Attachment C UFC 1-200-01 DOD Building Code.pdf
PDF 672 KB Posted
- Attached to
- MDG Building 383 Ambulance Bay Enclosure Federal contract opportunity
- Solicitation number
- FA309924Q0022
About this file
This document is a government solicitation for the enclosure of the Ambulance Bay at Building 383 at Laughlin AFB in Texas. The work includes furnishing all labor, materials, and equipment to complete the project in accordance with the plans, specifications, and applicable Unified Facilities Criteria (UFC) guidelines. The total period of performance is 75 calendar days, divided into two Notices to Proceed. The acquisition is a total small business set-aside under NAICS code 236220, with a $45M small business size standard. An organized site visit is scheduled for September 12, 2024. The government anticipates awarding a firm-fixed price contract as a result of this solicitation. All prospective offerors must be registered in the System for Award Management (SAM) to be eligible for award.
View the file
Other files for this federal contract opportunity
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UFC 1-200-01
01 September 2022
Change 3, 26 February 2024
UNIFIED FACILITIES CRITERIA (UFC)
APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED
DOD BUILDING CODE
This Page Intentionally Left Blank
UNIFIED FACILITIES CRITERIA (UFC)
DOD BUILDING CODE
Any copyrighted material included in this UFC is identified at its point of use.
Use of the copyrighted material apart from this UFC must have the permission of the copyright holder.
Indicate the Military Department Preparing Activity responsible for the document.
U.S. ARMY CORPS OF ENGINEERS
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND (Preparing Activity)
AIR FORCE CIVIL ENGINEER CENTER
Record of Changes (changes are indicated by \1\ ... /1/)
Change No. Date Location 1 24 FEB 2023 1-3.3.3 replaced entire paragraph; removed UFC 1-202-
01 reference from Appendix C 2 12 JUN 2023 1-4.4 Add paragraph; Chapter 3 and Appendix C:
removed references to OUSD Memorandum, Floodplain Management on DoD Installations;
3 26 FEB 2024 1-4.5, Inclusion of NDAA PL 117-263 Sec. 2810 Consideration of Installation of Integrated Solar Roofing.
US Army Base name changes, and minor admin.
This UFC supersedes UFC 1-200-01, dated 01 Oct 2020.
FOREWORD
The Unified Facilities Criteria (UFC) system is prescribed by MIL-STD 3007 and provides planning, design, construction, sustainment, restoration, and modernization criteria, and applies to the Military Departments, the Defense Agencies, and the DoD Field Activities in accordance with USD (AT&L) Memorandum dated 29 May 2002. UFC will be used for all DoD projects and work for other customers where appropriate. All construction outside of the United States, its territories, and possessions is also governed by Status of Forces Agreements (SOFA), Host Nation Funded Construction Agreements (HNFA), and in some instances, Bilateral Infrastructure Agreements (BIA). Therefore, the acquisition team must ensure compliance with the most stringent of the UFC, the SOFA, the HNFA, and the BIA, as applicable.
UFC are living documents and will be periodically reviewed, updated, and made available to users as part of the Military Department’s responsibility for providing technical criteria for military construction. Headquarters, U.S. Army Corps of Engineers (HQUSACE), Naval Facilities Engineering Systems Command (NAVFAC), and Air Force Civil Engineer Center (AFCEC) are responsible for administration of the UFC system. Technical content of UFC is the responsibility of the cognizant DoD working group. Defense Agencies should contact the respective DoD Working Group for document interpretation and improvements. Recommended changes with supporting rationale may be sent to the respective DoD working group by submitting a Criteria Change Request (CCR) via the Internet site listed below.
UFC are effective upon issuance and are distributed only in electronic media from the following source:
• Whole Building Design Guide website https://www.wbdg.org/ffc/dod.
Refer to UFC 1-200-01, DoD Building Code, for implementation of new issuances on projects.
AUTHORIZED BY:
PETE G. PEREZ, P.E., SES
Chief, Engineering and Construction U.S. Army Corps of Engineers
R. DAVID CURFMAN, P.E., SES
Chief Engineer Naval Facilities Engineering Systems Command
DAVID H. DENTINO, SES
Deputy Director of Civil Engineers DCS/Logistics, Engineering & Force Protection (HAF/A4C) HQ United States Air Force
MICHAEL McANDREW, SES Deputy Assistant Secretary of Defense (Construction) Office of the Secretary of Defense http://www.wbdg.org/pdfs/ufc_implementation.pdf https://www.wbdg.org/ffc/dod i
TABLE OF CONTENTS
INTRODUCTION
1-1 BACKGROUND
1-2 PURPOSE AND SCOPE
1-3 APPLICABILITY
1-3.1 Implementation, Administration, and Enforcement
1-3.2 Levels of Construction
1-3.3 Facilities in Support of Military Operations
1-3.4 Waivers and Exemptions
1-3.5 UFC Hierarchy
1-4 OVERARCHING CRITERIA OR REGULATORY REQUIREMENTS
1-4.1 Vending Facilities for the Blind
1-4.2 Nursing and Lactation Rooms
1-4.3 Investigation of Microgrid Feasibility
1-4.4 Government Fleet Electric Vehicle Charging Capability
1-4.5 Photovoltaic Roofs
1-5 UFC AUTHORITIES
1-5.1 ESEP
1-5.2 Building Official / Authority Having Jurisdiction (BO/AHJ)
1-5.3 Component Technical Representative (CTR)
1-6 GENERAL BUILDING REQUIREMENTS
1-6.1 Building Codes
1-6.2 Referenced Codes and Substitutions
1-6.3 Other Criteria
1-7 CYBERSECURITY
1-8 NON-GOVERNMENT STANDARD MODIFICATIONS
1-9 GLOSSARY
1-10 REFERENCES
MODIFICATIONS TO IBC
2-1 CHAPTER 1 – SCOPE AND ADMINISTRATION [SUPPLEMENT]
2-1.1 Section 101 – SCOPE AND GENERAL REQUIREMENTS
2-1.2 Section 102 – APPLICABILITY ii
2-1.3 Section 103 – CODE COMPLIANCE AGENCY [Deletion]
2-1.4 Section 104 – DUTIES AND POWERS OF BUILDING OFFICIAL
2-1.5 Section 105 – PERMITS [Deletion]
2-1.6 Section 106 – FLOOR AND ROOF DESIGN LOADS [Deletion]
2-1.7 Section 107 – CONSTRUCTION DOCUMENTS [Deletion]
2-1.8 Section 108 – TEMPORARY STRUCTURES AND USES [Deletion]. . 15
2-1.9 Section 109 – FEES [Deletion]
2-1.10 Section 111 – CERTIFICATE OF OCCUPANCY [Deletion]
2-1.11 Section 113 – MEANS OF APPEALS [Deletion]
2-1.12 Section 114 – VIOLATIONS [Deletion]
2-1.13 Section 115 – STOP WORK ORDER [Deletion]
2-1.14 Section 116 – UNSAFE STRUCTURES AND EQUIPMENT [Deletion]
2-2 CHAPTER 2 – DEFINITIONS [SUPPLEMENT]
2-3 CHAPTER 3 – OCCUPANCY CLASSIFICATION AND USE
[SUPPLEMENT]
2-4 CHAPTER 4 – SPECIAL DETAILED REQUIREMENTS BASED ON
OCCUPANCY AND USE [SUPPLEMENT]
2-5 CHAPTER 5 – GENERAL BUILDING HEIGHTS AND AREAS
[SUPPLEMENT]
2-5.1 Section 506 – BUILDING AREA
2-6 CHAPTER 6 – TYPES OF CONSTRUCTION [SUPPLEMENT]
2-7 CHAPTER 7 – FIRE AND SMOKE PROTECTION FEATURES
[SUPPLEMENT]
2-8 CHAPTER 8 – INTERIOR FINISHES [REPLACEMENT]
2-9 CHAPTER 9 – FIRE PROTECTION AND LIFE SAFETY SYSTEMS
[REPLACEMENT]
2-10 CHAPTER 10 – MEANS OF EGRESS [REPLACEMENT]
2-11 CHAPTER 11 – ACCESSIBILITY [REPLACEMENT]
2-11.1 Electrical vehicle charging stations
2-11.2 Water bottle-filling stations
2-12 CHAPTER 12 – INTERIOR ENVIRONMENT [SUPPLEMENT]
2-12.1 Section 1203 – TEMPERATURE CONTROL
2-12.2 Section 1206 – SOUND TRANSMISSION iii
2-12.3 Section 1207 – ENHANCED CLASSROOM ACOUSTICS
[REPLACEMENT]
2-12.4 Section 1208 – INTERIOR SPACE DIMENSIONS
2-13 CHAPTER 13 – ENERGY EFFICIENCY [REPLACEMENT]
2-14 CHAPTER 14 – EXTERIOR WALLS [SUPPLEMENT]
2-15 CHAPTER 15 – ROOF ASSEMBLIES AND ROOFTOP
STRUCTURES [SUPPLEMENT]
2-16 CHAPTER 16 – STRUCTURAL DESIGN [SUPPLEMENT]
2-16.1 Section 1604 – GENERAL DESIGN REQUIREMENTS
2-16.2 Section 1612 – FLOOD LOADS [Supplement]
2-17 CHAPTER 17 – SPECIAL INSPECTIONS AND TESTS
[SUPPLEMENT]
2-17.1 Section 1701 – GENERAL
2-17.2 Section 1704 – SPECIAL INSPECTIONS AND TESTS, CONTRACTOR RESPONSIBILITY AND STRUCTURAL
OBSERVATION
2-18 CHAPTER 18 – SOILS AND FOUNDATIONS [SUPPLEMENT]
2-18.1 Section 1804 – EXCAVATION, GRADING, AND FILL
2-19 CHAPTER 19 – CONCRETE [SUPPLEMENT]
2-20 CHAPTER 20 – ALUMINUM [SUPPLEMENT]
2-21 CHAPTER 21 – MASONRY [SUPPLEMENT]
2-22 CHAPTER 22 – STEEL [SUPPLEMENT]
2-23 CHAPTER 23 – WOOD [SUPPLEMENT]
2-23.1 Section 2301 – GENERAL
2-23.2 Section 2303 – MINIMUM STANDARDS AND QUALITY
2-24 CHAPTER 24 – GLASS AND GLAZING [SUPPLEMENT]
2-25 CHAPTER 25 – GYPSUM BOARD, GYPSUM PANEL PRODUCTS
AND PLASTER
2-26 CHAPTER 26 – PLASTIC [SUPPLEMENT]
2-27 CHAPTER 27 – ELECTRICAL [SUPPLEMENT]
2-28 CHAPTER 28 – MECHANICAL SYSTEMS [SUPPLEMENT]
2-29 CHAPTER 29 – PLUMBING SYSTEMS [SUPPLEMENT]
2-30 CHAPTER 30 – ELEVATORS AND CONVEYING SYSTEMS
[REPLACEMENT]
2-31 CHAPTER 31 – SPECIAL CONSTRUCTION
iv
2-32 CHAPTER 32 – ENCROACHMENTS INTO THE PUBLIC RIGHT-OF-
WAY
2-33 CHAPTER 33 – SAFEGUARDS DURING CONSTRUCTION
[SUPPLEMENT]
2-34 CHAPTER 34 – RESERVED [DELETION]
2-35 CHAPTER 35 – REFERENCED STANDARDS [SUPPLEMENT]
2-36 APPENDICES [DELETION]
MODIFICATIONS TO IEBC
3-1 CHAPTER 1 – SCOPE AND ADMINISTRATION
3-1.1 Section 101 – SCOPE AND GENERAL REQUIREMENTS
3-1.2 Section 102 – APPLICABILITY
3-1.3 Section 103 – CODE COMPLIANCE AGENCY [Deletion]
3-1.4 Section 104 – DUTIES AND POWERS OF CODE OFFICIAL [Deletion]
3-1.5 Section 105 – PERMITS [Deletion]
3-1.6 Section 106 – CONSTRUCTION DOCUMENTS [Deletion]
3-1.7 Section 108 – FEES [Deletion]
3-1.8 Section 110 – CERTIFICATE OF OCCUPANCY [Deletion]
3-1.9 Section 112 – MEANS OF APPEALS [Deletion]
3-1.10 Section 113 – VIOLATIONS [Deletion]
3-1.11 Section 114 – STOP WORK ORDER [Deletion]
3-1.12 Section 115 – UNSAFE STRUCTURES AND EQUIPMENT [Supplement]
3-1.13 Section 116 – EMERGENCY MEASURES [Deletion]
3-1.14 Section 117 – DEMOLITION [Deletion]
3-2 CHAPTER 2 – DEFINITIONS [SUPPLEMENT]
3-3 CHAPTER 3 – PROVISIONS FOR ALL COMPLIANCE METHODS
[SUPPLEMENT]
3-3.1 Section 302 – GENERAL PROVISIONS
3-3.2 Section 304 – STRUCTURAL DESIGN LOADS AND EVALUATION
AND DESIGN PROCEDURES
3-3.3 Section 306 – ACCESSIBILITY FOR EXISTING BUILDINGS [Replacement]
3-3.4 Section 307 – SMOKE ALARMS [Replacement]
3-3.5 Section 308 – CARBON MONOXIDE DETECTION [Replacement] v
3-4 CHAPTER 4 – REPAIRS [SUPPLEMENT]
3-4.1 Section 401 – GENERAL
3-4.2 Section 403 – FIRE PROTECTION [Replacement]
3-4.3 Section 404 – MEANS OF EGRESS [Replacement]
3-5 CHAPTER 5 – PRESCRIPTIVE COMPLIANCE METHOD
[SUPPLEMENT]
3-5.1 Section 501 – GENERAL
3-5.2 Section 502 – ADDITIONS
3-5.3 Section 503 – ALTERATIONS
3-5.4 Section 506 – CHANGE OF OCCUPANCY
3-5.5 Section 507 – HISTORIC BUILDINGS
3-6 CHAPTER 6 – CLASSIFICATION OF WORK
3-7 CHAPTER 7 – ALTERATIONS – LEVEL 1 [SUPPLEMENT]
3-7.1 Section 701 – GENERAL
3-7.2 Section 702 – BUILDING ELEMENTS AND MATERIALS [Supplement]
3-7.3 Section 703 – FIRE PROTECTION [Replacement]
3-7.4 Section 704 – MEANS OF EGRESS [Replacement]
3-7.5 Section 706 – STRUCTURAL
3-8 CHAPTER 8 – ALTERATIONS – LEVEL 2 [SUPPLEMENT]
3-8.1 Section 802 – BUILDING ELEMENTS AND MATERIALS [Supplement]
3-8.2 Section 803 – FIRE PROTECTION [Replacement]
3-8.3 Section 804 – MEANS OF EGRESS [Replacement]
3-9 CHAPTER 9 – ALTERATIONS – LEVEL 3 [SUPPLEMENT]
3-9.1 Section 903 – BUILDING ELEMENTS AND MATERIALS
3-9.2 Section 904 – FIRE PROTECTION [Replacement]
3-9.3 Section 905 – MEANS OF EGRESS [Replacement]
3-10 CHAPTER 10 – CHANGE OF OCCUPANCY [SUPPLEMENT]
3-10.1 Section 1001 – GENERAL
3-10.2 Section 1002 – SPECIAL USE AND OCCUPANCY [Replacement]
3-10.3 Section 1007 – ELECTRICAL
3-10.4 Section 1009 – PLUMBING vi
3-10.5 Section 1011 – CHANGE OF OCCUPANCY CLASSIFICATION [Replacement]
3-11 CHAPTER 11 – ADDITIONS [SUPPLEMENT]
3-11.1 Section 1101 – GENERAL
3-11.2 Section 1102 – HEIGHTS AND AREAS
3-12 CHAPTER 12 – HISTORIC BUILDINGS [SUPPLEMENT]
3-12.1 Section 1201 – GENERAL
3-12.2 Section 1203 – FIRE SAFETY [Replacement]
3-12.3 Section 1204 – CHANGE OF OCCUPANCY [Supplement]
3-13 CHAPTER 13 – PERFORMANCE COMPLIANCE METHODS
[SUPPLEMENT]
3-13.1 Section 1301 – GENERAL
3-14 CHAPTER 14 – RELOCATED OR MOVED BUILDINGS
3-15 CHAPTER 15 – CONSTRUCTION SAFEGUARDS
3-16 CHAPTER 16 – REFERENCED STANDARDS [SUPPLEMENT]
3-17 APPENDICES [DELETION]
3-18 RESOURCES [DELETION]
CORROSION PREVENTION AND CONTROL
4-1 GENERAL
4-1.1 Definition of Corrosion
4-1.2 Identification of Project Environmental Severity Classification
4-1.3 Corrosion Prone Locations
4-1.4 Requirements for Corrosion Prone Locations
4-1.5 Design Geometries
4-1.6 Environmental Severity Factors
4-1.7 System, Component, and Material Design Requirements
APPENDIX A ESC FOR DOD LOCATIONS
APPENDIX B GLOSSARY
B-1 ACRONYMS
B-2 DEFINITION OF TERMS
APPENDIX C REFERENCES
TABLES
Table 1-1 Policy Related to Physical Security vii
Table A-1 ESC for United States, Its Territories and Possessions
Table A-2 ESC for Outside United States, Its Territories and Possessions viii
INTRODUCTION
1-1 BACKGROUND.
Unified Facilities Criteria (UFC) provide common requirements across DoD for safety, sustainability, durability, and functionality for DoD facilities. UFC incorporate a combination of consensus building codes, DoD-defined technical and user requirements, and applicable statutory and regulatory requirements.
1-2 PURPOSE AND SCOPE.
UFC 1-200-01 represents the foundational document of the UFC program in providing general building requirements and overarching criteria, establishing the use of consensus building codes and standards, establishing criteria implementation rules and protocols (including core UFC), and identifying unique military criteria. In accordance with the authority in MIL-STD-3007G, UFC are prepared by DoD committees called Discipline Working Group (DWG), and are published by the Military Services under the authority of the Engineering Senior Executive Panel (ESEP), comprised of the following:
• Deputy Assistant Secretary of Defense (Construction) Office of the Secretary of Defense
• Chief, Engineering and Construction, Headquarters United States Army Corps of Engineers (HQ USACE)
• Chief Engineer, Naval Facilities Engineering Systems Command
(NAVFAC)
• Headquarters US Air Force, Deputy Director of Civil Engineers DCS/Logistics, Engineering & Force Protection (HAF/A4C)
1-3 APPLICABILITY.
This UFC applies to the planning, design, construction, sustainment, restoration, and modernization of DoD-owned facilities. It is applicable to all methods of project delivery and levels of construction as defined below. For facilities supporting military operations see Paragraph 1-3.3.
1-3.1 Implementation, Administration, and Enforcement.
UFC and their referenced codes and Criteria are effective upon issuance for projects as follows:
• Design-Bid-Build projects that have not proceeded beyond 35% design completion.
• Design-Build projects that have not proceeded beyond date of Request for Proposal (RFP) issuance. When an RFP is issued in multiple phases or steps use the date of the last phase of the RFP issuance.
• Projects that have a delay, either planned or unintentional, of more than 18 months between design completion and the solicitation of offers for construction must be re-evaluated to determine if any design revision is necessary due to changes in criteria (including codes and standards) or site infrastructure (for example, water supply for fixed fire suppression systems, water for hose stream allowances, or fire department vehicle access). Note: The evaluation must also include retroactive requirements that have been included in the new editions of the criteria.
1-3.2 Levels of Construction.
1-3.2.1 Permanent Construction.
Permanent facilities must follow Chapter 2 of this UFC, which contains modifications to the IBC. Buildings and facilities are considered permanent construction unless meeting other definitions herein. Permanent construction is intended to address a level of quality and durability to achieve a life expectancy of more than 25 years.
1-3.2.2 Temporary Construction.
In accordance with the IBC Section 3103, temporary construction includes structures erected for a period less than 180 days. Temporary structures must conform to the structural strength, fire safety, means of egress, accessibility, light, ventilation and sanitary requirements of the IBC, as modified in Chapter 2 of this UFC. Extension of temporary construction occupancy or usage 180 days or beyond requires a written justification request and approval from the BO/ AHJ. Extension approvals may be renewed at the discretion of the BO/AHJ; however, occupancy or facility usage cannot occur beyond 5 years from date of initial occupancy.
1-3.3 Facilities in Support of Military Operations.
Use the following UFC for facilities used in support of military operations. These UFC are self-contained documents and contain all design requirements for the respective subjects. The UFC hierarchy stated in paragraph 1-3.5, and subparagraphs does not apply to these UFC. These UFC apply to all DoD components involved with planning, design, construction and renovation of non-permanent facilities, both new construction and renovations to non-permanent facilities (where renovation does not convert the facility to permanent), used by US military and DoD civilian personnel in support of Military Operations, actions with written Operation Orders (OPORDS); examples include Kinetic actions, Disaster Recovery, Humanitarian Assistance, and Defense Support to Civil Authorities.
1-3.3.1 UFC 1-201-01.
Use UFC 1-201-01 for planning, design, construction and renovation of non-permanent facilities used by US military and DoD civilian personnel in support of military operations.
1-3.3.2 UFC 1-201-02.
Use UFC 1-201-02 to assess existing facilities for life safety and habitability for potential occupancy by DoD personnel in support of military operations. Requirements for preliminary evaluations do not apply when forces occupying the facility are engaged in actual combat operations.
1-3.3.3 \1\ Host Nation Facilities.
Use the International Building Code® (IBC) for planning, design and construction of all facilities built for Host Nation personnel use outside of the United States and its territories and possessions. Use the IBC in conjunction with Status of Forces agreements (SOFA), bilateral agreements or other Host Nation (HN) agreements. /1/
1-3.4 Waivers and Exemptions.
A waiver provides authority to deviate from a criteria requirement for a specific period, typically 12 months. An exemption provides authority to deviate from a requirement indefinitely. Refer to MIL-STD-3007 for the waiver and exemption request and approval process.
1-3.5 UFC Hierarchy.
UFC 1-200-01 is the overarching document for buildings and facilities owned by DoD.
UFC 1-200-01 directs the use of the International Building Code® (IBC), the International Existing Building Code® (IEBC), International Green Construction Code® (IgCC), Core UFC, other UFC as applicable to the building, facility, structure, or system, and Facility Criteria (FC) as they pertain to the applicable DoD Component.
1-3.5.1 UFC 3- Series.
The UFC 3- Series and FC 3- Series (simply referred to as UFC 3- Series) provide discipline specific criteria requirements for the various engineering disciplines.
• If conflict occurs between two UFC within the UFC 3- Series, the requirements of the UFC that is more detailed pertaining to that specific building, facility, structure, or system take precedence.
1-3.5.2 UFC 4- Series.
The UFC 4- Series and FC 4- Series (simply referred to as UFC 4- Series) provide requirements for multi-disciplinary and facility-specific design.
• If conflict occurs between two UFC within the UFC 4- Series, the requirements of the UFC that is more detailed pertaining to that specific building, facility, structure, or system take precedence.
• If conflict occurs between a UFC 4- Series and a UFC 3- Series, the requirements of the UFC 4- Series take precedence.
1-4 OVERARCHING CRITERIA OR REGULATORY REQUIREMENTS.
Design and Construction must comply with Public Laws (P.L.), Executive Orders (E.O.), Code of Federal Regulations (CFR), Department of Defense Instructions (DoDI), Department of Defense Manuals (DoDM), and Department of Defense Directives (DoDD) or other higher authority documents as applicable.
1-4.1 Vending Facilities for the Blind.
Verify with the using activity the requirement to provide blind-operated vending facilities in compliance with the Randolph-Sheppard Act and DoDI 1125.03. This requirement generally applies in buildings that are over 15,000 square feet (1,400 square meters) that will contain over 100 employees, but may also apply in other situations at the discretion of the using activity.
1-4.2 Nursing and Lactation Rooms.
Provide a private space for nursing mothers as required by the Office of the Undersecretary of Defense (OUSD) Memorandum, Department-Wide Policy for Nursing and Lactation Rooms at military installations and DoD facilities. Use the Office of Personnel Management (OPM) Guide for Establishing a Federal Nursing Mother’s Program to implement best practices for creating a successful nursing mother’s program, consistent with the demand of the workplace and the needs of the mission.
This space must not be a bathroom, and must be shielded from view and free from intrusion of others. A nursing mother’s space must be functional, with a private space with a place to sit and a flat surface, other than the floor, to place the breast pump and other supplies. Although there are no size or permanency requirements, this space must provide access to electricity for the use of a breast pump, as well as good lighting, a comfortable temperature, and proper ventilation; and be near a source of hot and cold running water. In addition, comply with any command-specific policy applicable to this requirement or applicable to the establishment of a working mothers program within the facility.
1-4.3 Investigation of Microgrid Feasibility.
Planning and design for military construction projects inside the United States must include consideration of the feasibility and cost-effectiveness of installing an energy microgrid as part of the project, including intentional islanding capability of at least seven consecutive days. \2\
1-4.4 Government Fleet Electric Vehicle Charging Capability.
Provide adequate electric charging capability, concurrently, for not less than 15 percent of Government motor vehicles planned to be parked at the facility. /2/ \3\
1-4.5 Photovoltaic Roofs.
Consider the Installation of Integrated Solar Roofing in planning, design, and construction of DoD projects. /3/
1-5 UFC AUTHORITIES.
1-5.1 ESEP.
The ESEP represents the senior technical facilities engineering leadership within each Military Department as identified in paragraph 1-2 and exercises exclusive authority to issue UFC and FC, and to approve waivers and exemptions thereof.
1-5.2 Building Official / Authority Having Jurisdiction (BO/AHJ).
The terms “Building Official” (BO), “Code Official” and “Authority Having Jurisdiction” (AHJ) used in the UFC or FC criteria, reference codes, and standards are synonymous.
The BO/AHJ represents the DoD design and construction agent responsible for accomplishing the project, and exercises authority to interpret and apply criteria to work in progress, evaluate compliance with criteria, and accept finished work that is in compliance. Chapter 2, Section 104, Duties and Powers of the Building Official, defines the authorities of the BO/AHJ. This authority does not include approval of waivers or exemptions to criteria.
1-5.3 Component Technical Representative (CTR).
The CTR represents the project sponsor or customers and exercises authority to establish project requirements on behalf of the user or facility owner in the following cases:
• When the Building Official / Authority Having Jurisdiction (BO/AHJ) has identified more than one option satisfies criteria and allows user preference, such as for different system choices that offer varying levels of performance, durability, compatibility, compatibility with other systems, esthetics, or the like. This authority would not apply where in conflict with requirements for installation-wide networks, architectural standards, or similar standards established by the installation or Component with jurisdiction of the installation.
• When the BO/AHJ has identified an approved equivalent standard that satisfies the intent of criteria (see Chapter 2, paragraph 104.11), such as a material or component meeting a host-nation standard in a foreign location.
• When the BO/AHJ has identified a design option is not specifically addressed in criteria.
1-6 GENERAL BUILDING REQUIREMENTS.
1-6.1 Building Codes.
Use 2021 IBC and 2021 IEBC as follows:
• Use IBC, including all published errata, as the building code for DoD, except as modified by this UFC, other UFC, and FC. Where a paragraph in any chapter of IBC references a paragraph in a different chapter, modify the referenced chapter as described in CHAPTER 2.
• Use IEBC, including published errata, except as modified by this UFC, other UFC, and FC. Where a paragraph in any chapter of IEBC references a paragraph in a different chapter, modify the referenced chapter as described in CHAPTER 3.
1-6.2 Referenced Codes and Substitutions.
Treat references in the DoD Building Code (see Paragraph 2-1.1) and the DoD Existing Building Code (see Paragraph 3-1.1) to other codes as follows:
• Dismiss references to the International Fuel Gas Code® (IFGC), as IFGC is not adopted. UFC 3-430-05 is used for gaseous fuel distribution, UFC 3- 460-01 is used for liquid fuel storage and distribution and specific NFPA codes are directly referenced by appropriate application in UFCs.
• References to the International Mechanical Code® (IMC) are references to UFC 3-410-01, which cites IMC.
• References to the International Plumbing Code® (IPC) are references to UFC 3-420-01, which cites IPC.
• Dismiss references to the International Property Maintenance Code® (IPMC), as IPMC is not adopted.
• References to the International Fire Code® (IFC) are references to UFC 3- 600-01, which cites NFPA 1.
• References to the International Energy Conservation Code® (IECC) are references to UFC 1-200-02, which cites IECC.
• References to the International Green Construction Code® (IgCC) are references to UFC 1-200-02, which cites IgCC.
• References to NFPA 70, National Electrical Code® (NEC) are references to UFC 3-501-01, which cites NFPA 70.
• References to the International Residential Code® (IRC) are references to the IRC. See also UFC 3-600-01. The DoD adopts the 2021 edition of the International Code Council (ICC) International Building Code® (IBC) and International Residential Code® (IRC) as the primary voluntary consensus standard for DoD Family Housing. Except as augmented or modified in this UFC, design, construct new, and improve Family Housing in accordance with the following:
− Detached one- and two-family dwellings and multiple attached single-family dwellings (townhouses) not more than three stories above grade plane in height with a separate means of egress and their accessory structures must comply with all sections of the International Residential Code (IRC) and referenced codes and standards (IBC Article 101.2).
− Other housing types must comply with this UFC, which augments the International Building Code® (IBC). This includes primarily multifamily (i.e. apartment style) housing.
1-6.3 Other Criteria.
In addition to IBC as modified in CHAPTER 2, and IEBC as modified in CHAPTER 3, comply with the following criteria.
1-6.3.1 UFC.
Comply with the UFC (latest version, refer to Paragraph 1-3.1) as noted herein.
1-6.3.1.1 Core UFC.
Core UFC are criteria that provide requirements for the majority of traditional building systems that are prevalent on DoD facility construction projects. Core UFC also identify additional criteria such as Antiterrorism, High Performance, and Sustainable Building requirements mandated by law and policy. Comply with the Core UFC listed here.
• 1-200-02, High Performance and Sustainable Building Requirements
• 3-101-01, Architecture
• 3-110-03, Roofing
• 3-120-10, Interior Design
• 3-190-06, Protective Coatings and Paint
• 3-201-01, Civil Engineering
• 3-201-02, Landscape Architecture
• 3-210-10, Low Impact Development
• 3-220-01, Geotechnical Engineering
• 3-230-01, Water Storage and Distribution
• 3-240-01, Wastewater Collection and Treatment
• 3-301-01, Structural Engineering
• 3-401-01, Mechanical Engineering
• 3-410-01, Heating, Ventilating and Air Conditioning
• 3-420-01, Plumbing Systems
• 3-490-06, Elevators
• 3-501-01, Electrical Engineering
• 3-520-01, Interior Electrical Systems
• 3-530-01, Interior and Exterior Lighting Systems and Controls
• 3-550-01, Exterior Electrical Power Distribution
• 3-560-01, Operation and Maintenance: Electrical Safety
• 3-580-01, Telecommunications Interior Infrastructure Planning and Design
• 3-600-01, Fire Protection Engineering for Facilities
• 4-010-01, DoD Minimum Antiterrorism Standards for Buildings
• 4-010-06, Cybersecurity of Facility-Related Control Systems
• 4-021-01, Design and O&M: Mass Notification Systems 1-6.3.1.2 Other UFC.
In addition to the “Core UFC”, comply with other UFC as applicable to the system, structure, or facility type defined in the scope of the construction project.
1-6.3.2 FC.
The designation "FC" is for criteria that are not applicable to all DoD Components.
For example: FC 4-721-10N "Navy and Marine Corps Unaccompanied Housing" has a final "N" designation because it is used by the Navy, including its Component, the U.S.
Marine Corps. FC are applicable only to the DOD Component in the title and are intended for use with unified technical requirements published in UFC. Comply with the FC for the designated facility type and the DoD Component.
1-6.3.3 Specification Requirements.
Use Unified Facilities Guide Specifications (UFGS) for projects, including Design-Build submittals, and in accordance with UFC 1-300-02 no later than 35% design completion for Design-Bid-Build projects or draft Request for Proposals (RFP) completion for Design-Build projects. Download, use, and edit the most current UFGS database available from the Whole Building Design Guide website at https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs. Modify and edit the UFGS as necessary to suit the work required by the specific project, including editing for metric or inch-pound and to reflect the latest proven technology, materials, and methods for the project. Follow Order of Precedence requirements for each Government Design Agent on use of Regional, Agency, Unified, and Other guide specifications. Other guide specifications may be used as a basis for information when https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs not available in the UFGS. Provide these specifications in UFGS format and modified to meet the requirements of UFC 1-300-02.
1-6.3.4 Other Military Criteria.
Military criteria other than those listed in this UFC may be applicable to specific types of structures, building systems, or building occupancies. Such structures, systems, or buildings must meet the additional requirements of applicable military criteria.
1-6.3.4.1 Explosive Safety.
Facilities that involve DoD Ammunition and Explosives (AE) storage, handling, maintenance, manufacture or disposal, as well as facilities within the explosives safety quantity distance (ESQD) arcs of AE facilities, must comply with the requirements found in DoDM 6055.09, as well as implementing Service criteria found in DA PAM 385-64 (Army), NAVSEA OP 5 (Navy and Marine Corps), and DESR6055.09_AFMAN91-201 (Air Force). DoD facilities exposed to potential explosion effects from AE belonging to other nations are also required to meet DoD and Service explosives safety criteria.
Closely coordinate the planning and design of new facilities, and occupation, repair, alteration, and restoration of existing AE-related facilities, or other facilities within ESQD arcs with knowledgeable explosives safety professionals in theater, or with the Services’ Explosives Safety Centers. Coordinate as early as possible in the planning and design process to avoid issues or problems and to ensure compliance. Facility construction or use within ESQD arcs requires review for compliance with explosives safety criteria, and must have either an approved explosives safety site plan or an approved explosives safety deviation. Refer to the DoD Service documents mentioned above for further applicable guidance.
1-6.3.4.2 Facility Systems Safety.
Safety is an important component of maintaining and operating DoD facilities. Consider safety during design. Incorporate a hazards review into the regular design review process to ensure systems safety has been considered at the earliest phases of project development to reduce and mitigate unintentional maintenance and operational hazards. For Army projects, incorporate the safety engineering practices delineated under the Facilities Systems Safety (FASS) program as prescribed under DA PAM 385- 16, to the extent practicable and feasible. For Air Force projects, incorporate the safety engineering practices delineated in DAFMAN 91-203, to the extent practicable and feasible. For Navy, the Designer of Record must follow the concepts from the most current ANSI/ASSP Z590.3. DoD facilities must comply with DoDI 6055.01 and applicable Occupational Safety and Health Administration (OSHA) safety and health standards.
1-6.3.4.3 Antiterrorism.
Antiterrorism is defined as defensive measures used to reduce the vulnerability of individuals and property to terrorist acts. UFC 4-010-01 sets the minimum requirements for DoD buildings, and the Geographic Combatant Commander Antiterrorism Construction Standards address unique requirements specific to their area of responsibility. Refer to UFC 4-010-01 and the Geographic Combatant Commander Antiterrorism Construction Standards for the minimum antiterrorism requirements.
1-6.3.4.4 Physical Security.
Physical security is defined as that part of security concerned with physical measures designed and placed to safeguard personnel; to prevent unauthorized access to installations, equipment, material and documents, and to safeguard them against espionage, sabotage, damage, and theft. Many buildings require some level of physical security. When required, integrate physical measures into the site, building, room, or area as applicable. DoD requirements for physical security related to specific assets are documented in DoD publications, directives, manuals, and instructions. The Services have related documents that implement the DoD policy for the Services. The main DoD documents that contain the physical security requirements for the protection of specific DoD assets are shown in Table 1-1. This does not include the policy documents associated with the protection of nuclear and chemical assets.
Table 1-1 Policy Related to Physical Security
Asset Policy and Documents
Classified Information DoDM 5200.01, Volume 3, DoD Information Security Program:
Protection of Classified Information;
https://www.esd.whs.mil/DD/DoD-Issuances/
Sensitive Compartmented Information (SCI)
DoDM 5105.21-Volume 1, Sensitive Compartmented Information (SCI) Administrative Security Manual: Administration of Information and Information Systems Security;
https://www.esd.whs.mil/DD/DoD-Issuances/
DoDM 5105.21-Volume 2, Sensitive Compartmented Information (SCI) Administrative Security Manual: Administration of Physical Security, Visitor Control, and Technical Security;
https://www.esd.whs.mil/DD/DoD-Issuances/
UFC 4-010-05, SCIF/SAPF Planning, Design, and Construction;
https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010- 05/
Special Access Program (SAP) Information
DoDM 5205.07, Volume 3, DoD Special Access Program (SAP) Security Manual: Physical Security;
https://www.esd.whs.mil/DD/DoD-Issuances/
Arms, Ammunition, and Explosives
DoDM 5100.76, Physical Security of Sensitive Conventional Arms, Ammunition, and Explosives (AA&E);
https://www.esd.whs.mil/DD/DoD-Issuances/ https://www.esd.whs.mil/DD/DoD-Issuances/ https://www.esd.whs.mil/DD/DoD-Issuances/ https://www.esd.whs.mil/DD/DoD-Issuances/ https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010-05/ https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-4-010-05/ https://www.esd.whs.mil/DD/DoD-Issuances/
Asset Policy and Documents
Weapons Systems and Platforms
DoD 5200.08-R, Physical Security Program;
https://www.esd.whs.mil/DD/DoD-Issuances/
Bulk Petroleum Products
Communications Systems
Controlled Inventory Items
1-6.3.4.5 Corrosion Prevention and Control Requirements.
Use the requirements in CHAPTER 4 in conjunction with other UFC requirements to design for durability and provide for a comprehensive corrosion prevention and control strategy.
1-7 CYBERSECURITY.
Plan, design, acquire, execute, and maintain control systems (including systems separate from a utility monitoring and control system) in accordance with UFC 4-010-06, and as required by individual Service Implementation Policy.
1-8 NON-GOVERNMENT STANDARD MODIFICATIONS.
CHAPTER 2 modifies IBC and is organized by the chapter of IBC that each section modifies. CHAPTER 3 modifies IEBC and is organized by the chapter of IEBC that each section modifies. The modifications are one of four actions, according to the following legend:
• [Addition] – Add new section, including new section number, not shown in IBC or IEBC.
• [Deletion] – Delete referenced IBC or IEBC section.
• [Replacement] – Delete referenced IBC or IEBC section or noted portion and replace it with the narrative shown.
• [Supplement] – Add narrative shown as a supplement to the narrative shown in the referenced section of IBC or IEBC.
The section modifiers are identified at the end of the paragraph title. Limited commentary has been added in the chapters. Section designations for such commentary are preceded by a “[C]”, and the commentary narrative is shaded.
1-9 GLOSSARY.
APPENDIX B contains a list of acronyms, abbreviations, and definitions.
1-10 REFERENCES.
APPENDIX C contains a list of references used in this document. The publication date of the code or standard is not included in this document. Unless otherwise specified, the most recent edition of the referenced publication applies.
MODIFICATIONS TO IBC
2-1 CHAPTER 1 – SCOPE AND ADMINISTRATION [SUPPLEMENT].
Use IBC Chapter 1 except as modified below and by UFC 3-301-01.
2-1.1 Section 101 – SCOPE AND GENERAL REQUIREMENTS.
101.1 Title [Replacement]
These regulations are to be known as the DoD Building Code, hereinafter referred to as “this code”.
101.4 Referenced codes [Supplement]
Refer to Paragraph 1-6.2 for referenced codes.
101.4.7 Existing buildings [Replacement]
The provisions of the International Existing Building Code® (IEBC), including the amendments in Chapter 3 of this UFC, apply to the repair, alteration, change of occupancy, addition to and relocation of existing buildings.
2-1.2 Section 102 – APPLICABILITY.
102.1 General [Replacement]
Where there is a conflict between a general requirement and a specific requirement, the specific requirement is applicable. Where, in a specific case, different sections of this code specify different materials, methods of construction or other requirements, the most restrictive govern. Refer to Paragraph 1-3.5 for hierarchy of UFC.
102.2 Other Laws [Replacement]
The provisions of this code does not intend to nullify applicable provisions of local, state, or federal law. In overseas locations the SOFA, HNFA, and in some instances, BIA may govern requirements.
102.4 Referenced codes and standards [Supplement]
Refer to Paragraph 1-6.2 and Paragraph 1-6.3 for referenced codes and criteria.
2-1.3 Section 103 – CODE COMPLIANCE AGENCY [Deletion].
2-1.4 Section 104 – DUTIES AND POWERS OF BUILDING OFFICIAL.
104.1 General [Replacement]
The Building Official/AHJ is a person authorized and directed to enforce the provisions of this code, UFC, or FC. They have the authority to render interpretations of this code, UFC, or FC and to clarify the application of the provisions. Such interpretations will be in compliance with the intent and purpose of this code, UFC, or FC and will not have the effect of waiving or exempting requirements specifically provided for in this code, UFC, or FC. For waiver and exemption process and authority refer to Section 104.10 Waivers and exemptions.
104.10 Waivers and exemptions [Replacement]
Where there are practical difficulties involved in carrying out the provisions of this code, UFC, or FC; the Building Official/AHJ must first find that special individual case or reason that makes the strict letter of this code, UFC, or FC impractical resulting in noncompliance with requirements or an increased risk to: health, accessibility, life and fire safety, structural requirements, or operational requirements. Such cases will be treated as a waiver or exemption. Waivers and exemptions to specific UFC or FC requirements are approved by the Service’s Chief Engineer, Engineering Senior Executive Panel signature authority for the Service. Refer to MIL-STD 3007 for waivers and exemption definitions and for specific requirements for approval.
104.11 Alternative materials, design and methods of construction and equipment [Replacement]
The provisions of this code, UFC, or FC are not intended to prevent the installation of any material or to prohibit any design or method of construction not specifically prescribed by this code, provided that any such alternative has been approved. An alternative material, design, or method of construction may be approved where the Building Official/AHJ finds that the proposed design is satisfactory and complies with the intent of the provisions of this code, UFC, or FC, and that the material, method, or work offered is, for the purpose intended, not less than the equivalent of that prescribed in this code, UFC, or FC in quality, strength, effectiveness, fire resistance, durability, and safety. When the alternative material, design, or method of construction is not
[C] 104.10 Waivers and exemptions [Supplement] Avoid requests for waivers and exemptions if possible. The objective is a criteria- or code-compliant engineering solution for the facility versus a waiver or exemption request. UFC and FC requirements are intended to address code-compliant facility requirements; life, health and safety requirements; property loss prevention; lowest lifecycle cost; and facility operational requirements. For issues dealing with life, health, and safety, cost is not a valid reason to grant a waiver or exemption. Waiving or exempting requirements typically results in increased risk to safety or property loss, increased operational risk, or poor return on investment.
approved, the Building Official/AHJ will respond in writing, stating the reasons why the alternative was not approved.
104.11.1 Research reports [Replacement]
Supporting data, where necessary to assist in the approval of materials or assemblies not specifically provided for in this code, UFC, or FC, must consist of valid research reports from approved sources.
104.11.2 Tests [Replacement]
Whenever there is insufficient evidence of compliance with the provisions of this code, or evidence that a material or method does not conform to the requirements of this code, or in order to substantiate claims for alternative materials or methods, the Building Official/AHJ has the authority to require tests as evidence of compliance to be made without expense to the government. Test methods are as specified in this code, UFC, or FC or by other recognized test standards. In the absence of recognized and accepted test methods, the Building Official/AHJ must approve the testing procedures.
Perform tests by an approved agency. Building Official/AHJ retains reports of such tests.
104.11.3 Overseas locations [Addition]
In overseas locations where the SOFA, HNFA, OEBGD, or BIA may govern requirements, the Building Official/AHJ will review the situation and determine what, if any, measures are appropriate to take to compensate for measures not allowed by the host nation or that present practical difficulties involved in carrying out the provisions.
Measures taken must not lessen quality, strength, effectiveness, fire resistance, durability, and safety. In these instances, formal exemptions are not required. The details of action granting alternative materials, design and methods of construction and equipment will be recorded and entered in the project document files by the Building Official/AHJ. Note that alternative materials, design and methods of construction and equipment must not be misconstrued as a waiver or exemption. Waivers and exemptions are addressed in 104.10.
2-1.5 Section 105 – PERMITS [Deletion].
2-1.6 Section 106 – FLOOR AND ROOF DESIGN LOADS [Deletion].
2-1.7 Section 107 – CONSTRUCTION DOCUMENTS [Deletion].
2-1.8 Section 108 – TEMPORARY STRUCTURES AND USES [Deletion].
2-1.9 Section 109 – FEES [Deletion].
2-1.10 Section 111 – CERTIFICATE OF OCCUPANCY [Deletion].
2-1.11 Section 113 – MEANS OF APPEALS [Deletion].
2-1.12 Section 114 – VIOLATIONS [Deletion].
2-1.13 Section 115 – STOP WORK ORDER [Deletion].
2-1.14 Section 116 – UNSAFE STRUCTURES AND EQUIPMENT [Deletion].
2-2 CHAPTER 2 – DEFINITIONS [SUPPLEMENT].
Use IBC Chapter 2 except as modified by APPENDIX B and by UFC 3-301-01.
2-3 CHAPTER 3 – OCCUPANCY CLASSIFICATION AND USE
[SUPPLEMENT].
Use IBC Chapter 3.
2-4 CHAPTER 4 – SPECIAL DETAILED REQUIREMENTS BASED ON
OCCUPANCY AND USE [SUPPLEMENT].
Use IBC Chapter 4 only as specifically referenced by UFC 3-600-01 and UFC 3-301-01.
2-5 CHAPTER 5 – GENERAL BUILDING HEIGHTS AND AREAS
Use IBC Chapter 5 except as modified below and by UFC 3-600-01.
[C] CHAPTER 2 – DEFINITIONS [SUPPLEMENT]
Definitions in IBC Chapter 2 apply to terms used in the model code and are not intended to replace definitions and terms in military and other referenced documents.
It is essential that the code defined meaning be known to understand the intent and correctly interpret the code.
[C] CHAPTER 3 – OCCUPANCY CLASSIFICATION AND USE [SUPPLEMENT]
IBC occupancy classifications are used as they relate to allowable construction type, building height, building area, building separation distance, occupancy separation and associated requirements. NFPA 101 occupancy classifications are used as they relate to fire/smoke resistance rating of interior non-load bearing partitions (other than occupancy separation), means of egress, interior finish, features of fire protection (including vertical openings) and associated requirements.
[C] CHAPTER 5 – GENERAL BUILDING HEIGHTS AND AREAS [SUPPLEMENT]
UFC 3-600-01 gives direction concerning the requirements for fire-rated partitions.
Note that the building area for funding and planning purposes is calculated differently than the method defined in IBC Chapter 5 for code compliance calculation.
2-5.1 Section 506 – BUILDING AREA.
2-5.1.1 Table 506.2 – Allowable Area Factor in Square Feet.
Table 506.2: Cell at I-4, S1, Type IA [Replacement]
242,000.
2-6 CHAPTER 6 – TYPES OF CONSTRUCTION [SUPPLEMENT].
Use IBC Chapter 6 except as modified by UFC 3-600-01.
2-7 CHAPTER 7 – FIRE AND SMOKE PROTECTION FEATURES
[SUPPLEMENT].
Use IBC Chapter 7 only where specifically referenced by IBC Chapter 5 or 6, otherwise use UFC 3-600-01 and modifications in UFC 3-101-01.
2-8 CHAPTER 8 – INTERIOR FINISHES [REPLACEMENT].
Use UFC 3-600-01, UFC 3-120-10 and UFC 3-101-01.
2-9 CHAPTER 9 – FIRE PROTECTION AND LIFE SAFETY SYSTEMS
[REPLACEMENT].
Use UFC 3-600-01.
2-10 CHAPTER 10 – MEANS OF EGRESS [REPLACEMENT].
Use UFC 3-600-01. Use IBC Chapter 10 when specifically referenced by US Access Board, Architectural Barriers Act (ABA) Standards and as referenced by UFC 3-600-01.
2-11 CHAPTER 11 – ACCESSIBILITY [REPLACEMENT].
Use the ABA Standards and the special provisions of the DoD Deputy Secretary of Defense Memorandum, Subject: Access for People with Disabilities, October 31, 2008.
Use the additional requirements listed in the subparagraphs below, in addition to the ABA Standards and Defense Memorandum.
[C] CHAPTER 7 – FIRE AND SMOKE PROTECTION FEATURES [SUPPLEMENT]
UFC 3-600-01 gives direction concerning the requirements for fire-rated partitions.
[C] CHAPTER 10 – MEANS OF EGRESS [REPLACEMENT]
UFC 3-600-01 references IBC Chapter 10 for requirements for stair to roof access.
Where the ABA Standards reference the previous versions of IBC, the applicable requirements of the 2021 IBC are acceptable.
2-11.1 Electrical vehicle charging stations.
Electrical vehicle charging stations provided to serve Group R-2, R-3 and R-4 occupancies are not required to comply with the following sub-sections.
2-11.1.1 Number of accessible vehicle spaces.
Not less than 5 percent of vehicle spaces on the site served by electrical vehicle charging systems, but not fewer than one for each type of electric vehicle charging system, must be accessible.
2-11.1.2 Accessible electric vehicle space size.
Accessible vehicle spaces at electrical vehicle charging stations must include an accessible parking space that is 132 inches (3350 mm) minimum in width with an access aisle on each side of the space that is 60 inches (1525 mm) minimum in width to allow for a pathway around the vehicle to variable locations of charging ports. Two parking spaces are permitted to share a common access aisle.
2-11.2 Water bottle-filling stations.
Where bottle-filling stations are provided, they must be accessible.
Exception: Bottle-filling stations over drinking fountains for standing persons are not required to be accessible, provided that bottle-filling stations are also located over the drinking fountains for persons using wheelchairs.
2-12 CHAPTER 12 – INTERIOR ENVIRONMENT [SUPPLEMENT].
Use IBC Chapter 12 except as modified below and by UFC 3-101-01.
2-12.1 Section 1203 – TEMPERATURE CONTROL.
1203.1 Equipment and systems [Replacement]
Use UFC 3-410-01.
1203.1 Equipment and systems, Exceptions [Deletion]
[C] CHAPTER 11 – ACCESSIBILITY [REPLACEMENT]
Refer to APPENDIX C for a link to the ABA Standards and the DoD policy memorandum.
[C] CHAPTER 12 – INTERIOR ENVIRONMENT [SUPPLEMENT]
Refer to other Federal guidance and UFC for additional interior space requirements for ventilation, lighting, acoustics, and other environmental characteristics.
2-12.2 Section 1206 – SOUND TRANSMISSION.
1206.2 Airborne sound [Replacement]
Use UFC 3-101-01 and UFC 3-120-10. For Navy and Marine Corps Unaccompanied Housing facilities, only use FC 4-721-10N.
1206.3 Structure-borne sound [Replacement]
Use UFC 3-101-01 and UFC 3-120-10. For Navy and Marine Corps Unaccompanied Housing facilities, only use FC 4-721-10N.
2-12.3 Section 1207 – ENHANCED CLASSROOM ACOUSTICS
[REPLACEMENT].
Use UFC 3-101-01.
2-12.4 Section 1208 – INTERIOR SPACE DIMENSIONS.
1208.3 Room area [Replacement]
Use UFC 3-101-01 and UFC 3-120-10. For Navy and Marine Corps Unaccompanied Housing facilities, only use FC 4-721-10N.
1208.4 Efficiency dwelling units [Replacement]
Use UFC 3-101-01 and UFC 3-120-10. For Navy and Marine Corps Unaccompanied Housing facilities, only use FC 4-721-10N.
2-13 CHAPTER 13 – ENERGY EFFICIENCY [REPLACEMENT].
Use UFC 1-200-02.
\3\ As per Public Law 117-263 Sec. 2810, consider the installation of integrated solar roofing to improve energy resiliency of military installation inside of the United States.
Consideration includes feasibility and cost-effectiveness of installing the system. /3/
2-14 CHAPTER 14 – EXTERIOR WALLS [SUPPLEMENT].
Use IBC Chapter 14 except as modified by UFC 3-101-01.
2-15 CHAPTER 15 – ROOF ASSEMBLIES AND ROOFTOP STRUCTURES
[SUPPLEMENT].
Use IBC Chapter 15 except as modified by UFC 3-110-03 and UFC 3-600-01.