This document is an Addendum to an Invitation to Bid (ITB) issued by the Oregon Department of Transportation (ODOT) for the Ontario Maintenance Station New Evaporation Pond Liner project. The purpose of this Addendum is to answer a question posed at the voluntary pre-bid meeting held on 8/21/2024, regarding how the liner will be required to be bonded together, and to add the pre-bid meeting notes to the attachments. The project involves the installation of a new geotextile layer and pond liner in a previously prepared pond, including liner edge termination trench excavation and backfill, and modification of an existing manhole. The closing date for this ITB is 09/03/2024 at 10:30 AM.

The addendum requires bidders to heat weld the liner panels per the manufacturer's requirements. No other pricing terms, set asides, incumbents, funding requirements, or other salient information are provided in this document.

View the file

Other files

File Type Posted
ITB_PW_Final~8.docx DOCX document
00011205 Addendum 1.docx DOCX document
00011205 Intent To Award.xlsx XLSX spreadsheet
Attachment B Specifications.docx DOCX document
Attachment A Plans~1.pdf PDF
20252010_E1_Response_Log_and_Abstract.pdf PDF
00011205 VoluntaryPreBidMeetingNotes.pdf PDF
00011205 Preliminary Results~1.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATE:
8/22/2024
OREGON DEPARTMENT OF TRANSPORTATION

INVITATION TO BID

ADDENDUM NO. 2

ITB NO.:
S-73000-00011205
CLOSING DATE:
09/03/2024
TIME:
10:30 AM
DESCRIPTION:
Ontario Maintenance Station New Evaporation Pond Liner
BUYER:
Dave Dethloff
EMAIL:
William.d.dethloff@odot.oregon.gov
PHONE:
503-569-8793

Requests for clarification, requests for change, and protests of this Addendum are due no later than:

08/23/2024 @ 5:00 PM

This Addendum modifies the Invitation To Bid (ITB) document(s) only to the extent indicated herein. All other areas not changed or otherwise modified by this Addendum remain in full force and effect. This Addendum is hereby made an integral part of the ITB document. Bidder must be responsive to any requirements of this Addendum as if the requirements were set forth in the ITB. Acknowledge receipt of this Addendum by indicating its number in the spaces provided ITB Section H – Addenda Acknowledgement. See the ITB regarding pre-opening modifications of Bids, where to send Bid modifications, requests for clarification or change and protests of this Addendum, and the deadlines for the foregoing.

THE PURPOSE OF THIS ADDENDUM IS TO:

· Answer a question posed at the voluntary pre-bid meeting held 08/21/2024. The question was: “How will the liner be required to be bonded together Seamed or Overlapped?”

· Answer: Heat weld liner panels per manufacturer’s requirements.

· Add document labelled “00011205VoluntaryPre-BidMeetingNotes.pdf” to the attachments tab in OregonBuys.

ITB_ADDENDUM, S006-G031521