ATTACHMENT C - BID ITEMS COST BREAKDOWN.xlsx

XLSX spreadsheet 49 KB Posted

Attached to
Y1BG--652-23-105 Campus Wide Camera (Construction) Federal contract opportunity
Solicitation number
36C24626B0024
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6

About this file

This is a pricing template for a construction cost breakdown used in response to an Invitational for Bid (IFB) for a federal construction project. The template is designed for the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6, specifically for solicitation number 36C24626B0024 related to Y1BG--652-23-105 Campus Wide Camera (Construction).

The template provides a standardized format for bidders to submit cost breakdowns across five bid items: a base bid and four deduct alternatives (Deduct No. 1 through Deduct No. 4). For each bid item, offerors must itemize labor costs and material costs organized by the 27 MasterFormat divisions, including General Requirements, Concrete, Masonry, Metals, HVAC, Electrical, Plumbing, and other construction categories. The template calculates subtotals for labor and materials by division, then applies overhead percentage, profit percentage, and bond percentage to arrive at the total offer cost for each bid item. The spreadsheet includes fields for project number, project title, location, offeror contact information, and date of offer submission. This is a blank template with all cost fields showing $0, requiring bidders to populate their actual labor, material, overhead, profit, and bond costs in accordance with their specific bid proposal.

View the file

Other files for this federal contract opportunity

Other files attached to Y1BG--652-23-105 Campus Wide Camera (Construction), newest first.
File Type Posted
MARKET SURVEY CONSTRUCTION MATERIALS TEMPLATE.xlsx XLSX spreadsheet
S02 - 36C24626B0024-Campus_02.pdf PDF
SITE VISIT ATTENDANCE LOG OF_05-14-2026-CAMPUS CAMERA_Redacted.pdf PDF
ATTACHMENT D - WAGE DETERMINATION_revised.pdf PDF
Response to Solicitation RFIs Tracker-Campus Wide-0002.xlsx XLSX spreadsheet
36C24626B0024 0002.docx DOCX document
36C24626B0024 0001.docx DOCX document
36C24626B0024_2.docx DOCX document
ATTACHMENT B - DRAWINGS.pdf PDF
ATTACHMENT D - WAGE DETERMINATION.pdf PDF
ATTACHMENT A - SPECIFICATIONS.docx DOCX document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID ITEM I (BASE BID)

BID ITEM I (BASE BID) Cost Breakdown

Project Number:

Edward L Roy: VA assigned project #

Date:
Project Title
Edward L Roy: VA assigned Project TitleProject Location
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Sum of Overhead, Profit and Bond %.

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

BID ITEM II (DEDUCT NO. 1)

BID ITEM II (DEDUCT NO. 1) Cost Breakdown

Project Number:

Edward L Roy: VA assigned project #

Date:
Project Title
Edward L Roy: VA assigned Project TitleProject Location
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

BID ITEM III (DEDUCT NO. 2)

BID ITEM III (DEDUCT NO. 2) Cost Breakdown

Project Number:

Edward L Roy: VA assigned project #

Date:
Project Title
Edward L Roy: VA assigned Project TitleProject Location
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

BID ITEM IV (DEDUCT NO. 3)

BID ITEM IV (DEDUCT NO. 3) Cost Breakdown

Project Number:

Edward L Roy: VA assigned project #

Date:
Project Title
Edward L Roy: VA assigned Project TitleProject Location
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

BID ITEM V (DEDUCT NO. 4)

BID ITEM V (DEDUCT NO. 4) Cost Breakdown

Project Number:

Edward L Roy: VA assigned project #

Date:
Project Title
Edward L Roy: VA assigned Project TitleProject Location
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

File details come from the government source that posted it. Updated .