Attachment D Description of Base Bid and Alternates.docx

DOCX document 14 KB Posted

Attached to
I-84: Farewell Bend Chain Up Paving Project
Solicitation number
S-73000-00012503
Issued by
Multnomah County, Oregon

About this file

This is an Attachment D document from the Oregon Department of Transportation (ODOT) describing the base bid and additive alternates for the I-84: Farewell Bend Chain Up Paving Project. The project encompasses pavement rehabilitation on Interstate 84, with the primary scope involving 4-inch asphalt concrete pavement (ACP) cold plane removal and inlay of 12-foot wide chain up areas for both eastbound and westbound lanes, extending 6 inches into the existing 10-foot paved shoulder to create a clean joint. The base bid includes temporary traffic control for both directions. The bid submission deadline is March 20, 2025, with posting date of February 24, 2025. Bidders are required to review Attachments A (Special Provisions) and B (Plans) for detailed technical specifications and project requirements.

The contract award will be based on the lowest responsive bid combining totals from the base bid and two additive alternates selected in alphabetical order if funding permits. Add Alternate A involves 2-inch ACP cold plane pavement removal and inlay of the eastbound existing 10-foot shoulder, while Add Alternate B involves the same work for the westbound 10-foot shoulder. ODOT has limited funding available for this project, necessitating the tiered bid structure to maximize construction work completion within available budget constraints. All alternates, if selected for inclusion, must comply with contract specifications and plans. The specific award amount and funding source are not detailed in this attachment, requiring reference to additional procurement documents.

View the file

Other files

File Type Posted
00012503 Intent To Award.xlsx XLSX spreadsheet
Attachment A Special Provisions~1.pdf PDF
Attachment B Plans~5.pdf PDF
Invitation.To.Bid~9.docx DOCX document
00012503 Preliminary Results.xlsx XLSX spreadsheet
Attachment C Bid Pricing Form~11.xlsx XLSX spreadsheet
Notice of Intent to Award~7.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT D

DESCRIPTION OF BASE BID AND ALTERNATES

ODOT has limited funding available for construction of this project and the funding may not be adequate to construct the entire project. Two (2) additive alternates are being used to maximize the work that can be completed within the available funding limits. If funding allows additive alternates will be selected in the alphabetical order, in which they are listed below. The contract award will be based on the lowest responsive bid combining totals from the base bid, add alternate A and add alternate B.

BASE BID: Includes temporary traffic control and construction of 4” grind/inlay of both Eastbound and Westbound 12’ wide chain up widening areas, extending 6” into existing 10’ paved shoulder in order to create a clean joint as described in Attachment A (Special Provisions) and Attachment B (Plans).

ALL ADD ALTERNATES IF SELECTED FOR INCLUSION IN THE PROJECT WILL COMPLY WITH CONTRACT SPECIFICATIONS AND PLANS.

ADD ALTERNATE A

I-84 Eastbound Paved Shoulder: Construct 2” ACP cold plane pavement removal and inlay of Eastbound existing 10’ shoulder as described in Attachment A (Special Provisions) & Attachment B (Plans)

ADD ALTERNATE B

I-84 Westbound Paved Shoulder: Construct 2” ACP cold plane pavement removal and inlay of Westbound 10’ shoulder as described in Attachment A (Special Provisions) and Attachment B (Plans).

File details come from the government source that posted it. Updated .