbing Rough In
Z2 AC - Plumbing Insulation
Z2 AC - Electrical Rough In
Z2 AC - Low Voltage & DDC Rough In
Z2 AC - Cover Inspections
Z2 AC - Plaster Work In Corridors Of Historic Preservation
Z2 AC - Sheetrock
Z2 AC - Tape & Finish
Z2 AC - Terrazzo Flooring
Z2 AC - Bathroom Tile Work
Z2 AC - Paint, First Two Coats
Z2 AC - ACT Grid
Z2 AC - Light Fixtures
Z2 AC - Casework
Z2 AC - Electrical Trim
Z2 AC - Plumbing Trim
Z2 AC - HVAC Trim
Z2 AC - Hang Doors
Z2 AC - Fire Sprinkler Trim
Z2 AC - Drop Ceiling Tile
Z2 AC - All Bathroom Fixtures, PTH, TPH, Mirrors
PROJECT ID : CAMS III - 02 18-Jul-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
CAMS III 071423
TASK filter: InCOMPLETE.
Start Finish Total Float
Predecessor Details
21470 Z2 AC - Carpet 10 11-Nov-24 22-Nov-24 154
21480 Z2 AC - Base 5 18-Nov-24 22-Nov-24 154
21490 Z2 AC - TAB / Commissioning 10 25-Nov-24 10-Dec-24 154
21500 Z2 AC - Punch / Substantial Completion 10 11-Dec-24 24-Dec-24 154
21510 Z2 AC - Grind and Polish Terrazzo 5 23-Aug-24 29-Aug-24 159
Zone 2 Elevator (007)Zone 2 Elevator (007)Zone 2 Elevator (007)Zone 2 Elevator (007)Zone 2 Elevator (007)Zone 2 Elevator (007)Zone 2 Elevator (007)
21525 Z2 Elev - Infill Level 1 Ledger & Decking 5 22-Nov-23 30-Nov-23 106
21530 Z2 Elev - FRP Level 1 Deck 10 01-Dec-23 14-Dec-23 106
21540 Z2 Elev - MEP Rough In For New Walls / Elevator Pit 10 15-Dec-23 29-Dec-23 106
21550 Z2 Elev - Elevator Shaft Buildout / Exterior Walls 14 02-Jan-24 19-Jan-24 106
21560 Z2 Elev - Install Rails Or Modify As Necessary 10 22-Jan-24 02-Feb-24 106
21570 Z2 Elev - Finish Exterior Shaft Walls & Install Elect 15 05-Feb-24 23-Feb-24 106
21580 Z2 Elev - Adjust Cars & Test 15 29-Jul-24 16-Aug-24 -2
21582 Z2 Elev - Refurbish Interiors 15 19-Aug-24 09-Sep-24 213
21590 Z2 Elev - Commission Elevator / State Inspections - Workman's 2 19-Aug-24 20-Aug-24 40
21600 Z2 Elev - Receive Elevator Workman's Permit 1 21-Aug-24 21-Aug-24 40
G Level Zone East Hearing Rooom Z2.1G Level Zone East Hearing Rooom Z2.1G Level Zone East Hearing Rooom Z2.1G Level Zone East Hearing Rooom Z2.1G Level Zone East Hearing Rooom Z2.1G Level Zone East Hearing Rooom Z2.1G Level Zone East Hearing Rooom Z2.1
Zone 2.1 StructuralZone 2.1 StructuralZone 2.1 StructuralZone 2.1 StructuralZone 2.1 StructuralZone 2.1 StructuralZone 2.1 Structural
22260 Z2.1 SC - Install Shotcrete, Soil Nail Wall At '77 Building 24 26-Jun-23 A 20-Jul-23 32
22270 Z2.1 SC - Excavate With Soil Nail Wall 20 14-Jul-23 10-Aug-23 32
22280 Z2.1 SC - Demobe All Equipment Out Of Zone 5 11-Aug-23 17-Aug-23 32
22290 Z2.1 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation20 28-Aug-23 25-Sep-23 26
22300 Z2.1 SC - Build / Strengthen Shoring Towers With Excavation 15 05-Sep-23 25-Sep-23 26
22310 Z2.1 SC - Install Under Slab Drainage 10 26-Sep-23 09-Oct-23 26
22320 Z2.1 SC - Waterproof / Prepare For Mat Slab 5 10-Oct-23 16-Oct-23 26
22325 FRP Mat Slab Pour #4 15 22-Nov-23 14-Dec-23 0
22330 FRP Base Isolator Pedestals 5 15-Dec-23 21-Dec-23 0
22332 Install Base Isolators 5 22-Dec-23 29-Dec-23 0
22335 FRP Concourse Pour #4 10 02-Jan-24 15-Jan-24 0
22340 FRP Concourse Pour #5 10 11-Jan-24 24-Jan-24 0
22342 Z2.1 SC - Concourse MEP Homerun 20 25-Jan-24 21-Feb-24 50
22345 FRP Interior Walls/Columns 15 25-Jan-24 14-Feb-24 0
22350 Column and Beam cure 20 15-Feb-24 13-Mar-24 25
22355 Stress PT 5 14-Mar-24 20-Mar-24 25
22360 Pressure inject/Dry Pack Base isolator/column 5 14-Mar-24 20-Mar-24 25
22365 Coordinate Removal of Shoring 2 21-Mar-24 22-Mar-24 25
22380 Z2.1 SC - Remove Shoring As Approved By Engineers 3 25-Mar-24 27-Mar-24 25
22420 Z2.1 SC - Install Structural Roof Steel 15 15-Feb-24 06-Mar-24 0
22430 Z2.1 SC - Install Metal Deck 7 07-Mar-24 15-Mar-24 0
22440 Z2.1 SC - MEP Install Hangers, Blockouts 5 18-Mar-24 22-Mar-24 0
22450 Z2.1 SC - FRP SOMD 10 25-Mar-24 05-Apr-24 0
2.1 First Floor Interior Hearing Room2.1 First Floor Interior Hearing Room2.1 First Floor Interior Hearing Room2.1 First Floor Interior Hearing Room2.1 First Floor Interior Hearing Room2.1 First Floor Interior Hearing Room2.1 First Floor Interior Hearing Room
Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D
2023 2024 2025 2026
Z2 AC - Carpet
Z2 AC - Base
Z2 AC - TAB / Commissioning
Z2 AC - Punch / Substantial Completion
Z2 AC - Grind and Polish Terrazzo
Z2 Elev - Infill Level 1 Ledger & Decking
Z2 Elev - FRP Level 1 Deck
Z2 Elev - MEP Rough In For New Walls / Elevator Pit
Z2 Elev - Elevator Shaft Buildout / Exterior Walls
Z2 Elev - Install Rails Or Modify As Necessary
Z2 Elev - Finish Exterior Shaft Walls & Install Elect
Z2 Elev - Adjust Cars & Test
Z2 Elev - Refurbish Interiors
Z2 Elev - Commission Elevator / State Inspections - Workman's
Z2 Elev - Receive Elevator Workman's Permit
Z2.1 SC - Install Shotcrete, Soil Nail Wall At '77 Building
Z2.1 SC - Excavate With Soil Nail Wall
Z2.1 SC - Demobe All Equipment Out Of Zone
Z2.1 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation
Z2.1 SC - Build / Strengthen Shoring Towers With Excavation
Z2.1 SC - Install Under Slab Drainage
Z2.1 SC - Waterproof / Prepare For Mat Slab
FRP Mat Slab Pour #4
FRP Base Isolator Pedestals
Install Base Isolators
FRP Concourse Pour #4
FRP Concourse Pour #5
Z2.1 SC - Concourse MEP Homerun
FRP Interior Walls/Columns
Column and Beam cure
Stress PT
Pressure inject/Dry Pack Base isolator/column
Coordinate Removal of Shoring
Z2.1 SC - Remove Shoring As Approved By Engineers
Z2.1 SC - Install Structural Roof Steel
Z2.1 SC - Install Metal Deck
Z2.1 SC - MEP Install Hangers, Blockouts
Z2.1 SC - FRP SOMD
PROJECT ID : CAMS III - 02 18-Jul-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
CAMS III 071423
TASK filter: InCOMPLETE.
Start Finish Total Float
Predecessor Details
22460 Z2.1 AC - Layout Walls / Top Track 10 02-May-24 15-May-24 0
22470 Z2.1 AC - Electrical OH Rough In 10 16-May-24 30-May-24 0
22480 Z2.1 AC - Fire Sprinkler OH Rough In 10 31-May-24 13-Jun-24 0
22490 Z2.1 AC - HVAC / Plumb OH Rough In 15 14-Jun-24 05-Jul-24 0
22500 Z2.1 AC - Door Frame Install 5 08-Jul-24 12-Jul-24 0
22510 Z2.1 AC - Wall Framing & Soffit Framing 15 15-Jul-24 02-Aug-24 0
22520 Z2.1 AC - HVAC Wall Rough In 10 05-Aug-24 16-Aug-24 0
22530 Z2.1 AC - HVAC Insulation 10 19-Aug-24 30-Aug-24 0
22540 Z2.1 AC - Fire Sprinkler Rough In 10 03-Sep-24 16-Sep-24 0
22550 Z2.1 AC - Plumbing Rough In 10 17-Sep-24 30-Sep-24 0
22560 Z2.1 AC - Plumbing Insulation 9 01-Oct-24 11-Oct-24 0
22570 Z2.1 AC - Electrical Rough In 10 14-Oct-24 25-Oct-24 0
22580 Z2.1 AC - Low Voltage & DDC Rough In 10 28-Oct-24 08-Nov-24 0
22590 Z2.1 AC - Cover Inspections 2 11-Nov-24 12-Nov-24 0
22600 Z2.1 AC - Plaster Work In Corridors Of Historic Preservation 15 13-Nov-24 05-Dec-24 0
22610 Z2.1 AC - Sheetrock 9 06-Dec-24 18-Dec-24 0
22620 Z2.1 AC - Tape & Finish 10 19-Dec-24 03-Jan-25 0
22630 Z2.1 AC - Terrazzo Flooring 15 06-Jan-25 24-Jan-25 0
22640 Z2.1 AC - Bathroom Tile Work 10 27-Jan-25 07-Feb-25 0
22650 Z2.1 AC - Paint, First Two Coats 10 10-Feb-25 21-Feb-25 0
22660 Z2.1 AC - ACT Grid 10 24-Feb-25 07-Mar-25 0
22670 Z2.1 AC - Light Fixtures 8 10-Mar-25 19-Mar-25 0
22680 Z2.1 AC - Casework 10 20-Mar-25 02-Apr-25 0
22690 Z2.1 AC - Electrical Trim 10 03-Apr-25 16-Apr-25 0
22700 Z2.1 AC - Plumbing Trim 10 17-Apr-25 30-Apr-25 0
22710 Z2.1 AC - HVAC Trim 10 01-May-25 14-May-25 0
22720 Z2.1 AC - Hang Doors 5 15-May-25 21-May-25 0
22730 Z2.1 AC - Fire Sprinkler Trim 5 22-May-25 29-May-25 0
22740 Z2.1 AC - Drop Ceiling Tile 5 30-May-25 05-Jun-25 0
22750 Z2.1 AC - All Bathroom Fixtures, PTH, TPH, Mirrors 5 06-Jun-25 12-Jun-25 0
22760 Z2.1 AC - Carpet 10 13-Jun-25 26-Jun-25 0
22770 Z2.1 AC - Base 5 27-Jun-25 03-Jul-25 0
22780 Z2.1 AC - TAB / Commissioning 10 07-Jul-25 18-Jul-25 0
22790 Z2.1 AC - Punch / Substantial Completion 10 21-Jul-25 01-Aug-25 0
Zone 2.1 Roof / CourtyardZone 2.1 Roof / CourtyardZone 2.1 Roof / CourtyardZone 2.1 Roof / CourtyardZone 2.1 Roof / CourtyardZone 2.1 Roof / CourtyardZone 2.1 Roof / Courtyard
22800 Z2.1 RC - Remove Windows & Install Doors For Access 15 28-Mar-24 17-Apr-24 0
22810 Z2.1 RC - Waterproof SOMD 10 18-Apr-24 01-May-24 0
22820 Z2.1 RC - Install Roof Insulation 10 02-May-24 15-May-24 203
22830 Z2.1 RC - Install Seismic Joints 20 16-May-24 13-Jun-24 203
22840 Z2.1 RC - Install Drains 10 14-Jun-24 27-Jun-24 203
22850 Z2.1 RC - Install Electrical 10 28-Jun-24 12-Jul-24 203
22860 Z2.1 RC - Install Irrigation 10 15-Jul-24 26-Jul-24 203
22870 Z2.1 RC - Install Organic Material 10 29-Jul-24 09-Aug-24 203
Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D
2023 2024 2025 2026
Z2.1 AC - Layout Walls / Top Track
Z2.1 AC - Electrical OH Rough In
Z2.1 AC - Fire Sprinkler OH Rough In
Z2.1 AC - HVAC / Plumb OH Rough In
Z2.1 AC - Door Frame Install
Z2.1 AC - Wall Framing & Soffit Framing
Z2.1 AC - HVAC Wall Rough In
Z2.1 AC - HVAC Insulation
Z2.1 AC - Fire Sprinkler Rough In
Z2.1 AC - Plumbing Rough In
Z2.1 AC - Plumbing Insulation
Z2.1 AC - Electrical Rough In
Z2.1 AC - Low Voltage & DDC Rough In
Z2.1 AC - Cover Inspections
Z2.1 AC - Plaster Work In Corridors Of Historic Preservation
Z2.1 AC - Sheetrock
Z2.1 AC - Tape & Finish
Z2.1 AC - Terrazzo Flooring
Z2.1 AC - Bathroom Tile Work
Z2.1 AC - Paint, First Two Coats
Z2.1 AC - ACT Grid
Z2.1 AC - Light Fixtures
Z2.1 AC - Casework
Z2.1 AC - Electrical Trim
Z2.1 AC - Plumbing Trim
Z2.1 AC - HVAC Trim
Z2.1 AC - Hang Doors
Z2.1 AC - Fire Sprinkler Trim
Z2.1 AC - Drop Ceiling Tile
Z2.1 AC - All Bathroom Fixtures, PTH, TPH, Mirrors
Z2.1 AC - Carpet
Z2.1 AC - Base
Z2.1 AC - TAB / Commissioning
Z2.1 AC - Punch / Substantial Completion
Z2.1 RC - Remove Windows & Install Doors For Access
Z2.1 RC - Waterproof SOMD
Z2.1 RC - Install Roof Insulation
Z2.1 RC - Install Seismic Joints
Z2.1 RC - Install Drains
Z2.1 RC - Install Electrical
Z2.1 RC - Install Irrigation
Z2.1 RC - Install Organic Material
PROJECT ID : CAMS III - 02 18-Jul-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
CAMS III 071423
TASK filter: InCOMPLETE.
Start Finish Total Float
Predecessor Details
22880 Z2.1 RC - Install Finish Products - Lights / Benches 10 12-Aug-24 23-Aug-24 203
22890 Z2.1 RC - Landscape 10 26-Aug-24 09-Sep-24 203
22900 Z2.1 RC - Finish Windows / Doors 10 10-Sep-24 23-Sep-24 203
22910 Z2.1 RC - Punchlist / Substantial Completion 10 24-Sep-24 07-Oct-24 203
22920 Z2.1 RC - Turnover 5 08-Oct-24 14-Oct-24 203
G Level Zone 1G Level Zone 1G Level Zone 1G Level Zone 1G Level Zone 1G Level Zone 1G Level Zone 1
Zone 1 Structural - Concourse LevelZone 1 Structural - Concourse LevelZone 1 Structural - Concourse LevelZone 1 Structural - Concourse LevelZone 1 Structural - Concourse LevelZone 1 Structural - Concourse LevelZone 1 Structural - Concourse Level
10270 Z1 SC - Build shoring towers 20 02-Aug-23 29-Aug-23 64
10310 Z1 SC - Transfer Load to shoring towers 5 30-Aug-23 06-Sep-23 94
10314 Z1 SC - Excavate To The Bottom Of (E) Footings 10 07-Sep-23 20-Sep-23 94
10315 Z1 SC - Demo Concrete Walls & Columns 15 21-Sep-23 11-Oct-23 94
10320 Z1 SC - Excavate To Bottom Of New Mat Slab with shoring wall 15 12-Oct-23 01-Nov-23 94
10325 Z1 SC - Install Shoring Wall South Of Sh Line 15 19-Oct-23 08-Nov-23 99
10360 Z1 SC - Add Bracing To Micro Piles While Excavating Down 15 19-Oct-23 08-Nov-23 99
10370 Z1 SC - Under Slab Drainage 10 09-Nov-23 22-Nov-23 99
10380 Z1 SC - Waterproof / Prepare For Mat Slab 5 27-Nov-23 01-Dec-23 99
10400 Z1 SC - FRP Mat Slab #8 15 04-Dec-23 22-Dec-23 99
10405 FRP Base Isolator Pedestals East 5 26-Dec-23 02-Jan-24 107
10406 Install base isolators East 5 03-Jan-24 09-Jan-24 107
10410 FRP Mat Slab #12 15 26-Dec-23 16-Jan-24 99
10415 FRP Base Isolator Pedestals West 5 17-Jan-24 23-Jan-24 99
10416 Install Base Isolators West 5 24-Jan-24 30-Jan-24 99
10420 FRP Concoures #7 10 10-Jan-24 23-Jan-24 107
10425 FRP Concoures #10 10 31-Jan-24 13-Feb-24 99
10427 Z1 SC - MEP Concourse Prep 20 24-Jan-24 20-Feb-24 157
10430 FRP Walls and Columns 25 14-Feb-24 19-Mar-24 99
10435 Wall and Column Cure 15 20-Mar-24 09-Apr-24 99
10440 Z1 SC - Pressure Inject / Dry Pack At Transfer / Column Connections 5 10-Apr-24 16-Apr-24 99
10445 Coordinate removal of Shoring 2 15-Apr-24 16-Apr-24 99
10450 Z1 SC - Remove Shoring towers 13 17-Apr-24 03-May-24 99
Zone 1 Architectural / MEP - Concourse LevelZone 1 Architectural / MEP - Concourse LevelZone 1 Architectural / MEP - Concourse LevelZone 1 Architectural / MEP - Concourse LevelZone 1 Architectural / MEP - Concourse LevelZone 1 Architectural / MEP - Concourse LevelZone 1 Architectural / MEP - Concourse Level
10520 Z1 AC - Layout Walls / Top Track 10 06-May-24 17-May-24 99
10530 Z1 AC - Electrical OH Rough In 15 13-May-24 03-Jun-24 99
10540 Z1 AC - Fire Sprinkler OH Rough In 15 20-May-24 10-Jun-24 99
10550 Z1 AC - HVAC / Plumb OH Rough In 15 28-May-24 17-Jun-24 99
10560 Z1 AC - Door Frame Install 5 04-Jun-24 10-Jun-24 99
10570 Z1 AC - Wall Framing & Soffit Framing 15 11-Jun-24 01-Jul-24 99
10580 Z1 AC - HVAC Wall Rough In 5 18-Jun-24 24-Jun-24 99
10590 Z1 AC - HVAC Insulation 10 25-Jun-24 09-Jul-24 99
10600 Z1 AC - Fire Sprinkler Rough In 10 02-Jul-24 16-Jul-24 99
10610 Z1 AC - Plumbing Rough In 10 24-Jul-24 06-Aug-24 99
10620 Z1 AC - Plumbing Insulation 10 31-Jul-24 13-Aug-24 99
Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D
2023 2024 2025 2026
Z2.1 RC - Install Finish Products - Lights / Benches
Z2.1 RC - Landscape
Z2.1 RC - Finish Windows / Doors
Z2.1 RC - Punchlist / Substantial Completion
Z2.1 RC - Turnover
Z1 SC - Build shoring towers
Z1 SC - Transfer Load to shoring towers
Z1 SC - Excavate To The Bottom Of (E) Footings
Z1 SC - Demo Concrete Walls & Columns
Z1 SC - Excavate To Bottom Of New Mat Slab with shoring wall
Z1 SC - Install Shoring Wall South Of Sh Line
Z1 SC - Add Bracing To Micro Piles While Excavating Down
Z1 SC - Under Slab Drainage
Z1 SC - Waterproof / Prepare For Mat Slab
Z1 SC - FRP Mat Slab #8
FRP Base Isolator Pedestals East
Install base isolators East
FRP Mat Slab #12
FRP Base Isolator Pedestals West
Install Base Isolators West
FRP Concoures #7
FRP Concoures #10
Z1 SC - MEP Concourse Prep
FRP Walls and Columns
Wall and Column Cure
Z1 SC - Pressure Inject / Dry Pack At Transfer / Column Connections
Coordinate removal of Shoring
Z1 SC - Remove Shoring towers
Z1 AC - Layout Walls / Top Track
Z1 AC - Electrical OH Rough In
Z1 AC - Fire Sprinkler OH Rough In
Z1 AC - HVAC / Plumb OH Rough In
Z1 AC - Door Frame Install
Z1 AC - Wall Framing & Soffit Framing
Z1 AC - HVAC Wall Rough In
Z1 AC - HVAC Insulation
Z1 AC - Fire Sprinkler Rough In
Z1 AC - Plumbing Rough In
Z1 AC - Plumbing Insulation
PROJECT ID : CAMS III - 02 18-Jul-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
CAMS III 071423
TASK filter: InCOMPLETE.
Start Finish Total Float
Predecessor Details
10630 Z1 AC - Electrical Rough In 10 07-Aug-24 20-Aug-24 99
10640 Z1 AC - Low Voltage & DDC Rough In 10 14-Aug-24 27-Aug-24 99
10650 Z1 AC - Cover Inspections 2 21-Aug-24 22-Aug-24 99
10660 Z1 AC - Plaster Work In Corridors Of Historic Preservation 15 23-Aug-24 13-Sep-24 99
10670 Z1 AC - Sheetrock 10 30-Aug-24 13-Sep-24 99
10680 Z1 AC - Tape & Finish 10 09-Sep-24 20-Sep-24 99
10690 Z1 AC - Terrazzo Flooring 20 16-Sep-24 11-Oct-24 99
10700 Z1 AC - Kitchen Build Out 10 23-Sep-24 04-Oct-24 99
10710 Z1 AC - Kitchen Appliances 10 30-Sep-24 11-Oct-24 99
10720 Z1 AC - Bathroom Tile Work 10 07-Oct-24 18-Oct-24 99
10730 Z1 AC - Paint, First Two Coats 10 14-Oct-24 25-Oct-24 99
10740 Z1 AC - ACT Grid 10 21-Oct-24 01-Nov-24 99
10750 Z1 AC - Light Fixtures 10 28-Oct-24 08-Nov-24 99
10760 Z1 AC - Casework 10 11-Nov-24 22-Nov-24 99
10770 Z1 AC - Electrical Trim 10 18-Nov-24 03-Dec-24 99
10780 Z1 AC - Plumbing Trim 5 25-Nov-24 03-Dec-24 99
10790 Z1 AC - HVAC Trim 5 04-Dec-24 10-Dec-24 99
10800 Z1 AC - Hang Doors 5 11-Dec-24 17-Dec-24 99
10810 Z1 AC - Fire Sprinkler Trim 5 18-Dec-24 24-Dec-24 99
10820 Z1 AC - Drop Ceiling Tile 10 26-Dec-24 09-Jan-25 99
10830 Z1 AC - All Bathroom Fixtures, PTH, TPH, Mirrors 5 03-Jan-25 09-Jan-25 99
10840 Z1 AC - Carpet 10 10-Jan-25 23-Jan-25 99
10850 Z1 AC - Base 10 17-Jan-25 30-Jan-25 99
10860 Z1 AC - TAB / Commissioning 20 24-Jan-25 20-Feb-25 99
10870 Z1 AC - Punch / Substantial Completion 15 21-Feb-25 13-Mar-25 99
10880 Z1 AC - Grind & Polish Terrazzo 5 04-Nov-24 08-Nov-24 99
G Level Zone 3G Level Zone 3G Level Zone 3G Level Zone 3G Level Zone 3G Level Zone 3G Level Zone 3
Zone 3 StructuralZone 3 StructuralZone 3 StructuralZone 3 StructuralZone 3 StructuralZone 3 StructuralZone 3 Structural
Exterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro Piles
30430 Z3 SC - Core / Cut Wall At Needle Beam Locations Along NEA 15 05-Jul-23 A 31-Jul-23 55
30435 Z3 SC - Install soil nails in lagging wall 5 25-Jul-23 31-Jul-23 55
30440 Z3 SC - Install Shoring Towers 15 01-Aug-23 21-Aug-23 100
30450 Z3 SC - Transfer Load Into Shoring Towers Along NE1 5 22-Aug-23 28-Aug-23 100
30460 Z3 SC - Excavate Down To Bottom Of Footings 10 29-Aug-23 12-Sep-23 100
30470 Z3 SC - Abatement Of Exterior Wall 5 13-Sep-23 19-Sep-23 100
30480 Z3 SC - Demo Exterior Wall 10 20-Sep-23 03-Oct-23 100
InteriorInteriorInteriorInteriorInteriorInteriorInterior
30530 Z3 SC - Drill Micro Piles 30 05-Jul-23 A 17-Aug-23 -20
30540 Z3 SC - Build Shoring Towers 20 26-Jul-23 22-Aug-23 64
30550 Z3 SC - Stress Transfer Beams 5 16-Aug-23 22-Aug-23 114
30560 Z3 SC - Transfer Load To Shoring Towers 5 23-Aug-23 29-Aug-23 114
30570 Z3 SC - Excavate To Bottom Of Footings 10 30-Aug-23 13-Sep-23 114
30580 Z3 SC - Demo Columns / Walls / Footings 15 04-Oct-23 24-Oct-23 100
Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D
2023 2024 2025 2026
Z1 AC - Electrical Rough In
Z1 AC - Low Voltage & DDC Rough In
Z1 AC - Cover Inspections
Z1 AC - Plaster Work In Corridors Of Historic Preservation
Z1 AC - Sheetrock
Z1 AC - Tape & Finish
Z1 AC - Terrazzo Flooring
Z1 AC - Kitchen Build Out
Z1 AC - Kitchen Appliances
Z1 AC - Bathroom Tile Work
Z1 AC - Paint, First Two Coats
Z1 AC - ACT Grid
Z1 AC - Light Fixtures
Z1 AC - Casework
Z1 AC - Electrical Trim
Z1 AC - Plumbing Trim
Z1 AC - HVAC Trim
Z1 AC - Hang Doors
Z1 AC - Fire Sprinkler Trim
Z1 AC - Drop Ceiling Tile
Z1 AC - All Bathroom Fixtures, PTH, TPH, Mirrors
Z1 AC - Carpet
Z1 AC - Base
Z1 AC - TAB / Commissioning
Z1 AC - Punch / Substantial Completion
Z1 AC - Grind & Polish Terrazzo
Z3 SC - Core / Cut Wall At Needle Beam Locations Along NEA
Z3 SC - Install soil nails in lagging wall
Z3 SC - Install Shoring Towers
Z3 SC - Transfer Load Into Shoring Towers Along NE1
Z3 SC - Excavate Down To Bottom Of Footings
Z3 SC - Abatement Of Exterior Wall
Z3 SC - Demo Exterior Wall
Z3 SC - Drill Micro Piles
Z3 SC - Build Shoring Towers
Z3 SC - Stress Transfer Beams
Z3 SC - Transfer Load To Shoring Towers
Z3 SC - Excavate To Bottom Of Footings
Z3 SC - Demo Columns / Walls / Footings
PROJECT ID : CAMS III - 02 18-Jul-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
CAMS III 071423
TASK filter: InCOMPLETE.
Start Finish Total Float
Predecessor Details
30590 Z3 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation20 25-Oct-23 21-Nov-23 100
30600 Z3 SC - Build / Strengthen Shoring Towers With Excavation 15 08-Nov-23 30-Nov-23 146
30610 Z3 SC - Excavate Utility Trench 5 22-Nov-23 30-Nov-23 100
30620 Z3 SC - Under Slab Drainage 5 01-Dec-23 07-Dec-23 146
30630 Z3 SC - Waterproof / Prepare For Mat Slab 5 08-Dec-23 14-Dec-23 146
30640 Z3 SC - FRP Utility Trench Pour #5 7 15-Dec-23 26-Dec-23 146
30645 FRP Mat Slab Pour #6 15 27-Dec-23 17-Jan-24 146
30646 FRP Base Isolator Pedestals North 5 18-Jan-24 24-Jan-24 156
30655 FRP Mat Slab Pour #7 15 18-Jan-24 07-Feb-24 146
30656 FRP Base Isolator Pedestals South 5 08-Feb-24 14-Feb-24 146
30657 FRP Concourse Pour #6 15 15-Feb-24 06-Mar-24 146
30670 Z3 SC - FRP Walls and columns 15 07-Mar-24 27-Mar-24 146
30680 Wall and Column Cure 10 28-Mar-24 10-Apr-24 146
30750 Z3 SC - Pressure Inject / Dry Pack At Transfer / Column Connections 10 11-Apr-24 24-Apr-24 146
30760 Z3 SC - Coordinate Removal Of Remaining Shoring 2 18-Apr-24 19-Apr-24 146
30770 Z3 SC - Remove Remaining Shoring 3 22-Apr-24 24-Apr-24 146
Zone 3 Architectural / MEPZone 3 Architectural / MEPZone 3 Architectural / MEPZone 3 Architectural / MEPZone 3 Architectural / MEPZone 3 Architectural / MEPZone 3 Architectural / MEP
30780 Z3 AC - Layout Walls / Top Track 10 25-Apr-24 08-May-24 146
30790 Z3 AC - Electrical OH Rough In 10 02-May-24 15-May-24 146
30800 Z3 AC - Fire Sprinkler OH Rough In 10 09-May-24 22-May-24 146
30810 Z3 AC - HVAC / Plumb OH Rough In 10 16-May-24 30-May-24 146
30820 Z3 AC - Door Frame Install 5 23-May-24 30-May-24 146
30830 Z3 AC - Wall Framing & Soffit Framing 15 31-May-24 20-Jun-24 146
30840 Z3 AC - HVAC Wall Rough In 10 07-Jun-24 20-Jun-24 146
30850 Z3 AC - HVAC Insulation 10 14-Jun-24 27-Jun-24 146
30860 Z3 AC - Fire Sprinkler Rough In 10 21-Jun-24 05-Jul-24 146
30870 Z3 AC - Plumbing Rough In 10 28-Jun-24 12-Jul-24 146
30880 Z3 AC - Plumbing Insulation 10 08-Jul-24 19-Jul-24 146
30890 Z3 AC - Electrical Rough In 10 15-Jul-24 26-Jul-24 146
30900 Z3 AC - Low Voltage & DDC Rough In 10 22-Jul-24 02-Aug-24 146
30910 Z3 AC - Cover Inspections 2 29-Jul-24 30-Jul-24 146
30920 Z3 AC - Plaster Work In Corridors Of Historic Preservation 15 31-Jul-24 20-Aug-24 146
30930 Z3 AC - Sheetrock 10 07-Aug-24 20-Aug-24 146
30940 Z3 AC - Tape & Finish 10 14-Aug-24 27-Aug-24 146
30950 Z3 AC - Terrazzo Flooring 15 21-Aug-24 11-Sep-24 146
30960 Z3 AC - Bathroom Tile Work 10 28-Aug-24 11-Sep-24 146
30970 Z3 AC - Paint, First Two Coats 10 05-Sep-24 18-Sep-24 146
30980 Z3 AC - ACT Grid 10 12-Sep-24 25-Sep-24 146
30990 Z3 AC - Light Fixtures 10 19-Sep-24 02-Oct-24 146
31000 Z3 AC - Casework 10 26-Sep-24 09-Oct-24 146
31010 Z3 AC - Electrical Trim 10 03-Oct-24 16-Oct-24 146
31020 Z3 AC - Plumbing Trim 10 10-Oct-24 23-Oct-24 146
31030 Z3 AC - HVAC Trim 10 17-Oct-24 30-Oct-24 146
Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D
2023 2024 2025 2026
Z3 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation
Z3 SC - Build / Strengthen Shoring Towers With Excavation
Z3 SC - Excavate Utility Trench
Z3 SC - Under Slab Drainage
Z3 SC - Waterproof / Prepare For Mat Slab
Z3 SC - FRP Utility Trench Pour #5
FRP Mat Slab Pour #6
FRP Base Isolator Pedestals North
FRP Mat Slab Pour #7
FRP Base Isolator Pedestals South
FRP Concourse Pour #6
Z3 SC - FRP Walls and columns
Wall and Column Cure
Z3 SC - Pressure Inject / Dry Pack At Transfer / Column Connections
Z3 SC - Coordinate Removal Of Remaining Shoring
Z3 SC - Remove Remaining Shoring
Z3 AC - Layout Walls / Top Track
Z3 AC - Electrical OH Rough In
Z3 AC - Fire Sprinkler OH Rough In
Z3 AC - HVAC / Plumb OH Rough In
Z3 AC - Door Frame Install
Z3 AC - Wall Framing & Soffit Framing
Z3 AC - HVAC Wall Rough In
Z3 AC - HVAC Insulation
Z3 AC - Fire Sprinkler Rough In
Z3 AC - Plumbing Rough In
Z3 AC - Plumbing Insulation
Z3 AC - Electrical Rough In
Z3 AC - Low Voltage & DDC Rough In
Z3 AC - Cover Inspections
Z3 AC - Plaster Work In Corridors Of Historic Preservation
Z3 AC - Sheetrock
Z3 AC - Tape & Finish
Z3 AC - Terrazzo Flooring
Z3 AC - Bathroom Tile Work
Z3 AC - Paint, First Two Coats
Z3 AC - ACT Grid
Z3 AC - Light Fixtures
Z3 AC - Casework
Z3 AC - Electrical Trim
Z3 AC - Plumbing Trim
Z3 AC - HVAC Trim
PROJECT ID : CAMS III - 02 18-Jul-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
CAMS III 071423
TASK filter: InCOMPLETE.
Start Finish Total Float
Predecessor Details
31040 Z3 AC - Hang Doors 5 24-Oct-24 30-Oct-24 146
31050 Z3 AC - Fire Sprinkler Trim 5 31-Oct-24 06-Nov-24 146
31060 Z3 AC - Drop Ceiling Tile 5 07-Nov-24 13-Nov-24 146
31070 Z3 AC - All Bathroom Fixtures, PTH, TPH, Mirrors 5 14-Nov-24 20-Nov-24 146
31080 Z3 AC - Carpet 10 21-Nov-24 06-Dec-24 146
31090 Z3 AC - Base 5 02-Dec-24 06-Dec-24 146
31100 Z3 AC - TAB / Commissioning 10 09-Dec-24 20-Dec-24 146
31110 Z3 AC - Punch / Substantial Completion 10 23-Dec-24 07-Jan-25 146
Zone 3 Elevator (001)Zone 3 Elevator (001)Zone 3 Elevator (001)Zone 3 Elevator (001)Zone 3 Elevator (001)Zone 3 Elevator (001)Zone 3 Elevator (001)
31130 Z3 Elev - Excavate New Pit 10 01-Dec-23 14-Dec-23 100
31140 Z3 Elev - Waterproof Pits 10 15-Dec-23 29-Dec-23 100
31150 Z3 Elev - FRP Pits 10 02-Jan-24 15-Jan-24 100
31160 Z3 Elev - MEP Rough In For New Walls / Elevator Pit 15 16-Jan-24 05-Feb-24 100
31170 Z3 Elev - Elevator Shaft Buildout / Exterior Walls 15 06-Feb-24 26-Feb-24 100
31180 Z3 Elev - Install Rails Or Modify As Necessary 10 27-Feb-24 11-Mar-24 100
31190 Z3 Elev - Finish Exterior Shaft Walls & Install Elect 10 12-Mar-24 25-Mar-24 100
31200 Z3 Elev - Adjust Cars & Test 15 19-Aug-24 09-Sep-24 -2
31210 Z3 Elev - Commission Elevator / State Inspections - Workman's 2 10-Sep-24 11-Sep-24 -2
31220 Z3 Elev - Receive Elevator Permit 1 12-Sep-24 12-Sep-24 20
Zone 3 NE Central StairZone 3 NE Central StairZone 3 NE Central StairZone 3 NE Central StairZone 3 NE Central StairZone 3 NE Central StairZone 3 NE Central Stair
31230 Z3 NE Str - Install Collector Steel Under 1st Floor 10 07-Mar-24 20-Mar-24 233
31240 Z3 NE Str - Shore Stairs As Necessary 5 21-Mar-24 27-Mar-24 233
31250 Z3 NE Str - Cut New Opening For Stair From G Level To Level 1 5 28-Mar-24 03-Apr-24 233
31260 Z3 NE Str - Install Steel At Opening 10 04-Apr-24 17-Apr-24 233
31270 Z3 NE Str - Install Stair From G To 1 15 18-Apr-24 08-May-24 233
31280 Z3 NE Str - Rebar & Pour Landing 10 09-May-24 22-May-24 233
31290 Z3 NE Str - Install Handrails 10 23-May-24 06-Jun-24 233
31300 Z3 NE Str - Frame Walls 10 07-Jun-24 20-Jun-24 233
31310 Z3 NE Str - MEP Rough In 10 21-Jun-24 05-Jul-24 233
31320 Z3 NE Str - Cover Walls & Ceilings 10 08-Jul-24 19-Jul-24 233
31330 Z3 NE Str - Terrazzo Flooring / Treads 15 22-Jul-24 09-Aug-24 233
31340 Z3 NE Str - Paint / Final Finishes 5 12-Aug-24 16-Aug-24 233
31350 Z3 NE Str - Punch / Substantial Completion 10 19-Aug-24 30-Aug-24 233
G Level Zone 4G Level Zone 4G Level Zone 4G Level Zone 4G Level Zone 4G Level Zone 4G Level Zone 4
Zone 4 StructuralZone 4 StructuralZone 4 StructuralZone 4 StructuralZone 4 StructuralZone 4 StructuralZone 4 Structural
Exterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro PilesExterior Micro Piles
40370 Z4 SC - Drill Micro Piles 10 01-Aug-23 14-Aug-23 55
40380 Z4 SC - Core / Cut Wall At Needle Beam Locations 5 15-Aug-23 21-Aug-23 80
40390 Z4 SC - Install Shoring Towers 15 23-Aug-23 13-Sep-23 79
40400 Z4 SC - Transfer Load Into Shoring Towers 5 14-Sep-23 20-Sep-23 79
40430 Z4 SC - Excavate Down To Bottom Of Footings 10 21-Sep-23 04-Oct-23 79
40440 Z4 SC - Abatement Of Exterior Wall 5 05-Oct-23 11-Oct-23 79
Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D
2023 2024 2025 2026
Z3 AC - Hang Doors
Z3 AC - Fire Sprinkler Trim
Z3 AC - Drop Ceiling Tile
Z3 AC - All Bathroom Fixtures, PTH, TPH, Mirrors
Z3 AC - Carpet
Z3 AC - Base
Z3 AC - TAB / Commissioning
Z3 AC - Punch / Substantial Completion
Z3 Elev - Excavate New Pit
Z3 Elev - Waterproof Pits
Z3 Elev - FRP Pits
Z3 Elev - MEP Rough In For New Walls / Elevator Pit
Z3 Elev - Elevator Shaft Buildout / Exterior Walls
Z3 Elev - Install Rails Or Modify As Necessary
Z3 Elev - Finish Exterior Shaft Walls & Install Elect
Z3 Elev - Adjust Cars & Test
Z3 Elev - Commission Elevator / State Inspections - Workman's
Z3 Elev - Receive Elevator Permit
Z3 NE Str - Install Collector Steel Under 1st Floor
Z3 NE Str - Shore Stairs As Necessary
Z3 NE Str - Cut New Opening For Stair From G Level To Level 1
Z3 NE Str - Install Steel At Opening
Z3 NE Str - Install Stair From G To 1
Z3 NE Str - Rebar & Pour Landing
Z3 NE Str - Install Handrails
Z3 NE Str - Frame Walls
Z3 NE Str - MEP Rough In
Z3 NE Str - Cover Walls & Ceilings
Z3 NE Str - Terrazzo Flooring / Treads
Z3 NE Str - Paint / Final Finishes
Z3 NE Str - Punch / Substantial Completion
Z4 SC - Drill Micro Piles
Z4 SC - Core / Cut Wall At Needle Beam Locations
Z4 SC - Install Shoring Towers
Z4 SC - Transfer Load Into Shoring Towers
Z4 SC - Excavate Down To Bottom Of Footings
Z4 SC - Abatement Of Exterior Wall
PROJECT ID : CAMS III - 02 18-Jul-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
CAMS III 071423
TASK filter: InCOMPLETE.
Start Finish Total Float
Predecessor Details
40450 Z4 SC - Demo Exterior Wall 10 12-Oct-23 25-Oct-23 79
40460 Z4 SC - Excavation To Bottom Of Mat Slab 15 01-Dec-23 21-Dec-23 75
InteriorInteriorInteriorInteriorInteriorInteriorInterior
40510 Z4 SC - Micro Pile Mobilization 2 18-Aug-23* 21-Aug-23 -20
40520 Z4 SC - Drill Micro Piles 30 22-Aug-23 03-Oct-23 -20
40530 Z4 SC - Build Shoring Towers 20 13-Sep-23 10-Oct-23 70
40540 Z4 SC - Stress Transfer Beams 5 11-Oct-23 17-Oct-23 70
40550 Z4 SC - Transfer Load To Shoring Towers 5 18-Oct-23 24-Oct-23 70
40560 Z4 SC - Excavate To Bottom Of Footings 10 25-Oct-23 07-Nov-23 70
40570 Z4 SC - Demo Columns / Walls / Footings 15 08-Nov-23 30-Nov-23 70
40580 Z4 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation15 01-Dec-23 21-Dec-23 70
40590 Z4 SC - Build / Strengthen Shoring Towers With Excavation 15 08-Dec-23 29-Dec-23 70
40600 Z4 SC - Excavate Utility Trench 5 22-Dec-23 29-Dec-23 70
40610 Z4 SC - Under Slab Drainage 5 02-Jan-24 08-Jan-24 70
40620 Z4 SC - Waterproof / Prepare For Mat Slab 5 09-Jan-24 15-Jan-24 70
40630 Z4 SC - FRP Utility Trench Pour #9 10 06-Feb-24 19-Feb-24 70
40635 FRP Mat Slab Pour #10 15 20-Feb-24 11-Mar-24 70
40640 FRP Mat Slab Pour #11 15 12-Mar-24 01-Apr-24 70
40645 FRP Base Isolator Pedestals North 5 12-Mar-24 18-Mar-24 85
40650 Install Base Isolators North 5 19-Mar-24 25-Mar-24 85
40655 FRP Base Isolator Pedestals South 5 02-Apr-24 08-Apr-24 70
40660 Install Base Isolators South 5 09-Apr-24 15-Apr-24 70
40665 FRP Concourse Pour #9 10 16-Apr-24 29-Apr-24 70
40670 FRP Concourse pour #11 10 30-Apr-24 13-May-24 70
40675 FRP Columns and Walls 25 14-May-24 18-Jun-24 70
40680 Columns and Walls Cure 20 19-Jun-24 17-Jul-24 70
40740 Z4 SC - Pressure Inject / Dry Pack At Transfer / Column Connections 10 18-Jul-24 31-Jul-24 70
40750 Z4 SC - Coordinate Removal Of Remaining Shoring 2 30-Jul-24 31-Jul-24 70
40760 Z4 SC - Remove Remaining Shoring 8 01-Aug-24 12-Aug-24 70
Zone 4 Architectural / MEPZone 4 Architectural / MEPZone 4 Architectural / MEPZone 4 Architectural / MEPZone 4 Architectural / MEPZone 4 Architectural / MEPZone 4 Architectural / MEP
40770 Z4 AC - Layout Walls / Top Track 10 13-Aug-24 26-Aug-24 70
40780 Z4 AC - Electrical OH Rough In 10 20-Aug-24 03-Sep-24 70
40790 Z4 AC - Fire Sprinkler OH Rough In 10 27-Aug-24 10-Sep-24 70
40800 Z4 AC - HVAC / Plumb OH Rough In 10 04-Sep-24 17-Sep-24 70
40810 Z4 AC - Door Frame Install 5 11-Sep-24 17-Sep-24 70
40820 Z4 AC - Wall Framing & Soffit Framing 15 18-Sep-24 08-Oct-24 70
40830 Z4 AC - HVAC Wall Rough In 10 25-Sep-24 08-Oct-24 70
40840 Z4 AC - HVAC Insulation 10 02-Oct-24 15-Oct-24 70
40850 Z4 AC - Fire Sprinkler Rough In 10 09-Oct-24 22-Oct-24 70
40860 Z4 AC - Plumbing Rough In 10 16-Oct-24 29-Oct-24 70
40870 Z4 AC - Plumbing Insulation 10 23-Oct-24 05-Nov-24 70
40880 Z4 AC - Electrical Rough In 10 30-Oct-24 12-Nov-24 70
40890 Z4 AC - Low Voltage & DDC Rough In 10 06-Nov-24 19-Nov-24 70
Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D
2023 2024 2025 2026
Z4 SC - Demo Exterior Wall
Z4 SC - Excavation To Bottom Of Mat Slab
Z4 SC - Micro Pile Mobilization
Z4 SC - Drill Micro Piles
Z4 SC - Build Shoring Towers
Z4 SC - Stress Transfer Beams
Z4 SC - Transfer Load To Shoring Towers
Z4 SC - Excavate To Bottom Of Footings
Z4 SC - Demo Columns / Walls / Footings
Z4 SC - Excavate At Lifts Required For Shoring Towers To Bottom Of Foundation
Z4 SC - Build / Strengthen Shoring Towers With Excavation
Z4 SC - Excavate Utility Trench
Z4 SC - Under Slab Drainage
Z4 SC - Waterproof / Prepare For Mat Slab
Z4 SC - FRP Utility Trench Pour #9
FRP Mat Slab Pour #10
FRP Mat Slab Pour #11
FRP Base Isolator Pedestals North
Install Base Isolators North
FRP Base Isolator Pedestals South
Install Base Isolators South
FRP Concourse Pour #9
FRP Concourse pour #11
FRP Columns and Walls
Columns and Walls Cure
Z4 SC - Pressure Inject / Dry Pack At Transfer / Column Connections
Z4 SC - Coordinate Removal Of Remaining Shoring
Z4 SC - Remove Remaining Shoring
Z4 AC - Layout Walls / Top Track
Z4 AC - Electrical OH Rough In
Z4 AC - Fire Sprinkler OH Rough In
Z4 AC - HVAC / Plumb OH Rough In
Z4 AC - Door Frame Install
Z4 AC - Wall Framing & Soffit Framing
Z4 AC - HVAC Wall Rough In
Z4 AC - HVAC Insulation
Z4 AC - Fire Sprinkler Rough In
Z4 AC - Plumbing Rough In
Z4 AC - Plumbing Insulation
Z4 AC - Electrical Rough In
Z4 AC - Low Voltage & DDC Rough In
PROJECT ID : CAMS III - 02 18-Jul-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
CAMS III 071423
TASK filter: InCOMPLETE.
Start Finish Total Float
Predecessor Details
40900 Z4 AC - Cover Inspections 2 13-Nov-24 14-Nov-24 70
40910 Z4 AC - Plaster Work In Corridors Of Historic Preservation 15 15-Nov-24 09-Dec-24 70
40920 Z4 AC - Sheetrock 10 22-Nov-24 09-Dec-24 70
40930 Z4 AC - Tape & Finish 10 03-Dec-24 16-Dec-24 70
40940 Z4 AC - Terrazzo Flooring 15 10-Dec-24 31-Dec-24 70
40950 Z4 AC - Bathroom Tile Work 10 17-Dec-24 31-Dec-24 70
40960 Z4 AC - Paint, First Two Coats 10 24-Dec-24 08-Jan-25 70
40970 Z4 AC - ACT Grid 10 02-Jan-25 15-Jan-25 70
40980 Z4 AC - Light Fixtures 10 09-Jan-25 22-Jan-25 70
40990 Z4 AC - Casework 10 16-Jan-25 29-Jan-25 70
41000 Z4 AC - Electrical Trim 10 23-Jan-25 05-Feb-25 70
41010 Z4 AC - Plumbing Trim 10 30-Jan-25 12-Feb-25 70
41020 Z4 AC - HVAC Trim 10 06-Feb-25 19-Feb-25 70
41030 Z4 AC - Hang Doors 5 13-Feb-25 19-Feb-25 70
41040 Z4 AC - Fire Sprinkler Trim 5 20-Feb-25 26-Feb-25 70
41050 Z4 AC - Drop Ceiling Tile 5 27-Feb-25 05-Mar-25 70
41060 Z4 AC - All Bathroom Fixtures, PTH, TPH, Mirrors 5 06-Mar-25 12-Mar-25 70
41070 Z4 AC - Carpet 10 13-Mar-25 26-Mar-25 70
41080 Z4 AC - Base 5 20-Mar-25 26-Mar-25 70
41090 Z4 AC - TAB / Commissioning 10 27-Mar-25 09-Apr-25 70
41100 Z4 AC - Punch / Substantial Completion 10 10-Apr-25 23-Apr-25 70
Zone 4 Elevator (002)Zone 4 Elevator (002)Zone 4 Elevator (002)Zone 4 Elevator (002)Zone 4 Elevator (002)Zone 4 Elevator (002)Zone 4 Elevator (002)
41110 Z4 Elev 2 - Elevator Shaft Demo As Required / Reshore 10 02-Jan-24 15-Jan-24 87
41120 Z4 Elev 2 - Excavate New Pit 10 16-Jan-24 29-Jan-24 87
41130 Z4 Elev 2 - Waterproof Pits 10 30-Jan-24 12-Feb-24 87
41140 Z4 Elev 2 - FRP Pits 10 13-Feb-24 26-Feb-24 87
41150 Z4 Elev 2 - MEP Rough In For New Walls / Elevator Pit 15 27-Feb-24 18-Mar-24 87
41160 Z4 Elev 2 - Elevator Shaft Buildout / Exterior Walls 15 19-Mar-24 08-Apr-24 87
41170 Z4 Elev 2 - Install Rails Or Modify As Necessary 10 09-Apr-24 22-Apr-24 87
41180 Z4 Elev 2 - Finish Exterior Shaft Walls & Install Elect 10 23-Apr-24 06-May-24 87
41190 Z4 Elev 2 - Adjust Cars & Test 10 12-Sep-24 25-Sep-24 -2
41200 Z4 Elev 2 - Commission Elevator / State Inspections 2 26-Sep-24 27-Sep-24 8
41210 Z4 Elev 2 - Receive Elevator Permit 1 30-Sep-24 30-Sep-24 8
Zone 4 Elevator (009)Zone 4 Elevator (009)Zone 4 Elevator (009)Zone 4 Elevator (009)Zone 4 Elevator (009)Zone 4 Elevator (009)Zone 4 Elevator (009)
41220 Z4 Elev 9 - Elevator Shaft Demo As Required / Reshore 10 02-Jan-24 15-Jan-24 97
41230 Z4 Elev 9 - Excavate New Pit 10 30-Jan-24 12-Feb-24 87
41240 Z4 Elev 9 - Waterproof Pits 10 13-Feb-24 26-Feb-24 87
41250 Z4 Elev 9 - FRP Pits 10 27-Feb-24 11-Mar-24 87
41260 Z4 Elev 9 - MEP Rough In For New Walls / Elevator Pit 15 12-Mar-24 01-Apr-24 87
41270 Z4 Elev 9 - Elevator Shaft Buildout / Exterior Walls 15 02-Apr-24 22-Apr-24 87
41280 Z4 Elev 9 - Install Rails Or Modify As Necessary 10 23-Apr-24 06-May-24 87
41290 Z4 Elev 9 - Finish Exterior Shaft Walls & Install Elect 10 07-May-24 20-May-24 87
41300 Z4 Elev 9 - Adjust Cars & Test 10 26-Sep-24 09-Oct-24 -2
Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D
2023 2024 2025 2026
Z4 AC - Cover Inspections
Z4 AC - Plaster Work In Corridors Of Historic Preservation
Z4 AC - Sheetrock
Z4 AC - Tape & Finish
Z4 AC - Terrazzo Flooring
Z4 AC - Bathroom Tile Work
Z4 AC - Paint, First Two Coats
Z4 AC - ACT Grid
Z4 AC - Light Fixtures
Z4 AC - Casework
Z4 AC - Electrical Trim
Z4 AC - Plumbing Trim
Z4 AC - HVAC Trim
Z4 AC - Hang Doors
Z4 AC - Fire Sprinkler Trim
Z4 AC - Drop Ceiling Tile
Z4 AC - All Bathroom Fixtures, PTH, TPH, Mirrors
Z4 AC - Carpet
Z4 AC - Base
Z4 AC - TAB / Commissioning
Z4 AC - Punch / Substantial Completion
Z4 Elev 2 - Elevator Shaft Demo As Required / Reshore
Z4 Elev 2 - Excavate New Pit
Z4 Elev 2 - Waterproof Pits
Z4 Elev 2 - FRP Pits
Z4 Elev 2 - MEP Rough In For New Walls / Elevator Pit
Z4 Elev 2 - Elevator Shaft Buildout / Exterior Walls
Z4 Elev 2 - Install Rails Or Modify As Necessary
Z4 Elev 2 - Finish Exterior Shaft Walls & Install Elect
Z4 Elev 2 - Adjust Cars & Test
Z4 Elev 2 - Commission Elevator / State Inspections
Z4 Elev 2 - Receive Elevator Permit
Z4 Elev 9 - Elevator Shaft Demo As Required / Reshore
Z4 Elev 9 - Excavate New Pit
Z4 Elev 9 - Waterproof Pits
Z4 Elev 9 - FRP Pits
Z4 Elev 9 - MEP Rough In For New Walls / Elevator Pit
Z4 Elev 9 - Elevator Shaft Buildout / Exterior Walls
Z4 Elev 9 - Install Rails Or Modify As Necessary
Z4 Elev 9 - Finish Exterior Shaft Walls & Install Elect
Z4 Elev 9 - Adjust Cars & Test
PROJECT ID : CAMS III - 02 18-Jul-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
CAMS III 071423
TASK filter: InCOMPLETE.
Start Finish Total Float
Predecessor Details
41310 Z4 Elev 9 - Commission Elevator / State Inspections 2 10-Oct-24 11-Oct-24 -2
41320 Z4 Elev 9 - Receive Elevator Permit 1 14-Oct-24 14-Oct-24 -2
Zone 4 NW Central StairZone 4 NW Central StairZone 4 NW Central StairZone 4 NW Central StairZone 4 NW Central StairZone 4 NW Central StairZone 4 NW Central Stair
41330 Z4 Str C - Install Floor Steel Under First Floor 10 14-May-24 28-May-24 215
41340 Z4 Str C - Shore Stairs As Necessary 5 29-May-24 04-Jun-24 215
41350 Z4 Str C - Install Steel Deck At Opening 10 05-Jun-24 18-Jun-24 215
41360 Z4 Str C - Rebar & Pour Landing 10 19-Jun-24 02-Jul-24 215
41370 Z4 Str C - Install Handrails 10 03-Jul-24 17-Jul-24 215
41380 Z4 Str C - Frame Walls 10 18-Jul-24 31-Jul-24 215
41390 Z4 Str C - MEP Rough In 10 01-Aug-24 14-Aug-24 215
41400 Z4 Str C - Cover Walls & Ceilings 5 15-Aug-24 21-Aug-24 215
41410 Z4 Str C - Terrazzo Flooring / Treads 15 22-Aug-24 12-Sep-24 215
41420 Z4 Str C - Paint / Final Finishes 5 13-Sep-24 19-Sep-24 215
41430 Z4 Str C - Punch / Substantial Completion 5 20-Sep-24 26-Sep-24 215
G Level Zone 5.1G Level Zone 5.1G Level Zone 5.1G Level Zone 5.1G Level Zone 5.1G Level Zone 5.1G Level Zone 5.1
Zone 5.1 StructuralZone 5.1 StructuralZone 5.1 StructuralZone 5.1 StructuralZone 5.1 StructuralZone 5.1 StructuralZone 5.1 Structural
52210 Z5.1 SC - Install Shoring Towers 20 30-Aug-23 27-Sep-23 64
52220 Z5.1 SC - Transfer Building Loads To Shoring Towers 2 28-Sep-23 29-Sep-23 64
52230 Z5.1 SC - Install Shotcrete, Soil Nail Wall At '77 Building 20 02-Oct-23 27-Oct-23 121
52240 Z5.1 SC - Excavate With Soil Nail Wall 20 09-Oct-23 03-Nov-23 121
52260 Z5.1 SC - Cross brace towers wtih Excavation 20 16-Oct-23 10-Nov-23 121
52270 Z5.1 SC - Install Under Slab Drainage 10 13-Nov-23 28-Nov-23 121
52280 Z5.1 SC - Waterproof / Prepare For Mat Slab 5 29-Nov-23 05-Dec-23 121
52282 FRP Mat Slab Pour #16 15 06-Dec-23 27-Dec-23 121
52284 FRP Base Isolator Pedestals 5 28-Dec-23 04-Jan-24 121
52286 Install Base Isolators 5 05-Jan-24 11-Jan-24 121
52288 FRP Concourse Pour #13 10 12-Jan-24 25-Jan-24 121
52290 FRP Concourse Pour #14 10 23-Jan-24 05-Feb-24 121
52292 MEP Homerun 20 06-Feb-24 04-Mar-24 178
52302 FRP Columns and Walls 15 06-Feb-24 26-Feb-24 121
52308 Column/Beam Cure 20 27-Feb-24 25-Mar-24 148
52318 Stress PT Beams 5 26-Mar-24 01-Apr-24 148
52323 Pressure Inject/Pack Base isolators 5 02-Apr-24 08-Apr-24 148
52333 Coordinate Removal of shoring towers 2 09-Apr-24 10-Apr-24 148
52343 Remove shoring towers 3 11-Apr-24 15-Apr-24 148
52400 Z5.1 SC - Install Structural Roof Steel 15 27-Feb-24 18-Mar-24 121
52410 Z5.1 SC - Install Metal Deck 7 19-Mar-24 27-Mar-24 121
52415 MEP Install Hangers 5 28-Mar-24 03-Apr-24 121
52420 Z5.1 SC - FRP SOMD 10 04-Apr-24 17-Apr-24 121
5.1 Interiror Hearing room5.1 Interiror Hearing room5.1 Interiror Hearing room5.1 Interiror Hearing room5.1 Interiror Hearing room5.1 Interiror Hearing room5.1 Interiror Hearing room
52430 Z5.1 Hr - Layout Walls / Top Track 10 23-May-24 06-Jun-24 121
52440 Z5.1 Hr - Electrical OH Rough In 10 31-May-24 13-Jun-24 121
Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D
2023 2024 2025 2026
Z4 Elev 9 - Commission Elevator / State Inspections
Z4 Elev 9 - Receive Elevator Permit
Z4 Str C - Install Floor Steel Under First Floor
Z4 Str C - Shore Stairs As Necessary
Z4 Str C - Install Steel Deck At Opening
Z4 Str C - Rebar & Pour Landing
Z4 Str C - Install Handrails
Z4 Str C - Frame Walls
Z4 Str C - MEP Rough In
Z4 Str C - Cover Walls & Ceilings
Z4 Str C - Terrazzo Flooring / Treads
Z4 Str C - Paint / Final Finishes
Z4 Str C - Punch / Substantial Completion
Z5.1 SC - Install Shoring Towers
Z5.1 SC - Transfer Building Loads To Shoring Towers
Z5.1 SC - Install Shotcrete, Soil Nail Wall At '77 Building
Z5.1 SC - Excavate With Soil Nail Wall
Z5.1 SC - Cross brace towers wtih Excavation
Z5.1 SC - Install Under Slab Drainage
Z5.1 SC - Waterproof / Prepare For Mat Slab
FRP Mat Slab Pour #16
FRP Base Isolator Pedestals
Install Base Isolators
FRP Concourse Pour #13
FRP Concourse Pour #14
MEP Homerun
FRP Columns and Walls
Column/Beam…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .