ATTACHMENT A - SPECIFICATIONS.docx

DOCX document 1 MB Posted

Attached to
Y1BG--652-23-105 Campus Wide Camera (Construction) Federal contract opportunity
Solicitation number
36C24626B0024
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 6

About this file

This file is an Attachment A - Specifications document for the VA Richmond Medical Center's Campus Wide Security Camera Replacement project (VA Project No. 652-23-105), issued for bids on October 17, 2025. The specifications establish comprehensive requirements for complete demolition of existing security camera systems and installation of new video surveillance infrastructure across multiple buildings and site locations at the medical center.

The project scope includes removal and disposal of existing cameras and associated equipment (to be stored for VA), replacement of telecommunications room (TR) racks with patch panels, installation of new cameras categorized as "fish eye" (252 to 170 units depending on alternates), "multisensor" (173 to 121 units), and "dome" cameras (215 to 150 units), along with complete cabling infrastructure. The work is divided into multiple phases: Phase IA covers Building 500 ICRA areas with after-hours work; Phase IB covers Building 500 non-after-hours ICRA areas; Phase II addresses site cameras on light poles; and Phase III encompasses Buildings 501, 507, 509, 511, 512, 513, 514, 515, 518, 519, 520, and 521. The contract includes three unit price options for credits related to J-Hook installations, rigid conduit reuse, and various underground utility pathways (asphalt, concrete, and planting areas), plus pricing for cabling and individual camera types. The specifications require detailed compliance with safety requirements (Section 01 35 26), infection control risk assessments (ICRA guidelines), communications installations standards (Section 27 05 11), and electronic safety and security systems (Section 28 23 00), along with comprehensive quality control, commissioning, testing, warranty management, and photographic documentation of construction progress. Contractor must maintain continuous negative pressure in work areas, provide decontamination facilities, coordinate with VA Police for security, and ensure minimal disruption to 24/7 medical center operations through carefully coordinated phasing and scheduling.

View the file

Other files for this federal contract opportunity

Other files attached to Y1BG--652-23-105 Campus Wide Camera (Construction), newest first.
File Type Posted
MARKET SURVEY CONSTRUCTION MATERIALS TEMPLATE.xlsx XLSX spreadsheet
ATTACHMENT D - WAGE DETERMINATION_revised.pdf PDF
Response to Solicitation RFIs Tracker-Campus Wide-0002.xlsx XLSX spreadsheet
36C24626B0024 0002.docx DOCX document
S02 - 36C24626B0024-Campus_02.pdf PDF
SITE VISIT ATTENDANCE LOG OF_05-14-2026-CAMPUS CAMERA_Redacted.pdf PDF
36C24626B0024 0001.docx DOCX document
ATTACHMENT B - DRAWINGS.pdf PDF
36C24626B0024_2.docx DOCX document
ATTACHMENT D - WAGE DETERMINATION.pdf PDF
ATTACHMENT C - BID ITEMS COST BREAKDOWN.xlsx XLSX spreadsheet
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIVISION 00 - SPECIAL SECTIONS

DATE

00 01 10
Table of Contents
05-10
00 01 07
Seals Page
n/a
00 01 15
List of Drawing Sheets
05-10

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00
General Requirements
11-21
01 10 00
Summary
-
01 22 00
Unit Prices
-
01 32 16.15
Network Analysis Schedules (Small Projects – Design/Bid/Build)
05-22
01 33 23
Shop Drawings, Product Data, and Samples
11-23
01 35 26
Safety Requirements for Major Projects
05-24
01 42 19
Reference Standards
11-20
01 45 00
Quality Control
02-21
01 45 29
Testing Laboratory Services
05-24
01 57 19
Temporary Environmental Controls
10-23
01 58 16
Temporary Interior Signage
07-15
01 73 29
Cutting and Patching
n/a
01 74 19
Construction Waste Management
10-23
01 91 00
General Commissioning Requirements
10-23

DIVISION 02 – EXISTING CONDITIONS

02 21 13
Site Surveys
10-23
02 41 10
Demolition and Site Clearing
10-23
02 83 11.13
Glovebag Asbestos Abatement
01-21
02 83 33.13
Lead-Based Paint Removal and Disposal
01-21

DIVISION 07 THERMAL AND MOISTURE PROTECTION

07 81 00
Applied Fireproofing
10-23
07 84 00
Firestopping
10-23
07 92 00
Joint Sealants
10-23

DIVISION 09 – FINISHES

09 91 00
Painting
10-23

DIVISION 27 – COMMUNICATIONS

27 05 11
Requirements for Communications Installations
n/a

Department of Veteran Affairs Richmond VA Medical Center Richmond, VA VA Project No.: 652-23-105 Campus Wide Security Camera Replacement Issued For Bids: 10/17/25

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

00 01 10-1

DIVISION 00 - SPECIAL SECTIONS
DATE
00 01 10
Table of Contents
05-10
00 01 07
Seals Page
n/a
00 01 15
List of Drawing Sheets
05-10

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00
General Requirements
11-21
01 10 00
Summary
-
01 22 00
Unit Prices
-
01 23 00
Alternates
-
01 32 16.13
Network Analysis Schedules
05-22
01 33 23
Shop Drawings, Product Data, and Samples
11-23
01 35 26
Safety Requirements for Major Projects
05-24
01 42 19
Reference Standards
11-20
01 45 00
Quality Control
02-21
01 45 29
Testing Laboratory Services
05-24
01 57 19
Temporary Environmental Controls
10-23
01 58 16
Temporary Interior Signage
07-15
01 74 19
Construction Waste Management
10-23
01 91 00
General Commissioning Requirements
10-23

DIVISION 02 – EXISTING CONDITIONS

02 21 00
Site Surveys
10-23
02 41 10
Demolition and Site Clearing
10-23
02 83 11.13
Glovebag Asbestos Abatement
01-21
02 83 33.13
Lead-Based Paint Removal and Disposal
01-21

DIVISION 03 – CONCRETE

DIVISION 04 – MASONRY

DIVISION 05 – METALS

05 50 00
Metal Fabrications
10-23

DIVISION 06 – WOOD,PLASTICS AND COMPOSITES

DIVISION 07 THERMAL AND MOISTURE PROTECTION

07 81 00
Applied Fireproofing
10-23
07 84 00
Firestopping
10-23
07 92 00
Joint Sealants
10-23

DIVISION 08 OPENINGS

DIVISION 09 – FINISHES

09 91 00
Painting
10-23

DIVISION 10 – SPECIALTIES

DIVISION 11 - EQUIPMENT

DIVISION 12 – FURNISHINGS

DIVISION 13 - SPECIAL CONSTRUCTION

DIVISION 22 – PLUMBING

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

DIVISION 25 – INTEGRATED AUTOMATION

DIVISION 26 – ELECTRICAL

DIVISION 27 – COMMUNICATIONS

27 05 11
Requirements for Communications Installations
n/a
27 05 26
Grounding and Bonding for Communications Systems
12-22
27 05 33
Conduits and Backboxes for Communications Systems
12-22
27 05 36
Cable Trays for Communications Systems
12-22
27 05 53
Identification for Communications Systems
12-22
27 10 00
Structured Cabling
12-22
27 11 19
Communications Termination Blocks and Patch Panels
12-22
27 11 26
Communications Rack-Mounted Power Protection and Power

Strips 12-22

27 13 13.13
Communications Copper Cable Splicing and Terminations
12-22
27 15 13
Communications Copper Horizontal Cabling
12-22
27 16 19
Communications Patch Cords, Station Cords, and Cross-

Connect Wire 12-22

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

27 05 00
Common Work Results for Electronic Security Systems
04-18

Department of Veteran Affairs Richmond VA Medical Center Richmond, VA

Issued For Bids: 10/17/25

00 01 10-2

28 05 01
Statement of Work for Electronic Safety and Security

Installations n/a

28 05 13
Conductors and Cables for Electronic Security Systems
10-18
28 05 26
Grounding and Bonding for Electronic Security Systems
09-11
28 05 28 33
Conduits and Backboxes for Electronic Security Systems
09-11
28 23 00
Video Surveillance
03-18

DIVISION 31 – EARTHWORK

31 20 00
Earth Moving
08-23

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23
Cement and Concrete for Exterior Improvements
11-16
32 12 16
Asphalt Paving
09-15
32 90 00
Planting
11-16

DIVISION 33 – UTILITIES

End of Section

SECTION 00 01 15 LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GI001COVER SHEET
GI002DEMOLITION INFORMATION AND SHEET INDEX
GI003GENERAL - ICRA GUIDLINES
GI004FIRE/SMOKE BARRIER LEGEND
GI-1-500-00A
INFECTION
CONTROL
PLAN
LEVEL
00
- OVERALL
GI-1-500-00B
INFECTION
CONTROL
PLAN
LEVEL
01
- OVERALL- BG-107
GI-1-500-01A
INFECTION
CONTROL
PLAN
LEVEL
01
- OVERALL
GI-1-500-01B
INFECTION
CONTROL
PLAN
LEVEL
01
- OVERALL CONT.
GI-1-500-02A
INFECTION
CONTROL
PLAN
LEVEL
02
- OVERALL
GI-1-500-02B
INFECTION
CONTROL
PLAN
LEVEL
02
- OVERALL CONT.
GI-1-500-03A
INFECTION
CONTROL
PLAN
LEVEL
03
- PART A
GI-1-500-03D
INFECTION
CONTROL
PLAN
LEVEL
03
- PART D
GI-1-500-04
INFECTION
CONTROL
PLAN
LEVEL
04
GI-1-500-05
INFECTION
CONTROL
PLAN
LEVEL
05
GI-1-501-00
INFECTION
CONTROL
PLAN
LEVEL
00
- OVERALL

GI-1-507-00 GENERAL - INFECTION CONTROL PLAN

GI-1-509-00
INFECTION
CONTROL
PLAN
LEVEL
00
- OVERALL
GI-1-509-01
INFECTION
CONTROL
PLAN
LEVEL
01
- OVERALL
GI-1-511-00
INFECTION
CONTROL
PLAN
LEVEL
00
- OVERALL
GI-1-512-00
INFECTION
CONTROL
PLAN
LEVEL
00
- OVERALL
GI-1-512-01
INFECTION
CONTROL
PLAN
LEVEL
01
- OVERALL
GI-1-513-00
INFECTION
CONTROL
PLAN
LEVEL
00
- OVERALL
GI-1-514-00
INFECTION
CONTROL
PLAN
LEVEL
00
- OVERALL
GI-1-515-00
INFECTION
CONTROL
PLAN
LEVEL
00
- OVERALL
GI-1-515-01
INFECTION
CONTROL
PLAN
LEVEL
01
- OVERALL

Department of Veteran Affairs Richmond VA Medical Center Richmond, VA

00 01 15 - 1

AE-1-518-00

OVERALL FLOOR PLAN - LICENSE PLATE CAMERA MOUNT DETAILS

GI-1-518-00 INFECTION CONTROL PLAN LEVEL 00 - OVERALL GI-1-519-00 INFECTION CONTROL PLAN LEVEL 00 - OVERALL GI-1-519-00 INFECTION CONTROL PLAN LEVEL 00 - OVERALL GI-1-520-00 INFECTION CONTROL PLAN LEVEL 00 - OVERALL GI-1-521-00 INFECTION CONTROL PLAN LEVEL 00 - OVERALL GI-1-521-01 INFECTION CONTROL PLAN LEVEL 01 - OVERALL CD-1-S01 CAMPUS SITE PLAN - DEMOLITION

CU-1-S01 CAMPUS SITE PLAN - NEW WORK

TD-1-500-00
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
00
- OVERALL
TD-1-500-00A
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
00
- PART A
TD-1-500-00B
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
00
- PART B
TD-1-500-00C
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
00
- PART C
TD-1-500-00D
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
00
- PART D
TD-1-500-00E
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
00
- PART E
TD-1-500-01
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
01
- OVERALL
TD-1-500-01A
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
01
- PART A
TD-1-500-01B
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
01
- PART B
TD-1-500-01C
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
01
- PART C
TD-1-500-01D
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
01
- PART D
TD-1-500-01E
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
01
- PART E
TD-1-500-02
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
02
- OVERALL
TD-1-500-02A
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
02
- PART A
TD-1-500-02B
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
02
- PART B
TD-1-500-02C
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
02
- PART C
TD-1-500-02D
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
02
- PART D
TD-1-500-03A
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
03
- PART A
TD-1-500-03D
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
03
- PART D
TD-1-500-04A
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
04
- PART A
TD-1-500-04D
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
04
- PART D
TD-1-500-05A
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
05
- PART A
TD-1-500-05D
SECURITY
FLOOR
PLAN
- DEMOLITION LEVEL
05
- PART D
TY-0-01
SECURITY
COVER
SHEET
TY-1-500-00
SECURITY
FLOOR
PLAN
LEVEL 00 - OVERALL
TY-1-500-00A
SECURITY
FLOOR
PLAN
LEVEL
00
-
PART
A
TY-1-500-00B
SECURITY
FLOOR
PLAN
LEVEL
00
-
PART
B
TY-1-500-00C
SECURITY
FLOOR
PLAN
LEVEL
00
-
PART
C
TY-1-500-00D
SECURITY
FLOOR
PLAN
LEVEL
00
-
PART
D
TY-1-500-00E
SECURITY
FLOOR
PLAN
LEVEL
00
-
PART
E
TY-1-500-01
SECURITY
FLOOR
PLAN
LEVEL
01
- OVERALL
TY-1-500-01A
SECURITY
FLOOR
PLAN
LEVEL
01
- PART A
TY-1-500-01B
SECURITY
FLOOR
PLAN
LEVEL
01
- PART B
TY-1-500-01C
SECURITY
FLOOR
PLAN
LEVEL
01
- PART C
TY-1-500-01D
SECURITY
FLOOR
PLAN
LEVEL
01
- PART D
TY-1-500-01E
SECURITY
FLOOR
PLAN
LEVEL
01
- PART E
TY-1-500-02
SECURITY
FLOOR
PLAN
LEVEL
02
- OVERALL
TY-1-500-02A
SECURITY
FLOOR
PLAN
LEVEL
02
- PART A
TY-1-500-02B
SECURITY
FLOOR
PLAN
LEVEL
02
- PART B
TY-1-500-02C
SECURITY
FLOOR
PLAN
LEVEL
02
- PART C
TY-1-500-02D
SECURITY
FLOOR
PLAN
LEVEL
02
- PART D
TY-1-500-03A
SECURITY
FLOOR
PLAN
LEVEL
03
- PART A
TY-1-500-03DSECURITY FLOOR PLAN LEVEL 03 - PART D TY-1-500-04SECURITY FLOOR PLAN LEVEL 04
TY-1-500-05SECURITY FLOOR PLAN LEVEL 05
TY-1-S01SECURITY SITE PLAN - DEMOLITION
TY-1-S02SECURITY SITE PLAN - NEW WORK
TY-5-01SECURITY DETAILS
TY-5-02SECURITY DETAILS
TY-5-03SECURITY DETAILS
TY-5-04SECURITY DETAILS

TY-6-500-01 SECURITY CCTV RISER DIAGRAM TY-6-500-02 SECURITY CCTV RISER DIAGRAM TY-6-500-03 SECURITY CCTV RISER DIAGRAM TY-6-500-04 SECURITY CCTV RISER DIAGRAM

TY-7-01

TY-7-02

CAMERA SCHEDULE

CAMERA SCHEDULE

TD-1-501-01 TY-1-501-01 TY-6-501-01 TD-1-507-00
SECURITY FLOOR PLAN - DEMOLITION LEVEL SECURITY FLOOR PLAN LEVEL 01

SECURITY CCTV RISER DIAGRAM

SECURITY FLOOR PLAN - DEMOLITION LEVEL

TY-1-507-00

TY-6-507-00

SECURITY FLOOR PLAN LEVEL 00

SECURITY CCTV RISER DIAGRAM

TD-1-509-00
SECURITY
FLOOR
PLAN
- DEMOLITION
LEVEL
00
TD-1-509-01
SECURITY
FLOOR
PLAN
- DEMOLITION
LEVEL
01
TY-1-509-00
SECURITY
FLOOR
PLAN
LEVEL 00
TY-1-509-01
SECURITY
FLOOR
PLAN
LEVEL 01
TY-6-509-01
SECURITY
CCTV
RISER
DIAGRAM
TD-1-511-00
SECURITY
FLOOR
PLAN
- DEMOLITION
LEVEL
00
TY-1-511-00
SECURITY
FLOOR
PLAN
LEVEL 00
TY-6-511-00
SECURITY
CCTV
RISER
DIAGRAM
TD-1-512-00
SECURITY
FLOOR
PLAN
- DEMOLITION
LEVEL
00
TD-1-512-01
SECURITY
FLOOR
PLAN
- DEMOLITION
LEVEL
01
TY-1-512-00
SECURITY
FLOOR
PLAN
LEVEL 00
TY-1-512-01
SECURITY
FLOOR
PLAN
LEVEL 01
TY-6-512-01
SECURITY
CCTV
RISER
DIAGRAM
TD-1-513-00
SECURITY
FLOOR
PLAN
- DEMOLITION
LEVEL
00
TY-1-513-00
SECURITY
FLOOR
PLAN
LEVEL 00
TY-6-513-00
SECURITY
CCTV
RISER
DIAGRAM
TD-1-514-00
SECURITY
FLOOR
PLAN
- DEMOLITION
LEVEL
00
TY-1-514-00
SECURITY
FLOOR
PLAN
LEVEL 00
TY-6-514-00
SECURITY
CCTV
RISER
DIAGRAM
TD-1-515-00
SECURITY
FLOOR
PLAN
- DEMOLITION
LEVEL
00
TD-1-515-01
SECURITY
FLOOR
PLAN
- DEMOLITION
LEVEL
01
TY-1-515-00
SECURITY
FLOOR PLAN
LEVEL 00
TY-1-515-01
SECURITY
FLOOR PLAN
LEVEL 01
TY-6-515-00
SECURITY
CCTV RISER
DIAGRAM
TD-1-518-01
SECURITY
FLOOR PLAN
- DEMOLITION
LEVEL
01
TD-1-518-02
SECURITY
FLOOR PLAN
- DEMOLITION
LEVEL
02
TD-1-518-03
SECURITY
FLOOR PLAN
- DEMOLITION
LEVEL
03
TD-1-518-04
SECURITY
FLOOR PLAN
- DEMOLITION
LEVEL
04
TY-1-518-01
SECURITY
FLOOR PLAN
LEVEL 01
TY-1-518-02
SECURITY
FLOOR PLAN
LEVEL 02
TY-1-518-03
SECURITY
FLOOR PLAN
LEVEL 03
TY-1-518-04
SECURITY
FLOOR PLAN
LEVEL 04
TY-6-518-00
SECURITY
CCTV RISER
DIAGRAM
TD-1-519-00
SECURITY
FLOOR PLAN
- DEMOLITION
LEVEL
00
TY-1-519-01
SECURITY
FLOOR PLAN
LEVEL 00
TY-6-519-00
SECURITY
CCTV RISER
DIAGRAM
TD-1-520-00
SECURITY
FLOOR PLAN
- DEMOLITION
LEVEL
00
TY-1-520-00
SECURITY
FLOOR PLAN
LEVEL 00
TY-6-520-00
SECURITY
CCTV RISER
DIAGRAM
TD-1-521-00
SECURITY
FLOOR PLAN
- DEMOLITION
LEVEL
00
TD-1-521-01
SECURITY
FLOOR PLAN
- DEMOLITION
LEVEL
01
TY-1-521-00
SECURITY
FLOOR PLAN
LEVEL 00
TY-1-521-01
SECURITY
FLOOR PLAN
LEVEL 01
TY-6-521-00
SECURITY
CCTV RISER
DIAGRAM

- - - E N D - - -

SECTION 01 00 00 GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing cameras, and furnish labor and materials and perform work for Campus Wide Security Camera Replacement as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer.

C. Offices of Logos BZ, LLC, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, BASE BID Work includes alterationsnecessary removal of existing (stored for the VA) and construction of other items to perform construction of Department of Veteran Affairs Richmond VA Medical Center Richmond, VA

01 00 00 -10 the CAMPUS WIDE SECURITY CAMERA REPLACEMENT as indicated in the drawings and specifications.

B. ALTERNATE DEDUCT NO.1: BASE BID and delete_30% of the outside fixtures. Alternate 1’s value should reduce the number of “fish eye” cameras from 252 to 170 and “Multisensor” cameras from 173 to 121. The VA will establish which cameras are to be removed from scope.

C. ALTERNATE DEDUCT NO.2: BASE BID except includes changes associated withALTERNATE DEDUCT NUMBER 1 and remove 30% of the Indoor fixtures reducing “dome cameras” from 215 to 150. The VA will establish which cameras are to be removed from scope.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub- contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).

a) Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

b) “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued to the General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

I. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

2. To ensure such executions, Contractor shall furnish the COR with a schedule (3 week lookahead) of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, as follows:

J. Phase IA: Building No.(s) 500, ICRA areas where after-hours work will occur as indicated on drawings. These areas may require additional provision by the VA Police. Coordinate as required with the VA for scheduling.

K. Phase IB: Building No.(s) 500, ICRA areas where work does not occur after- hours as indicated on drawings.

L. Phase II: Site cameras not on buildings.

M. Phase III: Building(s) No.(s) 501, 507, 509, 511, 512, 513, 514, 515, 515, 518, 519, 520, and 521. These buildings will be occupied during performance of work; but immediate areas of alterations will be vacated where possible. Building 507 areas may require additional provision by the VA Police. Coordinate as required with the VA for scheduling.

N. Work Requirements for all Phases: Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractors shall permit access to Department of Veterans Affairs personnel and patients through other construction areas that serve as routes of access to such affected areas and equipment. These routes, whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.

O. When a construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

P. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 14 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

Q. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those that are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

R. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

S. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of buildingsin which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

4. PCB Transformers and Capacitors: The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl (PCB) transformers and capacitors. The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the Environmental Protection Agency (EPA) and the Department of Transportation (DOT) as outlined in Code of Federal Regulation (CFR), Titled 40 and 49 respectively. The EPA's Toxic Substance Control Act (TSCA) Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-7 also apply. Upon removal of PCB transformers and capacitors for disposal, the "originator" copy of the Uniform Hazardous Waste Manifest (EPA Form 8700-22), along with the Uniform Hazardous Waste Manifest Continuation Sheet (EPA Form 8700-22A) shall be returned to the Contracting Officer who will annotate the contract file and transmit the Manifest to the Medical Center'sChief.

a) Copies of the following listed CFR titles may be obtained from the Government Printing Office:

40
CFR
261
.......Identification and Listing of Hazardous Waste
40
CFR
262
.......Standards Applicable to Generators of Hazardous

Waste 40 CFR 263 .......Standards Applicable to Transporters of Hazardous Waste

40 CFR 761 .......PCB Manufacturing, Processing, Distribution in Commerce, and use Prohibitions 49 CFR 172 .......Hazardous Material tables and Hazardous Material Communications Regulations 49 CFR 173 .......Shippers - General Requirements for Shipments and Packaging

49
CRR
173
.......Subpart A General
49
CFR
173
.......Subpart B Preparation of Hazardous Material for

Transportation 49 CFR 173 .......Subpart J Other Regulated Material; Definitions and Preparation TSCA Compliance Program Policy Nos. 6- PCB-6 and 6-PCB-7

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS (FAR 52.236-9) A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed, and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work.

C. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

D. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 PHYSICAL DATA – SITE AND SOIL CONDITIONS

A. Available Data: The subsurface data, site surveys, and investigation results provided in the contract documents are for informational purposes. This data represents the conditions at the specific locations and times indicated.

B. Subsurface Investigations:

1. Subsurface conditions were determined via core borings and test pits as shown in the [Insert Drawing/Attachment Reference].

2. The Government does not warrant that these conditions are continuous across the entire site or that the proportions of materials will remain constant between boring locations.

C. Contractor Responsibility: In accordance with the Site Investigation and Conditions Affecting the Work requirements, the Contractor is responsible for:

1. Reviewing all provided logs and site data.

2. Conducting an independent site visit to evaluate surface and visible conditions.

3. Forming independent conclusions regarding the character and difficulty of the work.

D. Supplemental Exploration: Upon written request to the Department of Veterans Affairs, bidders may be permitted to conduct independent subsurface explorations at their own expense, subject to agency security and scheduling requirements.

1.12 PROFESSIONAL SURVEYING SERVICES

A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.13 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(FAR 52.236-17)

B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, and parking lots are in accordance with lines and elevations shown on contract drawings.

C. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.

1. Lines of each building and/or addition.

2. Elevations of bottoms of footings and tops of floors of each building and/or addition.

3. Lines and elevations of sewers and of all outside distribution systems.

4. Lines of elevations of all swales and interment areas.

5. Lines and elevations of roads, streets and parking lots.

D. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work, fifty foot stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.

E. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying Services".

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications. All Red Lines (changes) to be provided to the A/E so that they can be incorporated into .pdf As-Builts.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to ensure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

E. Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

a) Code 1-Life Safety Systems

1) Fire suppression systems.

2) Fire alarm system(s).

b) Code 1-Air Conditioning Systems

1) Air conditioning leak in part of the building, if causing damage.

2) Air conditioning system not cooling properly.

c) Code 1 Doors

1) Overhead doors not operational, causing a security, fire or safety problem.

1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

d) Code 3-Doors

1) Overhead doors not operational.

2) Interior/exterior personnel doors or hardware not functioning properly.

e) Code 1-Electrical

1) Power failure (entire area or any building operational after 1600 hours).

2) Security lights.

3) Smoke…