00011205 Preliminary Results~1.xlsx

XLSX spreadsheet 21 KB Posted

Attached to
Ontario Maintenance Station New Evaporation Pond Liner
Solicitation number
S-73000-00011205
Issued by
Malheur County, Oregon

About this file

This document is a bid tabulation for the Ontario Maintenance Station New Evaporation Pond Liner project, which is a state and local contract opportunity in Oregon's Marion County. The project includes the installation of a new geotextile layer and pond liner in a previously prepared pond, as well as the excavation and backfill of a liner edge termination trench and the modification of an existing manhole. The bid closing date is 09/03/2024 at 10:30 AM. The bid tabulation shows the unit prices and total prices submitted by two bidders, Realm Mining Inc. and Hamilton Excavation.

The bid tabulation indicates that the estimated total price for the project is $65,900.00 for Realm Mining Inc. and $77,055.00 for Hamilton Excavation. No other pricing information or contract details are provided in the document.

View the file

Other files

File Type Posted
ITB_PW_Final~8.docx DOCX document
00011205 Addendum 1.docx DOCX document
00011205 Intent To Award.xlsx XLSX spreadsheet
00011205 Addendum 2~1.docx DOCX document
Attachment B Specifications.docx DOCX document
Attachment A Plans~1.pdf PDF
20252010_E1_Response_Log_and_Abstract.pdf PDF
00011205 VoluntaryPreBidMeetingNotes.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Date Issued:9/3/24
ITB No.S-73000-00011205BIDDER
NAME:Realm Mining IncHamilton Excavation
Bid Closing:09/03/2024 @ 10:30 AM
Description:Ontario Maintenance Station New Evaporation Pond Liner
This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration.
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1Project includes the installation of a new geotextile layer and pond liner in a previously prepared pond. Installation includes liner edge termination trench excavation and backfill. Project also includes modification of an existing manhole as shown on drawings. Refer to attached drawings and specifications1EA$ 65,900.00$ 65,900.00$ 77,055.00$ 77,055.00$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
TOTAL$ 65,900.00$ 77,055.00$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0