This document is an attachment to a state and local contract opportunity from the Oregon Department of Transportation (ODOT) for the Ontario Maintenance Station New Evaporation Pond Liner & Excavation Work project. The scope of work includes the installation of a new geotextile layer and pond liner in a previously prepared pond, rerouting of an oil/water separator outlet, and trenching and backfilling at the liner perimeter. The project must be substantially completed by October 1, 2024 and finally completed by October 15, 2024. The contractor is responsible for coordinating suppliers and subcontractors, maintaining a clean worksite, securing necessary permits, scheduling special inspections, and addressing any conflicts with existing utilities. ODOT will provide contact information for the special inspections firm, but the contractor is responsible for scheduling inspections.
The contractor must submit product information for the geotextile sub-liner and pond liner prior to the start of work. At the completion of the project, the contractor must provide a set of marked-up record drawings and operations, maintenance, and warranty information to ODOT. ODOT will inspect the work for substantial and final completion within a specified number of business days after the contractor's written request.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB_PW_Final~8.docx | DOCX document | |
| 00011205 Addendum 1.docx | DOCX document | |
| 00011205 Intent To Award.xlsx | XLSX spreadsheet | |
| 00011205 Addendum 2~1.docx | DOCX document | |
| Attachment A Plans~1.pdf | ||
| 20252010_E1_Response_Log_and_Abstract.pdf | ||
| 00011205 VoluntaryPreBidMeetingNotes.pdf | ||
| 00011205 Preliminary Results~1.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
August 5, 2024 Oregon Department of Transportation Ontario Maintenance Station New Evaporation Pond Liner & Excavation Work
Project Description Installation of a new geotextile layer and pond liner in a previously prepared pond, reroute oil/water separator outlet from catch basin to daylight into pond, cap pipe leaving the catch basin, trenching and backfilling at liner perimeter. See attached plans and specifications for further details.
Project Location 541 Stanton Blvd, Ontario, OR 97914
ODOT Contacts The ODOT Project Managers for this work are:
· Travis Duby
· Email: travis.duby@odot.oregon.gov
· Cell phone: (971) 599-9473
· Shelby Stout
· Email: shelby.stout@odot.oregon.gov
· Cell phone: (541) 952-1165
The ODOT Project Managers may designate an additional ODOT contact person or engineer to support with inspections or questions in the field.
Scheduling of Work under the Contract
1. Substantial completion of the Work shall be no later than October 1, 2024. Final Completion shall be no later than October 15, 2024.
2. After award of the contract, the Contractor shall contact the ODOT Project Managers to schedule the Work at least ten (10) business days prior to the start of the Work.
3. The Work shall be accomplished on weekdays between the hours of 8 a.m. and 5 p.m. Work hours shall exclude weekends and State Holidays, unless specifically requested by the Contractor and approved by the ODOT Project Managers.
4. The Contractor shall coordinate the efforts of all suppliers and Subcontractors and shall maintain orderly progress of the Work, prevent duplication of effort, and ensure proper sequence of operations.
5. The Contractor shall submit to the ODOT Project Managers a list of the contact information for the Contractor’s project manager and site superintendent, as well as a list of all Subcontractors and their key representatives.
Clean-Up/Conditions of Site
1. The Contractor shall be responsible for keeping the ODOT Project Managers informed of all activity throughout the duration of the Contract.
2. The Contractor shall clean up all worksite debris resulting from construction and remove all excess construction materials and scraps from the Project Location. The Contractor shall broom-clean its work area at the end of each workday and neatly stack materials and debris in a location approved by the Project Managers. Failure to clean the work area up allows the State to perform the necessary clean-up actions and bill the Contractor the direct costs, plus $300.00, to be deducted from the final payment to the Contractor.
3. The Contractor shall protect any materials subject to damage by temperature or other weather conditions.
4. The location for storage of materials, debris, or dumpster at the Project Location shall be approved in advance by the ODOT Project Managers. Disposal facilities, bins, or dumpsters shall not be provided by ODOT.
5. The Contractor shall notify the ODOT Project Managers at least two (2) days in advance of any deliveries.
6. Contractor shall immediately notify the ODOT Project Managers of any damage done by the Contractor to the Project Location, grounds, or adjacent State properties. Damage done by the Contractor shall be repaired to existing conditions as found prior to the commencement of the Work.
7. ODOT shall not be responsible for the security of the Contractor’s materials, tools, personal belongings, or equipment on the Project Location.
8. It is the responsibility of the Contractor to ensure the Work is performed in accordance with Oregon OSHA rules and regulations.
9. Any permits required for the Work are the responsibility of the Contractor. The Contractor shall provide copies of permits to the ODOT Project Managers prior to the start of Work. The Contractor shall be responsible for posting all permits at the Project Location in accordance with local jurisdictional requirements.
10. ODOT shall be responsible for contracting with a special inspections firm based upon the list of inspections required by the Architect/Engineer of Record, manufacturer, or jurisdiction. ODOT shall provide contact info for the approved special inspections firm to the Contractor. The Contractor shall be responsible for scheduling special inspections as to not delay the project schedule. The special inspections firm shall be required by contract to provide copies of the special inspections report to ODOT and the Contractor. The Contractor shall be solely responsible for addressing any deficiencies identified during special inspections.
11. The Contractor shall immediately bring to the attention of the ODOT Project Managers any conflicts or issues between existing utilities and the Work.
12. Contractor shall be responsible for making arrangements for temporary utility requirements during the Work and for all related costs.
13. Restroom and drinking water shall be provided by the Contractor.
Detailed Specifications See specifications on attached construction documents.
Submittals The Contractor shall provide the following submittals to the ODOT Project Managers, at a minimum. Submittals shall be approved by the ODOT Project Managers prior to the start of any Work.
1. Geotextile sub-liner product information
2. Pond liner product information
Close-Out
1. Contractor shall maintain drawings for recording as-built conditions. Contractor shall mark (in red) any changes made to drawings during the course the Work.
2. All special inspections must be completed prior to Substantial Completion.
3. Inspection of the Work by the ODOT Project Managers for establishment of Substantial Completion shall be made within three (3) business days after receipt of the Contractor’s written request. At the time of inspection, the ODOT Project Managers and the Contractor shall develop a punchlist document of any incomplete or deficient Work.
4. Prior to Final Completion, Contractor shall fully instruct ODOT’s operating and maintenance personnel in the operation, adjustment, and maintenance of products, equipment, and systems that form part of the Work.
5. Prior to Final Completion, Contractor shall provide a digital copy via email of all operations, maintenance, and warranty information to the ODOT Project Managers.
6. Prior to Final Completion, Contractor shall complete all items on the punchlist document.
7. At the time of Final Completion, Contractor shall turn over the one marked-up set of record drawings to the ODOT Project Managers.
8. Inspection of the Work by the ODOT Project Managers for establishment of Final Completion shall be made within five (5) business days after receipt of the Contractor’s written request.
File details come from the government source that posted it. Updated .