Attachment C - Financial Rep. Req..pdf

PDF 117 KB Posted

Attached to
Global Modeling & Assimilation Support (GLOMAS) Draft Request For Proposal (DRFP) Federal contract opportunity
Solicitation number
80GSFC24R0036
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

This document is the Financial Management Reporting Requirements attachment for the NASA Goddard Space Flight Center's (GSFC) Global Modeling & Assimilation Support (GLOMAS) draft solicitation. The attachment outlines the financial reporting requirements for the GLOMAS contract, which will be an Indefinite Delivery Indefinite Quantity (IDIQ) contract with Cost Plus Fixed Fee (CPFF) task orders.

The key requirements include submitting NASA 533 series financial management reports at the individual task order and cumulative contract levels, providing variance narratives for cost and labor hour variances over 10%, and reporting costs by detailed labor categories for both prime and subcontractor direct labor. The reports must be distributed to specified addressees on a monthly and quarterly basis. This contract will be a Small Business Set-Aside competition with an effective ordering period of 5 years.

View the file

Other files for this federal contract opportunity

Other files attached to Global Modeling & Assimilation Support (GLOMAS) Draft Request For Proposal (DRFP), newest first.
File Type Posted
Attachment I.1 - DEIA Plan.pdf PDF
Enclosure CC - GPM.pdf PDF
Enclosure DD -QASP.pdf PDF
Attachment A -SOW.pdf PDF
Attachment E - Safety and Health Plan.pdf PDF
Attachment I.2 - DEIA Plan DRD.pdf PDF
Attachment J.2 - OCI Plan.pdf PDF
Enclosure AA - Sample SH Plan.pdf PDF
GLOMAS DRFP 09.04.pdf PDF
Attachment F - IT DRD.pdf PDF
Attachment G -Req Statements List.pdf PDF
Enclosure BB - Contract Historical Data.pdf PDF
GLOMAS DRFP Cover Letter_signed.pdf PDF
GLOMAS SF33.pdf PDF
Attachment B -Rate Matrix.pdf PDF
Attachment D - Contract Historical Data.pdf PDF
Attachment H - List of IAGP.pdf PDF
Attachment J.1 - OCI DRD.pdf PDF
Exhibits 1A-1B All IDIQ Std by CY MAR 2016.pdf PDF
Exhibits 2-11 All IDIQ by CY JUL 2016.pdf PDF
Exhibits 12 - PastPerfQues.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT C

FINANCIAL MANAGEMENT REPORTING

REQUIREMENTS

RFP 80GSFC24R0036

CONTRACT TBD

Contract 80GSFC24R0036 Attachment C

(06/2014) 2

FINANCIAL MANAGEMENT REPORTING REQUIREMENTS

Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial Management Reporting,” dated May 27, 2011, and additional instructions issued by the Contracting Officer.

a. Level of Detail

An individual 533 Report shall be provided for each Task Order in addition to a cumulative 533 Report summarizing all Task Orders issued. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d below.

b. Variance Narrative Reporting

In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 10 percent (+/- 10%) between the Total Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total Cost amount shown in the current month for each individual task order. (For example, the Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the Actual June Total Cost amount shown in column 7a in the June NF 533M.)

Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the individual task order, and (3) specific corrective action(s) being taken or to be taken.

c. Distribution

The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.

After the initial report, the NF 533M reports shall be distributed not later than the tenth (10th) working day following the close of the contractors' monthly accounting period.

The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.

d. Reporting Requirements

Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:

1. Prime Direct Labor Hours:

(06/2014) 3

Prime Direct Labor Hours - Onsite (List applicable labor categories)

Prime Direct Labor Hours – Offsite

Total Prime Direct Labor Hours

2. Subcontractor Direct Labor Hours:

Subcontractor A Direct Labor Hours – Onsite

Subcontractor A Direct Labor Hours – Offsite (List applicable labor categories)

Subcontractor B Direct Labor Hours – Onsite (List applicable labor categories) Subcontractor B Direct Labor Hours – Offsite (List applicable labor categories)

Subcontractor C Direct Labor Hours – Onsite (List applicable labor categories) Subcontractor C Direct Labor Hours – Offsite

Total Subcontractors Direct Labor Hours

3. Total Prime and Subcontractors Direct Labor Hours:

Total Prime and Subcontractors Hours – Onsite Total Prime and Subcontractors Hours – Offsite

Total Prime and Subcontractors Direct Labor Hours

4. Prime Direct Labor Costs:

Prime Direct Labor Costs - Onsite

Prime Direct Labor Costs – Offsite

Total Prime Direct Labor Costs

5. Prime Overhead Expenses:

(06/2014) 4

Onsite Overhead

Offsite Overhead

Total Prime Overhead

6. Other Direct Costs (ODCs):

a. Subcontracts (list separately, Subcontractor A, B, C, etc.)

b. Material

c. Travel

d. Other (specify)

Total ODCs

7. Subtotal (Direct Labor, Overhead & ODCs)

8. G&A Expense

9. Total Estimated Cost

10. Fixed Fee

11. Total Cost-Plus-Fixed-Fee (CPFF)

ATTACHMENT C

File details come from the government source that posted it. Updated .